You can copy from here when filling out the rest of the page.
All Florida Counties. You are invited to a webinar on the Federal Supplement to Florida Joint Application form at 2 pm, March 1, 2017. Please fill in and include the form when submitting the Joint Application Form 62-330.060(1) (JA) to the Florida Department of Environmental Protection, Water Management District or delegated local program (DEP/WMD). Absence of the Supplement may cause us to pause review of your application to ask for this information.
Please fill in and include the enclosed Supplemental Information for Federal Permitting (Supplement) when submitting the Joint Application Form 62-330.060(1) (JA) to the Florida Department of Environmental Protection, Water Management District or delegated local program (DEP/WMD). The Supplement provides federal-only information fields not found in the JA. Absence of the Supplement may cause us to pause review of your application to ask for this information. Please keep the Supplement separate from the rest of the JA (electronically or hardcopy) so the DEP/WMD can easily forward to us the Supplement along with the applicable portions of the JA.
You are invited to a webinar on this topic at 2 pm, March 1, 2017 (flyer enclosed).
The Supplement is designed to provide, in combination with certain fields in the JA, the information required at 33 CFR 325.1(d) Content of application. Absence of this information may delay our issuing the Public Notice and/or coordination letters that are among our initial review steps toward determining whether to issue a Standard Permit (SP) or Letter of Permission (LOP). If you are seeking verification under a specific Nationwide Permit (NWP) or Regional General Permit (RGP), note that the terms and conditions of that NWP/RGP may require information not found on the Supplement and some fields may not be applicable.
If you transmit directly to the Corps your request for a Department of Army authorization, you must use the APPLICATION FOR DEPARTMENT OF THE ARMY PERMIT ENG Form 4345 if seeking an SP or LOP. For a NWP or RGP, we strongly encourage you use the ENG Form 4345 (because the standardized format speeds our initial processing steps) but note the specific NWP/RGP may require information not found on ENG Form 4345 and some fields may not be applicable. Enclosed are our mailing and electronic addresses.
If you fill in and include the ENG form 4345 when submitting either the Request for Verification of an Exemption, Form 62-330.050(1), or Notice of Intent to Use an Environmental Resource General Permit, Form 62-330.402(1), then the DEP/WMD will forward to us. That information will speed our initial review processes.
We welcome any questions or comments on the above. Please send them Jacksonville District, Regulatory Division, PO Box 4970, Jacksonville, Florida 32232, Attn: Bob Barron; by phone number at 904-232-2203, or by email at robert.b.barron@usace.army.mil.
SUPPLEMENTAL INFORMATION FOR
FEDERAL PERMITTING
PRIVACY ACT STATEMENT
Authorities: Rivers and Harbors Act, Section 10, 33 USC 403; Clean Water Act, Section 404, 33 USC 1344;
Marine Protection, Research, and Sanctuaries Act, Section 103, 33 USC 1413; Regulatory Programs of the
Corps of Engineers; Final Rule 33 CFR 320-332. Principal Purpose: Information provided on this form will
be used in evaluating the application for a permit. Routine Uses: This information may be shared with the
Department of Justice and other federal, state, and local government agencies, and the public and may be
made available as part of a public notice as required by federal law. Submission of requested information
is voluntary, however, if information is not provided the permit application cannot be evaluated nor can a
permit be issued.
Federal authorization for activities in, on, under, or over wetlands or other surface waters is often required
in addition to State of Florida authorization. Information on the federal program in Florida is available at the
US Army Corps of Engineers (Corps), Jacksonville District, Regulatory Division home page
(http://www.saj.usace.army.mil/Missions/Regulatory.aspx). The following information is necessary to
facilitate the federal review of work affecting waters of the United States, including wetlands, and should be
submitted in conjunction with Section A of the Joint Application for Individual and Conceptual Environmental
Resource Permit/Authorization to Use State-Owned Submerged Lands/Federal Dredge and Fill Permit.
1.
In addition to the information provided in Section A of the application, for all projects:
a. Identify the project purpose. (Describe the purpose and need for the proposed project. Why are
you proposing the work? How will you use the proposed structure(s); and/or, how will the proposed
fill area(s) be used?) Include a description of any related activities that may be developed as a
result of the proposed project. Provide the approximate dates you plan to both begin and complete
all work:
b. List all other certificates or approvals/denials received or pending from federal, state, or local
agencies for work affecting wetlands and/or other surface waters encompassed by the overall
project site: (You need not have obtained all other permits before applying for a Corps permit.)
Agency
Action Type
Supplemental Information for Federal Permitting
ID Number
Date Applied
Date Approved/Denied
Page 1 of 5
c. Is any portion of the work already completed:
Yes
No
If YES, describe the completed work (Provide any background information on any part of the
proposed project that has already been completed. Describe any area already developed,
structures completed, and any dredged or fill material already discharged, including the type of
material, volume in cubic yards, acres or square feet filled, and/or any wetland or other waterbody
affected. If the work was done under an existing Corps permit, please identity the file number of
the authorization if possible. Please note that the receipt of a permit from the Florida Department
of Environmental Protection or any Water Management District does not eliminate the requirement
for obtaining a Corps permit prior to commencing the proposed work.)
2.
Please be advised, the extent of federal jurisdiction and State of Florida jurisdiction may be different.
In addition to the information provided in Section C of the application, for projects proposing the
discharge of dredge or fill material in, on, or over wetlands or other surface waters:
a. Was the extent of waters of the United States, including wetlands, identified within the proposed
project site determined in accordance with the Corps of Engineers Wetland Delineation Manual
(1987) and the Regional Supplement to the Corps of Engineers Wetland Delineation Manual:
Atlantic and Gulf Coastal Plain Region (Version 2.0)?
YES
NO
(1)
If YES: Please provide the name and contact information for the person(s) who performed
the proposed delineation; and, submit a copy of the data sheets and any other information
gathered in support of the proposed delineation.
(2) If NO: Please provide the basis for any delineation submitted; and, be advised that the extent
of aquatic resources under federal jurisdiction may need to be determined before any
evaluation of work proposed can commence.
Information on the documents referenced above may be reviewed at the U.S. Army Corps of
Engineers, Jacksonville District, Regulatory Division Internet site.
b. Identify the specific reason/need for the proposed discharge (What will the discharge be used for
and why? Include activities that are linked to or reasonably related to the discharge)
Supplemental Information for Federal Permitting
Page 2 of 5
c. Identify the surface area (square feet or acres) of waters of the United States, including wetlands,
(as identified by federal regulations) that would be affected by the proposed discharge of fill
material; and, differentiate any temporary work area(s) from permanent work area(s). If more space
is needed, use additional sheets as necessary.
Square feet /
Acres of
temporary
permanent work
Square feet /
Acres of
temporary
permanent work
Square feet /
Acres of
temporary
permanent work
d. Identify the type of material that would be discharged and the amount (cubic feet or cubic yards) of
each type of material: (Please be sure this description agrees with your illustrations. Discharge
materials could include, but are not limited to, soil, rock, sand, clay, concrete, etc.)
Type:
Amount:
Type:
Cubic ft /
Cubic yds
Amount:
Cubic ft /
Cubic yds
e. Describe measures to avoid, minimize, and compensate any work affecting waters of the United
States, including wetlands. Use additional sheets as necessary. (Information regarding
compensatory mitigation requirements may be viewed on the Regulatory Division home page,
within the Source Book, under the heading Compensatory Mitigation; and, includes a copy of the
Final Compensatory Mitigation Rule (April 10, 2008) and Regulatory Guidance Letter 08-03:
Minimum Monitoring Requirements for Compensatory Mitigation Projects Involving the Restoration,
Establishment, and/or Enhancement of Aquatic Resources):
Supplemental Information for Federal Permitting
Page 3 of 5
For your information: Part 332, § 325.1, and Subpart J "Compensatory Mitigation for Losses of
Aquatic Resources" were added to 33 CFR and 40CFR Part 230, respectively, on April 10, 2008
(see Federal Register, Volume 73, No. 70, Pages 19594 through 19705 at:
http://water.epa.gov/lawsregs/guidance/wetlands/upload/2008_04_10_wetlands_wetlands_mitigat
ion_final_rule_4_10_08.pdf
and
http://www.saj.usace.army.mil/Portals/44/docs/regulatory/sourcebook/Mitigation/wetlands_mitigati
on_final_rule_4_10_08.pdf).
Part 332 and § 230.94(c) describe information that is to be in any compensatory mitigation plan
pursuant to Section 404 of the Clean Water Act.t. To avoid potential future conflicts between any
issued ERP permit and the corresponding federal permit, it is recommended that applicants
submitting a mitigation plan for an ERP permit design the plan to meet the requirements of Part
332 and § 230.94(c). This will also avoid the need to modify the issued ERP permit to comply with
any associated compensatory mitigation requirements subsequently imposed by the Corps. It is
highly recommended that applicants conduct pre-application meetings with both state and Corps
staff to discuss mitigation requirements prior to submitting an application for a permit.
f. Provide the complete names and full correct mailing address of the owners (public and private) of
properties contiguous to the overall project site where the work is proposed. Use additional sheets
as necessary. (This information may be obtained from your County Property Appraiser Office,
which is typically accessible on the Internet; this information is needed so that, if required, the
contiguous owners may be notified of the proposed activity (for example, through a public notice.)
1. Name:
Mailing Address:
City, State, Zip Code:
2. Name:
Mailing Address:
City, State, Zip Code:
3. Name:
Mailing Address:
City, State, Zip Code:
4. Name:
Mailing Address:
City, State, Zip Code:
5. Name:
Mailing Address:
City, State, Zip Code:
6. Name:
Mailing Address:
City, State, Zip Code:
g. Provide a set of project drawings that meet the requirements of the Corps of Engineers Standards
for Permit Application Drawings, attached.
Supplemental Information for Federal Permitting
Page 4 of 5
Corps of Engineers Standards for Permit Application Drawings
1. Location Map:
a. Show north arrow.
b. Project location must be clearly marked.
c. Show key landmarks and adjacent local roadways.
2. Plan View:
a. Show north arrow.
b. Show the dimensions of the applicant's property.
c. Show the dimensions of the work; dimensions of pier, length of bulkhead or shoreline
stabilization, dimensions of dredge area, dimensions of disposal area, dimensions of fill areas,
including bulkhead backfill.
d. Clearly show location and extent of all areas potentially meeting the criteria for waters of the U.S.,
including special aquatic sites (e.g., wetlands, sanctuaries and refuges, mudflats, vegetated shallows,
and riffle and pool complexes), and/or navigable waters. Each type of boundary (for example,
ordinary high water mark, mean high water, wetlands or other special aquatic sites, and high tide line)
must be clearly annotated and/or symbolized to ensure they are differentiable on the map.
e. Show the total plan of development for projects involving fill of wetlands. This includes the
proposed use of uplands as well as wetlands.
f. Show the location and dimensions of existing bulkheads and/or shoreline stabilization on adjacent
properties and if applicable, how the proposed work will tie into existing structures.
g. Show any existing structures (piers) in waters immediately adjacent to the activity and indicate the
distance the proposed work will be from existing structures.
h. Show the distance between the proposed activity and the nearest edge of Federal or other
navigation channels. If within 100' of a Federal navigation channel, X,Y coordinates of the most
waterward point utilizing NAD83 are required. See the Corps website at
http://www.saj.usace.army.mil/Portals/44/docs/regulatory/sourcebook/other_permitting_factors/S
etbackGuidance-final_Revised_Dec2013.pdf for more information on structures adjacent to the
Atlantic Intracoastal Waterway.
i. Show the width of the waterway at the work site.
j. Show the location of culverts under road crossings.
k. Indicate the relationship of the proposed work site to waters of the U.S., i.e., adjacent wetlands,
tidally influenced through culverts, etc.
l. Show legend for any relevant items (e.g. wetlands and/or other water types including the area,
project construction footprint (e.g., impacts to water of the U.S. fill versus excavation).
m. Indicate the location of cross-sectional views.
n. Show date prepared and name of preparer.
3. Cross-Sectional View
a. Show the high tide line and mean high water elevations or the ordinary high water mark in nontidal areas.
b. Show the existing contours and the proposed contours indicating existing and proposed
elevations.
c. Show the depth at the waterward end of pier.
d. Show the dimensions of work.
e. Show the disposal area including retention dikes and overflow.
f. Show the finished top elevation of the disposal site.
g. Show the top width, bottom width, and side slopes of road crossings. Include bottom and invert
elevations of culverts and the finished top elevation.
Supplemental Information for Federal Permitting
Page 5 of 5
Addresses for Submission of Permit Applications
in Florida to the
Regulatory Division, Jacksonville District, U.S. Army Corps of Engineers
Holmes
Jackson
Santa Rosa Okaloosa
Pensacola
Walton
Nassau
Gadsden
Leon
Bay
Hamilton
Madison
Liberty
Wakulla
Suwannee
Taylor
Gulf
Jacksonville District Web Page
http://www.saj.usace.army.mil/Missions/Regulatory/
Franklin
Mailing Address
Telephone:, Facsimile and Email* Address
Pensacola
Pensacola Permits Section
41 North Jefferson Street, Suite 301
Pensacola, FL 32502 5644
Telephone:: (850) 4393474 Facsimile: (850) 4338160
Email: CorpsjaxregNL@usace.army.mil
Click on this box to open a new email with your default mail client
Cocoa
Gainesville
Putnam
Gilchrist
Office
Panama City Permits Section
1002 West 23rd Street, Suite 350
Panama City, FL 324053648
Telephone:: 8507630717 Facsimile: (850) 8720231s
Email: CorpsjaxregNP@usace.army.mil
Click on this box to open a new email with your default mail client
Jacksonville Permits Section
P.O. Box 4970
Jacksonville, FL 322320019
Telephone:: (904) 2323286 Facsimile: (904) 2321904
Email: corpsjaxreg@usace.army.mil
Click on this box to open a new email with your default mail client
Cocoa Permits Section
400 High Point Drive, Suite 600
Cocoa, FL 329266662
Telephone: (321) 5043771 Facsimile: (321) 5043803
Email: northbranchapps@usace.army.mil
Click on this box to open a new email with your default mail client
Clay
Bradford
Permit Office locations and their geographic responsibilities shown by the map.
Jacksonville
Duval
Union
Lafayette
Dixie
Panama City
Jacksonville
Baker
Panama City
Alachua
Flagler
Levy
Marion
Volusia
Citrus
Lake
Seminole
Sumter
Hernando
Tampa
OSsceola
Polk
Indian River
Manatee
Hardee
St. Lucie
Highlands
Sarasota
DeSoto
Martin
Tampa Permits Section
10117 Princess Palm Drive, Suite 120
Tampa, FL 336108302
Telephone:: (813) 7697073 Facsimile: (813) 7697061
Email: Tampareg@usace.army.mil
Click on this box to open a new email with your default mail client
Gainesville
Gainesville Regulatory Office
2833 NW 41st St, Unit 130
Gainesville, FL 326066987
Telephone:: (352) 2647672 Facsimile: (352) 2647733
Email: Tampareg@usace.army.mil
Click on this box to open a new email with your default mail client
Ft Myers
Fort Myers Permits Section
1520 Royal Palm Square Boulevard Suite 310
Ft Myers, FL 339191036
Telephone: (239) 3341975 Facsimile: (239) 3340797
Email: SF.New.Applications@usace.army.mil
Click on this box to open a new email with your default mail client
Palm Beach
Gardens
Palm Beach Gardens Permit Section
4400 PGA Boulevard, Suite 500
Palm Beach Gardens, FL 334106557
Telephone:: (561) 4723504 Facsimile: (561) 6266791
Email: Applicationsp@usace.army.mil
Click on this box to open a new email with your default mail client
Miami
Miami Permits Section
9900 SW 107th Ave., Suite 203
Miami, FL 331762785
Telephone:: (305) 5267181 Facsimile: (305) 5267184
Email: SEAPPLS@usace.army.mil
Click on this box to open a new email with your default mail client
*For some offices, there may be a different email address for use by a particular agency to implement an applicable agreement.
Palm Beach
Gardens
Glades
Charlotte
Tampa
Cocoa
Orange
Pasco
Ft. Myers
Hendry
Palm Beach
Lee
Collier
Broward
Miami
Miami-Dade
Map version February 8, 2017
Join us for a webinar!
Streamlining the Process: Using the Supplemental
Information for Federal Permitting Form
March 1, 2017, 2-3 pm
The Florida Department of Environmental Protection, Florida's five water
management districts, and the US Army Corps of Engineers (Corps) have worked
together to create a "Supplemental Information for Federal Permitting" form to
be used in conjunction with the ERP joint application. Use of this form when
submitting ERP applications will help ensure that the Corps gets the information
that they need to process federal permits. Including this information is expected
to reduce the amount of additional information the Corps must request to
process federal permits. Please join us as we discuss the form, where to find it,
and how to submit it using the state agencies' electronic application portals.
Register here: https://attendee.gotowebinar.com/register/47130946354593026
The Supplemental Information for Federal Permitting Form may be found at:
http://www.dep.state.fl.us/water/wetlands/erp/forms.htm