PUBLIC NOTICE: ISSUANCE OF REGIONAL GENERAL PERMIT RGP-003-MN IN THE STATE OF MINNESOTA EXCEPT FOR WITHIN THE EXTERIOR BOUNDARIES OF INDIAN RESERVATIONS
PROJECT DESCRIPTION AND PURPOSE: ISSUANCE OF REGIONAL GENERAL PERMIT RGP-003-MN IN THE STATE OF MINNESOTA EXCEPT FOR WITHIN THE EXTERIOR BOUNDARIES OF INDIAN RESERVATIONS
Public Notice
ISSUED: February 3, 2017
EXPIRES: February 2, 2022
ISSUANCE OF REGIONAL GENERAL PERMIT RGP-003-MN IN THE STATE OF MINNESOTA EXCEPT FOR
WITHIN THE EXTERIOR BOUNDARIES OF INDIAN RESERVATIONS
REFER TO: MVP-2016-02832
1. PURPOSE AND BACKGROUND
The purpose of this notice is to announce the issuance of Regional General Permit (RGP)-003-MN in
the State of Minnesota.
On February 1, 2012 the St. Paul District (District) issued RGP-003-MN authorizing the discharge of
dredged or fill materials into waters of the United States and work in Section 10 navigable waters for
specific activities that meet the terms, conditions and limitations of the permit. RGP-003-MN is
intended to streamline the review of permit applications for a range of projects in Minnesota, establish
consistency in permit decisions, and provide more certainty for the public seeking Department of the
Army authorization under Section 404 of the Clean Water Act and Section 10 of the Rivers and
Harbors Act of 1899.
A draft version of the RGP with minor revisions was noticed on October 4, 2016, for a 30-day public
comment period. Comments received in response to the Public Notice were considered and when
appropriate, resulted in minor changes to, and refinement of RGP-003-MN. The final version of RGP003-MN has minor changes from the version attached to the October 4, 2016 public notice. A brief
summary of those minor revisions contained within the issued permit are provided below.
1. Category C (Utility Line Discharges): Language regarding the duration of temporary
discharges was revised to be consistent with General Condition 6 and the proposed Regional
Conditions for the 2017 Nationwide Permits.
2. Language in General Condition 6 (Removal of Temporary Fills) has been revised to read:
PARAGRAPH A, ACTIVITIES WITHOUT PCN REQUIREMENTS: Temporary discharges
in waters of the U.S., including wetlands, must be avoided and limited to the smallest area and
the shortest duration required to accomplish the project purpose. Temporary impacts may not
remain in place longer than 90 days of the growing season (May 1 through October 1). Before
90 days has lapsed, or the alternative timeframe specified by the District in writing, all
temporary fills must be removed in their entirety. Temporary discharges must be fully
contained with appropriate erosion control or containment methods. If the temporary impact
would remain in place for longer than 90 days a PCN is required and the activity is subject to
the requirements and limitations described in paragraph B of this general condition.
PARAGRAPH B, ACTIVITIES WITH PCN REQUIREMENTS: Temporary discharges in
waters of the U.S., including wetlands, must be avoided and limited to the smallest area and the
shortest duration required to accomplish the project purpose. The PCN must specify how long
Operations - Regulatory (MVP-2016-02832)
the temporary discharge will remain in place and include a restoration plan showing how all
temporary fills and structures will be removed and the area restored to pre-project conditions.
Temporary fills are allowed to stay in place as long as specified in the PCN unless noted
differently in the verification letter provided by the District. All temporary fills must be
removed in their entirety in accordance with the PCN unless noted differently in the
verification letter provided by the District. Temporary discharges must be fully contained with
appropriate erosion control or containment methods.
These changes will ensure that activities verified under RGP-003-MN will be minimal, both
individually and cumulatively.
2. APPLICATION PROCEDURES
Prospective permittees seeking authorization for the activities described in RGP-003-MN must follow
the notification procedures in Section 4 of the general permit and submit the required information to
the appropriate Corps office. Pre-construction notifications should be sent to the Regulatory office
covering the county where the proposed project is located. Pre-construction notifications sent directly
to the St. Paul office will be forwarded to the appropriate office for processing. Prospective permittees
may visit the Corps website at http://www.mvp.usace.army.mil/Missions/Regulatory.aspx to
obtain contact information for a specific county.
3. ADDITIONAL INFORMATION
RGP-003-MN may be viewed on the District Internet web site at:
http://www.mvp.usace.army.mil/Missions/Regulatory/PermittingProcessProcedures.aspx.
Persons with questions may obtain information by calling our general information number at (800)
290-5847 x 5525 or (651) 290-5525. Alternatively, questions can be submitted via email to mvp-reginquiry@usace.army.mil.
FOR THE DISTRICT ENGINEER:
_________________________________________
Chad Konickson
Chief, Regulatory Branch
Enclosure
-2-
DEPARTMENT OF THE ARMY PERMIT
Permittee:
The General Public in Minnesota
Permit No:
Regional General Permit (RGP)-003-MN
Issuing Office:
Issuance Date:
Expiration Date:
St. Paul District U.S. Army Corps of Engineers
February 3, 2017
February 2, 2022
NOTE: The term "you" and its derivatives, as used in this permit, means the permittee or any future transferee. The
term "this office" refers to the appropriate district or division office of the Corps of Engineers having jurisdiction over the
permitted activity or the appropriate official of that office acting under the authority of the commanding officer.
AUTHORITIES. Authorities include Section 404 of the Clean Water Act (CWA) (33 U.S.C. 1344) and Section 10 of the
Rivers and Harbors Act (RHA) of 1899 (33 U.S.C. 403), as designated for each category of activities below in the
section "Activities Authorized by the RGP-003-MN". General permits are issued for activities that are similar in nature
and cause only minimal individual and cumulative impacts.
Project Description: The general public in Minnesota is hereby authorized to discharge dredged and fill material into
waters of the United States, and perform work in/over/under Section 10 navigable waters, for the specified activities
listed below. This authorization is subject to the enclosed terms, conditions, and limitations.
Project Location: RGP-003-MN project worksites are located in various waters of the United States, including streams,
rivers, lakes, wetlands and navigable waters of the U.S. at various locations in the state of Minnesota, except within the
exterior boundaries of Indian Reservations. For a complete list of Section 10 Waters in Minnesota please refer to the St.
Paul District Regulatory Website: http://www.mvp.usace.army.mil
Activities Specifically Excluded From RGP-003-MN: RGP-003-MN authorization is not valid for any activity that:
1. Would permanently alter over 500 linear feet of a natural watercourse in a single location through
channelization, diversion or filling. NOTE: This exclusion does not apply to projects where the permanent alteration
would have an overall beneficial effect on the aquatic ecosystem associated with discharges proposed under Activities I
(Stream and Wetland Restoration, Enhancement or Establishment Activities) or Q (Compensatory Mitigation Bank
Construction);
2. Is located within a component of a designated Federal Wild and Scenic River, when the responsible Federal
Agency has determined that the project would have a direct and adverse impact on the values that made the designated
river eligible. (See General Condition 15);
3. Except as noted below, is in a calcareous fen, or in wetlands adjacent to and within 300 feet of a state
designated calcareous fen. A list of calcareous fens can be found on the Minnesota Department of Natural Resources
(MN DNR) Website http://www.dnr.state.mn.us. This restriction does not apply to work for which the MN DNR has
approved a calcareous fen management plan specific to a project that otherwise qualifies for authorization under this
general permit. Project proponents must provide evidence of an approved fen management plan to the District;
4. Is part of a project that would divert more than 10,000 gallons per day of surface or ground water into or out of
the Great Lakes Basin;
5. Is within the exterior boundaries of a Federally-recognized Indian Reservation; or
6. May impact federally listed threatened or endangered species, species proposed for such designation or
designated critical habitat until notified by the District that the requirements of the Endangered Species Act have been
satisfied and that the activity is authorized(See General Condition 21).
(2017) RGP-003-MN Page 1 of 19
TERMS and PROVISIONS:
1. DISCRETIONARY AUTHORITY. As allowed under 33 CFR 325.2(e)(2), the Corps retains discretionary authority to
require an individual permit review of any activity eligible for authorization under RGP-003-MN based on concern for the
aquatic environment or for any other factor of the public interest.
2. PRECONSTRUCTION NOTIFICATION (PCN). Where required by the terms of this regional general permit, a
prospective permittee must notify the District Engineer by submitting a PCN prior to beginning the activity and shall not
begin the activity until written confirmation that the project is authorized by RGP-003-MN is provided, except as
otherwise indicated. See Activities Requiring a PCN in How to Apply for Authorization Information in #4 below.
3. CALCULATING AQUATIC IMPACTS. For those activities with threshold limits, impacts shall be calculated using the
units of measure specified in each permitting category (i.e. area, linear feet, and/or volume) of waters of the United
States temporarily and permanently occupied by a structure, plus the area (or other measure as required by the
category) of waters of the United States temporarily and permanently filled, excavated, inundated, drained, or converted
to a different cover type (unless otherwise indicated). Waters of the United States permanently converted to another
wetland cover type are considered a permanent impact. Activities must meet all limitations contained in a permit
category (for example: linear and area threshold limits).
For activities requiring PCN, all impacts, permanent and temporary, must be included in the PCN.
4. HOW TO APPLY FOR AUTHORIZATION UNDER RGP-003-MN:
a. Activities Requiring a PCN- Where required by the terms of this RGP, the prospective permittee must notify the
District Engineer with a PCN, and shall not begin the activity until notified by the St. Paul District that the project is
eligible for authorization under this RGP and work may proceed with any special conditions imposed by the District
Engineer, or designated representative.
PCN requirements give the Corps the opportunity to evaluate certain proposed RGP activities on a case-by-case basis
to ensure that they will have no more than minimal adverse effects, individually and cumulatively. This case-by-case
review often results in adding project-specific conditions to the authorization to ensure that the RGP authorizes only
activities that result in minimal individual and cumulative effects on the aquatic environment and other public interest
review factors. Review of the PCN may also result in the Corps asserting discretionary authority to require a higher level
of individual permit review.
Contents of the PCN: The notification must be in writing and include the following: (1) Name, address, and telephone
numbers of prospective permittee; (2) Location of the proposed project; (3) A description of the proposed project and
scope of work; (4) all direct and indirect adverse environmental effects the project would cause; (5) identification of
aquatic resources in the project area (in some cases the Corps may require a delineation of the project area prepared in
accordance with the current Corps of Engineers Wetland Delineation Manual and appropriate regional supplement); (6)
a statement regarding compensatory mitigation (33 CFR 325.1(d)(7)); (7) drawings or sketches should be provided as
necessary to show that the activity complies with the terms of the RGP; and (8) any other general or individual permits
used or intended to be used to authorize the project.
b. Activities Not Requiring PCN- Activities authorized by this RGP that do not require a PCN may commence when
project proponents have carefully confirmed that the activity will be conducted in compliance with all of the terms and
conditions of RGP-003-MN. No PCN to the Corps is required; however, if requested, the Corps will confirm whether or
not proposed work is authorized by the RGP. Persons proposing to do work should note that conditions of the RGP
require that adverse impacts on water and wetland resources be avoided and minimized to the maximum extent
practical. Activities that would adversely affect Federal endangered plant or animal species, certain
cultural/archaeological resources, or activities specifically excluded from authorization under RGP-003-MN are excluded
from authorization under the no PCN required categories of this RGP.
General Information- Information about the Corps Regulatory Program, Corps staff contacts by county and permit
requirements may be obtained by emailing mvp-reg-inquiry@usace.army.mil or on the District's web page
http://www.mvp.usace.army.mil. If the necessary information is not available on the referenced web site, the Corps
contact for your county can be obtained by calling 651-290-5525 or 1-800-290-5847 ext. 5525.
5. ENDANGERED SPECIES. The Corps review will include a determination regarding compliance with Section 7 of the
Endangered Species Act (ESA). Corps staff will consult directly with the U.S. Fish and Wildlife Service (USFWS)
(2017) RGP-003-MN Page 2 of 19
concerning projects or proposals which appear to have the potential to affect threatened or endangered species (listed
species), species proposed for such designation or designated critical habitat as identified under the Federal ESA.
Projects that impact waters of the U.S, including wetlands, within areas with known occurrences of listed species must
be coordinated with the St. Paul District to assure listed species will not be affected. Work on projects that may affect
listed species or designated critical habitat shall not begin until the project proponent is notified by the District that the
requirements of the ESA have been satisfied and that the activity is authorized. Information about currently listed
Federal Threatened or Endangered species in Minnesota may be obtained by contacting the USFWS Twin Cities Field
Office at 952-252-0092 or visiting http://www.fws.gov. The USFWS evaluates species and habitats as proposed
candidates for listing and continually updates the federal list. See General Condition 21.
Persons performing work should be aware that Federal or state regulations concerning endangered species may apply
to their projects whether or not the work requires a Corps permit.
6. HISTORIC PROPERTIES AND CULTURAL RESOURCES. The Corps review will include a determination regarding
compliance with Section 106 of the National Historic Preservation Act (NHPA), as appropriate. The National Register of
Historic Places will be consulted to determine the presence or absence of known cultural resources. Corps staff will
consult cultural resources staff concerning projects with the potential to affect cultural resources. Corps staff will consult
with the State Historic Preservation Office as appropriate. Cultural resources surveys will be required where necessary
and in most cases, the District will require that the project proponent conduct the investigation (survey). (33 CFR Part
325 Appendix C.5(e)). See General Condition 8.
Information concerning cultural resources may be obtained from the State Historic Preservation Office website
(http://www.mnhs.org) or by calling
(651) 259-3457.
Persons performing work should be aware that Federal or state regulations concerning cultural resources may apply to
their projects whether or not the work requires a Corps permit.
7. State Designated Trout Streams. Projects with impacts to a state designated trout stream or a water of the U.S.,
including wetlands, that are adjacent to and within 300 feet of a state designated trout stream must notify the District
Engineer with a PCN, and shall not proceed until written verification that the project is authorized by RGP-003-MN is
provided. Special conditions may be imposed by the District Engineer, or designated representative.
8. Federal Projects (Section 408). Projects with the potential to affect federal projects must notify the District Engineer
with a PCN, and shall not proceed until notified by the St. Paul District that the project is eligible for authorization under
this RGP and work may proceed with any special conditions imposed by the District Engineer, or designated
representative.
Examples of federal projects include but are not limited to works that were built by the Corps and are locally maintained
(such as local flood control projects) or operated and maintained by the Corps (such as locks and dams).
Section 14 of the Rivers and Harbors Act of 1899 and codified in 33 USC 408 (commonly referred to as "Section 408")
authorizes the Secretary of the Army, on the recommendation of the Chief of Engineers of the US Army Corps of
Engineers (USACE), to grant permission for the alteration or occupation or use of a USACE civil works project if the
Secretary determines that the activity will not be injurious to the public interest and will not impair the usefulness of the
project.
9. FEDERAL TRUST RESPONSIBILITY TO INDIAN TRIBES. Projects that the Corps finds to have potential to affect
tribal interests will be coordinated with the appropriate Indian Tribal governments. The Tribe's views and the federal
trust responsibility will be considered in the Corps evaluation. See General Condition 14.
10. OTHER AGENCY PERMIT REQUIREMENTS. Corps RGP-003-MN authorization does not eliminate the need for
other local, state or federal authorizations, including but not limited to, National Pollutant Discharge Elimination System
(NPDES) or State Disposal System (SDS) permits from the Minnesota Pollution Control Agency (MPCA), public waters
work permits from the Minnesota Department of Natural Resources (DNR), or Wetland Conservation Act authorizations
from the applicable local governmental unit.
11. OTHER AGENCY INFORMATION. Other agency information may assist project proponents in designing projects or
preparing information about their project. This information, such as Best Practices for Meeting DNR General Public
Waters Work Permit GP2004-0001: MN Department of Transportation Projects with Bridges, Culverts, or Outfalls, dated
(2017) RGP-003-MN Page 3 of 19
May 2011, is located on the DNR's website at www.dnr.state.mn.us.
12. DEFINITIONS.
Bioengineering - Bioengineering is the combination of biological, mechanical, and ecological concepts to control
erosion and stabilize shorelines through the use of vegetation or a combination of vegetation and construction materials.
Some examples of bioengineering techniques include: coir fabric, fascines, rootwad revetments, live pole cuttings, brush
mattresses, vegetated reinforced soil slope (VRSS), etc.
Compensatory Mitigation - The restoration (re-establishment or rehabilitation), establishment (creation), enhancement,
and/or, in certain circumstances, preservation of aquatic resources for the purposes of offsetting unavoidable adverse
impacts which remain after all appropriate and practicable avoidance and minimization measures have been
incorporated into the project.
Conversion or Exchange - Activities that involve converting one type of wetland or aquatic resource to another.
Conversion typically does not result in increased functions. For example, excavating a sedge meadow to create deep
marsh, impounding water over a forested wetland that drowns out the woody vegetation and replaces it with an aquatic
bed community, or placing a control structure on a stream to create an impoundment, may degrade the functions of the
existing wetland or aquatic resource and, if regulated, can trigger the requirement for compensatory mitigation to offset
adverse impacts and loss of functions of the previously existing wetland or aquatic resource.
Creation(Establishment) Activities that involve manipulating an area or constructing a wetland in an upland site
where wetlands have not historically existed.
Currently Serviceable - Useable as is or with some maintenance, but not so degraded as to essentially require reconstruction.
Enhancement - Enhancement involves activities or management techniques that result in improvement or a net
increase to specific functions(s) of an existing wetland or aquatic resource, such as invasive weed eradication or control,
prescribed burns, planting of native vegetation, or instream habitat structures. This increase in one or more functions
does not result in a gain in aquatic resource acres and may result in a decrease in other aquatic resource functions.
Work resulting in a change in type does not constitute enhancement.
Discharge of Dredged or Fill Material - Fill material (as defined in 33 CFR 323.2) means material placed in waters of
the United States where the material has the effect of:
(a) Replacing any portion of a water of the United States with dry land; or
(b) Changing the bottom elevation of any portion of a water of the United States.
Examples of fill material include, but are not limited to: rock, sand, soil, clay, plastics, construction debris, wood chips,
overburden from mining or other excavation activities, and materials used to create any structure or infrastructure in the
waters of the United States. The term fill material does not include trash or garbage.
Forested Wetlands - Forested wetlands include all wetlands that meet the technical criteria established by Eggers, S.D.
and D.M. Reed. 1997. [Wetland Plants and Plant Communities of Minnesota and Wisconsin. U.S. Army Corps of
Engineers, St. Paul District] for Coniferous Bog, Hardwood Swamp, Coniferous Swamp, or Floodplain Forest plant
community types. This definition includes areas that have been deforested within the last 5 years.
Historic Property - Any prehistoric or historic district, site (including archaeological site), building, structure, or other
object included in, or eligible for inclusion in, the National Register of Historic Places (NRHP) maintained by the
Secretary of the Interior. This term includes artifacts, records, and remains that are related to and located within such
properties. The term includes properties of traditional religious and cultural importance to an Indian tribe or Native
Hawaiian organization that also meet the National Register criteria (36 CFR 60).
Independent Utility - A test to determine what constitutes a single and complete project in the Corps regulatory
program. A project is considered to have independent utility if it would be constructed absent the construction of other
projects in the project area. Portions of a multi-phase project that depend upon other phases of the project do not have
independent utility. Phases of a project that would be constructed even if the other phases were not built can be
considered as separate single and complete projects with independent utility.
Invasive/Nonnative plant species - For the purposes of this RGP invasive and/or non-native plant species include but
(2017) RGP-003-MN Page 4 of 19
are not limited to: reed canary grass (Phalaris arundinacea), Canada thistle (Cirsium arvense), bull thistle (Cirsium
vulgare), smooth brome grass (Bromus inermis), giant ragweed (Ambrosia trifida), common ragweed (Ambrosia
artemisiifolia), quack grass (Elytrigia repens), black locust (Robinia pseudoacacia), sweet clovers (Melilotus alba and M.
officinalis), garlic mustard (Alliaria petiolata), flowering rush (Butomus umbellatus), yellow iris (Iris psuedacorus), crown
vetch (Coronilla varia) , birdsfoot trefoil (Lotus corniculatus), non-native honeysuckles (e.g., Lonicera x bella), non-native
buckthorns (Rhamnus cathartica and R. frangula), and purple loosestrife (Lythrum salicaria).
Note this list is provided primarily for informational purposes only and is applicable for project proponents developing
on-site compensatory mitigation plans; and for those proposing projects under categories I, J, M and N. This list is not a
General Condition for which all RGP-003-MN authorizations are subject.
Loss of Waters - Waters of the United States that are permanently adversely affected by filling, flooding, excavation, or
drainage because of the regulated activity. Permanent adverse effects include permanent discharges of dredged or fill
material that change an aquatic area to dry land, increase the bottom elevation of a waterbody, or change the use of a
waterbody. The acreage of loss of waters of the U.S. is a threshold measurement of the impact to jurisdictional waters
for determining whether a project may qualify for RGP-003-MN; it is not a net threshold that is calculated after
considering compensatory mitigation that may be used to offset losses of aquatic functions and services. The loss of
stream bed includes the linear feet of stream bed that is filled or excavated. Waters of the United States temporarily
filled, flooded, excavated, or drained, but restored to pre-construction contours and elevations after construction, are not
included in the measurement of loss of waters of the United States. Impacts resulting from activities eligible for
exemptions under Section 404(f) of the Clean Water Act (CWA) are not considered when calculating the loss of waters
of the United States.
Ordinary High Water Mark - The term ordinary high water mark means that line on the shore established by the
fluctuations of water and indicated by physical characteristics such as a clear, natural line impressed on the bank,
shelving, changes in the character of the soil, destruction of terrestrial vegetation, the presence of litter or debris, or
other appropriate means that consider the characteristics of the surrounding areas (33 CFR 328.3(e)).
Practicable Available and capable of being done after taking into consideration cost, existing technology and logistics
in light of the overall project purpose.
Preconstruction Notification - A written request submitted by the prospective permittee to the Corps for confirmation
that a particular activity is authorized by a general permit. The request may be a permit application, letter, or similar
document that includes information about the proposed scope of work, location, extent of resources in the project area,
and the projects anticipated environmental effects. A PCN may be voluntarily submitted in cases where PCN is not
required but the prospective permittee wants Corps confirmation that the activity is authorized by a general permit (See
section 4a under Terms and Provisions for PCN requirements).
Previously Authorized - For the purposes of this RGP, this refers to projects that have previously received
authorization under Section 404 of the CWA or Section 10 of the Rivers and Harbors Act of 1899. This includes projects
authorized by general permits that do not require a PCN but does not include projects constructed under CWA
exemptions, projects constructed prior to enactment of the CWA, or unauthorized fills.
Real Estate Subdivision - Any land that is divided for the purposes of disposition into two or more lots, parcels, units,
or interests.
Restoration - Restoration consists of the re-establishment or rehabilitation of sites that historically supported wetlands
or streams and frequently retain some wetland components (e.g., hydric soils) or stream processes even after manmade disturbances such as drainage, cropping or channelization. Re-establishment involves techniques for returning
wetland functions to a location where no wetland currently exists and generally results in a gain in wetland function and
acres. Rehabilitation involves repairing or increasing the functions of an existing, degraded wetland or stream and does
not result in a gain in wetland acres.
Reversion - The act of returning an area or part of the landscape to a previous land use condition (i.e. agricultural land
that is returned to agricultural production after the terms of a wetland enhancement agreement has expired).
Section 10 - Refers to Section 10 of the Rivers and Harbors Act of 1899. This act addresses activities in, over or under
navigable waters of the United States.
Shoreland (Wetland) Protection Zone For the purposes of RGP-003-MN, the term shoreland wetland protection
(2017) RGP-003-MN Page 5 of 19
zone includes areas defined under Minnesota Statute 103G.005, subdivision 15b. (https://www.revisor.mn.gov)
Single and Complete Project - For purposes of RGP-003-MN, the term, "single and complete project" means the total
project proposed. For example, if construction of a residential development or linear project such as a road or utility line
affects several different areas of waters/wetlands, the cumulative total of impacted waters of the U.S., including
wetlands, is the basis for deciding the project's total wetland/water impact. For "phased" developments, each phase
may constitute a single and complete project if it has independent utility and would accomplish its intended purpose
whether or not other phases were constructed.
Special Aquatic Site - Special aquatic sites are defined in the Environmental Protection Agency's Section
404(b)(1)Guidelines (40 CFR part 230) as those sites identified in subpart E. They are geographic areas, large or small,
possessing special ecological characteristics of productivity, habitat, wildlife protection, or other important and easily
disrupted ecological values. These areas are generally recognized as significantly influencing or positively contributing
to the general overall environmental health or vitality of the entire ecosystem of a region. Those most frequently found
in Minnesota are wetlands, riffle-pool complexes, and vegetated shallows.
Structure - An object that is arranged in a definite pattern of organization. Examples of structures include, without
limitation, any pier, boat dock, boat ramp, wharf, dolphin, weir, boom, breakwater, bulkhead, revetment, riprap, jetty,
artificial island, artificial reef, permanent mooring structure, power transmission line, permanently moored floating vessel,
piling, aid to navigation, or any other manmade obstacle or obstruction.
(2017) RGP-003-MN Page 6 of 19
ACTIVITIES AUTHORIZED BY
THE RGP-003-MN:
A. Maintenance activities.
Discharges of dredged or fill
material in waters of the U.S. or
work in/over/under Section 10
waters required for the repair,
rehabilitation or replacement of
any previously authorized,
currently serviceable structure or
fill, or any currently serviceable
structure or fill authorized by 33
CFR 330.3, that permanently
impacts not more than ½ acre of
waters of the U.S., including
wetlands, or 500 linear feet of a
stream in a single location, in
addition to the area that has
already been disturbed by the
structure or fill to be maintained.
This category authorizes
discharges for the repair,
rehabilitation, or replacement of
structures or fill that do not qualify
for the CWA Section 404(f)
exemption for maintenance.
The structure or fill to be
maintained is for its original
purpose or most recently
authorized modification. Minor
deviations to a structure,
configuration, or the area of fill
that is necessary to conform to
modern construction practices,
materials, construction codes or
safety standards is authorized.
Temporary structures, fills and
work necessary to conduct the
maintenance activity are
authorized. Temporary impacts
are not included in the ½ acre
limitation. Temporary impacts
must be kept to the minimum
necessary to complete the work.
Appropriate measures must be
taken to maintain normal
downstream flows and minimize
flooding to the maximum extent
practicable, when temporary
structures/work/discharges
including cofferdams, are
necessary for construction
activities, access fills or
dewatering of construction sites.
Temporary fills must consist of
clean fill materials, and be placed
in a manner that will not be eroded
by expected high flows.
Temporary fills must be removed
in their entirety and the affected
areas returned to pre-construction
contours and elevations. The
areas affected by temporary fills
must be re-vegetated with native,
non-invasive plant species, as
appropriate.
Projects to repair or replace
structures or fills destroyed by
storms, floods, fire or other
discrete events are included,
provided the work is commenced
or under contract to commence
within two years of the date that
the damage occurred.
This RGP category does not
authorize maintenance dredging
for the primary purpose of
navigation. The disposal of
excavated or dredged material
into a water of the U.S. obtained
from a maintenance dredging
operation is not authorized under
this RGP category. No new
stream channelization or stream
relocation work is authorized.
(Section 10 RHA / Section 404
CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN and receive
written confirmation that the
project is authorized by the
RGP-003-MN, if any of the
following criteria are met:
Impacts to waters of the U.S.,
including wetlands, exceed
0.10 acre; or the impact
amounts requiring mitigation
identified in General Condition
1 are exceeded; or the
structure or fill being
maintained or repaired is
more than 50 years old; or
activities are conducted
in/over/under waters covered
by Section 10 of the Rivers
and Harbors Act of 1899.
B. Bank Stabilization.
Discharges of dredged or fill
material in waters of the U.S., or
(2017) RGP-003-MN Page 7 of 19
work in/over/under Section 10
waters for bank stabilization
activities necessary for erosion
protection, such as vegetation
stabilization, sills, rip rap,
revetment, gabion baskets, stream
barbs, and bulkheads, provided
that no material is placed in
wetlands and the bank
stabilization activity is no more
than 500 feet in length. The
discharge shall not exceed an
average of one cubic yard per
running foot placed along the bank
below the plane of the ordinary
high water mark, unless the
activity consists primarily of
utilizing bioengineering techniques
to accomplish the stabilization.
No material shall be placed in any
location or in a manner that
impairs surface water flow. No
material shall be placed in a
location where it may be eroded
by normal or expected high flows.
Construction of temporary staging
areas and/or platforms in waters
of the U.S., including wetlands, is
not authorized. Materials that are
considered solid or hazardous
waste products under the MPCA
guidelines shall not be used. No
stream channelization is
authorized. (Section 10 RHA /
Section 404 CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN and receive
written confirmation that the
project is authorized by the
RGP-003-MN , if any of the
following criteria are met:
More than 50 feet of existing
bank is disturbed by grading
or reshaping; or activities are
conducted in/over/under
waters covered by Section 10
of the Rivers and Harbors Act
of 1899.
C. Utility Line Discharges.
Discharges of dredged or fill
material in waters of the U.S. or
work in/over/under Section 10
waters required for the
construction, maintenance and
repair of utility lines and
associated facilities, including:
1. Utility lines: Discharges of
dredged or fill material
associated with excavation,
backfilling or placement of
bedding material for the
construction or maintenance of
utility lines for a single and
complete project provided that
the area is restored to
preconstruction contours and
elevations.
A utility line is defined as any
pipe or pipeline for the
transportation of any gaseous,
liquid, liquefiable, or slurry
substance, for any purpose,
and any cable, line, or wire for
the transmission of electrical
energy, telephone, electronic
data, and radio or television
communication. The term
utility line does not include
activities which drain a water of
the United States, such as
drainage tile or french drains,
but does apply to pipes
conveying drainage from
another area.
Material resulting from trench
excavation may be temporarily
sidecast into waters of the U.S.
for up to 90 days during the
growing season (May 1 through
October 1), provided that the
material is not placed in such a
manner that it is dispersed by
currents or other forces.
Temporary fills that would
remain in place for longer
periods must be approved by
the District Engineer and must
comply with the PCN
requirements identified in
General Condition 6. In
wetlands, the top 6" to 12" of
the trench shall normally be
backfilled with topsoil from the
trench. Furthermore, the trench
shall not be constructed in such
a manner as to drain waters of
the U.S. (e.g. backfilling with
extensive gravel layers,
creating a French drain effect).
Utility line trenches can be
backfilled with clay blocks to
ensure that the trench does not
drain waters of the U.S. Any
exposed slopes and stream
banks must be stabilized
immediately upon completion of
the utility line crossing of each
water body.
2. Foundations for overhead
utility lines, utility poles or
anchors: Discharges of dredged
or fill material for the construction
or maintenance of foundations,
utility poles or anchors in waters
of the U.S., provided that the
foundations are the minimum
size necessary and separate
footings are used where feasible.
3. Utility line substation or
associated facilities: Discharges
of dredged or fill material for
construction of substation or
other facilities associated with a
utility line that permanently
impact not more than ½ acre of
waters of the U.S.
Temporary structures, fills and
work necessary to construct or
conduct the maintenance/repair
activity are authorized. This
includes the placement of
temporary construction mats and
mechanized land clearing
necessary for the construction,
repair or maintenance of utility
lines, substations and foundations,
provided that the cleared area is
kept to a minimum and preconstruction contours and
elevations are restored.
Temporary fill impacts must be
kept to the minimum necessary to
complete the work. Appropriate
measures must be taken to
maintain normal downstream
flows and minimize flooding to the
maximum extent practicable,
when temporary
structures/work/discharges
including cofferdams, are
necessary for construction
activities, access fills or
dewatering of construction sites.
Temporary fills must consist of
clean fill materials, and be placed
in a manner that will not be eroded
by expected high flows.
Temporary fills must be removed
in their entirety and the affected
(2017) RGP-003-MN Page 8 of 19
areas returned to pre-construction
contours and elevations. The
areas affected by temporary fills
must be re-vegetated, with native,
non-invasive plant species, as
appropriate. (Section 10 RHA /
Section 404 CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN and receive
written confirmation that the
project is authorized by the
RGP-003-MN , if any of the
following criteria are met:
The utility line that is in or
crosses waters of the U.S.
totals more than 500 feet in
length; or mechanized land
clearing of forested wetland or
permanent conversion of
forested wetlands would
occur; or activities are
conducted in/over/under
waters covered by Section 10
of the Rivers and Harbors Act
of 1899; or temporary fills
would remain in place in
excess of 90 days during the
growing seasion (May 1
through October 1).
D. United States Coast Guard
Approved Bridges. Discharges
of dredged or fill material
incidental to the construction of
bridges across navigable waters
of the U.S., including cofferdams,
abutments, foundation seals,
piers, and temporary construction
and access fills provided such
discharges have been authorized
by the U.S. Coast Guard as part of
the bridge permit. Causeway and
approach fills are not included.
(Section 404 CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN and receive
written confirmation that the
project is authorized by the
RGP-003-MN.
E. Return Water From Upland
Contained Disposal Areas.
Discharges associated with return
water. The return water from a
contained disposal area is
administratively defined as a
discharge of dredged material by
33 CFR 323.2(d), even though the
disposal itself occurs on the
upland area and does not require
a 404 permit.
The dredging activity may require
a section 404 permit (33 CFR
323.2(d)), and will require a
section 10 permit if located in
navigable waters of the United
States. (Section 404 CWA).
F. Oil spill/Hazardous
substance clean up. Discharges
of dredged or fill material in waters
of the U.S. or work in/over/under
Section 10 waters required for the
containment and cleanup of oil
and hazardous substances which
are subject to the National Oil and
Hazardous Substances Pollution
Contingency Plan, (40 CFR Part
300), provided that (1) the work is
done (a) in accordance with the
Spill Control and Countermeasure
Plan required by 40 CFR 112.3, or
(b) under the direction or oversight
of the federal on-scene
coordinator designated by 40 CFR
part 300, and/or (c) in accordance
with any existing State
contingency plan, and (2) provided
that the Regional Response Team
(if one exists in the area) concurs
with the proposed containment
and cleanup action. Discharges in
waters of the U.S. or work
conducted in/over/under Section
10 waters for such containment or
cleanup are authorized by this
RGP; however, all appropriate
governmental units, as well as the
Corps, shall be informed of any
such discharge or work as soon
as practical. (Section 10 RHA /
Section 404 CWA)
G. Structural Discharges.
Discharges of material such as
concrete, sand, rock, etc. into
tightly sealed forms or cells where
the material will be used as a
structural member for support for
standard pile supported structures
such as a utility pole foundation,
bridge support, or pier support.
This activity does not include
building foundations or other
structures such as pilings intended
for use as building supports. The
structure itself may require a
Section 10 RHA permit if located
in navigable waters of the United
States. (Section 404 CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN and receive
written confirmation that the
project is authorized by the
RGP-003-MN.
H. Completed Enforcement
Actions. Discharges of dredged
or fill material in waters of the U.S.
or any structures or work
in/over/under Section 10 waters:
(1) remaining in place or (2)
undertaken for mitigation,
restoration, or environmental
benefit in compliance with either:
(a) The terms of a signed written
Corps non-judicial settlement
agreement resolving a violation of
Section 404 of the Clean Water
Act and/or Section 10 of the
Rivers and Harbors Act of 1899,
or (b) the terms of a United States
Environmental Protection Agency
309(a) order on consent resolving
a violation of Section 404 of the
Clean Water Act, provided that:
(i) The settlement agreement
provides for environmental
benefits, to an equal or greater
degree, than the environmental
detriments caused by the
unauthorized activity to be
authorized by this RGP; and
(ii) The District Engineer issues a
verification letter authorizing the
activity subject to the terms and
conditions of this RGP and the
settlement agreement or order on
consent. The District Engineer's
verification letter shall include a
specified completion date and
may also include additional
conditions not inconsistent with
the settlement agreement or order
on consent; or
(c) The terms of a final federal
court decision, consent decree, or
settlement agreement resulting
from an enforcement action
(2017) RGP-003-MN Page 9 of 19
brought by the United States for
violation of Section 404 of the
Clean Water Act and/or Section
10 of the Rivers and Harbors Act
of 1899; or
(d) The terms of a final court
decision, consent decree,
settlement agreement, or nonjudicial settlement agreement
resulting from a natural resource
damage claim brought by a
trustee or trustees for natural
resources (as defined by the
National Contingency Plan at 40
CFR subpart G) under Section
311 of the Clean Water Act,
Section 107 of the Comprehensive
Environmental Response,
Compensation and Liability Act,
Section 1002 of the Oil Pollution
Act of 1990, or the Park System
Resource Protection Act at 16
U.S.C. 19jj, to the extent that a
Corps permit is required.
Compliance with the underlying
court decision, consent decree,
settlement agreement, or nonjudicial settlement agreement, or
order on consent is a condition of
this RGP. A violation of this RGP
occurs if the permittee does not
comply with the terms of this RGP
or the terms of the underlying
court decision, consent decree, or
judicial/non-judicial settlement
agreement, or order on consent.
This RGP does not apply to any
discharges occurring after the
date of the decision, decree, or
agreement that are not in
compliance with the underlying
order or settlement agreement
and for the purpose of mitigation,
restoration, or environmental
benefit. For purposes of this
authorization, the term "violation of
Section 404 of the Clean Water
Act" includes both violations of
Section 404 and violations of
Section 301 of the Act involving
discharges regulated under
Section 404. (Section 10 RHA
/Section 404 CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN and receive
written confirmation that the
project is authorized by the
RGP-003-MN.
I. Stream and Wetland
Restoration, Enhancement or
Establishment Activities.
Discharges of dredged or fill
material in waters of the U.S. or
work in/over/under Section 10
waters associated with the
restoration and enhancement of
former non-tidal wetlands and
riparian areas, the enhancement
of degraded wetlands and riparian
areas, the creation of wetlands
and riparian areas, or the
restoration and enhancement of
streams and open water areas,
provided that the discharges are:
(i) on non-Federal public lands or
private lands, in accordance with
the terms and conditions of a
binding stream or wetland
enhancement or restoration
agreement or wetland creation
agreement between the
landowner and the U.S. Fish and
Wildlife Service (FWS), the
Natural Resources Conservation
Service (NRCS), the Farm Service
Agency (FSA), the U.S. Forest
Service (USFS), or their
designated state cooperating
agencies; or (ii) voluntary stream
or wetland restoration or
enhancement, or wetland creation
actions documented by the NRCS
or USDA Technical Service
Provider pursuant to NRCS Field
Office standards; or (iii) on any
Federal land; or (iv) by or funded
by a state agency on any public or
private land. Authorized activities
include, but are not limited to, the
installation, removal and
maintenance of small water
control structures, dikes and
berms; the installation of current
deflectors; the enhancement,
restoration, or creation of riffle and
pool stream structures; the
placement of in-stream habitat
structures; modifications of the
stream bed and/or banks to
restore or create stream
meanders; the backfilling of
artificial channels and drainage
ditches; the removal of existing
drainage structures; the removal
of small dams; the construction of
small nesting islands; the
construction of open water areas;
activities needed to reestablish
vegetation, including plowing or
discing for seed bed preparation;
mechanized land-clearing to
remove non-native invasive,
exotic, or nuisance vegetation; the
removal of small dams; and other
related activities. This RGP
category cannot be used to
authorize activities for the
conversion of a stream to another
aquatic use, such as the creation
of an impoundment for waterfowl
habitat. This RGP category cannot
be used to channelize a stream
and does not authorize the
conversion of natural wetlands to
another aquatic use, such as
creation of an impoundment for
waterfowl where a forested
wetland or fresh meadow
previously existed. However, this
RGP category may be used to
relocate aquatic habitat types on
the project site, provided there are
net gains in aquatic resource
functions and values.
Reversion: This RGP category
also authorizes any future
discharge of dredged or fill
material associated with the
reversion of the area to its
documented prior condition and
use (i.e., prior to the restoration,
enhancement, or establishment
activities authorized under this
RGP category). The reversion
must occur within five years after
expiration of a limited term
wetland restoration or
establishment agreement or
permit, and is authorized in these
circumstances even if the
discharge occurs after this RGP
expires. The five-year reversion
limit does not apply to agreements
without time limits reached
between the landowner and the
FWS, NRCS, FSA, USFS, or an
appropriate state cooperating
agency. This RGP category also
authorizes discharges of dredged
or fill material in waters of the
United States for the reversion of
wetlands that were restored,
enhanced, or established on priorconverted cropland or on uplands,
(2017) RGP-003-MN Page 10 of 19
in accordance with a binding
agreement between the
landowner and FWS, NRCS, FSA,
USFS, or their designated state
cooperating agencies (even
though the restoration,
enhancement, or establishment
activity did not require a section
404 permit). The prior condition
will be documented in the original
agreement or permit, and the
determination of return to prior
conditions will be made by the
Federal agency or appropriate
state agency executing the
agreement or permit. Before
conducting any reversion activity
the project proponent or the
appropriate Federal or state
agency must notify the District
Engineer and include the
documentation of the prior
condition. Once an area has
reverted to its prior physical
condition, it will be subject to
whatever the Corps Regulatory
requirements are applicable to
that type of land at the time.
Except for the activities described
above, this RGP category does
not authorize any future discharge
of dredged or fill material
associated with the reversion of
the area to its prior condition. In
such cases a separate permit
would be required for any
reversion. (Section 10 RHA
/Section 404 CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN.
For activities under (i) and (ii)
above, the project proponent
must submit to the District
Engineer a copy of 1) the
binding stream or wetland
enhancement or restoration
agreement or wetland creation
agreement, including a project
description and project plans,
or (2) the NRCS or USDA
Technical Service Provider
documentation for the
voluntary stream or wetland
enhancement or restoration
action or wetland creation
action, including a project
description, project plans and
applicable standards.
J. Moist soil management for
wildlife. Discharges of dredged
or fill material in waters of the U.S.
that are associated with moist soil
management for wildlife, for the
purpose of continuing ongoing,
site-specific, wildlife management
activities where soil manipulation
is used to manage habitat and
feeding areas for wildlife. Such
activities include, but are not
limited to: the repair, maintenance
or replacement of existing water
control structures; the repair or
maintenance of existing dikes;
and, actions implemented to
impede succession, prepare seed
beds, or establish fire breaks.
Sufficient vegetated buffers must
be maintained adjacent to all open
water bodies, including streams,
to preclude water quality
degradation due to erosion and
sedimentation. This RGP category
does not authorize the
construction of new dikes, roads,
water control structures, or similar
features associated with the
management areas. This RGP
category does not authorize
converting wetlands to uplands,
impoundments or other open
water bodies. (Section 404
CWA)
K. Minor discharges.
Discharges of dredged or fill
material in waters of the U.S., or
activities in/over/under Section 10
waters, for a single and complete
project that would result in filling,
draining, excavating or inundating
not more than 400 square feet of
waters of the U.S., including
wetlands. This authorization may
NOT be used more than once by
the permittee or property owner so
as to impact more than 400
square feet of the same wetland
basin. (Section 10 RHA / Section
404 CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN if activities
are conducted in/over/under
navigable waters covered by
Section 10 of the Rivers and
Harbors Act of 1899.
L. Linear transportation
crossings. Discharges of
dredged or fill material in waters of
the U.S. or work in/over/under
Section 10 waters required for the
construction, expansion,
modification, or improvement of
linear transportation projects (e.g.
roads, highways, railways, and
taxiways). The discharge into
waters of the U.S. cannot exceed
0.5 acre of total permanent
impacts or 500 linear feet of
permanent impacts to a tributary
at a single location. The width of
the crossing must be limited to the
minimum necessary for the actual
crossing, and shall be culverted,
bridged or otherwise designed to
prevent the restriction of and
withstand the expected high flows,
prevent the restriction of low flows,
and provide for the movement of
organisms and the natural
transport of sediment. This RGP
category cannot be used to
authorize non-linear features that
may be associated with
transportation projects, such as
maintenance buildings, parking
lots or aircraft hangars.
Additionally, this RGP category
cannot be used to authorize
discharges associated with the
maintenance, reconstruction,
expansion, modification, or
improvement of existing public
road systems proposed by public
road authorities; such discharges
will be evaluated pursuant to
RGP-004-MN.
Temporary structures, fills and
work necessary to conduct the
construction activity are
authorized. Temporary impacts
are not included in the ½ acre
limitation. Temporary impacts
must be kept to the minimum
necessary to complete the work.
Appropriate measures must be
taken to maintain normal
downstream flows and minimize
flooding to the maximum extent
practicable, when temporary
structures/work/discharges
(2017) RGP-003-MN Page 11 of 19
including cofferdams, are
necessary for construction
activities, access fills or
dewatering of construction sites.
Temporary fills must consist of
clean fill materials, and be placed
in a manner that will not be eroded
by expected high flows.
Temporary fills must be removed
in their entirety and the affected
areas returned to pre-construction
contours and elevations. The
areas affected by temporary fills
must be re-vegetated with native,
non-invasive plant species, as
appropriate. (Section 10 RHA /
Section 404 CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN and receive
written confirmation that the
project is authorized by the
RGP-003-MN, if any of the
following criteria are met:
There is any discharge into a
special aquatic site, including
wetlands; or there is any
discharge into a stream or
river; or activities are
conducted in/over/under
waters covered by Section 10
of the Rivers and Harbors Act
of 1899.
M. Grassed waterways.
Discharges of dredged or fill
material associated with the
installation of grassed waterways
in waters of the U.S., including
wetlands, under the technical
supervision of NRCS, for the
purpose of erosion control on
agricultural land planted to annual
commodities for at least 3 of the
previous 5 years. Eligible sites
shall have less than 10% woody
vegetation. No annual cropping or
grazing shall take place after
construction, and mowing shall be
restricted to July 15-August 15.
The waterway shall be seeded
with a seed mix consisting of
native, non-invasive plant species
designed for swales and ditches.
(Section 404 CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN if the project
has segments with slopes of
less than 1%.
N. Wildlife Ponds. Discharges
of dredged or fill material for the
construction of wildlife ponds that
result in permanent and temporary
impacts, through filling,
excavation, or inundation, of up to
½ acre of waters of the U.S.,
including wetlands. Wildlife ponds
shall be constructed with irregular
shorelines, shallow side slopes
that are 8-foot horizontal to 1-foot
vertical or flatter, dominated by
water depths of 4 feet or less and
no deeper than 6.6 feet (2
meters). All excess excavated
material must be placed at an
upland location and no temporary
stockpiling of excavated material
is allowed in wetlands outside the
footprint of the pond site. The
primary purpose of this activity
must be wildlife habitat. The
creation of nesting islands is not
authorized and impacts to forested
wetlands is not authorized under
this category. This RGP category
does not authorize the discharge
of dredged or fill material into
streams. (Section 404 CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN and receive
written confirmation that the
project is authorized by the
RGP-003-MN.
O. Residential, Commercial,
Agricultural and Institutional
Developments. Discharges of
dredged or fill material in waters of
the U.S. or work in/over/under
Section 10 waters for a single and
complete project for the
construction or expansion of
residential, commercial,
agricultural, or institutional
operations or developments that
do not result in impacts to more
than ½ acre of waters of the U.S.
or 500 linear feet of a stream.
Activities authorized include
building foundations, building
pads, and attendant features.
Attendant features include, but are
not limited to: roads, parking lots,
garages, utility lines, geothermal
systems, yards, storm water
management facilities, culvert
installation, and recreational
facilities that are integral to the
development.
For any development or
subdivision, the aggregate total
loss of waters of the U.S.
authorized under this category
cannot exceed ½ acre. This RGP
category does not authorize
maintenance dredging for the
primary purpose of navigation.
The disposal of excavated or
dredged material into a water of
the U.S. obtained from a
maintenance dredging operation is
not authorized under this RGP
category. No new stream
channelization or stream
relocation work is authorized
under this RGP category.
(Section 10 RHA / Section 404
CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN and receive
written confirmation that the
project is authorized by the
RGP-003-MN.
P. [RESERVED]
Q. Compensatory Mitigation
Bank Construction. Discharges
of dredged or fill material in waters
of the U.S. associated with the
creation, rehabilitation or
restoration (via re-establishment
or enhancement) of non-tidal
wetlands in accordance with the
terms and conditions of an
approved wetland mitigation
banking instrument signed by the
Corps. Such activities include, but
are not limited to, the removal of
accumulated sediments; the
installation, removal and
maintenance of small water
control structures, dikes and
berms; the backfilling of artificial
channels and drainage ditches;
the removal of existing drainage
(2017) RGP-003-MN Page 12 of 19
structures; the construction of
open water areas; activities
needed to reestablish vegetation,
including plowing or discing for
seed bed preparation;
mechanized land-clearing to
remove undesirable vegetation;
and other related activities.
This RGP category includes
projects that have been planned,
reviewed and approved in
accordance with the St. Paul
District Army Corps of Engineers
compensatory mitigation policy
(http://www.mvp.usace.army.mil)
and federal mitigation banking
procedures (http://www.epa.gov).
Work authorized under this RGP
category cannot proceed until the
Corps has completed the
mitigation bank approval process
and provided the project
proponent with a signed banking
instrument. This RGP category
may be used to relocate aquatic
habitat types on the project site,
provided there are net gains in
aquatic resource functions and
values. This RGP category does
not authorize the reversion of an
area used for a compensatory
mitigation project to its prior
condition, since compensatory
mitigation is generally intended to
be permanent.
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN. (Section
404 CWA)
R. Scientific Measuring
Devices. Discharges of dredged
or fill material or work
in/over/under Section 10 waters in
conjunction with scientific devices
used to measure and record
scientific data, such as staff
gauges, water recording devices,
water quality testing and
improvement devices, and similar
devices. Small weirs and flumes
constructed primarily to record
water quantity and velocity are
also authorized provided the
discharge is limited to 150 square
feet. Upon completion of the
study, the measuring device and
any other structures or fills
associated with that device (e.g.,
anchors, buoys, lines etc.) must
be removed and the area restored
to pre-construction contours and
elevations. (Section 10 RHA /
Section 404 CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN. Written
confirmation from the Corps is
not required prior to the start
of work.
S. Survey Activities/Test
Drilling. Discharges of dredged
material in waters of the U.S. or
work in/over/under Section 10
waters in conjunction with survey
activities, such as core sampling
or mineral exploratory operations.
This RGP category authorizes the
construction of temporary pads,
provided the discharge does not
exceed 1/10 acre. Fill placed for
access roads to survey or drilling
sites is not authorized by the RGP
category. The RGP category
does not authorize any permanent
fill or structures, and the area
must be restored to preconstruction contours and
elevations. (Section 10 RHA /
Section 404 CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN. The PCN
must include a restoration
plan showing how all
temporary fills and structures
will be removed and the area
restored to pre-project
conditions. Written
confirmation from the Corps is
not required prior to the start
of work.
T. Restoration of Impacts from
Exempted Activities. Discharges
of dredged or fill material required
for the removal of work exempt
from Section 404 CWA regulation
under 33 CFR § 323.4, and
restoration of the areas impacted
by the exempt activities.
Restoration activities must restore
wetland functions and services to
the extent practicable. Activities
include but are not limited to, the
de-commissioning of farm and
forestry roads, removal or
cessation of minor drainage
activities and restoration of stock
ponds to original contours.
Restored areas must be seeded to
native, non-invasive plant species,
or actively farmed if the restored
area is part of an established (i.e.
on-going) farming operation.
(Section 404 CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN and receive
written confirmation that the
project is authorized by the
RGP-003-MN.
U. Temporary Access,
Structures or Dewatering.
Discharges of dredged or fill
material in waters of the U.S. or
work in/over/under Section 10
waters necessary for temporary
access fills or dewatering of
construction sites. Impacts must
be temporary and kept to the
minimum necessary to complete
the work. Activities authorized
include, but are not limited to
cofferdams and construction mats.
Appropriate measures must be
taken to maintain normal
downstream flows and minimize
flooding to the maximum extent
practicable. Fill material must be
clean and be placed in a manner
that will not be eroded by
expected high flows. Following
construction, the fill and structures
authorized by this RGP must be
removed in their entirety and the
affected areas returned to preconstruction contours and
elevations. The areas affected by
the fill or structures must be revegetated with native, noninvasive plant species, as
appropriate. (Section 10 RHA /
Section 404 CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
(2017) RGP-003-MN Page 13 of 19
submitting a PCN and receive
written confirmation that the
project is authorized by the
RGP-003-MN. The PCN must
include a restoration plan
showing how all temporary
fills and structures will be
removed and the area
restored to pre-project
conditions.
V. Time Sensitive Pipeline
Repair or Maintenance.
Discharges of dredged or fill
material in waters of the U.S. or
work in/over/under Section 10
waters required for the inspection,
repair, rehabilitation, or
replacement of any currently
serviceable structure or fill for
pipelines that have been identified
by the Pipeline and Hazardous
Materials Safety Administration's
Pipeline Safety Program (PHP) as
time-sensitive (see 49 CFR parts
192 and 195).
This RGP category does not
authorize the construction of new
pipelines. This RGP category
does not authorize the realignment of existing pipelines to a
new area. This RGP category
does not authorize any repair that
permanently impacts the flow or
circulation of waters of the U.S.,
such as an alteration or
channelization of streams.
(Section 10 RHA / Section 404
CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN and receive
written confirmation that the
project is authorized by the
RGP-003-MN.
The exclusion to work in a
calcareous fen or in wetlands
adjacent to or within 300 feet
of a state designated
calcareous fen do not apply to
this category if the project
proponent provides a MN
DNR approved fen
management plan specific to
the work.
W. Outfall Structures and
Associated Intake Structures.
Discharges of dredged or fill
material in waters of the U.S. or
work in/over/under Section 10
waters related to the construction
or modification of outfall structures
and associated intake structures,
where the effluent from the outfall
is authorized, conditionally
authorized, or specifically
exempted by, or that are
otherwise in compliance with
regulations issued under the
National Pollutant Discharge
Elimination System Program
(Section 402 of the Clean Water
Act). The construction of intake
structures is not authorized by this
RGP category, unless they are
directly associated with an
authorized outfall structure.
(Section 10 RHA / Section 404
CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN and receive
written confirmation that the
project is authorized by the
RGP-003-MN.
X. Beach Sand Blankets.
Discharges associated with the
placement of sand blankets in
waters of the U.S. or work
in/over/under Section 10 waters,
provided that no material is placed
in wetlands above the ordinary
high water mark (OHWM) and that
the sand blanket does not exceed
50 feet in width (parallel to the
shoreline) and 10 feet in length
(perpendicular to the shoreline)
waterward of the OHWM. This
RGP category does not authorize
material to be placed in areas of
existing emergent vegetation
without first obtaining a MN DNR
permit to control aquatic plants.
This RGP category does not
authorize material to be placed in
posted fish spawning areas. This
RGP category does not authorize
the use of a plant barrier or liner.
(Section 10 RHA /Section 404
CWA)
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN if a sand
blanket is proposed to be
placed in the same location
more than twice or activities
are conducted in/over/under
navigable waters covered by
Section 10 of the Rivers and
Harbors Act of 1899.
Notification Requirements:
The project proponent must
notify the District Engineer by
submitting a PCN if activities
are for a public boat ramp; or
conducted in/over/under
navigable waters covered by
Section 10 of the Rivers and
Harbors Act of 1899.
General Conditions
The limitation on sand
reapplication applies
regardless of the maintenance
provisions of Category A of
this RGP.
Y. Boat Ramps. Discharges of
dredged or fill material in waters of
the U.S. or work in/over/under
Section 10 waters related to the
construction of private boat ramps,
provided the activity meets all of
the following criteria:
a) The boat ramp does not exceed
12 feet in width or extend 10 feet
waterward of the ordinary high
water mark (OHWM);
b) No more than 5 cubic yards of
excavation and no more than 5
cubic yards of fill is used to
construct a stable base;
c) The ramp consists of crushed
stone, gravel, natural rock, precast concrete planks, clean sand,
steel matting, or other suitable
material; and
d) No material is placed in
wetlands above the OHWM.
Public boat ramps are subject to
the same criteria as private boat
ramps with the following
exceptions:
a) Public boat ramps may be up to
36ft wide and 30ft waterward of
the OHWM;
b) No more than 200 cubic yards
of excavation and no more than
80 cubic yards of fill may be used
to construct a stable base.
This RGP category does not
authorize material to be placed in
posted fish spawning areas.
(Section 10 RHA/ Section 404
CWA)
All RGP-003-MN authorizations
are subject to the following
General Conditions, as applicable,
in addition to any case-specific
conditions imposed by the District
Engineer. These conditions and
any special conditions must be
satisfied for any RGP
authorization to be valid:
1. Mitigation/Sequencing.
Discharges of dredged or fill
material into waters of the U.S.
must be minimized or avoided
to the maximum extent
practicable.
When determining the least
environmentally damaging
practicable on-site alternative,
impacts to all resources including
jurisdictional waters, nonjurisdictional waters, and high
quality uplands should be
considered.
Mitigation in all its forms (avoiding,
minimizing, or compensating) will
be required to the extent
necessary to ensure that the
adverse effects to the aquatic
environment are minimal.
Compensatory mitigation
requirements are determined on a
case by case basis and may be
required to reduce adverse effects
of a project, either temporary or
permanent, to the minimal level.
The District Engineer will
determine appropriate
compensatory mitigation
requirements in accordance with
Federal guidelines and
established District policy.
Generally, compensatory wetland
(2017) RGP-003-MN Page 14 of 19
mitigation shall be required for
projects that impact more than:
400 square feet in a shoreland
wetland protection zone,
2,000 square feet in a "lessthan-50 percent" county,
5,000 square feet in a "50%-to80%" county, and
10,000 square feet in a
"greater than 80%" county.
as shown on the attached map
labeled enclosure 1:
When the above project
thresholds are exceeded, the
compensatory mitigation
requirement applies to the
project's total wetland impacts,
including the threshold amounts
specified above. Use of Corpsapproved mitigation banks and inlieu fee procedures are generally
acceptable methods of providing
compensatory mitigation for small
projects having compensatory
mitigation requirements.
Compensatory mitigation shall be
designed to replace the functions
lost as result of the project. Where
certain functions and services of
waters of the U.S. are
permanently adversely affected as
a result of the authorized
discharge, such as the conversion
of a forested or scrub-shrub
wetland to a herbaceous wetland
in a permanently maintained utility
right of way, or are temporarily
affected, such as the temporary
conversion of forested or scrubshrub wetlands in a linear project
corridor, compensatory mitigation
may be required to reduce the
adverse effects of the project to
the minimal level.
For activities where compensatory
mitigation is required, project
proponents should include a
mitigation plan prepared in
accordance with 33 CFR Part 332,
and St. Paul District Policy.
(http://www.mvp.usace.army.mil).
The plan prepared should
describe the measures proposed
to ensure that the activity complies
with the Section 404(b)(1)
guidelines (40 CFR Part 230). In
cases where a Corps-approved
bank is proposed to be used, a
statement of intent to use the bank
is generally sufficient.
Compensatory mitigation required
by other Federal or state
programs may, but will not
necessarily, satisfy this CWA
requirement.
2. Navigation. (a) No activity
may cause more than a minimal
adverse effect on navigation. (b)
The permittee understands and
agrees that, if future operations by
the United States require the
removal, relocation, or other
alteration, of the structure or work
herein authorized, or if, in the
opinion of the Secretary of the
Army or authorized representative,
said structure or work shall cause
unreasonable obstruction to the
free navigation of the navigable
waters, the permittee will be
required, upon due notice from the
Corps of Engineers, to remove,
relocate, or alter the structural
work or obstructions caused
thereby, without expense to the
U.S. No claim shall be made
against the U.S. on account of any
such removal or alteration.
3. Suitable fill material. No
activity may use unsuitable
material (e.g., trash, debris, car
bodies, unprocessed asphalt,
etc.). All fill (including riprap)
authorized under this RGP, must
be free from toxic pollutants in
toxic amounts.
4. Proper maintenance. Any
authorized structure or fill shall be
properly maintained, including
maintenance to ensure public
safety.
5. Erosion and siltation
controls. Appropriate erosion and
siltation controls must be used
and maintained in effective
operating condition during
construction, and all exposed soil
and other fills, as well as any work
(2017) RGP-003-MN Page 15 of 19
below the ordinary high water
mark, must be permanently
stabilized at the earliest
practicable date. Work should be
done in accordance with stateapproved, published practices,
such as those defined in the
MPCA document, PROTECTING
WATER QUALITY IN URBAN
AREAS - BEST MANAGEMENT
PRACTICES FOR MINNESOTA.
Upon completion of earthwork
operations, all exposed slopes,
fills and disturbed areas must be
given sufficient protection by
appropriate means such as
landscaping, planting and/or
maintaining vegetative cover to
prevent subsequent erosion.
Cofferdams shall be constructed
and maintained so as to prevent
erosion into the water. If earthen
material is used for cofferdam
construction, sheet piling, riprap or
a synthetic cover must be used to
prevent dam erosion.
6. Removal of temporary fills.
PARAGRAPH A, ACTIVITIES
WITHOUT PCN
REQUIREMENTS: Temporary
discharges in waters of the U.S.,
including wetlands, must be
avoided and limited to the smallest
area and the shortest duration
required to accomplish the project
purpose. Temporary impacts may
not remain in place longer than 90
days of the growing season (May
1 through October 1). Before 90
days has lapsed, or the alternative
timeframe specified by the District
in writing, all temporary fills must
be removed in their entirety.
Temporary discharges must be
fully contained with appropriate
erosion control or containment
methods. If the temporary impact
would remain in place for longer
than 90 days a PCN is required
and the activity is subject to the
requirements and limitations
described in paragraph B of this
general condition.
PARAGRAPH B, ACTIVITIES
WITH PCN REQUIREMENTS:
Temporary discharges in waters of
the U.S., including wetlands, must
be avoided and limited to the
smallest area and the shortest
duration required to accomplish
the project purpose. The PCN
must specify how long the
temporary discharge will remain in
place and include a restoration
plan showing how all temporary
fills and structures will be removed
and the area restored to preproject conditions. All temporary
fills must be removed in their
entirety in accordance with the
PCN unless noted differently in
the verification letter provided by
the District. Temporary discharges
must be fully contained with
appropriate erosion control or
containment methods.
7. Obstruction of high flows. To
the maximum extent practicable,
discharges must not permanently
restrict or impede the passage of
normal or expected high flows or
cause the relocation of the water
(unless the primary purpose of the
fill is to impound waters).
8. Historic Properties, Cultural
Resources. (a) No activity which
may affect historic properties
listed or potentially eligible for
listing on the National Register of
Historic Places is authorized until
the District Engineer has complied
with the requirements of Section
106 of the NHPA. Federal project
proponents should follow their
own procedures for complying
with the requirements of Section
106 and provide documentation of
compliance with those
requirements. Information on the
location and existence of historic
resources can be obtained from
the State Historic Preservation
Office and the National Register of
Historic Places. (b) If cultural
resources, such as historic
structures or buildings, or
archaeological remains are
identified in the project area, or
are discovered during activities
authorized by this permit, you
must immediately stop work and
notify the District Engineer of what
you have found. The District will
initiate the Federal and state
coordination required to satisfy our
responsibilities under Section 106
of the NHPA. (c) Rock or fill
material used for activities
authorized by this permit must
either be obtained from existing
quarries or, if a new borrow site is
opened up to obtain fill material,
the Corps must be notified prior to
the use of the new site to
determine whether a cultural
resources survey of the site is
necessary.
9. Adverse effects from
impoundments. If the activity
creates an impoundment of water,
adverse effects on the aquatic
system caused by the accelerated
passage of water and/or the
restriction of its flow shall be
minimized to the maximum extent
practicable.
10. Migratory Bird breeding
areas. Activities in waters of the
U.S. that serve as breeding areas
for migratory birds, including
waterfowl, must be avoided to the
maximum extent practicable.
11. Aquatic life movements. No
activity may substantially disrupt
the movement of those species of
aquatic life indigenous to the
water body, including those
species that normally migrate
through the area, unless the
activity's primary purpose is to
impound water.
12. Spawning areas. Activities in
spawning areas during spawning
seasons must be avoided to the
maximum extent practicable.
Activities that result in the physical
destruction (e.g., through
excavation, fill, or downstream
smothering by substantial
turbidity) of an important spawning
area are not authorized.
13. Equipment. Heavy equipment
working in wetlands must be
placed on mats, or other
measures must be taken to
minimize soil disturbance.
Equipment should be clean and
free of greases, oils, fuels, and
sediments prior to working within
aquatic habitats.
(2017) RGP-003-MN Page 16 of 19
14. Tribal rights. No activity or its
operation may impair reserved
tribal rights, including, but not
limited to, reserved water rights
and treaty fishing and hunting
rights.
15. Wild and Scenic Rivers. No
activity may occur in a component
of the National Wild and Scenic
River System, or in a river officially
designated by Congress as a
"study river" for possible inclusion
in the system while the river is in
an official study status, unless the
appropriate Federal agency with
direct management responsibility
for such river has determined that
the proposed activity will not
adversely affect the Wild and
Scenic River designation or study
status. Information on Wild and
Scenic Rivers may be obtained
from the appropriate Federal land
management agency in the area
(e.g., National Park Service, U.S.
Forest Service, Bureau of Land
Management, U.S. Fish and
Wildlife Service.)
16. Water quality standards. All
work or discharges to a
watercourse resulting from
permitted construction activities,
particularly hydraulic dredging,
must meet applicable Federal,
State, and local water quality and
effluent standards on a continuing
basis.
17. Preventive measures.
Measures must be adopted to
prevent potential pollutants from
entering the watercourse.
Construction materials and debris,
including fuels, oil, and other liquid
substances, shall not be stored in
the construction area in a manner
that would allow them to enter the
watercourse as a result of
spillage, natural runoff, or flooding.
To the extent practicable and
appropriate, measures should be
taken to control and minimize the
spread of invasive species via
equipment transfer.
18. Spill contingency plan. A
contingency plan must be
formulated that would be effective
in the event of a spill. This
requirement is particularly
applicable in operations involving
the handling of petroleum
products. If a spill of any potential
pollutant should occur, it is the
responsibility of the permittee to
remove such material, to minimize
any contamination resulting from
this spill, and to immediately notify
the State Duty Officer at 1-800422-0798 and the U.S. Coast
Guard at 1-800424-8802.
19. Disposal sites. If dredged or
excavated material is placed on
an upland disposal site (above the
ordinary high-water mark or
wetland boundary), the site must
be securely diked or contained by
some other acceptable method
that prevents the return of
potentially polluting materials to
the watercourse by surface runoff
or by leaching. The containment
area, whether bulkhead or upland
disposal site, must be fully
completed prior to the placement
of any dredged material.
20. Water intakes/activities. No
activity may occur in the proximity
of a public water supply intake,
except where the activity is for
repair or improvement of the
public water supply intake
structures or adjacent bank
stabilization.
21. Endangered Species.
(a) No activity is authorized under
RGP-003-MN which is likely to
directly or indirectly jeopardize the
continued existence of a
threatened or endangered species
or a species proposed for such
designation, as identified under
the Federal ESA, or which will
directly or indirectly destroy or
adversely modify the critical
habitat of such species. No activity
is authorized under RGP-003-MN
which "may affect" a listed species
or critical habitat, unless Section 7
consultation addressing the
effects of the proposed activity
has been completed. Direct
effects are the immediate effects
on listed species and critical
habitat caused by the RGP-003MN activity. Indirect effects are
those effects on listed species and
critical habitat that are caused by
the RGP-003-MN activity and are
later in time, but still are
reasonably certain to occur.
(b) Federal agencies should follow
their own procedures for
complying with the requirements
of the ESA. If pre-construction
notification is required for the
proposed activity, Federal
permittees must provide the
district engineer with the
appropriate documentation to
demonstrate compliance with
those requirements. The district
engineer will verify that the
appropriate documentation has
been submitted. If the appropriate
documentation has not been
submitted, additional ESA section
7 consultation may be necessary
for the activity and the respective
federal agency would be
responsible for fulfilling its
obligation under Section 7 of the
ESA.
(c) Non-federal permittees must
submit a pre-construction
notification to the district engineer
if any listed species or designated
critical habitat might be affected or
is in the vicinity of the activity, or if
the activity is located in
designated critical habitat, and
shall not begin work on the activity
until notified by the district
engineer that the requirements of
the ESA have been satisfied and
that the activity is authorized. For
activities that might affect
Federally-listed endangered or
threatened species or designated
critical habitat, the preconstruction notification must
include the name(s) of the
endangered or threatened species
that might be affected by the
proposed activity or that utilize the
designated critical habitat that
might be affected by the proposed
work. The district engineer will
(2017) RGP-003-MN Page 17 of 19
determine whether the proposed
activity "may affect" or will have
"no effect" to listed species and
designated critical habitat. In
cases where the non-Federal
applicant has identified listed
species or critical habitat that
might be affected or is in the
vicinity of the activity, and has so
notified the Corps, the applicant
shall not begin work until the
Corps has provided notification
the proposed activities will have
"no effect" on listed species or
critical habitat, or until Section 7
consultation has been completed.
(d) As a result of formal or
informal consultation with the
FWS the district engineer may add
species-specific permit conditions
to the RGP-003-MN authorization.
(e) Authorization of an activity by
RGP-003-MN does not authorize
the "take" of a threatened or
endangered species as defined
under the ESA. In the absence of
separate authorization (e.g., an
ESA Section 10 Permit, a
Biological Opinion with "incidental
take" provisions, etc.) from the
FWS, the ESA prohibits any
person subject to the jurisdiction
of the United States to take a
listed species, where "take"
means to harass, harm, pursue,
hunt, shoot, wound, kill, trap,
capture, or collect, or to attempt to
engage in any such conduct. The
word "harm" in the definition of
"take'' means an act which
actually kills or injures wildlife.
Such an act may include
significant habitat modification or
degradation where it actually kills
or injures wildlife by significantly
impairing essential behavioral
patterns, including breeding,
feeding or sheltering.
(f) Information on the location of
threatened and endangered
species and their critical habitat
can be obtained directly from the
offices of the FWS on their web
page at http://www.fws.gov
is reached.
22. Bald and Golden Eagle
Protection Act and Migratory
Bird Treaty Act
PCN to the Corps is required for
projects within 0.5 miles (2,640
feet) of an eagle nest. There are
approximately 1300 bald eagle
nests distributed among 64 of
Minnesota's 87 counties. In
Minnesota, bald eagles typically
nest in old, large diameter trees
within approximately 500 feet of a
water body.
It is recommended that the project
proponent also contact the
USFWS TCFO (952-252-0092) if
the proposed project will disturb a
bald eagle or a bald eagle nest.
Projects involving the placement
of potentially lethal infrastructure
(communication towers, wind
turbines, transmission lines, etc.)
within two miles of a bald eagle
nest may warrant additional
review.
For more information concerning
the Bald and Golden Eagle
Protection Act or the Migratory
Bird Treaty Act refer to the
following website:
http://www.fws.gov
23. Expiration Date. Unless
otherwise specified in the District's
letter confirming your project
complies with the requirements of
this RGP, the time limit for
completing work authorized by
RGP-003-MN ends upon the
expiration date of this RGP-003MN. Activities authorized under
the RGP-003-MN that have
commenced construction or are
under contract to commence
construction, will remain
authorized provided the activity is
completed within 12 months of the
date of the RGP-003-MN
expiration, suspension, or
revocation;
whichever is sooner. If you find
that you need more time to
complete the authorized activity,
submit your request for a time
extension to this office for
consideration at least three
months before the expiration date
24. Maintenance and Transfer.
You must maintain the authorized
activity in good condition and in
conformance with the terms and
conditions of this permit. You are
not relieved of this requirement if
you abandon the permitted
activity, although you may make a
good faith transfer to a third party.
Should you wish to cease to
maintain the authorized activity or
should you desire to abandon it
without a good faith transfer, you
must obtain a modification of this
permit from this office, which may
require restoration of the area.
25. Inspection. You must allow
representatives from this office to
inspect the authorized activity at
any time deemed necessary to
ensure that it is being or has been
accomplished in accordance with
the terms and conditions of RGP003-MN.
26. State Section 401 Water
Quality Certification. The MPCA
has issued a 401 water quality
certification for the RGP-003-MN.
Permittees must comply with the
conditions specified in the
certification as special conditions
to this permit. For your
convenience, a copy of the
certification is attached.
27. Coastal Zone Management
consistency determination. The
State of Minnesota has
determined that the RGP-003-MN
is consistent with the CZM
program.
Further Information:
1. Congressional Authorities:
You have been authorized to
undertake the activity described
above pursuant to Section 404 of
the Clean Water Act (33 U.S.C.
1344) and/or Section 10 of the
Rivers and Harbors Act of 1899
(33 U.S.C. 403).
Federal, state, or local
authorizations required by law.
b. RGP-003-MN does not grant
any property rights or exclusive
privileges.
c. RGP-003-MN does not
authorize any injury to the
property or rights of others.
d. RGP-003-MN does not
authorize interference with any
existing or proposed Federal
project.
3. Limits of Federal Liability. In
authorizing work, the Federal
Government does not assume any
liability, including but not limited to
the following:
a. Damages to the permitted
project or uses thereof as a result
of other permitted or un-permitted
activities or from natural causes.
b. Damages to the permitted
project or uses thereof as a result
of current or future activities
undertaken by or on behalf of the
United States in the public
interest.
c. Damages to persons,
property, or to other permitted or
un-permitted activities or
structures caused by the activity
authorized by this permit.
d. Design or construction
deficiencies associated with the
permitted work.
e. Damage claims associated
with any future modification,
suspension, or revocation of this
permit.
4. Reliance on Project
Proponent's Data: The
determination by this office that an
activity is not contrary to the public
interest will be made in reliance on
the information provided by the
project proponent.
2. Limits of this authorization.
a. RGP-003-MN does not
obviate the need to obtain other
(2017) RGP-003-MN Page 18 of 19
5. Reevaluation of Decision. This
office may reevaluate its decision
on an authorization at any time the
circumstances warrant.
Circumstances that could require
a reevaluation include, but are not
limited to, the following:
a. The permittee fails to comply
with the terms and conditions of
this permit.
_________________________
Samuel L. Calkins
Colonel, Corps of Engineers
District Engineer
__________________________
Date
b. The information provided by
the permittee in support of the
preconstruction notification proves
to have been false, incomplete, or
inaccurate (see 4 above).
c. Significant new information
surfaces which this office did not
consider in reaching the original
public interest decision.
Such a reevaluation may result in
a determination that it is
appropriate to use the suspension,
modification, and revocation
procedures contained in 33 CFR
325.7 or enforcement procedures
such as those contained in 33
CFR 326.4 and 326.5. The
referenced enforcement
procedures provide for the
issuance of an administrative
order requiring the permittee to
comply with the terms and
conditions of the permit and for
the initiation of legal action where
appropriate.
6. This Office may also reevaluate
its decision to issue RGP-003-MN
at any time the circumstances
warrant. Circumstances that
could require a reevaluation
include, but are not limited to, the
following: significant new
information surfaces which this
office did not consider in reaching
the original public interest
decision. Such a reevaluation
may result in a determination that
it is appropriate to use the
suspension, modification, and
revocation procedures contained
in 33 CFR 325.7.
This permit becomes effective
when the Federal official,
designated to act for the Secretary
of the Army, has signed below.
(2017) RGP-003-MN Page 19 of 19