You can copy from here when filling out the rest of the page.
Bay County. Mr. Bryan Mack, BMack Enterprises, LLC. Franklin, Tennessee.
PROJECT PURPOSE:
Basic: Residential development.
Overall: To construct a residential development to provide housing for moderate income families in central Panama City in Bay County, Florida.
TO WHOM IT MAY CONCERN: The Jacksonville District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344) as described below:
APPLICANT: Mr. Bryan Mack
BMack Enterprises, LLC
1545 Championship Boulevard
Franklin, Tennessee 37064
WATERWAY AND LOCATION: The project would affect waters of the United States associated with Mill Bayou. The project site is located at Ten Acre Road in Section 26, Township 3 South, Range 14 West, Panama City, Bay County, Florida.
Directions to the site are as follows: Travel north of Highway 231. Turn right onto Transmitter Road and right onto Ten Acre Road. The property is located on the south side of Ten Acre Road between Naples Avenue and McGraw Lane.
APPROXIMATE CENTRAL COORDINATES:
Latitude 30.19410°
Longitude -85.6117°
PROJECT PURPOSE:
Basic: Residential development.
Overall: To construct a residential development to provide housing for moderate income families in central Panama City in Bay County, Florida.
EXISTING CONDITIONS: The wetland system consists of 2.92 acres scrub shrub palustrine system. The onsite vegetation consists of Chinese tallow, sedge species, beakrush, slash pine, sweet bay, and titi. The existing area surrounding the project area consists of residential housing to the east, west, and south and a road to the north.
PROPOSED WORK: The applicant seeks authorization to impact 2.34 acres of palustrine wetlands in order to develop a single family residential subdivision. The development would be constructed in 2 phases. The first phase would impact 0.25 acre and the second phase would impact 2.09 acres. The applicant proposes to preserve 0.59 acre of the remaining onsite wetlands. Erosion and sedimentation controls are proposed.
AVOIDANCE AND MINIMIZATION INFORMATION – The applicant has provided the following information in support of efforts to avoid and/or minimize impacts to the aquatic environment:
Impacts have been limited to wetland areas that were previously disturbed areas prior to the onsite wetlands being jurisdictional for the Corps or areas that were created as a result of previous land disturbing activities.
COMPENSATORY MITIGATION – The applicant has offered the following compensatory mitigation plan to offset unavoidable functional loss to the aquatic environment:
The applicant proposes to purchase 0.08 palustrine mitigation bank credits for Phase 1 and 0.684 credits for Phase II from Breakfast Point Mitigation Bank.
CULTURAL RESOURCES: The Corps is not aware of any known historic properties within the permit area. By copy of this public notice, the Corps is providing information for review. Our final determination relative to historic resource impacts is subject to review by and coordination with the State Historic Preservation Officer and those federally recognized tribes with concerns in Florida and the Permit Area.
ENDANGERED SPECIES: The Corps has determined the proposal would have no effect on any listed threatened or endangered species or designated critical habitat.
NOTE: This public notice is being issued based on information furnished by the applicant. This information has not been verified or evaluated to ensure compliance with laws and regulation governing the regulatory program. The jurisdictional line has not been verified by Corps personnel.
AUTHORIZATION FROM OTHER AGENCIES: Water Quality Certification may be required from the Florida Department of Environmental Protection and/or one of the state Water Management Districts.
COMMENTS regarding the potential authorization of the work proposed should be submitted in writing to the attention of the District Engineer through the Panama City Permit Section, 1002 West 23rd Street, Suite 350, Panama City, Florida 32405 within 30 days from the date of this notice.
The decision whether to issue or deny this permit application will be based on the information received from this public notice and the evaluation of the probable impact to the associated wetlands. This is based on an analysis of the applicant's avoidance and minimization efforts for the project, as well as the compensatory mitigation proposed.
QUESTIONS concerning this application should be directed to the project manager, Mrs. Lisa S. Lovvorn, in writing at the Panama City Permits Section, 1002 West 23rd Street, Suite 350, Panama City, Florida 32405; by electronic mail at lisa.s.lovvorn@usace.army.mil; by facsimile transmission at (850)872-0231; or, by telephone at (850)763-0717, extension 27.
IMPACT ON NATURAL RESOURCES: Coordination with U.S. Fish and Wildlife Service, Environmental Protection Agency (EPA), the National Marine Fisheries Services, and other Federal, State, and local agencies, environmental groups, and concerned citizens generally yields pertinent environmental information that is instrumental in determining the impact the proposed action will have on the natural resources of the area.
EVALUATION: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefits, which reasonably may be expected to accrue from the proposal, must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including cumulative impacts thereof; among these are conservation, economics, esthetics, general environmental concerns, wetlands, historical properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food, and fiber production, mineral needs, considerations of property ownership, and in general, the needs and welfare of the people. Evaluation of the impact of the activity on the public interest will also include application of the guidelines promulgated by the Administrator, EPA, under authority of Section 404(b) of the Clean Water Act or the criteria established under authority of Section 102(a) of the Marine Protection Research and Sanctuaries Act of 1972. A permit will be granted unless its issuance is found to be contrary to the public interest.
The Corps is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other Interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this determination, comments are used to assess impacts to endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.
COASTAL ZONE MANAGEMENT CONSISTENCY: In Florida, the State approval constitutes compliance with the approved Coastal Zone Management Plan. In Puerto Rico, a Coastal Zone Management Consistency Concurrence is required from the Puerto Rico Planning Board. In the Virgin Islands, the Department of Planning and Natural Resources permit constitutes compliance with the Coastal Zone Management Plan.
REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The request must be submitted in writing to the District Engineer within the designated comment period of the notice and must state the specific reasons for requesting the public hearing.
DEPARTMENT OF THE ARMY
JACKSONVILLE DISTRICT CORPS OF ENGINEERS
1002 WEST 23RD STREET, SUITE 350
PANAMA CITY, FLORIDA 32405
August 24, 2017
REPLY TO
ATTENTION OF
Regulatory Division
North Permits Branch
Panama City Permits Section
PUBLIC NOTICE
Permit Application No. SAJ-2007-03918(SP-LSL)
TO WHOM IT MAY CONCERN: The Jacksonville District of the U.S. Army Corps of
Engineers (Corps) has received an application for a Department of the Army permit
pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344) as described below:
APPLICANT: Mr. Bryan Mack
BMack Enterprises, LLC
1545 Championship Boulevard
Franklin, Tennessee 37064
WATERWAY AND LOCATION: The project would affect waters of the United States
associated with Mill Bayou. The project site is located at Ten Acre Road in Section 26,
Township 3 South, Range 14 West, Panama City, Bay County, Florida.
Directions to the site are as follows: Travel north of Highway 231. Turn right onto
Transmitter Road and right onto Ten Acre Road. The property is located on the south
side of Ten Acre Road between Naples Avenue and McGraw Lane.
APPROXIMATE CENTRAL COORDINATES: Latitude 30.19410°
Longitude -85.6117°
PROJECT PURPOSE:
Basic: Residential development.
Overall: To construct a residential development to provide housing for moderate
income families in central Panama City in Bay County, Florida.
EXISTING CONDITIONS: The wetland system consists of 2.92 acres scrub shrub
palustrine system. The onsite vegetation consists of Chinese tallow, sedge species,
beakrush, slash pine, sweet bay, and titi. The existing area surrounding the project
area consists of residential housing to the east, west, and south and a road to the north.
PROPOSED WORK: The applicant seeks authorization to impact 2.34 acres of
palustrine wetlands in order to develop a single family residential subdivision. The
development would be constructed in 2 phases. The first phase would impact 0.25 acre
and the second phase would impact 2.09 acres. The applicant proposes to preserve
0.59 acre of the remaining onsite wetlands. Erosion and sedimentation controls are
proposed.
AVOIDANCE AND MINIMIZATION INFORMATION The applicant has provided the
following information in support of efforts to avoid and/or minimize impacts to the
aquatic environment:
Impacts have been limited to wetland areas that were previously disturbed areas prior to
the onsite wetlands being jurisdictional for the Corps or areas that were created as a
result of previous land disturbing activities.
COMPENSATORY MITIGATION The applicant has offered the following
compensatory mitigation plan to offset unavoidable functional loss to the aquatic
environment:
The applicant proposes to purchase 0.08 palustrine mitigation bank credits for Phase 1
and 0.684 credits for Phase II from Breakfast Point Mitigation Bank.
CULTURAL RESOURCES: The Corps is not aware of any known historic properties
within the permit area. By copy of this public notice, the Corps is providing information
for review. Our final determination relative to historic resource impacts is subject to
review by and coordination with the State Historic Preservation Officer and those
federally recognized tribes with concerns in Florida and the Permit Area.
ENDANGERED SPECIES: The Corps has determined the proposal would have no
effect on any listed threatened or endangered species or designated critical habitat.
NOTE: This public notice is being issued based on information furnished by the
applicant. This information has not been verified or evaluated to ensure compliance
with laws and regulation governing the regulatory program. The jurisdictional line has
not been verified by Corps personnel.
AUTHORIZATION FROM OTHER AGENCIES: Water Quality Certification may be
required from the Florida Department of Environmental Protection and/or one of the
state Water Management Districts.
COMMENTS regarding the potential authorization of the work proposed should be
submitted in writing to the attention of the District Engineer through the Panama City
Permit Section, 1002 West 23rd Street, Suite 350, Panama City, Florida 32405 within 30
days from the date of this notice.
The decision whether to issue or deny this permit application will be based on the
information received from this public notice and the evaluation of the probable impact to
the associated wetlands. This is based on an analysis of the applicant's avoidance and
minimization efforts for the project, as well as the compensatory mitigation proposed.
2
QUESTIONS concerning this application should be directed to the project manager,
Mrs. Lisa S. Lovvorn, in writing at the Panama City Permits Section, 1002 West 23rd
Street, Suite 350, Panama City, Florida 32405; by electronic mail at
lisa.s.lovvorn@usace.army.mil; by facsimile transmission at (850)872-0231; or, by
telephone at (850)763-0717, extension 27.
IMPACT ON NATURAL RESOURCES: Coordination with U.S. Fish and Wildlife
Service, Environmental Protection Agency (EPA), the National Marine Fisheries
Services, and other Federal, State, and local agencies, environmental groups, and
concerned citizens generally yields pertinent environmental information that is
instrumental in determining the impact the proposed action will have on the natural
resources of the area.
EVALUATION: The decision whether to issue a permit will be based on an evaluation of
the probable impact including cumulative impacts of the proposed activity on the public
interest. That decision will reflect the national concern for both protection and utilization
of important resources. The benefits, which reasonably may be expected to accrue from
the proposal, must be balanced against its reasonably foreseeable detriments. All
factors which may be relevant to the proposal will be considered including cumulative
impacts thereof; among these are conservation, economics, esthetics, general
environmental concerns, wetlands, historical properties, fish and wildlife values, flood
hazards, floodplain values, land use, navigation, shoreline erosion and accretion,
recreation, water supply and conservation, water quality, energy needs, safety, food,
and fiber production, mineral needs, considerations of property ownership, and in
general, the needs and welfare of the people. Evaluation of the impact of the activity on
the public interest will also include application of the guidelines promulgated by the
Administrator, EPA, under authority of Section 404(b) of the Clean Water Act or the
criteria established under authority of Section 102(a) of the Marine Protection Research
and Sanctuaries Act of 1972. A permit will be granted unless its issuance is found to be
contrary to the public interest.
The Corps is soliciting comments from the public; Federal, State, and local agencies
and officials; Indian Tribes; and other Interested parties in order to consider and
evaluate the impacts of this proposed activity. Any comments received will be
considered by the Corps to determine whether to issue, modify, condition, or deny a
permit for this proposal. To make this determination, comments are used to assess
impacts to endangered species, historic properties, water quality, general environmental
effects, and the other public interest factors listed above. Comments are also used to
determine the need for a public hearing and to determine the overall public interest of
the proposed activity.
COASTAL ZONE MANAGEMENT CONSISTENCY: In Florida, the State approval
constitutes compliance with the approved Coastal Zone Management Plan. In Puerto
Rico, a Coastal Zone Management Consistency Concurrence is required from the
Puerto Rico Planning Board. In the Virgin Islands, the Department of Planning and
Natural Resources permit constitutes compliance with the Coastal Zone Management
Plan.
3
REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The
request must be submitted in writing to the District Engineer within the designated
comment period of the notice and must state the specific reasons for requesting the
public hearing.
4
GENERAL NOTES
1. ELEVATIONS SHOWN ON THESE PLANS ARE BASED ON A TOPOGRAPHIC SURVEY PROVIDED BY SEA LEVEL SURVEYING
AND MAPPING, INC. DATED
7/15/2008.
2. SURVEY DATUM NGVD
1929: USC AN GS BRASS DISK No. L42 - ELEV. 29.99'
DREDGE & FILL
PERMIT DOCUMENTS
3. EROSION/SEDIMENTATION CONTROLS SHALL BE PLACED PRIOR TO EXCAVATION AND DEMOLITION. THESE DEVICES
SHALL BE MAINTAINED DURING THE ENTIRE DURATION OF CONSTRUCTION.
4. THE CONTRACTOR SHALL COORDINATE A PRE-CONSTRUCTION MEETING WITH THE ENGINEER, OWNER, AND OTHER
NECESSARY PARTIES. AT THE PRE CONSTRUCTION MEETING THE CONTRACTOR SHALL DESIGNATE A REPRESENTATIVE
WHO SHALL BE CAPABLE OF BEING REACHED 24 HOURS A DAY, 7 DAYS A WEEK. ALL PERMITS SHALL BE IN PLACE PRIOR
TO CONSTRUCTION.
5. THE UTILITIES SHOWN IN THESE PLANS ARE MINIMUM REQUIRED. EXISTING UTILITIES HAVE BEEN LOCATED BY SEA
LEVEL SURVEYING AND MAPPING, INC.,7/15/2008
ON
. IT IS THE CONTRACTOR'S RESPONSIBILITY TO VERIFY THE LOCATION
OF ALL EXISTING UTILITIES PRIOR TO THE COMMENCEMENT OF CONSTRUCTION ACTIVITIES AND PROVIDE FOR
PROTECTION OF EXISTING UTILITIES DURING CONSTRUCTION. THE CONTRACTOR SHALL NOTIFY SUNSHINE ONE, CALL
(1-800-432-4770), 48 HOURS PRIOR TO COMMENCEMENT OF CONSTRUCTION.
BAY COUNTY, FLORIDA
FOR
Ten Acre Terrace
Springfield, Florida
6. HORIZONTAL AND VERTICAL CONTROL SHALL BE PROVIDED FOR THE CONTRACTOR. THE CONTRACTOR IS
RESPONSIBLE FOR MAINTAINING THE CONTROLS THROUGHOUT THE DURATION OF CONSTRUCTION.
PREPARED FOR:
Millirons Construction
PO Box 15148
Panama City, Florida 32406
7. ALL DISTURBED AREAS THAT ARE NOT STABILIZED OR PLANTED SHALL BE GRASSED, AS APPLICABLE, UNLESS
OTHERWISE SHOWN ON THE CONSTRUCTION PLANS. PROBLEM AREAS SHALL BE SODDED AS DIRECTED BY THE OWNER.
8. UNLESS OTHERWISE INDICATED OR MODIFIED ON THE PLANS, ALL ROADWAY AND DRAINAGE CONSTRUCTION SHALL
BE IN ACCORDANCE WITH THE LATEST EDITION OF F.D.O.T. STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE
CONSTRUCTION, SUPPLEMENTS AND SPECIAL PROVISIONS THERETO.
9. WHERE REFERENCE IS MADE TO STANDARD INDEX OR DETAIL, THE FDOT ROADWAY AND TRAFFIC DESIGN STANDARDS,
LATEST EDITION, SHALL BE USED AS IF A PART OF THIS PLAN.
10. ALL UTILITY CONSTRUCTION SHALL BE IN ACCORDANCE WITH THE CITY OF SPRINGFIELD PUBLIC WORKS LATEST
STANDARD SPECIFICATIONS AND LATEST FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION REQUIREMENTS.
11. MINIMUM COMPACTION FOR FILL SECTIONS SHALL BE 95% MODIFIED PROCTOR. SOIL UNDER ALL STRUCTURES AND
PAVED AREAS (MIN. 18" DEPTH) SHALL BE COMPACTED TO 95% MODIFIED PROCTOR THROUGHOUT ITS FULL DEPTH.
BORROW MATERIAL, IF REQUIRED, IS TO BE PROVIDED BY THE CONTRACTOR AND HAVE A MINIMUM LBR VALUE OF 40.
TOPSOIL IS TO BE STRIPPED AND STOCKPILED. FOLLOWING FINAL GRADING, PLACE STOCKPILED TOPSOIL, AS NEEDED,
OVER DISTURBED AREA. UPON SUBGRADE COMPLETION, DENSITIES SHALL BE OBTAINED AND SUBMITTED TO THE
ENGINEER FOR APPROVAL PRIOR TO PLACING THE BASE COARSE.
PROJECT LOCATION
EAST C.R. 2314
16. THE FOLLOWING PERMITS/APPROVALS HAVE OR WILL BE OBTAINED FOR THIS PROJECT:
A. CITY OF SPRINGFIELD - DEVELOPMENT ORDER
B. ENVIRONMENTAL RESOURCE PERMIT
C. FDEP - POTABLE WATER PERMIT
D. FDEP - WASTEWATER PERMIT
E. FDEP/ACOE - WETLAND RESOURCE PERMIT
F. FDEP - NPDES
* - OWNER/CONTRACTOR IS RESPONSIBLE FOR SUBMITTING THE "NOTICE OF INTENT TO
USE GENERIC PERMIT FOR STORMWATER DISCHARGE FROM LARGE AND SMALL CONSTRUCTION
ACTIVITIES" IN ACCORDANCE WITH F.A.C. RULE 62-621.300(4)
*PERMIT CAN BE FOUND AT HTTP://WWW.DEP.STATE.FL.US/WATER/STORMWATER/NPDES/CONSTRUCTION3.HTM
17. PRIOR TO FINAL ACCEPTANCE OF THE PROJECT, ALL SILT AND DEBRIS SHALL BE REMOVED FROM THE PROJECT SITE.
DOUGLAS ROAD
TRANSMITTER ROAD
15. THE CONTRACTOR SHALL NOTIFY THE ENGINEER OF THE DISCOVERY OF ANY ERRORS AND/OR OMISSIONS IN THE
PLANS OR SPECIFICATIONS. THE ENGINEER WILL MAKE SUCH CORRECTIONS AND INTERPOLATIONS AS DEEMED
NECESSARY REFLECTING THE ACTUAL SPRIRIT AND INTENT OF THE PLANS AND SPECIFICAITONS.
TEN ACRE ROAD
NAPLES AVE
14. THE CONTRACTOR SHALL SUBMIT A POST-CONSTRUCTION CERTIFICATION AND REPRODUCIBLE RECORD DRAWINGS
TO THE ENGINEER PRIOR TO INSPECTION AND ACCEPTANCE. THE RECORD DRAWINGS SHALL BE PREPARED AND
CERTIFIED BY A PROFESSIONAL LAND SURVEYOR.
McGRAW LN
13. TOLERANCE FOR ALL FINISHED GRADES SHALL BE 0.1'±.
SHEET NO. SHEET DESCRIPTION
COVER SHEET
1
PROJECT AERIAL
2
MASTER SITE PLAN
3
UTILITY DETAILS
4
5
CONSTRUCTION DETAILS
BOUNDARY/TOPO SURVEY
DATE
11/18/2016
11/18/2016
11/18/2016
11/18/2016
11/18/2016
REVISION
7/25/2017
7/25/2017
7/25/2017
7/25/2017
7/25/2017
See Sheets
18. THE CONTRACTOR SHALL CONFINE ALL WORK WITHIN THE PROPERTY BOUNDARIES, EASEMENTS OR PUBLIC RIGHT
OF WAY. NO TRESPASSING IS ALLOWED.
19. MAINTENANCE OF TRAFFIC SHALL BE IN ACCORDANCE WITH THE FDOT, LATEST EDITION, DESIGN STANDARDS (600
SERIES) AT ALL TIMES.
20. NONCOMPLIANCE WITH NPDES REQUIREMENTS MAY RESULT IN ISSUANCE OF A STOP WORK ORDER.
21. CONTRACTOR SHALL PERFORM ALL NOTIFICATIONS TO REQUIRED PARTIES AS SET FORTH IN PERMIT REQUIREMENTS,
SPECIFIC CONDITIONS, AND INSPECTIONS. REQUIRED PARTIES SHALL INCLUDE, BUT NOT LIMITED TO, THE FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION (FDEP), THE NORTHWEST FLORIDA WATER MANAGEMENT DISTRICT
(NWFWMD), THE LOCAL APPROVING AUTHORITY (THE CITY OF SPRINGFIELD, ETC.), THE ENGINEER, THE ARCHITECT, AND
THE OWNER.
PROJECT LOCATION
ATTENTION IS DIRECTED TO THE FACT
THAT THESE PLANS MAY HAVE BEEN
ALTERED IN SIZE BY REPRODUCTION.
THIS MUST BE CONSIDERED WHEN
OBTAINING SCALED DATA.
GE
Gortemoller Engineering, Inc.
708 Thomas Drive
Panama City Beach, FL 32408
(850) 249-2425
CA-00009505
ENGINEER OF RECORD
Brad M. Harris, P.E.
FLORIDA NO. 68420
708 Thomas Drive
Panama City Beach, Florida 32408
(850) 249-2425
(850) 249-2426-Fax
bharris@gorteng.com
N
CIVIL ENGINEERING BY:
Pe
ot rm
Fo it
r C ting
on P
st lan
ru s
ct
io
n
LOCATION MAP
Ten Acre Terrace: 16-016
SHEET INDEX
12. THE CONTRACTOR SHALL COMPLY WITH ALL LOCAL, STATE, AND FEDERAL REGULATIONS. SEDIMENT CONTROL
DEVICES SHOWN ON THE PLANS ARE MINIMUM REQUIREMENTS. ADDITIONAL SEDIMENT CONTROLS MAY BE REQUIRED
TO PREVENT SEDIMENTS FROM LEAVING THE SITE. THESE ADDITIONAL SEDIMENT CONTROLS ARE THE CONTRACTORS
RESPONSIBILITY. ADDITIONALLY, STORMWATER RUNOFF IS TO BE CONTROLLED DURING CONSTRUCTION AS TO NOT
DETRIMENTALLY AFFECT ADJACENT PROPERTIES.
BRENTWOOD PLACE
Gortemoller Engineering, Inc.
708 Thomas Drive
Panama City Beach, FL 32408
(850) 249-2425
CA-00009505
Ten Acre Terrace
Residential Subdivision
Springfield, Florida
PROJECT:
ARDEN AVENUE
TEN ACRE TERRACE PROJECT
BOUNDARY
NOT VALID FOR CONSTRUCTION
UNLESS SIGNED IN THIS BLOCK
Date:
E.O.R.: Brad M. Harris
P.E. No. 68420 (Florida)
AVON ROAD
IF THIS LINE DOES NOT
MEASURE ONE INCH IN
LENGTH, THE SCALES ON
THIS DRAWING ARE NOT
VALID.
1"
AMELIA AVENUE
GLENVIEW AVENUE
Project Aerial
TEN ACRE ROAD
Millirons Construction
PO Box 15148
Panama City, FL 32406
CLIENT:
NAPLES AVENUE
LANE ROAD
GE
DOUGLAS ROAD
MONICA ROAD
TRANSMITTER ROAD
QUIET OAKS DRIVE
McGRAW LANE
VOLUSIA AVENUE
ORMOND AVENUE
AVON COURT
AVON ROAD
11/18/2016
7/25/2017
2
REVISION
SHEET
BMH
BRF
16-016
DATE
CHECKED
DRAWN
JOB NO.
7/25/2017
4
REVISION
SHEET
EXIST. BASE
6"
TYP.
11/18/2016
SEEDING OR SODDING WIDTH "W"
EXIST. BASE
BMH
EXIST. WEARING
SURFACE
DATE
SEE NOTE 5
SEE NOTE 7
BRF
16-016
12"
CHECKED
3"- 4" CROWN
FINISH GRADE
*
*
PIPE O.D.
UNDISTURBED STABLE MATERIAL
2.)
NOTES:
1. PVC PIPE SHALL REQUIRE INSULATED METALLIC LOCATING TAPE (12
GAUGE COPPER) CAPABLE OF DETECTION BY A CABLE LOCATOR AND
SHALL BE BURIED DIRECTLY ABOVE THE CENTERLINE OF THE PIPE.
2. LOCATING WIRE SHALL TERMINATE AT THE TOP OF EACH VALVE BOX
AND BE CAPABLE OF EXTENDING 12" ABOVE TOP OF BOX IN SUCH A
MANNER SO AS NOT TO INTERFERE WITH VALVE OPERATION.
3. USE DUCT TAPE AS NECESSARY TO HOLD WIRE ON THE TOP OF THE
PIPE.
4. ALL SPLICES SHALL BE MADE USING A WATER-TIGHT SEALING
METHOD APPROVED BY THE CITY.
PVC PIPE LOCATING TAPE DETAIL
3.)
4.)
5.)
USE OF TYPE A-2 AND A-3 PIPE BEDDING TO BE DETERMINED IN THE
FIELD BY THE ENGINEER.
10" MAX. FOR PIPE DIAMETERS LESS THAN 24"; 12" MAX. FOR PIPE DIAMETER
24" AND LESS THAN 42"; 24" MAX. FOR PIPE DIAMETER 42" AND OVER.
4" MAX. FOR PIPE 16" DIAMETER & LESS; 6" MAX. FOR PIPE 18"
TO 36" DIAMETER; AND 9" MAX. FOR PIPE 42" DIAMETER AND LARGER.
INSTALLATION SHALL BE IN ACCORDANCE WITH THE MANUFACTURER'S SPECIFICATIONS.
WEARING SURFACE TO BE SAME TYPE & THICKNESS.
6.)
SHEETING ORDERED LEFT IN PLACE TO BE CUT OFF 24" BELOW
FINISHED GRADE OR 12" BELOW SUBGRADE.
7.)
BASE SHALL BE 6" MINIMUM THICKNESS SAND ASPHALT, 10" MIN. THICKNESS
CRUSHED CONCRETE, OR APPROVED EQUAL.
8.)
BACKFILL AASHTO M-145 SHALL BE PLACED IN LAYERS NOT TO
EXCEED 6 INCHES. EACH LAYER SHALL BE THOROUGHLY TAMPED
AND/OR ROLLED TO 98% AASHTO T-180 DENSITY.
9.)
NTS
10.)
TEMPORARY PATCHES WILL BE INSTALLED TO PROVIDE A SMOOTH
ALL WEATHER SURFACE AT ALL TIMES. PERMANENT REPLACEMENT
TO BE MADE AS SOON AS POSSIBLE.
NOTES 5.) THRU 9.) ARE MINIMUM REQUIREMENTS. REFER TO F.D.O.T.
ROADWAY AND TRAFFIC DESIGN STANDARDS FOR ADDITIONAL REQUIREMENTS.
TRENCH DETAIL
IMPROVED SURFACE: TYPE A-1 BEDDING
POLYETHYLENE
TUBING (1" MIN.)
POLYETHYLENE
TUBING (1" MIN.)
SINGLE METER BOX
AND WATER METER
(BY CITY)
DOUBLE METER BOX
AND WATER METER
(BY CITY)
SINGLE SERVICE
CORPORATION STOP
& FITTING
(NORMALLY OPEN)
AWWA TYPE
CC THREADS
TO METER BOX
ASSEMBLY
SADDLE
POLYETHYLENE
TUBING
30 - 45 DEG.
SEE NOTE 3
THESE WIDTHS ARE FOR PAYMENT
PURPOSES ONLY. SAFETY REQUIREMENTS
MAY DICTATE INCREASED WIDTHS.
Date:
DOUBLE SERVICE
FOR PIPE SIZES 6" THRU 40"
W = 2'-4"+PIPE O.D.+ D
FOR PIPE SIZES OVER 40"
W = 4'-4"+PIPE O.D.+ D
IF THIS LINE DOES NOT
MEASURE ONE INCH IN
LENGTH, THE SCALES ON
THIS DRAWING ARE NOT
VALID.
1"
WATER MAIN
WATER MAIN
DEPTH "D"
2' MINIMUM
SEEDING OR SODDING WIDTH "W"
1.)
TO 90% DENSITY, AASHTO T-180
SEE NOTE 2
CURB STOP
2 EA.
Utility Details
THESE WIDTHS ARE FOR PAYMENT
PURPOSES ONLY. SAFETY REQUIREMENTS
MAY DICTATE INCREASED WIDTHS.
MARK WITH
WOOD PAINTED
BLUE & WITH
LOT NUMBERS
U-BRANCH
FITTING
(1" x 3/4"
x 3/4")
WATER MAIN
UNDISTURBED STABLE MATERIAL
NOTES:
1. ALL FITTINGS SHALL BE BRASS WITH COMPRESSION/PACK JOINT
TYPE CONNECTIONS.
2. NO SERVICE LINE SHALL TERMINATE UNDER A DRIVEWAY.
3. EACH SERVICE SHALL TERMINATE AT A CURB STOP(S) WHICH
SHALL BE BURIED APPROXIMATELY 3" BELOW FINAL GRADE AND
SHALL BE CLEARLY MARKED WITH A 2" X 2" X 18" STAKE WITH
THE TOP PAINTED BLUE AND MARKED WITH THE NUMBER OF THE
LOT(S) TO BE SERVED.
NOTES:
1.) USE OF TYPE A-2 AND A-3 PIPE BEDDING TO BE DETERMINED IN THE
FIELD BY THE ENGINEER.
2.) 10" MAX. FOR PIPE DIAMETER LESS THAN 24"; 12" MAX. FOR PIPE DIAMETER
24" AND LESS THAN 42"; 24" MAX. FOR PIPE DIAMETER 42" AND OVER.
3.) 4" MAX. FOR PIPE 16" DIAMETER & LESS; 6" MAX. FOR PIPE 18"
TO 36" DIAMETER; AND 9" MAX FOR PIPE 42" DIAMETER AND LARGER.
WATER SERVICE CONNECTION DETAILS
NTS
4.) INSTALLATION SHALL BE IN ACCORDANCE WITH THE MANUFACTURER'S
SPECIFICATIONS.
TRENCH DETAIL
UNIMPROVED SURFACE: TYPE A-1 BEDDING
NTS
NTS
Ten Acre Terrace
Residential Subdivision
Springfield, Florida
METALLIC LOCATION TAPE
FOR PIPE SIZES 24" THRU 40"
" "
"W =" 5'-0"+PIPE O.D.+ D
SELECTED
COMMON FILL
(SEE NOTE 1)
CORPORATION
STOP (1" MIN.)
PROJECT:
1" MAX.
P.V.C. WATER MAIN
OR FORCE MAIN
"
SEE
NOTE 3
FOR PIPE SIZES 6" THRU 22"
"
" W"= 4'-8"+PIPE O.D.+ D
BACKFILLED AND COMPACTED
4"LAYERS
COMMON FILL
PIPE BEDDING
"
PAVEMENT REPLACEMENT WIDTH W"
12" LAYERS
*
6" LAYERS
PIPE O.D.
12"MIN.
*
CURB STOP
(SEE NOTE 3)
TRENCH WIDTH
3" DETECTABLE TAPE 12" BELOW
GRADE OR 6" DETECTABLE TAPE
BETWEEN 12" & 24" BELOW GRADE
OVER PVC PIPE. TAPE SHALL BE
MARKED "RECLAIMED WATER"
"POTABLE WATER" OR
"SANITARY SEWER"
12"MIN.
FINISHED GRADE
1" MAX.
3" DETECTABLE TAPE 12" BELOW
GRADE OR 6" DETECTABLE TAPE
BETWEEN 12" & 24" BELOW GRADE
OVER PVC PIPE. TAPE SHALL BE
MARKED "RECLAIMED WATER"
"POTABLE WATER" OR
"SANITARY SEWER"
PIPE BEDDING
SEE NOTE 2
"
DEPTH D"
COMMON FILL
(SEE NOTE 1)
CORPORATION
STOP (1" MIN.)
BACKFILLED & COMPACTED
TO 98% DENSITY, AASHTO T-180
VARIES
SEE NOTE 6
6" LAYERS
3"DETECTABLE TAPE 12" BELOW
GRADE OR 6" DETECTABLE TAPE
BETWEEN 12" & 24" BELOW GRADE
OVER PVC PIPE. TAPE SHALL BE
MARKED "RECLAIMED WATER"
"POTABLE WATER" OR
SELECTED
"SANITARY SEWER"
E.O.R.: Brad M. Harris
P.E. No. 68420 (Florida)
CLEAN COMMON FILL
NOT VALID FOR CONSTRUCTION
UNLESS SIGNED IN THIS BLOCK
12"
DRAWN
SAW CUT
JOB NO.
PAVEMENT REPLACEMENT WIDTH W""
CONCRETE BASE
PE
SL
WATER
MAIN
BOX SHALL REST ON
BEDDING ROCK NOT
ON VALVE OR PIPE
AND SHALL BE
CENTERED ON
OPERATING NUT
1'-6" MIN.
3'-0" MAX.
5"
EPOXY COAL TAR COATINGS
PER SPECIFICATIONS
RESILIENT SEAT GATE
VALVE AND BOX
(SEE DETAIL)
NOTES:
1. FIRE HYDRANT SHALL BE SUPPLIED WITHOUT A WEEP HOLE,
OR WITH A PERMANENTLY PLUGGED WEEP HOLE.
2. THE DEVELOPER MAY INSTALL THE SHEAR PAD RECESSED UP TO
4 INCHES BELOW FINISHED GRADE AND SOD THE RECESSED SECTION.
3. CLEARANCE BETWEEN BOTTOM OF BOLTS AND TOP OF SHEAR PAD
SHALL BE A 6" MINIMUM.
FIRE HYDRANT ASSEMBLY DETAIL
NTS
2'-0"
4'-0"
12"
1"
NOTES:
1. PVC EXTENSIONS SHALL NOT BE USED ON VALVE BOX INSTALLATION.
2. THE ACTUATING NUT FOR DEEPER VALVES SHALL BE EXTENDED TO
COME UP TO 4 FOOT DEPTH BELOW FINISHED GRADE.
PRE-PRIMED
JOINT SURFACES
COMPLETED
JOINT WITH
SQUEEZE-OUT
9"
BEDDING ROCK
TERMINAL DEPTH
AS REQUIRED FOR
"HOUSE" SERVICE
(3' MIN.) (TYP.)
(TY RO
P.) TA
(S TE
EE 30
NO °
TE
SINGLE
LATERAL
VARIES
CLIENT:
SPRING LINE
SEWER MAIN
2)
PROFILE
PRECAST MONOLITHIC
BASE
GATE VALVE AND BOX DETAIL
NTS
PRE-MOLDED
PLASTIC JOINT
SEALER WITH
PROTECTIVE
WRAPPER
(WRAPPER TO
BE REMOVED)
SLOPE TO TERMINAL
DEPTH AT 1.0% MIN.
(TYP.)
9"
2" MIN.
CAST-IN-PLACE
CONCRETE BASE
OUTSIDE WALL
SQUEEZE-OUT
8" MIN.
9"
FINISHED GRADE
PRE-PRIMED
JOINT SURFACES
6"
MIN.
REINFORCEMENT AND JOINT
DETAIL TO BE DESIGNED BY
THE ENGINEER AND
APPROVED BY THE
COUNTY. 9"
6" BEDDING ROCK
D
5" MIN.
INSIDE WALL
PLAN
3'
2 COURSES OF BRICK (MIN.)
4 COURSES (MAX.)
BENCHING PER SPECIFICATIONS
6" BEDDING ROCK
M J ANCHORING
COUPLING
FRAMES BEDDED IN MORTAR
NOTES:
1. MANHOLE SHOWN IS FOR SEWER SIZE 8" THRU 24", SEE SECTION 20.4.3 OF THE
MANUAL FOR MANHOLE DIAMETER FOR SEWERS LARGER THAN 24".
2. DROP CONNECTIONS ARE REQUIRED WHENEVER INVERT OF INFLUENT SEWER IS
24" OR MORE ABOVE THE INVERT OF THE MANHOLE. SEE MANHOLE
CONNECTION DETAILS.
3. APPROVED CONCENTRIC CONE DESIGN MAY BE USED AS AN ALTERNATIVE.
PRECAST CONCRETE MANHOLE
NTS
NOTES:
1. LOCATE SINGLE LATERAL AS CLOSE TO LOT LINE AS
POSSIBLE, 25' MAXIMUM.
2. INVERT OF SERVICE LATERAL SHALL NOT ENTER SEWER
MAIN BELOW SPRING LINE.
3. ALL SERVICE LATERALS SHALL BE SINGLE SERVICE.
SEWER SERVICE LATERAL DETAIL
NTS
GE
RESILIENT SEAT
M. J. GATE VALVE
ADJUSTABLE CAST IRON
VALVE BOX
SET COVERS FLUSH IN
PAVED AREAS & AT
ELEVATIIONS SHOWN IN
UNPAVED AREAS.
Gortemoller Engineering, Inc.
708 Thomas Drive
Panama City Beach, FL 32408
(850) 249-2425
CA-00009505
12" MIN.
SEE NOTE 2
REMOVABLE
PLUG
MANHOLE FRAME & COVER
(SEE STANDARD DETAIL)
R/W
SEE NOTE 3
M J HYDRANT
ANCHORING TEE
FINISHED GRADE
AS
VARIES
REQ'D
COMPACTED
BACKFILL
VARIES
2 - #4 AT 9"
O.C. ALL
AROUND
VALVE COLLAR
(SEE DETAIL)
CONCRETE COLLAR
IN UNPAVED AREAS
(SEE DETAILS)
VARIES
18" MIN.
PUMPER NOZZLE
FACING STREET
R/W LINE
SET TOP OF VALVE BOX
TO FINISHED GRADE
0.8 D
24" SQUARE OR
ROUND AND 6" THICK
REINFORCED CONCRETE
SHEAR PAD. SEE
NOTE 2
SEWER MAIN
SIZE VARIES
4" 45°
BEND
PE
O
AS REQ'D.
WYE WITH
4" BRANCH
O
SL
HOSE NOZZLE
LOT LINE
SEE
NOTE 1
PE
SL
O
PE
O
SL
HYDRANT
OPERATING
NUT
SEE MANHOLE
CONNECTION
DETAILS
Millirons Construction
PO Box 15148
Panama City, FL 32406
TROWEL-FINISHED
CONCRETE BENCHING
15
1
1
4:
1
DEWATERING NOTE:
1) SEDIMENT BASIN TO BE COSTRUCTED PRIOR TO THE CUT AND
FILL PROCESS.
2) SEDIMENT BASIN TO REMAIN INTACT FOR ENTIRE LENGTH OF
CUT ANF FILL PROCESS.
3) AFTER COMPLETION OF CUT AND FILL PROCESS, THE SEDIMENT
BASIN IS TO BE REMOVED.
1"
EXISTING GRADE
LOT LINE
N.T.S.
TEMPORARY SEDIMENT & DEWATERING BASIN SECTION
EASEMENT LINE
NTS
3.0'
12' SWALE
PROPOSED 5' FENCE
2.5' FROM POND TOP (MIN)
PROPOSED 5' FENCE
2.5' FROM POND TOP (MIN)
X
0.5'
12
X
X
1
X
EXISTING GRADE
(APPROX 39.00 - 41.50)
41.50
4
41.50
EXISTING GRADE
PROPOSED GRADE
PROPOSED GRADE
1
MAX 25 YEAR STORM - 40.60
NOTE: DISTURBED AREAS TO BE SEED AND MULCHED
4
TREATMENT - 39.80
1
CONVEYANCE SWALE (SECTION B-B)
4
N.T.S.
1
37.00
PROJECT:
39.00
37.00
2
2
1
1
30.00
30.00
NOTE: SWF SLOPES TO BE SODDED
WET POND SECTION
N.T.S.
PLAN
PROPOSED GRADE
8.00'
8"
ELEV - 39.00
12"
4:1
ELEV - 38.30
ELEV - 38.00
A
4" PVC SCREW IN CAP
4" PVC
ELEV - 41.00
4" PVC TEE
30"
30" WEIR
ELEV - 39.80
4" PVC
ELEV - 39.00
4" PVC CAP WITH
1.75" HOLE DRILLED IN CENTER
EXISTING GRADE
12"
12"
6"
18" RCP
ELEV - 35.50
ELEV - 34.50
18" RCP
ELEV - 35.50
SECTION
BUBBLE UP STRUCTURE (DS - 13)
TYPE "D" INLET - FDOT INDEX 232
NOTE: ALL DISTURBED AREAS TO BE SODDED
ELEV - 34.50
SECTION A-A
SECTION B-B
CONTROL STRUCTURE (DS - 12)
TYPE "D" INLET - FDOT INDEX 232
GE
B
Gortemoller Engineering, Inc.
5 Miracle Strip Loop, Suite 16
Panama City Beach, FL 32407
(850) 249-2425
CA-00009505
24"
B
36"
CLIENT:
A
36"
4' BERM
(ELEV - 39.00)
SHEET
12
1
Millirons Construction
PO Box 15148
Panama City, FL 32406
PROPOSED 5' BERM
CUT
Ten Acre Terrace - Phase I
Lots 1-15
Residential Subdivision
Springfield, Florida
FILL
4:1
REVISION
Construction Details
CONVEYANCE SWALE (SECTION A-A)
PROPERTY LINE
NOTE: DISTURBED AREAS TO BE SEED AND MULCHED
Date:
E.O.R.: Brad M. Harris
P.E. No. 68420 (Florida)
15
6:1
EXISTING GRADE LINE
4:1
5
11/ 18 / 2016
DATE
BMH
CHECKED
DRAWN
0.5'
0.50% MIN
IF THIS LINE DOES NOT
MEASURE ONE INCH IN
LENGTH, THE SCALES ON
THIS DRAWING ARE NOT
VALID.
6:1
TIE BACK
15' SWALE
SEE PLANS
1
4:
3' BERM
NOT VALID FOR CONSTRUCTION
UNLESS SIGNED IN THIS BLOCK
7.5'
PROPOSED GRADE LINE
BRF
16-016
JOB NO.
LOT LINE
SWALE CENTER LINE
EASEMENT LINE
LOT LINE / WETLAND LINE