The Montana Department of Transportation is proposing to create a state-wide compensatory mitigation banking program to create aquatic resources mitigation sites to be used to compensate for unavoidable wetland and/or stream impacts for transportation improvement projects. MDT proposes that this Umbrella Agreement will consist of multiple mitigation bank sites. Banks established under this Umbrella Agreement will restore, enhance, create and/or preserve streams and wetlands and their functions and values to compensate for unavoidable impacts for activities authorized by USACE.
The Montana Department of Transportation is proposing to create a state-wide compensatory mitigation banking program to create aquatic resources mitigation sites to be used to compensate for unavoidable wetland and/or stream impacts for transportation improvement projects. MDT proposes that this Umbrella Agreement will consist of multiple mitigation bank sites. Banks established under this Umbrella Agreement will restore, enhance, create and/or preserve streams and wetlands and their functions and values to compensate for unavoidable impacts for activities authorized by USACE.
PUBLIC NOTICE
Omaha District
Application No: NWO-2010-01938-MTH
Applicant: Montana Department of Transportation (MDT)
Waterway: Various Waterways (all Montana Counties)
Issue Date: May 30, 2017
Expiration Date: June 29, 2017
30 DAY NOTICE
Helena Regulatory Office 10 West 15th Street, Suite 2200 Helena, MT 59626-9705
JOINT PUBLIC NOTICE
For the Montana Department of Transportation Umbrella Mitigation Agreement
Submitted to
US Army Corps of Engineers, in cooperation with the Interagency Review Team
For the Proposed Umbrella Agreement the Interagency Review Team (IRT) will consist of
the following agencies: US Army Corps of Engineers (USACE), US Environmental
Protection Agency (EPA), US Fish and Wildlife Service (USFWS), Montana Department
of Environmental Quality (MT DEQ), and Montana Fish, Wildlife and Parks (FWP).
History and Purpose
Section 404 of the Clean Water Act establishes a permit requirement, administered by the
Corps of Engineers, for projects that involved discharging dredged or fill material into
waters of the United States. The Corps of Engineers requires compensatory mitigation
(33 CFR 332) as a permit condition for stream or wetland losses that are determined to
have greater than minimal effects. The goal of mitigation is to replace the physical,
chemical, and biological functions of these Waters of the US. The mitigation banking
concept was established to provide alternatives to applicant-provided mitigation, and ease
the regulatory burden of mitigating permitted impacts to waters of the US.
The proposed Umbrella Mitigation Banking Agreement intends to set up sites throughout
Montana based on service area criteria established through the process.
This notice may also be viewed at the Corps web site at:
http://www.nwo.usace.army.mil/Missions/RegulatoryProgram/Montana/PublicNotices.aspx
Scope of Agreement
This prospectus refers to the development of a statewide mitigation program that will
provide compensatory mitigation to offset impacts regulated under Section 404 of the
CWA and Section 10 of the Rivers and Harbors Appropriation Act. Separate
prospectuses will be developed for each individual mitigation sites are proposed
The Prospectus outlines the circumstances and manner in which MDT's mitigation
banking sites will serve to satisfy compensatory mitigation requirements of the COE
Regulatory Program.
Description of Proposed Project: MDT's objective is to create aquatic resources
mitigation sites to be used to compensate for unavoidable wetland and/or stream impacts
for transportation improvement projects. MDT proposes that this Umbrella Agreement will
consist of multiple mitigation bank sites. Banks established under this Umbrella
Agreement will restore, enhance, create and/or preserve streams and wetlands and their
functions and values to compensate for unavoidable impacts for activities authorized by
USACE.
Cultural Resources: The Corps of Engineers, Omaha District will comply with the
National Historic Preservation Act of 1966, as amended. For each bank site we will check
the National Register of Historic Places and its current supplements. We will evaluate
input by the State Historic Preservation Office, Tribal Historic Preservation Office(s), and
the public in response to this public notice, and we may conduct or require a
reconnaissance survey of the mitigation bank area to check for unknown historic or
prehistoric properties, if warranted.
Threatened / Endangered Species: In compliance with the Endangered Species Act, a
preliminary determination will be made for each bank site. In order to complete our
evaluation of this activity, comments will be solicited from the US Fish and Wildlife
Service and other interested agencies and individuals.
Public Interest Review: The decision to approve the Umbrella Agreement will be
based on an evaluation of the probable impacts including cumulative impacts of the
proposed/completed activity on the public interest. That decision will reflect the national
concern for both protection and utilization of important resources. The benefits, which
reasonably may be expected to accrue from the proposal, must be balanced against
their reasonably foreseeable detriments. All factors which may be relevant to the
proposal will be considered including the cumulative effects thereof; among those are
conservation, economics, aesthetics, general environmental concerns, wetlands,
historic properties, fish and wildlife values, flood hazards, floodplain values, land use,
navigation, shoreline erosion and accretion, recreation, water supply and conservation,
water quality, energy needs, safety, food and fiber production, mineral needs,
considerations of property ownership and, in general, the needs and welfare of the
people. In addition, the evaluation of the impact of the work on the public interest will
include application of the guidelines promulgated by the Administrator, Environmental
Protection Agency, under authority of Section 404(b) of the Clean Water Act (40 C.F.R.
Part 230).
Comments: The Corps of Engineers is soliciting comments from the public; Federal,
state, and local agencies and officials; Indian Tribes; and other interested parties in order
to consider and evaluate the impacts of the proposed Umbrella Agreement. Any
2
comments received will be considered by the Corps and the IRT to determine whether to
approve, modify, or deny this proposal. To make this decision, comments are used to
assess impacts on endangered species, historic properties, water quality, general
environmental effects, and the other public interest factors. Comments are also used to
determine the need for a public hearing and to determine the overall public interest of the
proposed activity. All Public Notice comments will be considered public information and
will be subject to review by the applicant.
Any person may request, in writing and within the comment period specified in this notice,
that a public hearing be held for the purpose of gathering additional information.
Requests for public hearings must be identified as such and shall state specifically the
reasons for holding a public hearing and what additional information would be obtained.
The request for public hearing must be submitted in writing to the U.S. Army Corps of
Engineers, 10 West 15th Street, Suite 2200, Helena, Montana 59626-9705. If it is
decided that additional information is required and that a public hearing should be held,
interested parties will be notified of the date, time and location.
Any interested party (particularly officials of any town, city, county, state, or Federal
agency; Indian tribe; or local association whose interests may be affected by the work) is
invited to submit to this office written facts, arguments, or objections on or before the
expiration date listed on the front of this notice. Any agency or individual having an
objection to the proposal should specifically identify it as an objection with clear and
specific reasons. Comments, both favorable and unfavorable, will be accepted, made a
part of the record and will receive full consideration in subsequent actions on this
proposal. All replies to the public notice should be addressed to the U.S. Army Corps of
Engineers, 10 West 15th Street, Suite 2200, Helena, Montana 59626-9705. Please
reference the Application Number found on the first page of this notice in any
correspondence. Robert Cole, telephone number (406) 441-1363, may be contacted
for additional information. You may e-mail comments to:
Robert.H.Cole@usace.army.mil .
Comments postmarked after the expiration date of this Public Notice, or received by fax
or email after the expiration date of this Public Notice, will not be considered. Comments
left on our voicemail system will not be considered.
Statutory Authorities: This proposal is intended to provide compensatory mitigation
opportunities for Department of Army permits issued under the provisions of Section 404
of the Clean Water Act and Section 10 of the Rivers and Harbors Act.
3
UMBRELLA MITIGATION BANKING AGREEMENT
PROSPECTUS
FOR
THE MONTANA DEPARTMENT OF TRANSPORTATION
____________________________________________________________________________
Between the
MONTANA DEPARTMENT OF TRANSPORTATION
And
US ARMY CORPS OF ENGINEERS
Prepared by:
Montana Department of Transportation
Environmental Services Bureau
April 2017
1
Table of Contents
1.0 INTRODUCTION .................................................................................................................... 3
2.0
GOALS AND OBJECTIVES .......................................................................................... 3
3.0
ESTABLISHMENT AND OPERATION PROCEDURE ............................................... 3
3.1
Service Area Establishment .......................................................................................... 3
3.2
Establishment of Bank Sites ......................................................................................... 5
3.2.1
Ecological Suitability ................................................................................................ 5
3.2.2
Water Rights ............................................................................................................. 5
3.3
Determining Credits ..................................................................................................... 5
3.3.1
Use of Bank Credits .................................................................................................. 6
3.3.2
Accounting ................................................................................................................ 6
3.4
Assessment Method ...................................................................................................... 7
3.5
Site Development Plan ................................................................................................. 7
3.6
Performance Standards ................................................................................................. 8
3.6.1
4.0
4.1
Monitoring and Reporting......................................................................................... 9
REAL ESTATE PROVISIONS AND LONG-TERM MANAGEMENT ....................... 9
Financial Assurances .................................................................................................... 9
5.0
IRT REVIEW AND USACE APPROVAL ..................................................................... 9
6.0
QUALIFICATIONS OF THE SPONSOR ..................................................................... 10
7.0
UPDATES ...................................................................................................................... 10
8.0
REFERENCES ............................................................................................................... 11
2
1.0 INTRODUCTION
The Montana Department of Transportation (MDT) proposes the development of an Umbrella
Mitigation Bank (Umbrella Agreement) to create aquatic resource mitigation sites to be used to
compensate for unavoidable wetland and/or stream impacts for proposed transportation
improvement projects (activities). MDT proposes that the Umbrella Agreement will consist of
multiple mitigation bank sites. Bank sites will be added to the Umbrella Agreement as approved
by the U.S. Army Corps of Engineers (USACE) and reviewed by the Interagency Review Team
(IRT) for MDT use.
2.0
GOALS AND OBJECTIVES
The goal of this Umbrella Agreement is to establish guidelines and responsibilities for the
establishment, operation, and maintenance of mitigation banks. Mitigation banks will be used
for compensatory mitigation for unavoidable adverse impacts on waters of the U.S., including
wetlands and/or streams, resulting from MDT construction projects, in accordance with 60 FR
58605-58614 guidance and 33CFR Part 332.
Banks established under this Umbrella Agreement will restore, enhance, create and/or preserve
stream and wetlands and their functions and values to compensate for unavoidable impacts for
activities authorized under the following:
Section 404 of the Clean Water Act
Section 10 of the Rivers and Harbors Act
23 CFR 777 (Mitigation of Impacts to Wetlands and Natural Habitat)
Executive Order 11990
3.0
ESTABLISHMENT AND OPERATION PROCEDURE
3.1
Service Area Establishment
Service areas for each specific Bank will typically be defined as being within one of the
established sixteen Major Watershed Basins, based on the United States Geological Survey
Hydrologic 4th Unit Code (USGS HUC) watershed boundaries (Figure 1). The USACE may
allow the use of a Bank outside of one of the sixteen watersheds on a case by case basis. Out of
service-area mitigation will only be feasible with ecological justification as per the Final Rule
(33 CFR Part 332).
3
Figure 1: Montana Watershed District Map
4
3.2
Establishment of Bank Sites
Each mitigation bank site proposed for inclusion under the Umbrella Agreement will be
submitted to the USACE. MDT retains legal rights to develop or sponsor wetland mitigation
projects throughout the state of Montana to satisfy Sections 404/401 and Section 10 permitting
requirements. Bank sites may include one or more parcels of land and may include one or more
types of compensatory mitigation (restoration, creation, enhancement, preservation, etc.).
3.2.1 Ecological Suitability
MDT's Umbrella Agreement will consist of multiple wetland and stream mitigation bank sites.
Each bank site will be evaluated during the site selection process to determine the ecological
suitability of the site to achieve the proposed goals of the mitigation bank, including the
physical, chemical, and biological aspects of the site. This evaluation will determine how the
site will support aquatic resources and functions. This evaluation will be included in the Site
Development Plan. Potential bank sites will be evaluated for potential development and
inclusion in the Umbrella Agreement based on the following criteria:
·
Location of the bank site relative to the service area;
·
Suitability of the bank site to meet the Umbrella Agreement's goals;
·
Physical, chemical, and biological characteristics;
·
Source and adequacy of hydrology;
·
Technical feasibility;
·
Method of establishing the site (restoration, creation, enhancement, and /or
preservation);
·
Upland areas to act as buffer zones;
·
Compatibility with adjacent land uses;
·
Cultural resources evaluation; and
·
Threatened and endangered species evaluations.
3.2.2 Water Rights
If required, a water right will be obtained under the current process with the Montana
Department of Natural Resource and Conservation (DNRC), or appropriate agency. Bank sites
not requiring a water right, the site hydrology will be protected through other means.
3.3
Determining Credits
Bank credits will be produced through restoration, creation, enhancement, and/or preservation.
Minimum credit ratios have been established in accordance with the Wetland Compensatory
Mitigation Ratios, Montana Regulatory Program April 2005 guidance (Table 1) and the
Compensatory Mitigation Final Rule (33 CFR Parts 325 and 332, April 10, 2008). The minimum
credit production ratio relates to the number of acres required to produce one (1) credit acre.
5
Table 1
Wetland Compensatory Crediting Ratios
Type of Compensatory Mitigation
Source:
Ratio A*
Ratio B*
Restoration (re-establishment)
1:1
1.5:1
Restoration (rehabilitation)
1.5:1
2:1
Enhancement
3:1
4:1
Establishment (Creation)
1:1
2:1
Preservation Protection
4:1
4:1
Upland Buffer
5:1
5:1
USACE, April 2005.
*Typical ratio determinations should be based on the following conditions:
Ratio A: Compensatory wetland mitigation site established and viable prior to project impact.
Ratio B: Compensatory wetland mitigation site not established prior to project impact (including pre-credits from a bank/reserve
and in-lieu fee mitigation). The Corps may, on a case-by-case basis, determine that a proposed out-of-kind mitigation wetland
has greater value in a given watershed than the impacted wetland, and apply Column A ratios.
All wetland mitigation will have a buffer area, where practicable. Some circumstances
relative to right-of-way or easement availability may preclude the ability to establish a
buffer. Pursuant to 33 CFR 332.8(o)(7), credits will be calculated for upland areas which
occur within the Bank, or as buffers around the Bank.
Stream credit production or debiting will be evaluated using the most current version of the
Montana Stream Mitigation Procedure (MTSMP).
3.3.1 Use of Bank Credits
The Umbrella Agreement and associated Bank sites will be used for MDT projects requiring
mitigation under Section 404 of the Clean Water Act and/or Executive Order 11990. Bank
sites may be used only after avoidance and/or minimization efforts are exhausted.
MDT maintains a wetland ledger that accounts for all USACE approved wetland credits
developed at MDT mitigation reserve sites. MDT's existing USACE approved mitigation
reserve sites are grandfathered into the Umbrella Banking Agreement for debiting and
crediting. Following execution of the Umbrella Banking Agreement, new Bank sites will be
added to the ledger for the purposes of tracking credits and debits.
MDT maintains a record of all stream credits developed within USACE approved mitigation
sites. Many of these sites were developed prior to the February 2013 MTSMP. MDT will submit
for release of these stream credits to the USACE upon approval of the Umbrella Banking
Agreement; these sites will be added to the MDT Stream Mitigation Ledger for the purposes of
tracking stream mitigation credits and debits.
3.3.2 Accounting
6
MDT maintains a Ledger for tracking credit and debit transactions for each Bank. The Ledger
contains the following information:
·
Name and permit number of the projects using compensatory mitigation;
·
Number of mitigation acres withdrawn for each transaction;
·
Transaction dates;
·
Number of mitigation acres remaining;
·
Running total of mitigation credits used; and
·
Overall credit balance within each watershed.
MDT will submit a copy of the Ledger to USACE on a semi-annual basis.
3.4
Assessment Method
Wetland delineations will be conducted using the most appropriate Regional Supplement for
Montana as it relates to the 1987 Corps of Engineers Wetlands Delineation Manual
(Environmental Laboratory, January 1987) to determine the area of wetlands developed. To
assess the quality and functionality of the developing wetlands, the Montana Wetland
Assessment Methodology (Berglund, J. & R. McEldowney, 2008) or other methodology
approved by USACE will be utilized.
Stream mitigation credits produced for the Bank will be determined utilizing the most current
version of the Montana Stream Mitigation Procedure (MTSMP) or other methodology
approved by the USACE.
3.5
Site Development Plan
A site development plan will be submitted to the USACE for each mitigation Bank site proposed
for inclusion in the Umbrella Banking agreement. It will include the following information:
·
Site goals and objectives;
·
·
Project location, including the geographic service area and a site map;
Factors considered during site selection;
·
Site protection arrangements;
·
Baseline evaluation of existing site conditions, including vegetation, soils,
and hydrology;
·
Site plans (engineering design and revegetation plans);
·
Anticipated impacts and credit production;
·
Construction schedule;
·
Site performance standards for determining crediting and success of the site;
·
Monitoring and reporting requirements;
7
·
Long-term management and maintenance plan;
·
Adaptive management plan; and
·
Financial assurances.
The information provided in the Site Development Plan will be reviewed by the USACE and
approved for addition of the bank site under the Umbrella Agreement.
3.6
Performance Standards
MDT will be responsible for evaluating the success of the restoration, creation, enhancement,
and/or preservation activities at the mitigation bank sites. Performance standards will be
developed based on best available methodologies for assessing site functions for the following
areas:
·
General Wetland Performance Standards
Wetland Criteria restored (rehabilitated/re-established), enhanced and
preserved wetlands must meet the three standard criteria (soils, vegetation,
hydrology) prescribed in the Corps' 1987 Delineation Manual and the
Regional Supplements applicable to Montana and the site (Arid West, Great
Plains, or Western Mountains, Valleys and Coast); created wetlands must
meet the vegetation and hydrology criteria only, which is presumed to lead
to hydric soils over time.
Vegetation Hydrophytic vegetation success is met when the
developing wetland plant community meets the dominant species
50/20 rule and the wetland plant prevalence index of 3.0 as
indicated within the appropriate US Army Corps of Engineers
Regional Supplement data forms.
Hydrology Hydrologic success is met when the site is inundated or
saturated to the surface continuously for at least 12.5% of the growing
season in most years (50% probability of recurrence 5 out of 10 years).
This will be determined by using the primary and secondary hydrologic
indicators outlined in the Corps' 1987 Delineation Manual and the
Regional Supplements applicable to Montana and the site (Arid West,
Great Plains, or Western Mountains, Valleys and Coast).
Upland Buffer Upland buffers must meet transition zone
requirements for protection of the wetland by providing an adequate
width (typically a minimum of 50 feet to a maximum of 150 feet).
·
General Stream Performance Standards
Stream Morphology The mitigated stream channel will be monitored to
determine if the stability and aquatic function are meeting the goals and
objectives for the site.
8
Upland Buffer Upland buffers must meet transition zone
requirements for protection of the stream and riparian community.
Performance standards will be site-specific and will be outlined in detail within each Site
Development Plan.
3.6.1 Monitoring and Reporting
The annual monitoring reports will describe the development of each mitigation Bank site and
compare those conditions to the performance standards. The monitoring reports will follow
the guidance outlined in RGL 08-03, Minimum Monitoring Requirements for Compensatory
Mitigation Projects Involving the Creation, Restoration, and/or Enhancement of Aquatic
Resources (USACE, October 10, 2008). Monitoring shall occur for a minimum of five (5)
years from the time the wetland is established. Success criteria will be based on the completion
of the goals set for each specific bank.
4.0
REAL ESTATE PROVISIONS AND LONG-TERM MANAGEMENT
MDT will attain ownership, establish a conservation easement, or implement other real estate
mechanisms, at an appropriate stage of development, to preserve the mitigation bank site
properties. MDT will provide copies of the final real estate mechanism to USACE. If MDT
relinquishes ownership of a mitigation bank site property, restrictive preservation mechanisms
will be provided.
4.1
Long Term Management
The operational life of each bank site will terminate when compensatory mitigation credits
have been exhausted, compensatory mitigation goals are met, or banking activity is mutually
terminated between MDT and USACE. MDT will provide USACE written request of
termination.
MDT will be in control of the Bank and will be responsible for management and long-term
maintenance. If MDT transfers ownership or operational control of the bank, a long-term
manager of the site will be determined and long term management plan approved prior to
closure of the site.
4.2
Financial Assurances
MDT will be responsible for securing adequate funding for operation and maintenance of the
Bank. MDT is a governmental unit with the financial capability and resources to implement
mitigation banking, including long-term management and unforeseen events.
5.0
IRT REVIEW AND USACE APPROVAL
Prospectus: IRT has a 30-day review period after receipt of a complete draft prospectus. After
receipt of a complete final prospectus, the USACE notifies the public that the Prospectus is out
for review. This is a 30-day review period.
9
Draft Instrument: Generally, the draft instrument goes through a 30-day comment period,
starting 5 days after the receipt of a complete draft instrument. The USACE has 90-days after
receipt of a complete draft instrument to notify the MDT of the status of the IRT review and
indicate whether the draft instrument is generally acceptable and which changes or comments
need to be addressed.
Final Instrument or Modification to the Final Instrument: The MDT will submit a final
instrument to the USACE and members of the IRT for approval. After receipt of a complete final
instrument, the USACE has 30-days to notify the IRT whether or not they intend to approve the
instrument.
6.0
QUALIFICATIONS OF THE SPONSOR
The Montana Department of Transportation has been developing aquatic resource mitigation
since 1989 and has developed approximately 55 sites ranging in size from ½ acre to 300 acres.
MDT is considered a state-wide leader in wetland and stream restoration within Montana, and
has a well-defined wetland and stream monitoring program. MDT has developed dedicated
funding programs for monitoring and maintaining these aquatic resource mitigation sites.
Monitoring reports for many of these aquatic resource mitigation sites can be found at these
websites:
http://www.mdt.mt.gov/publications/brochures/wetland_mitigation.shtml
http://www.mdt.mt.gov/publications/brochures/stream-mitigation.shtml
7.0
UPDATES
The Umbrella Agreement will be formally reviewed five years from the execution date by MDT
and USACE, in consultation with the IRT. Such review is to ensure consistency with current
policies, guidance, rules and laws which provide the authority for activities under the Umbrella
Agreement. The USACE, in consultation with the IRT, and MDT shall develop consensus on
any requisite changes needed to amend the Umbrella Agreement. The Umbrella Agreement may
be amended or modified at any time with the written approval of all signatory parties.
10
8.0
REFERENCES
33 CFR 325. November 13, 1986. Processing of Department of the Army Permits.
33 CFR 332. April 10, 2008. Compensatory Mitigation for Losses of Aquatic Resources.
60 FR 5860558614. November 28, 1995. Federal Guidance for the Establishment, Use and
Operation of Mitigation Banks.
33 USC 403 et seq. Rivers and Harbors Act of 1899, Section 10.
33 USC 1344. Clean Water Act, Section 404.
Environmental Laboratory. January 1987. Corps of Engineers Wetlands Delineation Manual Technical Report Y-87-1. U.S. Army Corps of Engineers, Waterways Experiment Station,
Vicksburg, Mississippi.
USACE. October 10, 2008. RGL 08-03, Minimum Monitoring Requirements for Compensatory
Mitigation Projects Involving the Creation, Restoration, and/or Enhancement of Aquatic
Resources.
U.S. Army Corps of Engineers. 2008. Regional Supplement to the Corps of Engineers Wetland
Delineation Manual: Arid West Region (Version 2.0),
ed. J. S. Wakeley, R. W. Lichvar, and C. V. Noble. ERDC/EL TR-08-28. Vicksburg, MS: U.S.
Army Engineer Research and Development Center.
U.S. Army Corps of Engineers. 2010. Regional Supplement to the Corps of Engineers Wetland
Delineation Manual: Great Plains Region (Version
2.0), ed. J. S. Wakeley, R. W. Lichvar, and C. V. Noble. ERDC/EL TR-10-1. Vicksburg, MS:
U.S. Army Engineer Research and Development Center.
U.S. Army Corps of Engineers. 2010. Regional Supplement to the Corps of Engineers Wetland
Delineation Manual: Western
Mountains, Valleys, and Coast Region (Version 2.0), ed. J. S. Wakeley, R. W. Lichvar, and C. V.
Noble. ERDC/EL TR-10-3.
Vicksburg, MS: U.S. Army Engineer Research and Development Center.
USACE, Omaha District, February 2013, Montana Stream Mitigation Procedure (MTSMP)