You can copy from here when filling out the rest of the page.
The applicant proposes to discharge dredged and/or fill material into 15,641 linear feet of streams and 0.14 acre of emergent wetland in conjunction with the construction, operation and reclamation of the Twin Branch Surface Mine No. 2 project.
TO WHOM IT MAY CONCERN: The following applicant has submitted an application for a Department of the Army Permit under the provisions of Section 404 of the Clean Water Act for the proposed discharge of dredged and/or fill material into waters of the United States (U.S.). This notice serves as the U.S. Army Corps of Engineers’ (Corps) request to the West Virginia Department of Environmental Protection (WVDEP) to act on Section 401 Water Quality Certification (WQC) for the following application.
APPLICANT: Southeastern Land LLC
P.O. Box 9
Naugatuck, WV 25685
LOCATION: As shown on attached Sheets 1 and 2 of 3, the proposed project is located approximately one mile north of Myrtle, in Mingo County, West Virginia (37.80917˚ North, -82.16833˚West). The proposed project would discharge fill material into Riffe Branch, Left Fork of Riffe Branch, Trace Fork, Buddy Branch, Ashcamp Branch and unnamed tributaries to these named streams. These named stream are all indirect tributaries of Pigeon Creek of the Tug Fork River, a traditional navigable water of the U.S.
DESCRIPTION OF THE PROPOSED WORK: The applicant proposes to discharge dredged and/or fill material into 15,641 linear feet of streams and 0.14 acre of emergent wetland in conjunction with the construction, operation and reclamation of the Twin Branch Surface Mine No. 2 project (West Virginia Surface Mining Control and Reclamation Act [SMCRA] permit S-5005-15).
Construction of the Valley Fill No. 1 underdrain system would result in the discharge of fill material into approximately 3,490 linear feet of perennial stream (Riffe Branch), 3,973 linear feet of intermittent streams, and 2,130 linear feet of ephemeral streams. Construction of Sediment Ponds #1A and #1B would result in the discharge of dredged and/or fill material into approximately 790 linear feet of perennial stream, 246 linear feet of intermittent stream and 67 linear feet of ephemeral stream. Excavation and backfill activities associated with recovery of coal reserves would result in the discharge of dredged and/or fill material into approximately 2,638 linear feet of ephemeral stream and 2,257 linear feet of intermittent stream. Construction of two road crossings would result in the discharge of dredged and/or fill material into 20 linear feet of perennial stream and 30 feet of intermittent stream. A summary of all proposed stream and wetland fill impacts is found on the attached Sheet 4.
A copy of the applicant’s Section 404 application, including all supplemental materials (alternative analysis, compensatory mitigation plan, environmental information etc.) are available for public review in the Huntington District Office, by appointment. The purpose of the project is to remove 26.4 million tons of bituminous coal reserves within the 1,302-acre SMCRA permit area (1,020 acres of mineral removal area) during its estimated 12-year project life. Plans (Sheets 1 through 3) for the proposal are attached to this Public Notice.
ALTERNATIVES ANALYSIS: A total of 15,641 linear feet of streams and 0.14 acre of emergent wetland would be filled as a result of the proposal. The project does not require access or proximity to, or siting within, the wetlands to fulfill its basic purpose and is considered a non-water dependent activity. The Section 404(b)(1) Guidelines state for non-water dependent activities, practicable alternatives that do not involve wetlands are presumed to be available, unless clearly demonstrated otherwise. The applicant is required to provide an alternatives analysis that must overcome this presumption prior to receiving authorization for the discharge of dredge and/or fill material. The applicant has submitted an alternatives analysis and it is currently under review. A complete copy of the applicant’s alternatives analysis can be reviewed by appointment at the above address. No permit will be issued until our office determines practicable upland alternatives are not available to achieve the overall project purpose based upon the applicant’s alternative analysis.
AVOIDANCE AND MINIMIZATION: In evaluating a project area containing waters of the U.S., consideration must be given to avoiding impacts on these sites. If waters of the U.S. cannot be avoided, then the impacts must be minimized. To minimize impacts and eliminate the need for additional fill sites, Valley Fill 1 was designed with a super-elevated top elevation equal to the maximum elevation allowable under the WVDEP’s Maximum Backfill Requirements. This design allowed the toe of the valley fill to be moved further upstream by 971 linear feet, thereby resulting in an overall reduction of stream impacts in the amount of 1,836 linear feet. The fill material proposed to be discharged into the waters of the U.S. associated with the valley fill underdrain would consist of durable, non-toxic rock. Best management practices, including the use of temporary sediment controls and revegetating disturbed areas, would be used. Surface drainage would flow to constructed sediment control structures, including sediment ponds to be constructed immediately below the toe of the valley fill. The applicant’s material handling plan would assure that all fill material discharged into waters of the U.S. would not contain toxic-forming material. All drainage from the project area would be managed and monitored pursuant to the Section 402 NPDES permit WV1028260 (pending with the WVDEP) to ensure water quality standards are met.
COMPENSATORY MITIGATION PLAN: To calculate an appropriate amount of mitigation to compensate for the loss of waters of the U.S. associated with the proposed project, the applicant used the Corps’ “West Virginia Stream and Wetland Valuation Metric” (SWVM). The SWVM compares baseline data with anticipated or actual post-mitigation data to calculate impact debits and required or achieved mitigation credits. In order to compensate for the impact debits, 11,092.18 stream credits and 0.14 wetland credits must be obtained. The applicant has proposed to obtain these credits from an approved stream and wetland mitigation bank with a service area covering the Tug Fork watershed (HUC 8: 05070201).
WATER QUALITY CERTIFICATION: A Section 401 WQC is required for the proposed activity, pursuant to Section 401 of the Clean Water Act. It is the applicant’s responsibility to obtain certification from the WVDEP.
HISTORIC AND CULTURAL RESOURCES: The National Register of Historic Places
(NRHP) has been consulted and it has been determined there are no properties currently listed on the NRHP that would be indirectly or directly affected by the proposed work. The project site was investigated, as described in “Abbreviated Technical Report: Archaeological Identification Survey for the Proposed Twin Branch Surface Mine No. 2, Hardee District, Mingo County, West Virginia”, dated January 19, 2015, prepared by Cultural Resource Analysts, Inc. As stated therein, systematic examination of the project area did not identify evidence for archaeological sites or historic structures. The report provided an opinion that the proposed project would have no effect on any known archaeological sites listed in or eligible for listing in the NRHP, and no further investigations are necessary. The report was coordinated with the State Historic Preservation Officer (SHPO). By letter dated May 15, 2015, the SHPO stated there are no architectural properties which are eligible for or listed on the NRHP that would be affected by the proposed project, and no further consultation is necessary with respect to architectural resources. The SHPO also stated they concur with the determinations of the above-referenced archaeological report, and concluded there are no historic archaeological properties that would be affected by the proposed project, and no further consultation is necessary with respect to archaeological resources. A copy of this Public Notice will be furnished to State Historic Preservation Office for their review. Comments concerning archaeological sensitivity of the project area should be based on collected data.
ENDANGERED AND THREATENED SPECIES: The proposed project lies within the natural range of the federally listed endangered Indiana bat (Myotis sodalis) and the threatened northern long-eared bat (Myotis septentrionalis). The project also lies upstream of the natural range of the federally listed threatened Big Sandy crayfish (Cambarus callainus). The effects of the project on federally-protected endangered and threatened species were evaluated by the WVDEP pursuant to a 1996 programmatic Endangered Species Act –Section 7 Consultation, Biological Opinion and Conference Report (’96 BO) between the U.S. Fish & Wildlife Service (USFWS) and the U.S. Office of Surface Mining Reclamation and Enforcement .
Concerning the above-listed bat species, the applicant investigated the area and indicated the project site does not contain known maternity roosts for the above bat species, and contains no caves or open portals. The applicant followed the “Range-wide Indiana Bat Protection and Enhancement Plan Guidelines for Surface Coal Mining Operations” (Guidelines). The applicant prepared an “Indiana Bat and Northern Long Eared Bat Protection and Enhancement Plan for the Twin Branch No. 2 Surface Mine” (PEP), dated June 14, 2016. By letter dated June 6, 2016, the WVDEP concluded that no Indiana bat or northern long-eared bat winter habitat is expected to be impacted by the project. By letter dated December 20, 2016, the WVDEP stated the PEP contains reasonable and prudent measures to avoid and minimize impacts to the above-stated bat species that may occur as a result of the proposed project. The PEP prescribes short- and long-term minimization measures, and prescribes that tree clearing must be conducted between October 15 to March 31. The WVDEP determined the PEP meets all requirements of the Guidelines and the 4(d) Rule, and fulfills all requirements necessary to protect threatened and endangered bats.
Concerning the Big Sandy crayfish, mapped aquatic buffer zone areas delineated by the USFWS for the Big Sandy crayfish (based on survey data) indicate the project area is roughly 5.6 miles upstream from the nearest aquatic buffer zone (near the mouth of the Right Fork of Laurel Fork). The applicant provided to the WVDEP a “Big Sandy Crayfish Habitat Evaluation and Permitted Protective Measures”, dated November 15, 2016 for this project. The report states the project area contains no suitable habitat for the Big Sandy Crayfish. Based on the letters dated December 20, 2016 and August 2, 2017 from the WVDEP, the Corps has determined the proposed discharge of dredged and/or fill material into waters of the U.S. (a) may affect, but is not likely to adversely affect either the Indiana bat or the northern long-eared bat and (b) would have no effect on the Big Sandy crayfish, respectively. The Corps believes the effects determinations and requirements determined by the WVDEP for this proposal, pursuant to the ’96 BO, assure that the proposal is not likely to jeopardize the continued existence of listed or proposed species, and are not likely to result in the destruction or adverse modification of designated or proposed critical habitats. This Public Notice serves as coordination with the USFWS concerning the above determinations, in accordance with Section 7(a) of the Endangered Species Act.
PUBLIC INTEREST REVIEW AND CUMULATIVE EFFECTS: This application will be reviewed in accordance with 33 CFR 320‑332, the Regulatory Program of the Corps, and other pertinent laws, regulations, and executive orders. Our evaluation will also follow the guidelines published by the U.S. Environmental Protection Agency pursuant to Section 404(b)(1) of the Clean Water Act (40 CFR 230). The decision whether to issue a permit will be based on an evaluation of the probable impact, including cumulative impacts, of the proposed discharge of dredged and/or fill material into waters of the U.S. on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit that reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors that may be relevant to the proposal will be considered, including the cumulative effects thereof; of those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people.
SOLICITATION OF COMMENTS: The Corps is soliciting comments from the public, Federal, state and local agencies and officials, Indian Tribes, and other interested parties in order to consider and evaluate the impacts of this proposed activity. For accuracy and completeness of the administrative record, all data in support of or in opposition to the proposed work should be submitted in writing setting forth sufficient detail to furnish a clear understanding of the reasons for support or opposition. Any person may request, in writing, within the comment period specified in the notice, that a public hearing be held to consider the application. Requests for public hearings shall state, with particularity, the reasons for holding a public hearing. Any comments received will be considered by the Corps to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. Written statements on these factors received in this office on or before the expiration date of this public notice will become a part of the record and will be considered in the final determination. A permit will be granted unless its issuance is found to be contrary to the public interest.
CLOSE OF COMMENT PERIOD: All comments pertaining to this Public Notice must reach this office on or before the close of the comment period listed on page one of this Public Notice. If no comments are received by that date, it will be considered that there are no objections. Comments and requests for additional information should be submitted to:
U.S. Army Corps of Engineers
502 Eighth Street
Huntington, West Virginia 25701-2070
ATTN: CELRH-RD-E, Public Notice No. LRH-2015-57
Please note that submitted comments in response to this Public Notice become part of our administrative record and, as such, are available to the public under provisions of the Freedom of Information Act. Thank you for your interest in our nation's water resources. If you have any questions concerning this Public Notice, please contact Richard Berkes of the Energy Resource Branch at (304) 399-6909.