You can copy from here when filling out the rest of the page.
The applicant proposes to perform hydraulic dredging to restore the mouth of the San Bernard River.
Full Public Notice Project Plans
PROJECT DESCRIPTION: The applicant proposes to perform hydraulic dredging to restore the mouth of the San Bernard River. Approximately 123,000 cubic yards of material would be dredged initially, and maintenance dredging would be performed every two years thereafter. The proposed dredging would impact 0.17 acre of beach area, 0.59 acre of dune area, and 0.35 acre of marsh within the dredging footprint. The applicant proposes to discharge suitable sand material into the surf zone for down shore beach nourishment. Dredged material suitable for marsh creation will be used at the mitigation site.