The applicant proposes to decommission-in-place the entire 10.7-mile length of the Segment 9002 pipeline.

Full Public Notice Proposed Plans The applicant proposes to decommission-in-place the entire 10.7-mile length of the Segment 9002 pipeline. The applicant has stated that the proposed project would not result in temporary or permanent impacts to the sea floor. The applicant states that full removal of these pipeline segments would cause significant disturbance and ecological damage to the sea bottom and would introduce an unnecessary safety risk to personnel involved in removal operations. In accordance with the Bureau of Safety and Environmental Enforcement 30 CFR 250.1750, pipeline decommissioning requirements, the applicant proposes to: 1.) disconnect from the previously serviced platform and subsea tie-in connection; 2.) flush by pigging and filling with seawater to equalize the line pressure; 3.) plug each end of the pipeline; and 4.) confirm depth of cover at the pipeline ends and cover endpoints with protective concrete mats.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas