PROPOSED CONSTRUCTION OF ENTERGY POWER STATION IN CALCASIEU PARISH
NAME OF APPLICANT: Entergy Louisiana, LLC, c/o CB&I, 4171 Essen Lane, Baton Rouge, Louisiana, 70809.
LOCATION: Located at Latitude 30.267378, Longitude -93.2896, The Lake Charles Power Station (LCPS) would be located within the boundary of the property on which the existing Entergy Louisiana, LLC (ELL) Roy S. Nelson Generating Plant (Nelson) is situated. Nelson is located in Calcasieu Parish, near Westlake, Louisiana.
DESCRIPTION: Proposed construction of a combined cycle power plant to include; Combined Cycle Gas Turbine equipment/building/enclosures, laydown and parking areas, road entrances, structures, buildings, tanks, sewage treatment plants, and supply lines, located on a 149.51 acre site. Further description of the LCPS is attached to this JPN. Approximately 77.67 acres of jurisdictional wetlands will be permanently, temporarily, and/or partially impacted through project construction. The applicant has proposed to purchase the required credits from an approved mitigation bank to offset any unavoidable losses to wetland functions caused by project implementation. The applicant has proposed to acquire pineflatwoods/savanna credits from an approved mitigation bank within the watershed, to offset in-kind and/or historically in-kind habitats at the site, should a DA permit be warranted.
JOINT PUBLIC NOTICE
March 20, 2016
United States Army
Corps of Engineers
New Orleans District
Regulatory Branch
7400 Leake Avenue
New Orleans, La. 70118-3651
State of Louisiana
Department of Environmental Quality
Post Office Box 4313
Baton Rouge, La. 70821-4313
Attn: Water Quality Certifications
(504) 862-2548/ FAX (504) 862-2574
Project Manager
Johnny Duplantis
Permit Application Number
MVN-2015-02516-WPP
(225) 219-3225/FAX (225) 325-8125
Project Manager
Elizabeth Hill
WQC Application Number
WQC # 170315-01
Interested parties are hereby notified that a permit application has been received by the New
Orleans District of the U.S. Army Corps of Engineers pursuant to: [ ] Section 10 of the Rivers
and Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or [X] Section 404 of the
Clean Water Act (86 Stat. 816; 33 USC 1344).
Application has also been made to the Louisiana Department of Environmental Quality, for a
Water Quality Certification (WQC) in accordance with statutory authority contained in Louisiana
Revised Statutes of 1950, Title 30, Chapter 11, Part IV, Section 2074 A(3) and provisions of
Section 401 of the Clean Water Act (P.L.95-17).
PROPOSED CONSTRUCTION OF ENTERGY POWER STATION IN CALCASIEU PARISH
NAME OF APPLICANT: Entergy Louisiana, LLC, c/o CB&I, 4171 Essen Lane, Baton Rouge,
Louisiana, 70809.
LOCATION: Located at Latitude 30.267378, Longitude -93.2896, The Lake Charles Power
Station (LCPS) would be located within the boundary of the property on which the existing
Entergy Louisiana, LLC (ELL) Roy S. Nelson Generating Plant (Nelson) is situated. Nelson is
located in Calcasieu Parish, near Westlake, Louisiana.
DESCRIPTION: Proposed construction of a combined cycle power plant to include; Combined
Cycle Gas Turbine equipment/building/enclosures, laydown and parking areas, road entrances,
structures, buildings, tanks, sewage treatment plants, and supply lines, located on a 149.51 acre
site. Further description of the LCPS is attached to this JPN. Approximately 77.67 acres of
jurisdictional wetlands will be permanently, temporarily, and/or partially impacted through project
construction. The applicant has proposed to purchase the required credits from an approved
mitigation bank to offset any unavoidable losses to wetland functions caused by project
implementation. The applicant has proposed to acquire pineflatwoods/savanna credits from an
approved mitigation bank within the watershed, to offset in-kind and/or historically in-kind
habitats at the site, should a DA permit be warranted.
-2-
The comment period for the Department of the Army Permit and the Louisiana Department of
Environmental Quality WQC will close 20 days from the date of this joint public notice. Written
comments, including suggestions for modifications or objections to the proposed work, stating
reasons thereof, are being solicited from anyone having interest in this permit and/or this WQC
request and must be mailed so as to be received before or by the last day of the comment
period. Letters concerning the Corps of Engineers permit application must reference the
applicant's name and the Permit Application Number, and be mailed to the Corps of Engineers
at the address above, ATTENTION: REGULATORY BRANCH. Similar letters concerning the
Water Quality Certification must reference the applicant's name and the WQC Application
number and be mailed to the Louisiana Department of Environmental Quality at the address
above.
The application for this proposed project is on file with the Louisiana Department of
Environmental Quality and may be examined during weekdays between 8:00 a.m. and 5:00 p.m.
Copies may be obtained upon payment of costs of reproduction.
Corps of Engineers Permit Criteria
The decision whether to issue a permit will be based on an evaluation of the probable
impacts, including cumulative impacts of the proposed activity on the public interest. That
decision will reflect the national concern for both protection and utilization of important
resources. The benefit which reasonably may be expected to accrue from the proposal must be
balanced against its reasonably foreseeable detriments. All factors which may be relevant to the
proposal will be considered including the cumulative effects thereof; among those are
conservation, economics, aesthetics, general environmental concerns, wetlands, historic
properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation,
shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy
needs, safety, food and fiber production, mineral needs, considerations of property ownership
and, in general, the needs and welfare of the people.
The U.S. Army Corps of Engineers is soliciting comments from the public, federal, state, and
local agencies and officials, Indian Tribes, and other interested parties in order to consider and
evaluate the impacts of this proposed activity. Any comments received will be considered by the
U.S. Army Corps of Engineers to determine whether to make, modify, condition, or deny a permit
for this proposal. To make this decision, comments are used to assess impacts on endangered
species, historic properties, water quality, general environmental effects, and other public
interest factors listed above. Comments are used in the preparation of an Environmental
Assessment and/or an Environmental Impact Statement pursuant to the National Environmental
Policy Act. Comments are also used to determine the need for a public hearing and to
determine the overall public interest of the proposed activity.
No properties listed on the National Register of Historic Places are near the proposed work.
The possibility exists that the proposed work may damage or destroy presently unknown
archeological, scientific, prehistorical, historical sites, or data. Copies of this notice are being
sent to the State Archeologist and the State Historic Preservation Officer.
-3-
Our initial finding is that the proposed work would neither affect any species listed as
endangered by the U.S. Departments of Interior or Commerce, nor affect any habitat designated
as critical to the survival and recovery of any endangered species. Utilizing Standard Local
Operating Procedure for Endangered Species in Louisiana (SLOPES), dated October 22, 2014,
between the U.S. Army Corps of Engineers, New Orleans and U.S. Fish and Wildlife Service,
Ecological Services Office, the Corps has determined that the proposed activity would have no
effect on any listed species.
This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the
Magnuson-Stevens Fishery Conservation and Management Act. The applicant's proposal would
result in the destruction or alteration of 0.00 acre(s) of EFH utilized by various life stages of red
drum and penaeid shrimp. Our initial determination is that the proposed action would not have a
substantial adverse impact on EFH or federally managed fisheries in the Gulf of Mexico. Our
final determination relative to project impacts and the need for mitigation measures is subject to
review by and coordination with the National Marine Fisheries Service.
If the proposed work involves deposits of dredged or fill material into navigable waters, the
evaluation of the probable impacts will include the application of guidelines established by the
Administrator of the Environmental Protection Agency. Also, a certification that the proposed
activity will not violate applicable water quality standards will be required from the Department of
Environmental Quality, before a permit is issued.
Any person may request, in writing, within the comment period specified in this notice, that a
public hearing be held to consider this application. Requests for public hearings shall state, with
particularity, the reasons for holding a public hearing.
You are requested to communicate the information contained in this notice to any other
parties whom you deem likely to have interest in the matter.
Darrell S. Barbara
Chief, Western Evaluation Section
Regulatory Branch
Attachments
ATTACHMENT 1
LAKE CHARLES POWER STATION PROJECT
1.0
Project Description
The Lake Charles Power Station (LCPS) is a proposed combined cycle power plant that will be located
within the boundary of the property on which existing Entergy Louisiana, LLC (ELL) Roy S. Nelson
Generating Plant (Nelson) is situated. Nelson is located in Calcasieu Parish near Westlake, Louisiana
(Figure 1).
Entergy is proposing to install two MHPSA 501GAC "G" Class combustion turbine generators (CTGs),
two heat recovery steam generators (HRSGs) with duct firing, and one steam turbine generator (STG) in a
2x1 Combined Cycle Gas Turbine (CCGT) configuration. The two gas turbines will be referred to as Unit
1A and 1B. The combustion turbines will use natural gas as its only fuel source. The steam turbine (Unit
1C) will receive steam from the combustion turbine flue gas. The LCPS has a predicted net output capacity
of a nominal 994 MW at ISO conditions with supplemental duct firing. The combustion turbine generators
will be connected to the existing 138 kV Nelson Switchyard. The steam turbine generator will connect to
the existing 230 kV Nelson switchyard.
Entergy is requesting Section 404 coverage for the construction of LCPS.
The LCPS project will involve the following:
·
·
·
·
·
·
·
·
·
·
·
·
·
Construct two new LA 379 (River Road) entrances and roads to LCPS
Construct laydown areas and parking lots
Construct retention basin
Install electrical duct bank, raw water line, potable water line, flocculant line, and treated
wastewater line
Install construction power transformer
Install 18-inch diameter Augered Cast-In-Place (ACIP) piles
Install underground utilities
Install foundations for all structures, buildings, and tanks
Install fuel gas supply line
Install water well for potable water
Install Package Sewage Treatment Plant (STP)
Install new intake pumps with filtered intake from existing Sabine River Authority (SRA) Makeup
Water Pond
Install CCGT equipment, enclosures, and buildings
The area of disturbance for these activities is shown on Figure 2A and Figure 2B. Details regarding the
LCPS project are provided in Section 2.0 below. A list of all excavations and fill for each project activity
are provided in Table 1.
1
Table 1: Structures and Materials for the LCPS Project
Project Component
Fill
Excavation Reference Figure(s)
cubic yards cubic yards
ACIP
6,126
6,126 7A, 7B
Utilities in Power Block
92,701
92,701 8H
Construction Transformer
39
0 5
Deep Excavations
141
291 8A, 8B, 8C, 8D, 8E, 8F, 8G
Ditches
8,465
0 17, 19A, 19B
Security Fence
75
75 2B
Flocculant Line
25
56 11
Foundations
15,668
0 14C
Fuel Supply Lateral Line
1,425
4,044 13A, 13B
Oil/Water Separator Process and Storm
58
200 8E, 16D
Parking, Laydown Areas, Etc.
72,687
65,174 2A, 2B
Potable Water
4
21 8H
Power Poles Steel and Timber
28
28 2A, 2B, 2C, 6, 18A, 18B
Raw Water/Duct Banks/Wastewater
991
2,778 8H, 9A, 9B, 10A, 10B
Roadways
12,059
3,630 2A, 2B
Sewer Line
92
328 8H
Spoils Pile
4,941
0 4
Storm Water Drainage
1,359
3,242 16A, 16B, 16C, 16D
Storm Water Retention Pond
0
29,631 2A, 2B, 16E
Water Well
3
23 12
TOTAL
216,891
208,353
2.0
Details of Lake Charles Power Station Project
2.1
Laydown Areas, Parking Lots and Roads
Roadway construction for the new power plant will consist of a main entrance road from Houston River
Road to the power plant and a construction parking entrance road that loops around the laydown area to the
construction parking lot. Additionally, service and maintenance roads to all major equipment or areas will
be serviced with limestone (Figure 2B).
New entrance roads will be constructed from LA 379. The first 50 feet of each road will be constructed of
concrete. A 24-inch reinforced concrete pipe (38 feet) will be installed in the existing ditch where each
entrance crosses (Figure 3A). All roads will be finished with approximately 2 to 3 inches of coarse
aggregate over 8 inches of aggregate and a geotextile fabric (Figure 3B). The road will be constructed 24
feet wide with 2-foot shoulders. The new entrance roads will accommodate employee vehicles and
construction deliveries.
A security guard house and gate will be constructed at the main entrance where all traffic will be checked
in by security prior to entering the facility. Employees will also use this entrance road as a means of ingress
and egress from the employee parking areas. A new 8-foot high security fence will be installed around the
perimeter of LCPS.
2
The entire power block area within the loop road not otherwise surfaced will be surfaced with crushed rock.
Construction parking and laydown areas will be covered with crushed rock or gravel surfacing.
Figure 2A and 3A denotes the limits of the parking areas and the laydown area. Approximately 8 inches
of aggregate will be installed in the laydown and parking areas.
2.2
Spoils Pile
Spoils will be stockpiled on the east side of the laydown area. The spoils will be placed as to not interfere
with drainage of the immediate areas. The location of the spoils pile and details are shown on Figure 4.
Silt fencing will be installed around the spoils area and drainage will be directed to the west via surface
flow.
Temporary spoils piles will be generated from utility installations. The excavated material will be utilized
to backfill the excavations/trenches. Unsuitable and excess spoils will be placed on the spoils pile.
2.3
Construction Power Transformer and Power Lines
A 3,000 kVA construction power transformer and power lines will be installed prior to site mobilization.
The power transformer will be installed southwest of the Power Block of the LCPS (Figure 2B). The
transformer slab will be a three-phase transformer slab structure (Figure 5). An overhead power line
supported by 18-inch diameter timber poles will be installed to provide power to the transformer. The
timber pole will be installed 8 feet below the ground surface (Figure 6) and an underground line (30-inch
trench) will be installed from the transformer to provide power to the site trailers and other services. The
locations of the overhead and underground lines are shown on Figure 2B.
2.4
ACIP Piles
Due to the soft soils conditions on site, heavily loaded plant equipment and structures will be supported on
pile foundations. ACIP piles are expected to be utilized. These ACIP piles will be used for the CTG,
HRSG, and STG foundations along with a select few other foundations (Figure 7A). The remaining
foundations for the Water Tanks, buildings and smaller equipment will be shallow foundations bearing on
native soil.
A typical pile section is shown on Figure 7B. Figure 7B also provides a schedule indicating the number
of piles to be used for all equipment that will be on pile supported foundations. Approximately, 1,294 18inch piles, 80 feet deep, are estimated to be required to support structures and equipment. ACIP piles will
be installed using a process that provides continuous grout pressure out from the borehole and on curing
will have an intimate bond with the surrounding soils providing little or no pathway for flow along the pilesoil interface.
Installation of piles will adhere to the American Concrete Institute (ACI) Specifications for Structural
Concrete (ACI 301).
Spoils generated during the ACIP pile installation will be placed in the spoils pile located on the eastern
side of the Power Block (Figure 4). A pile subcontractor will mobilized to install the piles in accordance
with engineering drawings and specifications.
2.5
Underground Utilities
Areas of deep excavation for the installation of the water treatment building sump, condensate pumps sump,
water wash sump, HRSG blowdown sump, oil/water separator, cooling tower basin, and circulating water
3
lines are shown on Figure 8A. A plan and section view of deep excavations are shown on Figures 8B
through 8G.
The raw water line, potable water line, electrical duct bank, and treated wastewater line will originate
outside of the Power Block.
A 16-inch high density polyethylene (HDPE) raw water line will be installed from a new pump structure
installed adjacent to the existing SRA pond to the Power Block (Figure 9A). A new 36-inch x 30-inch
electrical duct bank will run parallel to the raw water line. The location, section, and details are shown on
Figures 9B. Section 2.6 discusses the modification to the cooling water intake on the SRA pond.
The 12-inch HDPE treated wastewater line runs from the Power Block to an existing drainage ditch (Figure
10A). A new 21-inch x 21-inch electrical duct bank will run parallel to the wastewater line. Figure 10B
shows the wastewater line in cross-section.
A new 1-inch polyethylene flocculant line will be installed to treat the raw water at the SRA pond. Figure
11 shows the location, section, and details of the flocculant line.
The Power Block area will be excavated to an average depth of 6 feet to accommodate utility installation.
The utilities that will be installed include closed cooling water, service and instrument air, storm water,
service water, fire protection water, demineralized water, plant drain, raw water, and electrical duct banks.
Excavations will be 12 feet in depth at the location that the underground utilities intersect with the
circulating water lines (Figure 8H).
2.6
Cooling Water Intake Structure Modification
Dual raw water pumps will be installed at the new intake structure on the SRA pond (Figure 9A). The raw
water pumps provide water for various plant uses and makeup water to the circulating water system. The
circulating water system will include two 50% capacity vertical pumps mounted in a sump incorporated in
the basin of the cooling tower. The pumps will be installed in a concrete structure with the appropriate
access and clearances for mobile cranes to remove the pumps for maintenance.
2.7
Water Well Installation
A new water well will be installed south of the Power Block near the Control Building to provide potable
water to LCPS (Figure 12). The 4-inch polyvinyl chloride (PVC) water well will be installed to
approximately 400 feet into the Chicot aquifer. The water will be installed by a registered driller. The
location and details are shown on Figure 12. Installation of the water well will produce drill cuttings. Drill
cuttings will be placed in the spoils pile discussed in Section 2.2. A 3-inch HDPE potable water line will
be installed above grade from the new water well to the Water Treatment to the Power Block.
2.8
Fuel Gas Piping
The LCPS Units 1A and 1B will connect to a 20-inch fuel gas line that will run from the metering station
to a proposed connection at the eastern property boundary. The proposed gas supply will be from an
existing gas pipeline located approximately 11 miles north of the Nelson Plant Facility. The proposed gas
supply line will be constructed by the supplier and will be located within an existing gas corridor (Figure
13A and 13B).
For access, ditches will be bridged and where the pipeline crosses Waters of the U.S., an open cut excavation
method will be used. Appropriate best management practices (BMPs) will be implemented to minimize
impacts. Construction will also include metering stations, surface interconnect sites, 24-foot wide access
roads, and temporary workspaces. The pipeline will be constructed with 6 feet of cover over the top of pipe
4
within the pipeline easement. Inside of the fenced metering station, the pipe will be installed with a
minimum 3 feet of cover over the top of pipe. Sections and details of the fuel gas piping installation are
show on Figure 13B.
2.9
LCPS Power Block
The LCPS Power Block will include the major equipment for the CCGT unit (Figures 14A and 14B). The
CCGT unit will consist of two CTGs, HRSGs, and one STG. A list of equipment to be installed is found
on Figure 14B. ACIP pile supported foundations will be used for the CTG, HRSG, and STG along with a
select other foundations. The remaining foundations for the Cooling Tower, Water Tanks, buildings and
smaller equipment will be shallow foundations. The arrangement of the foundations for the Power Block
equipment is provided on Figure 14C.
Approximately 37 components of the HRSG, CTGs, and STG equipment will be hauled from a barge
landing in the city of Westlake. Self-propelled modular transporters will be used to transport all of the
components.
2.10
Drainage and Erosion Control
Existing swales and ditches will be used to allow for proper drainage of all roads, parking areas, and the
laydown area. Storm water culverts will be provided at the entrance and exit drives of all laydown and
parking areas.
Silt fencing will be installed throughout the project site to control storm water and will be installed around
all excavations and embankment areas. Temporary fabric inlets or hay bales will be used to control storm
water entering catch basins. Typical silt fencing details and fabric inlets are shown on Figure 15.
Storm water drainage in the Power Block is designed for a 25 year, 24-hour storm return period. The LCPS
storm water system will operate independently from the Operating Facility system. The permanent storm
water drainage system for the project shall consist primarily of catch basins and underground piping in the
power block area with surface drainage in the other plant areas and culverts at the perimeter loop roads.
Underground piping material will typically be reinforced concrete pipe (RCP) unless code requires another
material. Roads which cross over open channels will be constructed with culverts to pass the design flow.
Culverts will be constructed of reinforced concrete or HDPE pipe.
Surface runoff will be collected via the storm water drainage system and processed through two storm water
oil/water separators (OWS). The discharge of the storm water OWS will be directed to a retention basin
and will discharge into an existing site drainage ditch that flows into the Houston River. The OWS will be
capable of processing the "first flush" only. The discharge of the storm water OWS will be directed to the
existing storm water drainage ditch system. Storm water drainage structure locations are shown on Figure
16A and Figure 16B. Figure 16C shows drainage details and schedule of catch basins and piping. Plan
and section views of the OWS is shown on Figure 16D. The Retention Basin Plan and Section views are
shown on Figure 16E.
A section of the existing drainage ditch east of the Power Block will be upgraded with rip rap for
approximately 2,761 feet between the LCPS discharge point and the haul road (Figure 17).
2.11
Sewer Treatment Plant
A new Sewer Treatment Plant (STP) will be installed for LCPS in accordance with Louisiana Department
of Health and Hospitals (DHH). Sewage will travel by gravity to the lift station located west of the STP
before treatment at the new STP. The effluent will discharge to the retention basin. Refer to Table 1 for
5
volumes of excavation and fill for the sewer line. The STP and lift station will be located near the
Administration Building (Figure 2B).
2.12
Radial Generation Interconnection Tie Lines
Once constructed, LCPS will be connected to the existing Nelson 138 kV and 230 kV switchyards. Radial
generation interconnection tie lines will be installed on 22 supporting structures (Figure 18A).
Each structure will consist of an 8-foot diameter concrete or steel pole attached to an 8-foot diameter steel
pile (Figure 18B). The steel piles will be installed using a vibrator hammer to drive the piles to a depth of
approximately 60 feet. The pile will be cleaned out with an auger and filled with concrete. The first 10
feet of each pile may be hydro-vacuumed to identify potential obstructions. Hydro-vacuuming will also be
used to install the associated anodes. Approximately eight anodes will be installed at each pole structure
for corrosion protection. A 1-foot diameter hole will be hydro-vacuumed to a maximum depth of 10 feet.
Once the anode is installed the hole will be backfilled with sand.
Hydro-vacuuming uses water to excavate an area and will produce a slurry of soil and water. The slurry
spoils will be collected into a vacuum truck as they are generated. The slurry spoils will be disposed in the
SRA dredge disposal area north of the SRA pond (Figure 2B).
3.0
Project Purpose and Need
Entergy Services, Inc. performs system planning functions for all Entergy operating companies. In
executing this function, an integrated resource plan is developed that defines the regional load projections
and determines the type and quantity of generation needs to meet system reliability criteria. The Lake
Charles area was identified as a region that requires additional baseload capacity due to the region's
industrial renaissance.
The proposed LCPS is scheduled to begin construction November 1, 2017. All work is expected to be
completed by May 1, 2020.
4.0
Impacts to Waters of the US, Avoidance, and Mitigation
The location of LCPS was selected to avoid high quality wetlands within the property boundaries of the
Nelson facility. However, the construction of the LCPS will impact low to moderate quality wetlands. In
addition to siting the LCPS to avoid high quality wetlands, the layout of the LCPS was modified to avoid
wetlands near LA 379 (Figure 19A and Figure 19B).
On November 12, 2015, a wetland determination request was submitted to the U.S. Army Corps of
Engineers for approximately 230 acres that included the LCPS project area of interest. A Preliminary
Jurisdictional Determination (PJD) was received on October 27, 2016 (Account Number MVN-201502516-SK) (Attachment 4). Based on project engineering designs, it was determined that three small areas
outside of the issued PJD (MVN-2015-02516-SK) were needed to incorporate a pipeline, utility line rightof-way, and an existing drainage ditch. On November 20, 2016 another wetland delineation was performed
on the needed additional areas. A report is being prepared for submittal to the USACE New Orleans District
to request a PJD amendment for the additional project areas. The data submitted in the issued PJD (MVN2015-02516-SK) and the data collected from the November 20 wetland delineation for the PJD amendment
were superimposed on the current project general arrangement to determine impacts to waters of the US.
As a result of this effort, approximately 77.67 acres of wetlands (including temporary and permanent
impacts) and 3.29 acres of other waters of the US (including temporary and permanent impacts) will be
impacted by the proposed project. The acreage and type of impacts to each wetland and habitat are listed
below and depicted in Figure 19B.
6
·
Palustrine emergent persistent (PEM1) wetlands; permanent impacts 0.36 acres and
temporary/partial impacts 1.80 acres (comprised of coastal prairie habitat)
·
Palustrine forested broad-leaved decisions (PFO1) wetlands; permanent impacts 19.40 acres and
temporary/partial impacts 0.0.09 acres (comprised of hardwood flatwoods and relic bottomland
hardwood forested habitats)
·
Palustrine forested needle-leaved evergreen (PFO4) wetlands; permanent impacts 0.98 acres and
temporary/partial impacts 1.73 acres (comprised of relic pine flatwoods and pine flatwoods pond
habitats now under silviculture)
·
Palustrine scrub-shrub broad-leaved deciduous and needle-leaved evergreen (PFO1/4) wetlands;
permanent impacts 42.18 acres and temporary/partial impacts 7.83 acres (comprised of relic pine
flatwoods and pine flatwoods ponds and hardwood flatwoods habitats in early successional stage
and now under silviculture)
The acreage and type of impacts to each other waters of the US consisted of artificial or modified drainages
which are listed below and depicted in Figure 19B.
·
Impacts to drainages (perennial, intermittent, and ephemeral); 0.73 acres of permanent impacts and
2.56 acres of temporary/partial impacts.
Approximately 77.67 acres of wetlands (including temporary and permanent impacts) will require
compensatory mitigation. Based on the Louisiana Wetland Rapid Assessment Method (LRAM) ImpactBank spreadsheet calculations 627 credits are needed in compensatory mitigation to offset the 77.67 acres
of wetland impacts from the proposed project (Attachment 5).
7
FIGURES
723206715-GS-MP-00012; Issueed for Review; Rev. 0; 08Feb2017
J:\Drafting\Entergy\723206715\ArcView\GIS_Documents\Project_Maps\lcps_723206715_0012_natural_gas_align.mxd; Analyst: ; Date: 2/8/2017 2:12:22 PM
Legend
Existing Natural Gas Line
Proposed Fuel Supply Line
LCPS Fuel Gas Lateral
Roy S. Nelson Property Boundary
NOTES:
1. Fuel Gas supply line (to be permitted, owned and operated by
fuel gas supplier).
2. Actual location of Fuel Gas Line to be determined.
REFERENCE:
Imagery provided by ESRI, dated 2013
0
o
1
Miles
LAKE CHARLES POWER STATION CCGT PROJECT
SECTION 404 APPLICATION
WESTLAKE, CALCASIEU PARISH, LOUISIANA
FIGURE
NUMBER
2
13A
ENTIRE FUEL PATH
WITH PROPERTY BOUNDARY
CB&I Government Solutions, Inc.
4171 Essen Lane
Baton Rouge, Louisiana 70809
723206715-GS-MP-00013.; Issued for Review; Rev. 0; 03Mar2017
J:\Drafting\Entergy\723206715\ArcView\GIS_Documents\Project_Maps\lcps_723206715_0013_natural_gas_align.mxd; Analyst: ; Date: 3/3/2017 8:08:11 AM
Legend
Proposed Fuel Supply Line
LCPS Fuel Gas Lateral
Roy S. Nelson Property Boundary
NOTES:
1. Fuel Gas supply line (to be permitted, owned and operated by
fuel gas supplier).
2. Actual location of Fuel Gas Line to be determined.
0
REFERENCE:
Imagery provided by ESRI, dated 2013
750
o
1,500
Feet
LAKE CHARLES POWER STATION CCGT PROJECT
SECTION 404 APPLICATION
WESTLAKE, CALCASIEU PARISH, LOUISIANA
FIGURE
NUMBER
3,000
13B
NATURAL GAS
PIPELINE ALIGNMENTS
CB&I Government Solutions, Inc.
4171 Essen Lane
Baton Rouge, Louisiana 70809
SUB DE A((SUB DE B
SUB DE C
(
8B
((
8A
6C
7A
(
( 7B
(
Fuel Gas Line
5C
(((6B
6A
4C
((( 5A
5B
3C
((( 4A
4B
2C
(((
3B
3A
2A
1C
((
( 2B
(
G:\Entergy\155175_Nelson\GIS_Documents\Project_Maps\entergy_155175_020_wet_pwr_line_Permit.mxd; Analyst: ; Date: 3/2/2017 9:54:11 AM
(
(
1A
1B
(
(
Legend
Proposed Fuel Supply Line
PJD Pending
LCPS Fuel Gas Lateral
Potential Wetlands
PJD Issued AOI
Potential Other Waters of the US
Unauthorized Impacts
Wetlands
o
Other Waters of the US
0
REFERENCE:
Imagery provided by ESRI, dated 2013
500
1,000
Feet
2,000
LAKE CHARLES POWER STATION CCGT PROJECT
SECTION 404 APPLICATION
WESTLAKE, CALCASIEU PARISH, LOUISIANA
FIGURE
NUMBER
19A
POTENTIAL WETLANDS/OTHER
WATERS OF THE US
AND PROJECT LAYOUT
4171 Essen Lane
Baton Rouge, Louisiana 70809
www.CBI.com
Preliminary Jurisdicitional
Determination *
PEM1 Wetlands
PFO1 Wetlands
Permanent
Impact (Ac.)
0.36
19.40
PFO4 Wetlands
PSS1/4 Wetlands
PJD Total
Non-Jurisdictional
Determination
Potential PEM1 Wetlands
0.09
0.95
-
42.18
7.83
62.89
Permanent
Impact (Ac.)
9.72
Temporary/Partial
Impact (Ac.)
-
Potential PFO1 Wetlands
3.30
-
-
Potential PFO4 Wetlands
0.03
1.73
Non-PJD Total
0.03
5.03
Potential PSS1/4 Wetlands
-
PJD and Non-PJD Total
62.92
Grand Total of All wetland Impacts
Preliminary Jurisdicitional
Determination *
Other Waters of the US
Non-Jurisdictional
Determination
Potential Other Waters of the US
-
77.67
14.75
Permanent
Impact (Ac.)
Temporary/Partial
Impact (Ac.)
-
1.12
0.73
Permanent
Impact (Ac.)
PJD and Non-PJD Total
Grand Total of All Waters Impacts
G:\Entergy\155175_Nelson\GIS_Documents\Project_Maps\entergy_155175_021_wet_clip_pwr_line_Permit.mxd; Analyst: ; Date: 3/2/2017 9:46:13 AM
Temporary/Partial
Impact (Ac.)
1.80
0.73
1.44
Temporary/Partial
Impact (Ac.)
3.29
Legend
PJD (MVN-2015-02516-SK)
2.56
Proposed Transmission
Pole Location (21' x 21')
PFO1 Wetlands
PFO4 Wetlands
PSS1/4 Wetlands
Permanent Impacts to Waters of the US
Temporary Impact to Waters of the US
PJD Pending
Potential PEM1 Wetlands
Potential PFO4 Wetlands
Potential Other Waters of the US
o
Project Impact Area (149.51 Ac.)
PEM1 Wetlands
0
400
800
1,600
Feet
* USACE Account # MVN-2015-02516-SK
REFERENCE:
Imagery provided by ESRI, dated 2013
LAKE CHARLES POWER STATION CCGT PROJECT
SECTION 404 PERMIT APPLICATION
WESTLAKE, CALCASIEU PARISH, LOUISIANA
FIGURE
NUMBER
19B
IMPACTS TO WETLANDS
AND OTHER WATERS OF THE US
4171 Essen Lane
Baton Rouge, Louisiana 70809
www.CBI.com