PERMIT MODIFICATION FOR PIPELINE REPLACEMENT IN ST. MARY PARISH

NAME OF APPLICANT: Shell Pipeline Company, Post Office Box 2648, OSP 41082B, Houston, Texas 77252-2648 LOCATION OF WORK: Bateman Island, crossing Atchafalaya River and Bayou Shaffer, located in the community of Morgan City, in St. Mary Parish, Louisiana, as shown on the enclosed drawings. Location: POB: Latitude: 29°40ʹ52ʺ N / Longitude: -91°13ʹ31ʺ W, POE: Latitude: 29°40ʹ47ʺ N / Longitude: -91°11ʹ21ʺ W, Hydrologic Unit Code for West of Bayou Shaffer: 08080101 – Atchafalaya River Basin, Hydrologic Unit Code for East of Bayou Shaffer: 08090302 – Terrebonne, West-Central Louisiana Coastal Basin. CHARACTER OF WORK: Shell is requesting amendment of their original permit issued December 20, 2016, to include the following work stated below. Amended Bateman Island Segment: Replace 2,980 linear feet of pipeline between two HDD exit sites while using one 4-foot deep flotation channel. The existing pipeline between the drill sites would be abandoned in place, increasing the total length of abandoned pipeline to approximately 12,205 feet. Approximately 2,980 feet of new pipeline would be installed between the drill exit sites. Shell would install an additional 50-foot wide by 1,289 foot long workspace between the Bayou Shaffer HDD exit site and the dock, and install one 15-foot wide by 3,665-foot long flotation ditch in a new pipeline Right-of-Way. A barge would be placed in a 35-foot wide by 400-foot long back string space, which only 0.77 of an acre out of the 1.61 acres permitted for the dock were cleared. Theback string workspace would be constructed within the cleared area. Temporary mats would beplaced in an approximately 30-foot wide by 1,740-foot long equipment access area. No clearing would be needed for the equipment access area. Shell would install five 25-foot wide by 100-foot long road turnoffs to allow equipment to travel, in which approximately 0.29 of an acre of additional forested wetland would be cleared. Shell would lower a 600 foot section of pipeline an additional 4-feet deep. Amended Bayou Shaffer Segment: Shell would add sand and cement bags under permitted rip rap in the Atchafalaya River and Bayou Shaffer, and conduct dredging operations within a 120-foot wide by 240-foot long area in Bayou Shaffer near the dock location, to restore Bateman Island work areas to original contours. Work completed includes the installation of 4,350 feet of pipeline from Bayou Shaffer HDD from Avoca Island to Bateman Island. Overall, approximately 33,000 cubic yards of fill material would be excavated, approximately 41,069 cubic yards of excavated and hauled-in material and 6,883 cubic yards of chipped trees would be placed onsite. The total amount of wetland impacts from the permit modification would be 11.92 acres, which is less than the originally permitted and mitigated amount of 14.1 acres of jurisdictional wetlands. Therefore, the applicant has not proposed to mitigate due to the reduction in overall project impacts from the modified plans.

JOINT PUBLIC NOTICE September 18, 2017 United States Army Corps of Engineers New Orleans District Regulatory Branch 7400 Leake Avenue New Orleans, Louisiana 70118-3651

State of Louisiana Department of Environmental Quality ATTN: Water Quality Certifications Post Office Box 4313 Baton Rouge, Louisiana 70821-4313

(504) 862-2284 Sara.B.Fortuna@usace.army.mil Project Manager Sara Fortuna Permit Application Number MVN-2015-01060-WKK

(225) 219-3225 Elizabeth.Hill@la.gov Project Manager Elizabeth Hill WQC Application Number WQC 160330-01

Interested parties are hereby notified that a permit application has been received by the New Orleans District of the U.S. Army Corps of Engineers pursuant to: [X] Section 10 of the Rivers and Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or [X] Section 404 of the Clean Water Act (86 Stat. 816; 33 USC 1344). Application has also been made to the Louisiana Department of Environmental Quality, Water Quality Certifications, for a Water Quality Certification (WQC) in accordance with statutory authority contained in LRS30:2047 A(3), and provisions of Section 401 of the Clean Water Act (P.L.95-17). PERMIT MODIFICATION FOR PIPELINE REPLACEMENT IN ST. MARY PARISH NAME OF APPLICANT: Shell Pipeline Company, Post Office Box 2648, OSP 41082B, Houston, Texas 77252-2648. LOCATION OF WORK: Bateman Island, crossing Atchafalaya River and Bayou Shaffer, located in the community of Morgan City, in St. Mary Parish, Louisiana, as shown on the enclosed drawings. Location: POB: Latitude: 29°4052 N / Longitude: -91°1331 W, POE: Latitude: 29°4047 N / Longitude: -91°1121 W, Hydrologic Unit Code for West of Bayou Shaffer: 08080101 ­ Atchafalaya River Basin, Hydrologic Unit Code for East of Bayou Shaffer: 08090302 ­ Terrebonne, West-Central Louisiana Coastal Basin CHARACTER OF WORK: Shell is requesting amendment of their original permit issued December 20, 2016, to include the following work stated below. Amended Bateman Island Segment: Replace 2,980 linear feet of pipeline between two HDD exit sites while using one 4-foot deep flotation channel. The existing pipeline between the drill sites would be abandoned in place, increasing the total length of abandoned pipeline to approximately 12,205 feet. Approximately 2,980 feet of new pipeline would be installed between the drill exit sites. Shell would install an additional 50-foot wide by 1,289 foot long workspace between the Bayou Shaffer HDD exit site and the dock, and install one 15-foot wide by 3,665-foot long flotation ditch in a new pipeline Right-of-Way. A barge would be placed in a 35-foot wide by 400-foot long back string space, which only 0.77 of an acre out of the 1.61 acres permitted for the dock were cleared. The back string workspace would be constructed within the cleared area. Temporary mats would be

-2placed in an approximately 30-foot wide by 1,740-foot long equipment access area. No clearing would be needed for the equipment access area. Shell would install five 25-foot wide by 100-foot long road turnoffs to allow equipment to travel, in which approximately 0.29 of an acre of additional forested wetland would be cleared. Shell would lower a 600 foot section of pipeline an additional 4feet deep. Amended Bayou Shaffer Segment: Shell would add sand and cement bags under permitted rip rap in the Atchafalaya River and Bayou Shaffer, and conduct dredging operations within a 120-foot wide by 240-foot long area in Bayou Shaffer near the dock location, to restore Bateman Island work areas to original contours. Work completed includes the installation of 4,350 feet of pipeline from Bayou Shaffer HDD from Avoca Island to Bateman Island. Overall, approximately 33,000 cubic yards of fill material would be excavated, approximately 41,069 cubic yards of excavated and hauled-in material and 6,883 cubic yards of chipped trees would be placed onsite. The total amount of wetland impacts from the permit modification would be 11.92 acres, which is less than the originally permitted and mitigated amount of 14.1 acres of jurisdictional wetlands. Therefore, the applicant has not proposed to mitigate due to the reduction in overall project impacts from the modified plans. The comment period for the Department of the Army Permit and the Louisiana Department of Environmental Quality WQC will close 20 days from the date of this joint public notice. Written comments, including suggestions for modifications or objections to the proposed work, stating reasons thereof, are being solicited from anyone having interest in this permit and/or this WQC request and must be mailed so as to be received before or by the last day of the comment period. Letters concerning the Corps of Engineers permit application must reference the applicant's name and the Permit Application Number, and be mailed to the Corps of Engineers at the address above, ATTENTION: REGULATORY BRANCH. Similar letters concerning the Water Quality Certification must reference the applicant's name and the WQC Application number and be mailed to the Louisiana Department of Environmental Quality at the address above. Individuals or parties may request an extension of time in which to comment on the proposed work by writing or e-mailing the Corps of Engineers Project Manager listed above. Any request must be specific and substantively supportive of the requested extension, and received by this office prior to the end of the initial comment period. The Section Chief will review the request and the requestor will be promptly notified of the decision to grant or deny the request. If granted, the time extension will be continuous to the initial comment period and, inclusive of the initial comment period, will not exceed a total of 30 calendar days. The application for this proposed project is on file with the Louisiana Department of Environmental Quality and may be examined during weekdays between 8:00 a.m. and 4:30 p.m. Copies may be obtained upon payment of costs of reproduction. Corps of Engineers Permit Criteria The decision whether to issue a permit will be based on an evaluation of the probable impacts, including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people.

-3The U.S. Army Corps of Engineers is soliciting comments from the public, federal, state, and local agencies and officials, Indian Tribes, and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the U.S. Army Corps of Engineers to determine whether to make, modify, condition, or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. The New Orleans District is unaware of properties listed on the National Register of Historic Places near the proposed work. The possibility exists that the proposed work may damage or destroy presently unknown archeological, scientific, prehistorical, historical sites, or data. Copies of this public notice are being sent to the State Archeologist and State Historic Preservation Officer regarding potential impacts to cultural resources. The New Orleans District has determined that out of the 18.53 acre project footprint, 0.31 of an acre is located in waters known to be utilized by the pallid sturgeon (Scaphirhynchus albus) and the West Indian Manatee (Trichechus manatus) and determined the activity is not likely to adversely affect these species based on the Standard Local Operating Procedure for Endangered Species in Louisiana (SLOPES), dated October 22, 2014, between the U.S. Army Corps of Engineers, New Orleans and U.S. Fish and Wildlife Service, Ecological Services Office. If this permit is issued, the applicant has agreed to the following conditions provided in the SLOPES manual: Standard Manatee Conditions for In-Water Activities. This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the MagnusonStevens Fishery Conservation and Management Act. The applicant's proposal would result in the destruction or alteration of 0.31 of an acre of EFH utilized by various life stages of red drum and penaeid shrimp. Our initial determination is that the proposed action would not have a substantial adverse impact on EFH or federally managed fisheries in the Gulf of Mexico. Our final determination relative to project impacts and the need for mitigation measures is subject to review by and coordination with the National Marine Fisheries Service. If the proposed work involves deposits of dredged or fill material into navigable waters, the evaluation of the probable impacts will include the application of guidelines established by the Administrator of the Environmental Protection Agency. Also, a certification that the proposed activity will not violate applicable water quality standards will be required from the Department of Environmental Quality, Water Quality Certifications, before a permit is issued. Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. Requests for public hearings shall state, with particularity, the reasons for holding a public hearing. You are requested to communicate the information contained in this notice to any other parties whom you deem likely to have interest in the matter.

Darrell S. Barbara Chief, Western Evaluation Section Regulatory Branch Enclosure

STEP 5 ­ PERMIT AMENDMENT Shell has completed the 4350' Bayou Shaffer HDD from Avoca Island to Bateman Island. Because of Corps restrictions limiting work when the Mississippi River is +11 on the Carrollton Gage and hurricane season, the second HDD has been delayed until November. Shell would like to amend the permits to allow for improvements in the work conditions on site and changes to the scope of the project. Shell requests the following changes to the permit: 1. Shell proposes replacing the 2980' of pipeline between the two HDD exit sites. The permits allow two, 2' deep floatation ditches to float pipe between the HDD exits. Since Shell was unable to perform both drills during one mobilization, Shell elected to use only one floatation channel. After the second HDD pipe is installed, the floatation ditch will be deepened to allow the new pipe between the exit sites to be installed 4' deep. Sheets 6-9 & 17 show the new pipeline segment to be installed. Excavation and fill impacts will increase. 2. The existing pipeline between the drill sites will be abandoned in place increasing the total length of pipeline abandoned in place to 12,205'. The POB of abandoned pipe is on Sheet 4 of the drawings. The POE is on Sheet 11. 3. An additional 2980' of pipe will be brought onto Bateman Island to install the new pipe segment between the drill exits. Shell will be pushing almost 8000' of 22" pipe from Bayou Shaffer to the Atchafalaya River HDD Exit. The permit allows two floatation channels (2860' X 10' X 2' and 2860' X 2' X 15'). An additional 1289' X 50' workspace is between the Bayou Shaffer HDD exit and a 1.61 acre dock. Shell proposes reconfiguring the Bateman Island workspaces. a. Shell proposes one floatation ditch (new pipeline ROW) 3665' X 15' X 7'. b. Sheet 9 shows a new 400' X 35' wide pipe back string to the bank of Bayou Shaffer. The barge will be stationed adjacent to the new 400' X 35' back string space. This reconfiguration allows the pipe to be pushed off the barge in a straight line, rather than the curved line originally permitted from the dock to the Bayou Shaffer Exit. During the Bayou Shaffer drill, the pipe fell off the barge as the workers tried to curve the string to stay within the permitted workspace. Pushing the pipe straight from the barge in to the new, proposed back string workspace is a safer alternative. Only 0.77 acres of the 1.61 acres permitted at the dock were cleared. Adding the new back string workspace is impact neutral.

4. Bateman Island soils are mostly soft clay over a layer of organics that is 60% water and 3.5' thick. The worksite between the HDD exits is muddy and slick. It is difficult to for equipment and personnel to maneuver safely. a. Shell proposes using the 30' pipeline right of way between the Atchafalaya River and the Atchafalaya River HDD Exit as additional access. Mats will be used as needed. No clearing is required. Sheets 5 and 6 show the proposed, 1740' X 30' equipment access. The area immediately adjacent to the river is shown as non-wetlands on the wetlands delineation. b. Five, new road turnoffs 25' X 100' are proposed to allow equipment to pass safely. The turnoffs require 0.29 acres of additional tree clearing. The cleared area between the HDDs on Bateman Island was permitted at 5.49 acres. The actual amount cleared was 4.33 acres. The five new turnoffs will not increase tree impacts above the permitted amount. 5. The pipeline at the tie-in location on Avoca Island is only 2' deep. The stopple that will be used to connect the new pipe to the existing pipe will extend at least 1' above the pipe. One foot of cover is not adequate to protect the stopple. Adding fill or lowering the pipeline is required to complete the project. Shell proposes lowering 600' of pipeline an additional 4'. All work will take place within the existing pipeline right of way. Sheets 11 & 19 show the lowering details. 6. Shell proposes adding sand/cement bags under the rip rap permitted to be added in Atchafalaya River and Bayou Shaffer. (Sheet 19) 7. Shell and the landowner agree the Bateman Island worksites are unlikely to return to their original contours without additional fill. Shell proposes dredging a 240' X 120' area in Bayou Shaffer near the dock location to restore the Bateman Island work areas to original contours. (Sheet 20)

The project, as depicted on the revised drawings, impacts 11.92 acres of trees. The permits allow 14.44 acres of tree clearing. All new excavation and fill occur east of the Berwick Floodwall.

30 15

M

Texas

is

si

ss

ip

p

i

Arkansas

0

30

60

Scale - Miles

L o u i s i a n a

LOCATION

Coastal Zone Boundary

Gulf

of

Mexico

PROJECT LOCATION: X = 3,326,623' (NAD 83) Y = 429,082' (NAD 83) LAT: 29° 40' 47" (NAD 83) LONG: 91° 11' 21" (NAD 83)

PROJECT LOCATION: X = 3,315,147' (NAD 83) Y = 429,574' (NAD 83) LAT: 29° 40' 52" (NAD 83) LONG: 91° 13' 31" (NAD 83)

P.O.B./ BEGIN PROPOSED PIPELINE INSTALLATION/ TIE-IN/ PROPOSED EXCAVATION X = 3,315,147' Y = 429,574' LAT = 29° 40' 52" LONG = 91° 13' 31"

NAD 83 NAD 83

BEGIN PROPOSED EXCAVATION /PROPOSED TIE-IN/ P.O.E. X = 3,326,623' Y = 429,082' LAT = 29° 40' 47" LONG = 91° 11' 21"

NAD 83 NAD 83

PROJECT VICINITY

SCALE: 1" = 20,000'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

20,000'

10,000'

0'

20,000'

SHEET 1 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93851 00

MHW = MLW =

+3.0' +1.0' A AY AL AF R CH VE AT RI

SITE A: (1) PIPELINE EXCAVATION1,140'±X40'±X7.5'± (2) TIE-IN PIT EXCAVATION50'±X40'±X7.5'± (3) WORK SPACE- 200'±X200'±

SITE F: (1) PIPELINE EXCAVATION415'±X40'±X7.5'± (2) TIE-IN PIT EXCAVATION50'±X40'±X7.5'± (3) LOWERING EXCAVATION600'±X10'±X6'± (4) WORK SPACE- 200'±X200'±

END PROPOSED EXCAVAION/ PROPOSED POINT OF ENTRY X = 3,314,573' Y = 430,177' LAT = 29° 40' 58" LONG = 91° 13' 37"

END PROPOSED EXCAVATION/ PROPOSED POINT OF ENTRY

NAD 83 NAD 83

X = 3,326,190' Y = 429,172' LAT = 29° 40' 48" LONG = 91° 11' 26"

END PROPOSED EXCAVATION/ PROPOSED POINT OF EXIT X = 3,321,850' Y = 428,970' LAT = 29° 40' 46.26" LONG = 91° 12' 15.01"

SHEET 3 & 4

NAD 83 NAD 83

NAD 83 NAD 83

SITE D: (1) PIPELINE EXCAVATION40'±X40'±X7.5'± (2) TIE-IN PIT EXCAVATION50'±X40'±X7.5'± (3) WORK SPACE- 200'±X200'±

PROPOSED EQUIPMENT ACCESS- 6,450'± X 30'±

SHEET 9 & 10

SHEET 6

SHEET 5

P.O.B./ BEGIN PROPOSED PIPELINE INSTALLATION/ TIE-IN/ PROPOSED EXCAVATION NAD 83 NAD 83

SHEET 11

SHEET 8

AREA TO BE CLEARED, CHIPPED, & USED AS FILL DUE TO EQUIPMENT ACCESS (10± YDS/ 0.02± ACRES)

PROPOSED EQUIPMENT ACCESS- 3,660'± X 30'±

SITE C: (1) FLOTATION CHANNEL3,665'±X15'±X7'± (2) EXISTING ROW- 30'± (3) WORK SPACE2,860'±X80'±

SITE B: (1) PIPELINE EXCAVATION150'±X40'±X7.5'± (2) TIE-IN PIT EXCAVATION50'±X40'±X7.5'± (3) WORK SPACE- 250'±X250'±

U BAYO

X = 3,315,147' Y = 429,574' LAT = 29° 40' 52" LONG = 91° 13' 31"

SHEET 7

SHAF

PROPOSED POINT OF EXIT/ END PROPOSED EXCAVATION

BEGIN EXCAVATION/TIE-IN/ END PIPELINE ABANDONMENT/P.O.E. X = 3,326,661' Y = 429,095' LAT = 29° 40' 47.43" LONG = 91° 11' 20.46"

NAD 83 NAD 83

FER

X = 3,318,765' Y = 428,547' LAT = 29° 40' 42.10" LONG = 91° 12' 49.98"

SITE E: (1) WORK SPACE- 1,800'±X80'±

NAD 83 NAD 83

NOTE: ONLY THE 4 TRENCHED AREAS OF THE PROPOSED PIPELINE WILL BE SUBJECT TO PHYSICAL INSPECTION IN THE FUTURE. THESE AREAS ARE: · THE 1,120' SEGMENT FROM BERWICK STATION TO THE ATCHAFALAYA RIVER HDD ENTRY TIE-IN · THE 60' TIE-IN OF THE BAYOU SHAFFER HDD EXIT TO THE EXISTING PIPELINE ON BATEMAN ISLAND · THE 415' TIE-IN OF THE BAYOU SHAFFER DRILL TO THE EXISTING PIPELINE ON AVOCA ISLAND THE TYPE OF EQUIPMENT AND CLEARING REQUIREMENTS WILL DEPEND ON THE NATURE OF THE REPAIR.

SCALE: 1" = 2000'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

2000'

1000'

0'

2000'

SHEET 2 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93852 00

MHW = MLW =

+3.0' +1.0'

WETLAND LEGEND: PALUSTRINE FORESTED WETLANDS PALUSTRINE EMERGENT WETLANDS

EXISTING SHELL PIPELINE TO REMAIN IN PLACE

PROPOSED TEMPORARY SPOIL PLACEMENT- 115'± X 85'± X 20'± (4,275± CY/ 0.22± ACRES) WORK AREA TO BE CLEARED, CHIPPED, & USED AS FILL (300± CY/ 0.74± ACRES)

20 0'±

20 0'±

PROPOSED BORE PIT EXCAVATION- 50'± X 40'± SEE SHEET 15 FOR DETAIL PROPOSED 22-INCH PIPELINE TO BE INSTALLED- 1,120'±

PROPOSED TEMPORARY SPOIL PLACEMENT- 60'± X 60'± X 10'± (900± CY/ 0.08± ACRES) END PROPOSED EXCAVATION/ PROPOSED POINT OF ENTRY X = 3,314,573' Y = 430,177' LAT = 29° 40' 58" LONG = 91° 13' 37"

75'±

NAD 83

EXISTING SHELL FACILITY

NAD 83

WORK AREA TO BE CLEARED, CHIPPED, & USED AS FILL (182± CY/ 0.45± ACRES) PROPOSED EXCAVATION (1,140'± X 40'±) SEE SHEET 12 & 18 FOR DETAIL P.O.B./ BEGIN PROPOSED PIPELINE INSTALLATION/ TIE-IN/ PROPOSED EXCAVATION/

BEGIN PIPELINE ABANDONMENT X = 3,315,147' Y = 429,574' LAT = 29° 40' 52" LONG = 91° 13' 31"

NAD 83 NAD 83

PROPOSED TEMPORARY SPOIL PLACEMENT- 90'± X 75'± X 15'± (2,650± CY/ 0.15± ACRES)

NOTE: PROPOSED TIMBER MATS TO BE USED FOR EQUIPMENT ACCESS. THIS SHEET TO SHOW LOOP CONNECTION ONLY. SEE SHEET 4 FOR HDD INSTALLATION PLAN VIEW.

EXISTING SHELL PIPELINE TO BE CUT, CAPPED, & ABANDONED IN PLACE- 12,205'± SCALE: 1" = 200'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

200'

100'

0'

200'

SHEET 3 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93853 00

MHW = MLW =

+3.0' +1.0'

WETLAND LEGEND: PALUSTRINE FORESTED WETLANDS PALUSTRINE EMERGENT WETLANDS

EXISTING SHELL PIPELINE TO REMAIN IN PLACE

PROPOSED TEMPORARY SPOIL PLACEMENT- 115'± X 85'± X 20'± (4,275± CY/ 0.22± ACRES) WORK AREA TO BE CLEARED, CHIPPED, & USED AS FILL (300± CY/ 0.74± ACRES)

20 0'±

20 0'±

PROPOSED BORE PIT EXCAVATION- 50'± X 40'± SEE SHEET 15 FOR DETAIL PROPOSED TEMPORARY SPOIL PLACEMENT- 60'± X 60'± X 10'± (900± CY/ 0.08± ACRES) END PROPOSED EXCAVATION/ PROPOSED POINT OF ENTRY X = 3,314,573' Y = 430,177' LAT = 29° 40' 58" LONG = 91° 13' 37"

75'±

NAD 83

EXISTING SHELL FACILITY

NAD 83

WORK AREA TO BE CLEARED, CHIPPED, & USED AS FILL (182± CY/ 0.45± ACRES)

PROPOSED 22-INCH HDD PIPELINE TO BE INSTALLED- 4,860'±

PROPOSED TEMPORARY SPOIL PLACEMENT- 90'± X 75'± X 15'± (2,650± CY/ 0.15± ACRES)

NOTE: PROPOSED TIMBER MATS TO BE USED FOR EQUIPMENT ACCESS. THIS SHEET TO SHOW HDD INSTALLATION ONLY. SEE SHEET 3 FOR LOOP CONNECTION PLAN VIEW.

EXISTING SHELL PIPELINE TO BE CUT, CAPPED, & ABANDONED IN PLACE- 12,205'± SCALE: 1" = 200'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

200'

100'

0'

200'

SHEET 4 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93854 00

MHW = MLW =

+3.0' +1.0'

WETLAND LEGEND: PALUSTRINE FORESTED WETLANDS

RI V

ER

PALUSTRINE EMERGENT WETLANDS

A

TC H

A

FA

LA

Y

A

PROPOSED SAND BAGS & RIP RAP MATERIAL- 75'± X 30'± (120± CY/ 0.05± ACRES) SEE SHEET 19 FOR DETAIL

PROPOSED SAND BAGS & RIP RAP MATERIAL- 230'± X 30'± (245± CY/ 0.16± ACRES) SEE SHEET 19 FOR DETAIL EXISTING SHELL PIPELINE TO BE CUT, CAPPED, & ABANDONED IN PLACE- 12,205'±

30'±

PROPOSED 22-INCH HDD PIPELINE TO BE INSTALLED- 4,860'±

EMERGENT WETLANDS/ EXISTING SHELL ROW UTILIZED DUE TO EQUIPMENT ACCESS- 1,740'± X 30'± (1.03± ACRES)

NOTE: PROPOSED TIMBER MATS TO BE USED FOR EQUIPMENT ACCESS SCALE: 1" = 200'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

200'

100'

0'

200'

SHEET 5 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93855 00

MHW = MLW =

+3.0' +1.0'

WETLAND LEGEND: PALUSTRINE FORESTED WETLANDS PALUSTRINE EMERGENT WETLANDS

INSTALLED 22-INCH PIPELINE- 2,980'± WORK AREA CLEARED, CHIPPED, & USED AS FILL (1,745± CY/ 4.33± ACRES) EXISTING 30' CLEARED ROW

PROPOSED EXCAVATION /PROPOSED TIE-IN X = 3,318,907' Y = 428,566' LAT = 29° 40' 42.29" LONG = 91° 12' 48.37"

NAD 83

EQUIPMENT ACCESS & FLOATATION CHANNEL SEE SHEET 17 FOR DETAIL

NAD 83

EMERGENT WETLANDS/ EXISTING SHELL ROW TO BE UTILIZED DUE TO EQUIPMENT ACCESS- 1,740'± X 30'± (1.03± ACRES) PROPOSED 22-INCH PIPELINE TO BE INSTALLED- 145'±

132'± 30'±

EXISTING SHELL PIPELINE TO BE CUT, CAPPED, & ABANDONED IN PLACE12,205'± 250'±

MATCHLINE A

250'±

WORK AREA CLEARED, CHIPPED, & USED AS FILL (475± CY/ 1.17± ACRES)

PROPOSED BORE PIT EXCAVATION- 50'± X 40'± SEE SHEET 15 FOR DETAIL

PROPOSED EXCAVATION150'± X 40'± SEE SHEET 18 FOR DETAIL

PROPOSED 22-INCH HDD PIPELINE TO BE INSTALLED- 4,860'±

PROPOSED POINT OF EXIT/ END PROPOSED EXCAVATION X = 3,318,765' Y = 428,547' LAT = 29° 40' 42.10" LONG = 91° 12' 49.98"

NAD 83 NAD 83

NOTE: PROPOSED TIMBER MATS TO BE USED FOR EQUIPMENT ACCESS SCALE: 1" = 200'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

200'

100'

0'

200'

SHEET 6 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93856 00

MHW = MLW =

+3.0' +1.0'

WETLAND LEGEND: PALUSTRINE FORESTED WETLANDS PALUSTRINE EMERGENT WETLANDS

FLOATATION CHANNEL EXCAVATION (9,165± CY/ 1.22± ACRES) SEE SHEET 17 FOR DETAIL PROPOSED ROAD TURNOFF TYP.- 100'± X 25'± (0.29 ACRES TOTAL TO BE CLEARED, CHIPPED, & USED AS FILL) WORK AREA CLEARED, CHIPPED, & USED AS FILL (1,745± CY/ 4.33± ACRES) EXISTING 30' CLEARED ROW

MATCHLINE A

EXISTING SHELL PIPELINE TO BE CUT, CAPPED, & ABANDONED IN PLACE- 12,205'± INSTALLED 22-INCH PIPELINE- 2,980'±

MATCHLINE B

80'±

TEMPORARY SPOIL PLACEMENT- 2,860'± X 10'± (7,415± CY/ 0.66± ACRES)

NOTE: PROPOSED TIMBER MATS TO BE USED FOR EQUIPMENT ACCESS SCALE: 1" = 200'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

200'

100'

0'

200'

SHEET 7 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93857 00

MHW = MLW =

+3.0' +1.0'

WETLAND LEGEND: PALUSTRINE FORESTED WETLANDS PALUSTRINE EMERGENT WETLANDS

INSTALLED 22-INCH HDD PIPELINE- 4,350'± BORE PIT EXCAVATION- 50'± X 40'± SEE SHEET 15 FOR DETAIL END EXCAVATION/ POINT OF EXIT X = 3,321,850' Y = 428,970' LAT = 29° 40' 46.26" LONG = 91° 12' 15.01"

NAD 83 NAD 83

TEMPORARY SPOIL PLACEMENT- 75'± X 75'± X 15'± (460± CY/ 0.13± ACRES)

INSTALLED 22-INCH PIPELINE- 2,980'± EQUIPMENT ACCESS & FLOATATION CHANNEL SEE SHEET 17 FOR DETAIL

200'±

80'±

80'±

MATCHLINE B

MATCHLINE C

200'±

EXISTING SHELL PIPELINE TO BE CUT, CAPPED, & ABANDONED IN PLACE- 12,205'±

EXCAVATION- 40'± X 40'± SEE SHEET 18 FOR DETAIL

WORK AREA CLEARED, CHIPPED, & USED AS FILL (1,745± CY/ 4.33± ACRES) EXISTING 30' CLEARED ROW

WORK AREA CLEARED, CHIPPED, & USED AS FILL (215± CY/ 0.53± ACRES) WORK AREA CLEARED, CHIPPED, & USED AS FILL (370± CY/ 0.91± ACRES) EXISTING 30' CLEARED ROW

NOTE: PROPOSED TIMBER MATS TO BE USED FOR EQUIPMENT ACCESS SCALE: 1" = 200'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

200'

100'

0'

200'

SHEET 8 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93858 00

MHW = MLW =

+3.0' +1.0'

WETLAND LEGEND: PALUSTRINE FORESTED WETLANDS PALUSTRINE EMERGENT WETLANDS

WORK AREA SEE SHEET 10 FOR DETAIL

ADDITIONAL WORK AREA CLEARED, CHIPPED, & USED AS FILL (60± CY/ 0.15± ACRES) WORK AREA- 640'± X 80'±

20

0' ±

35 0'

±

WORK AREA CLEARED, CHIPPED, & USED AS FILL (370± CY/ 0.91± ACRES) WORK AREA- 660'± X 50'±

50'± 80'±

WORK AREA TO BE CLEARED, CHIPPED, & USED AS FILL (125± CY/ 0.31± ACRES)

35'±

ER

INSTALLED 22-INCH HDD PIPELINE- 4,350'±

Y O

U

SH

A FF

EXISTING SHELL PIPELINE TO BE CUT, CAPPED, & ABANDONED IN PLACE- 12,205'±

BA

MATCHLINE C

PROPOSED BACK STRING

TEMPORARY SPOIL PLACEMENT- 620'± X 10'± (1,750± CY/ 0.14± ACRES)

PROPOSED SAND BAGS & RIP RAP MATERIAL- 155'± X 30'± (240± CY/ 0.10± ACRES) SEE SHEET 19 FOR DETAIL

NOTE: PROPOSED TIMBER MATS TO BE USED FOR EQUIPMENT ACCESS SCALE: 1" = 200'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

200'

100'

0'

200'

SHEET 9 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93859 00

MHW = MLW =

+3.0' +1.0'

WETLAND LEGEND: PALUSTRINE FORESTED WETLANDS PALUSTRINE EMERGENT WETLANDS

±

WORK AREA CLEARED, CHIPPED, & USED AS FILL (310± YDS/ 0.77± ACRES)

35

0'

20

0' ±

PROPOSED BACK STRING

O

U

SH

A

FF

ER

INSTALLED 22-INCH HDD PIPELINE- 4,350'±

BA

Y

NOTE: PROPOSED TIMBER MATS TO BE USED FOR EQUIPMENT ACCESS

SCALE: 1" = 100'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

100'

50'

0'

100'

SHEET 10 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 03/11/2015 TBS-2014.0525

SPLC-GOM-HE-SA-90918 01

MHW = MLW =

+3.0' +1.0'

END EXCAVATION/ POINT OF ENTRY X = 3,326,190' Y = 429,172' LAT = 29° 40' 48" LONG = 91° 11' 26"

NAD 83

EXISTING SHELL PIPELINE TO REMAIN IN PLACE

TEMPORARY SPOIL PLACEMENT- 125'± X 75'± X 20'± (3,025± CY/ 0.22± ACRES)

200'±

BORE PIT EXCAVATION- 50'± X 40'± SEE SHEET 15 FOR DETAIL

NAD 83

200'±

INSTALLED 22-INCH HDD PIPELINE- 4,350'±

WORK AREA CLEARED, CHIPPED, & USED AS FILL (170± CY/ 0.42± ACRES) 90'±

WORK AREA CLEARED, CHIPPED, & USED AS FILL (490± CY/ 0.92± ACRES)

30'±

EXCAVATION- 415'± X 40'± SEE SHEET 18 FOR DETAIL

BEGIN EXCAVATION/TIE-IN/ END PIPELINE ABANDONMENT/P.O.E. X = 3,326,661' Y = 429,095' LAT = 29° 40' 47.43" LONG = 91° 11' 20.46"

30'±

INSTALLED 22-INCH PIPELINE- 485'±

EXISTING SHELL PIPELINE TO BE CUT, CAPPED, & ABANDONED IN PLACE- 12,205'±

NAD 83 NAD 83

PROPOSED LOWERING600'± X 10'± SEE SHEET 19 FOR DETAIL PROPOSED TEMPORARY SPOIL PLACEMENT- 600'± X 10'± X 6'± (1,000± CY/ 0.14± ACRES)

EMERGENT WETLANDS/ EXISTING SHELL ROW UTILIZED DUE TO EQUIPMENT ACCESS- 3,375'± X 30'± (2.44± ACRES)

WETLAND LEGEND: PALUSTRINE FORESTED WETLANDS

NOTE: PROPOSED TIMBER MATS TO BE USED FOR EQUIPMENT ACCESS

PALUSTRINE EMERGENT WETLANDS SCALE: 1" = 200'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

200'

100'

0'

200'

SHEET 11 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93860 01

MHW = MLW =

+3.0' +1.0'

P.O.B./ BEGIN PROPOSED PIPELINE INSTALLATION/ TIE-IN/ PROPOSED EXCAVATION X = 3,315,147' Y = 429,574' LAT = 29° 40' 52" LONG = 91° 13' 31"

END PROPOSED EXCAVATION/ PROPOSED POINT OF ENTRY X = 3,314,573' Y = 430,177' LAT = 29° 40' 58" LONG = 91° 13' 37"

NAD 83 NAD 83

NAD 83 NAD 83

1,140'± NATURAL GROUND

PROPOSED 22" SHELL PIPELINE TO BE INSTALLED

4' MIN. EXSITING 22" SHELL PIPELINE TO REMAIN IN PLACE

PROPOSED EXCAVATION (7,640± YDS³/ 1.02± ACRES)

7.5'± EXSITING DRAINAGE DITCH PROPOSED 22" HDD PIPELINE TO BE INSTALLED

PIPELINE EXCAVATION PROFILE BERWICK STATION TIE-IN PIPE

NOT TO SCALE THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

SHEET 12 OF 21 HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93861 00

MHW = MLW =

+3.0' +1.0'

END PROPOSED EXCAVAION/ PROPOSED POINT OF ENTRY

PROPOSED POINT OF EXIT/ END PROPOSED EXCAVATION

X = 3,314,573' Y = 430,177' LAT = 29° 40' 58" LONG = 91° 13' 37"

X = 3,318,765' Y = 428,547' LAT = 29° 40' 42.10" LONG = 91° 12' 49.98"

NAD 83 NAD 83

EXISTING LEVEE & FLOOD WALL

NAD 83 NAD 83

NATURAL GROUND

ATCHAFALAYA RIVER

PROPOSED 22-INCH HDD PIPELINE TO BE INSTALLED- 4,860'±

HORIZONTAL SCALE: 1" = 600'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

600'

300' 0' VERTICAL SCALE: 1" = 100'

600'

100'

50'

100'

0'

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

SHEET 13 OF 21 PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93862 00

MHW = MLW =

+3.0' +1.0'

HDD COMPLETED

END EXCAVATION/ POINT OF EXIT X = 3,321,850' Y = 428,970' LAT = 29° 40' 46.26" LONG = 91° 12' 15.01"

END EXCAVATION/ POINT OF ENTRY X = 3,326,190' Y = 429,172' LAT = 29° 40' 48" LONG = 91° 11' 26"

NAD 83 NAD 83

NAD 83 NAD 83

EXISTING LEVEE

NATURAL GROUND

BAYOU SHAFFER

INSTALLED 22-INCH HDD PIPELINE- 4,350'±

HORIZONTAL SCALE: 1" = 600'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

600'

300' 0' VERTICAL SCALE: 1" = 100'

600'

100'

50'

100'

0'

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

SHEET 14 OF 21 PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93863 00

PROPOSED 22" HDD PIPELINE TO BE INSTALLED

50'±

40'±

PROPOSED BORE PIT EXCAVATION (185± YDS³/ 0.05± ACRES)

40'±

4' MIN. PROPOSED BORE PIT EXCAVATION (185± YDS³/ 0.05± ACRES)

10'±

7.5'±

PROPOSED 22" HDD PIPELINE TO BE INSTALLED

Proposed temporary spoil placement to be stockpiled within workspace and used as backfill. See plan views for location & dimensions.

EXCAVATION DETAIL- BORE PIT SCALE: 1" = 20'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

20'

10'

0'

20'

SHEET 15 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93864 00

+3.0' +1.0'

20'±

MHW = MLW =

185'±

250'±

20'±

250'±

20'±

20'± 160'±

PROPOSED TEMPORARY RING LEVEE (2,495± YDS³/ 0.35± ACRES)

PROPOSED EXCAVATION FOR RING LEVEE CONSTRUCTION (1,150± YDS³/ 0.33± ACRES)

250'± 20'±

5'±

20'± NATURAL GROUND

20'±

160'±

PROPOSED TEMPORARY RING LEVEE (2,495± YDS³/ 0.35± ACRES)

5'±

20'±

PROPOSED EXCAVATION FOR RING LEVEE CONSTRUCTION (1,150± YDS³/ 0.33± ACRES)

Approximately 330± yds³ of native material to be used for ring levee construction will derive from bore pit & tie-in excavation.

EXCAVATION DETAIL- RING LEVEE SCALE: 1" = 20'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

20'

10'

0'

20'

SHEET 16 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93865 00

MHW = MLW =

+3.0' +1.0'

EXISTING 30' ROW (CLEARED)

25'±

45'±

15'±

ROAD TURNOFF

EQUIPMENT ACCESS

5'±

FLOATATION CHANNEL EXCAVATION (9,165± YDS³/ 1.22± ACRES)

TIMBER MATS

TEMPORARY SPOIL PLACEMENT (7,415± YDS³/ 0.66± ACRES)

INSTALLED 22-INCH PIPELINE

105'±

25'±

EXISTING SHELL PIPELINE TO BE ABANDONED IN PLACE

EXISTING 30' ROW (CLEARED) PROPOSED FLOATATION CHANNEL

EQUIPMENT ACCESS

ROAD TURNOFF

15'±

10'±

2,860'±

100'±

105'±

45'±

15'±

5'±

15'±

10'±

7'± TIMBER MATS

FLOTATION CHANNEL EXCAVATION (9,165± YDS³/ 1.22± ACRES)

5'± 4' MIN.

5'±

INSTALLED 22-INCH PIPELINE

TEMPORARY SPOIL PLACEMENT (7,415± YDS³/ 0.66± ACRES)

EXISTING SHELL PIPELINE TO BE ABANDONED IN PLACE

EXCAVATION DETAIL- FLOATATION CHANNEL SCALE: 1" = 20'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

20'

10'

0'

20'

SHEET 17 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93866 00

Pipeline Installation Excavations: Sheet 3 1,140'Lx40'W 7,640± yds³ Sheet 6 150'Lx40'W 1,030± yds³ Sheet 8 40'Lx40'W 275± yds³ Sheet 11 415'Lx40'W 2,840± yds³

1.02± acres 0.14± acres 0.03± acres 0.37± acres

VARIES

40'±

PROPOSED EXCAVATION FOR PIPELINE INSTALLATION

PROPOSED 22" PIPELINE TO BE INSTALLED

NATURAL GROUND

40'±

7.5'±

4' MIN. PROPOSED EXCAVATION FOR PIPELINE INSTALLATION

10'±

PROPOSED 22" PIPELINE TO BE INSTALLED

Proposed temporary spoil placement to be stockpiled within workspace and used as backfill. See plan views for location & dimensions.

EXCAVATION DETAIL- ON LAND SCALE: 1" = 10'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

10'

5'

0'

10'

SHEET 18 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93867 00

MHW = MLW =

+3.0' +1.0' 2'± 4'±

1.5'± PROPOSED SAND BAG PLACEMENT

PROPOSED RIP RAP MATERIAL EXISTING MUDLINE

EXISTING 22" PIPELINE TO BE ABANDONED

RIP RAP DETAIL

5'± NATURAL GROUND

10'±

10'±

6'±

PROPOSED EXCAVATION (1,000± YDS³/ 0.14± ACRES) EXISTING 22" PIPELINE TO BE LOWERED

6'±

5'±

PROPOSED TEMPORARY SPOIL PLACEMENT (1,000± YDS³/ 0.14± ACRES)

5'±

LOWERING DETAIL PROPOSED TIMBER MATS

VARIES

Temporary board mats will be used as needed to minimize impacts.

NATURAL GROUND PROPOSED EXCAVATION

TIMBER MAT DETAIL

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

NOT TO SCALE

SHEET 19 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93868 00

MHW = MLW =

+3.0' +1.0'

PROPOSED BORROW PIT (9,160± CY/ 0.66 ACRES) ACCESS ROUTE AND OFFLOADING AREA TO BE RECLAIMED WITH BORROW MATERIAL (4,110± CY/ 0.97 ACRES) 20

12 0'

0'

±

24

0'

35 0' ±

ACCESS ROUTE- 1,300'± X 40'± TO BE RECLAIMED WITH BORROW MATERIAL. APPROXIMATELY 85% OF AREA TO BE RESTORED (5,050± CY / 1.19 ACRES) 40'±

200'±

35'±

WORK AREA TO BE CLEARED (SEE SHEET 9)

200'±

YO U

SH

AF F

ER

INSTALLED 22-INCH HDD PIPELINE- 4,350'±

BA

ARMORING (SEE SHEET 9) SCALE: 1" = 300'

NOTE: ±9,160 CY OF BORROW MATERIAL DREDGED FROM BAYOU SHAFFER TO BE PLACED WITHIN ACCESS ROUTE AND OFFLOADING AREA TO RESTORE WORK AREA TO PRE-EXISTING CONDITIONS. APPROXIMATELY 1.5' OF FILL REQUIRED TO RESTORE WORK AREA.

300'

150'

0'

300'

EXISTING BANK LINE 50.0'

120.0'

1 PROPOSED BORROW PIT EXCAVATION

1

10.0' 100.0'

EXISTING GRADE

SECTION VIEW - BORROW PIT SCALE: 1" = 40'

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

SHEET 20 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93869 00

NOTES

SEE EXHIBIT "A" FOR TOTAL IMPACTS TOTAL IMPACTS

EQUIPMENT

EXCAVATIONS

FILL AREAS

FILL MATERIALS

THESE PLATS ARE TO BE USED EXCLUSIVELY FOR THE ACQUISITION OF REGULATORY PERMITS.

SHEET 21 OF 21

HOUMA-ERATH CRUDE PL SEG-BERWICK TO HOUMA

PROPOSED HORIZONTAL DIRECTIONAL DRILL ACROSS ATCHAFALYA RIVER & BAYOU SHAFFER ST. MARY PARISH, LOUISIANA 04/09/2015 TBS-2014.0525

SPLC-GOM-HE-SA93870 01

EXHIBIT "A"

PERMITTED PROJECT IMPACTS WEST OF RIVER EXCAVATIONS Non-Vegetated Water 80 CYS Bottoms 0.01 ACS 4425 CY Wetlands 0.623 ACS 3400 CY Non-Wetlands 0.46 ACS Fill Excavated Material 2650 CY 0.15 ACS Non-Wetlands 5255 CY Wetlands 0.3 ACS Chipped Trees 906 CY Wetlands 1.84 ACS 74 CY Non-Wetlands 0.15 ACS

EAST OF RIVER

EXCAVATIONS Non-Vegetated Water Bottoms 10,970 CY 2.897 ACS

Wetlands Non-Wetlands Fill Excavated Material Non-Wetlands

10,970 CY 3.33 ACS 6402 CY 12.29 ACS 82 CY 0.16 ACS

Rip Rap

Non-Vegetated Water Bottoms

PROPOSED AMENDED PROJECT IMPACTS WEST OF EAST OF RIVER RIVER

605 CY 0.31 ACS

Wetlands Chipped Trees Wetlands Non-Wetlands Rip Rap/Sand Bags

Non-Vegetated Water Bottoms

80 CYS 0.01 ACS 4425 CY 0.623 ACS 3400 CY 0.44 ACS

9160 CYS 0.66 ACS 15,935 CY 3.37 ACS

2650 CY 0.15 ACS 5255 CY 0.3 ACS

25,095 CY 5.43 ACS

906 CY 1.84 ACS 74 CY 0.15 ACS

6402 CY 12.29 ACS 82 CY 0.16 ACS

605 CY 0.31 ACS

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas