You can copy from here when filling out the rest of the page.
Broward County. Westrec Marinas. Dania Beach. FL. PROJECT PURPOSE: Basic: To reconfigure existing docks at a commercial marina. Overall: To reconfigure existing docks at a commercial marina along the Intracoastal Waterway near the Port Everglades Inlet to accommodate for larger vessels.
TO WHOM IT MAY CONCERN: The Jacksonville District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344) and Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. §403) as described below:
APPLICANT: Westrec Marinas
801 NE 3rd Street
Dania Beach, FL 33004
WATERWAY AND LOCATION: The project would affect waters of the United States associated with the Intracoastal Waterway. The project site is located at 431 and 425 Seabreeze Boulevard Section 12, Township 50, Range 42, Fort Lauderdale, Broward County, Florida.
Directions to the site are as follows: Take 95 South to exist 27, East on Broward Boulevard. Take a right onto SE 12th Avenue. Take a left onto E Las Olas Boulevard. Turn right onto Seabreeze Boulevard. The property will be on the right in 0.2 miles.
APPROXIMATE CENTRAL COORDINATES:
Latitude: 26.11588°
Longitude: -80.13052°
PROJECT PURPOSE:
Basic: To reconfigure existing docks at a commercial marina.
Overall: To reconfigure existing docks at a commercial marina along the Intracoastal Waterway near the Port Everglades Inlet to accommodate for larger vessels.
EXISTING CONDITIONS: The developed property consists of an existing 43-slip marina along the Intracoastal Waterway. The project site contains an existing concrete panel seawall with cap, marginal wood docks and finger piers. The existing area surrounding the project area consists of commercial and residential developments. The submerged bottom of the project footprint includes silt, sand, and algae.
PROPOSED WORK: The applicant seeks authorization for the replacement and reconfiguration of a portion of the existing finger piers and docks. The existing marina consists of ±10,152 ft² of finger piers, of which ±6,703 ft² are to remain. The proposed project includes installation of ±6,251 ft² of floating docks, for a total of ±12,954 ft², and a slip increase of 1 (from 43 slips to 44 slips).
AVOIDANCE AND MINIMIZATION INFORMATION – The applicant has provided the following information in support of efforts to avoid and/or minimize impacts to the aquatic environment:
The applicant has agreed to install turbidity curtains during all in-water work. The applicant agrees to abide by the Sea Turtle and Smalltooth Sawfish Construction Conditions and the Standard Manatee Conditions.
COMPENSATORY MITIGATION – The applicant has provided the following explanation why compensatory mitigation should not be required:
As there are no mangroves, wetland vegetation, submerged resources, or submerged grassbeds within the project boundary, there are no proposed adverse impacts to resources as a result of this project, and therefore, no compensatory mitigation is proposed.
CULTURAL RESOURCES:
The Corps is not aware of any known historic properties within the permit area. By copy of this public notice, the Corps is providing information for review. Our final determination relative to historic resource impacts is subject to review by and coordination with the State Historic Preservation Officer and, if applicable, those federally recognized tribes with concerns in Florida and the Permit Area.
ENDANGERED SPECIES:
The Corps has determined the proposed project would have no effect on the American Crocodile (Crocodylus acutus), Piping Plover (Charadrius melodus), and the Wood stork (Mycteria americana); however the proposed project may affect, but is not likely to adversely affect the threatened West Indian Manatee (Trichechus manatus). The Corps will request U.S. Fish and Wildlife Service concurrence with this determination for the manatee pursuant to Section 7 of the Endangered Species Act.
The Corps has determined the proposed project would have no effect on Johnson’s seagrass (Halophila johnsonii); however the project may affect, but is not likely to adversely affect the threatened and endangered swimming sea turtles; loggerhead (Caretta caretta), green (Chelonia mydas), leatherback (Dermochelys coriacea), hawksbill (Eretmochelys imbricata), and Kemp's Ridley (Lepidochelys kempii), and the threatened smalltooth sawfish (Pristis pectinata) and would not adversely modify their designated critical habitat. The Corps will request National Marine Fisheries Service concurrence with these determinations pursuant to Section 7 of the Endangered Species Act by separate letter.
ESSENTIAL FISH HABITAT (EFH): This notice initiates consultation with the National Marine Fisheries Service on EFH as required by the Magnuson-Stevens Fishery Conservation and Management Act 1996. The proposal would impact approximately 0.14 acres of sand, silt, algae, and crushed shell bottom utilized by various life stages of penaeid shrimp complex, reef fish, stone crab, spiny lobster, migratory/pelagic fish, and snapper/grouper complex. Our initial determination is that the proposed action would not have a substantial adverse impact on EFH or Federally managed fisheries in the South Atlantic Region. Our final determination relative to project impacts and the need for mitigation measures is subject to review by and coordination with the National Marine Fisheries Service.
NAVIGATION: Based on the Florida State Plane coordinates provided by the applicant, the waterward edge of the proposed structure is 112.51 feet away from the near bottom edge of the Intracoastal Waterway Federal channel.
NOTE: This public notice is being issued based on information furnished by the applicant. This information has not been verified or evaluated to ensure compliance with laws and regulation governing the regulatory program. The jurisdictional line [has/has not] been verified by Corps personnel.
AUTHORIZATION FROM OTHER AGENCIES: Water Quality Certification may be required from the Florida Department of Environmental Protection and/or one of the state Water Management Districts.
COMMENTS regarding the potential authorization of the work proposed should be submitted in writing to the attention of the District Engineer through the Palm Beach Gardens Permits Section, 4400 PGA Boulevard, Suite 500, Palm Beach Gardens, FL 33410 within 21 days from the date of this notice.
The decision whether to issue or deny this permit application will be based on the information received from this public notice and the evaluation of the probable impact to the associated wetlands. This is based on an analysis of the applicant's avoidance and minimization efforts for the project, as well as the compensatory mitigation proposed.
QUESTIONS concerning this application should be directed to the project manager, Kelly Egan, in writing at the Palm Beach Gardens Permits Section, 4400 PGA Boulevard, Suite 500, Palm Beach Gardens, FL 33410; by electronic mail at Kelly.Egan@usace.army.mil; or, by telephone at (561) 472-3514.
IMPACT ON NATURAL RESOURCES: Coordination with U.S. Fish and Wildlife Service, Environmental Protection Agency (EPA), the National Marine Fisheries Services, and other Federal, State, and local agencies, environmental groups, and concerned citizens generally yields pertinent environmental information that is instrumental in determining the impact the proposed action will have on the natural resources of the area.
EVALUATION: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefits, which reasonably may be expected to accrue from the proposal, must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including cumulative impacts thereof; among these are conservation, economics, esthetics, general environmental concerns, wetlands, historical properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food, and fiber production, mineral needs, considerations of property ownership, and in general, the needs and welfare of the people. Evaluation of the impact of the activity on the public interest will also include application of the guidelines promulgated by the Administrator, EPA, under authority of Section 404(b) of the Clean Water Act or the criteria established under authority of Section 102(a) of the Marine Protection Research and Sanctuaries Act of 1972. A permit will be granted unless its issuance is found to be contrary to the public interest.
The US Army Corps of Engineers (Corps) is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other Interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this determination, comments are used to assess impacts to endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.
COASTAL ZONE MANAGEMENT CONSISTENCY: In Florida, the State approval constitutes compliance with the approved Coastal Zone Management Plan. In Puerto Rico, a Coastal Zone Management Consistency Concurrence is required from the Puerto Rico Planning Board. In the Virgin Islands, the Department of Planning and Natural Resources permit constitutes compliance with the Coastal Zone Management Plan.
REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The request must be submitted in writing to the District Engineer within the designated comment period of the notice and must state the specific reasons for requesting the public hearing.
DEPARTMENT OF THE ARMY
JACKSONVILLE DISTRICT CORPS OF ENGINEERS
4400 PGA BLVD, SUITE 500
PALM BEACH GARDENS, FLORIDA 33410
September 15, 2017
REPLY TO
ATTENTION OF
Regulatory Division
South Permits Branch
Palm Beach Gardens Permits Section
PUBLIC NOTICE
Permit Application No. SAJ-2017-00806 (SP-KAE)
TO WHOM IT MAY CONCERN: The Jacksonville District of the U.S. Army Corps of
Engineers (Corps) has received an application for a Department of the Army permit
pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344) and Section 10 of the
Rivers and Harbors Act of 1899 (33 U.S.C. §403) as described below:
APPLICANT: Westrec Marinas
801 NE 3rd Street
Dania Beach, FL 33004
WATERWAY AND LOCATION: The project would affect waters of the United States
associated with the Intracoastal Waterway. The project site is located at 431 and 425
Seabreeze Boulevard Section 12, Township 50, Range 42, Fort Lauderdale, Broward
County, Florida.
Directions to the site are as follows: Take 95 South to exist 27, East on Broward
Boulevard. Take a right onto SE 12th Avenue. Take a left onto E Las Olas Boulevard.
Turn right onto Seabreeze Boulevard. The property will be on the right in 0.2 miles.
APPROXIMATE CENTRAL COORDINATES: Latitude 26.11588°
Longitude -80.13052°
PROJECT PURPOSE:
Basic: To reconfigure existing docks at a commercial marina.
Overall: To reconfigure existing docks at a commercial marina along the Intracoastal
Waterway near the Port Everglades Inlet to accommodate for larger vessels.
EXISTING CONDITIONS: The developed property consists of an existing 43-slip
marina along the Intracoastal Waterway. The project site contains an existing concrete
panel seawall with cap, marginal wood docks and finger piers. The existing area
surrounding the project area consists of commercial and residential developments. The
submerged bottom of the project footprint includes silt, sand, and algae.
PROPOSED WORK: The applicant seeks authorization for the replacement and
reconfiguration of a portion of the existing finger piers and docks. The existing marina
consists of ±10,152 ft² of finger piers, of which ±6,703 ft² are to remain. The proposed
project includes installation of ±6,251 ft² of floating docks, for a total of ±12,954 ft², and
a slip increase of 1 (from 43 slips to 44 slips).
AVOIDANCE AND MINIMIZATION INFORMATION The applicant has provided the
following information in support of efforts to avoid and/or minimize impacts to the
aquatic environment:
The applicant has agreed to install turbidity curtains during all in-water work. The
applicant agrees to abide by the Sea Turtle and Smalltooth Sawfish Construction
Conditions and the Standard Manatee Conditions.
COMPENSATORY MITIGATION The applicant has provided the following explanation
why compensatory mitigation should not be required:
As there are no mangroves, wetland vegetation, submerged resources, or submerged
grassbeds within the project boundary, there are no proposed adverse impacts to
resources as a result of this project, and therefore, no compensatory mitigation is
proposed.
CULTURAL RESOURCES:
The Corps is not aware of any known historic properties within the permit area. By copy
of this public notice, the Corps is providing information for review. Our final
determination relative to historic resource impacts is subject to review by and
coordination with the State Historic Preservation Officer and, if applicable, those
federally recognized tribes with concerns in Florida and the Permit Area.
ENDANGERED SPECIES:
The Corps has determined the proposed project would have no effect on the American
Crocodile (Crocodylus acutus), Piping Plover (Charadrius melodus), and the Wood stork
(Mycteria americana); however the proposed project may affect, but is not likely to
adversely affect the threatened West Indian Manatee (Trichechus manatus). The Corps
will request U.S. Fish and Wildlife Service concurrence with this determination for the
manatee pursuant to Section 7 of the Endangered Species Act.
The Corps has determined the proposed project would have no effect on Johnson's
seagrass (Halophila johnsonii); however the project may affect, but is not likely to
adversely affect the threatened and endangered swimming sea turtles; loggerhead
(Caretta caretta), green (Chelonia mydas), leatherback (Dermochelys coriacea),
hawksbill (Eretmochelys imbricata), and Kemp's Ridley (Lepidochelys kempii), and the
threatened smalltooth sawfish (Pristis pectinata) and would not adversely modify their
designated critical habitat. The Corps will request National Marine Fisheries Service
concurrence with these determinations pursuant to Section 7 of the Endangered
Species Act by separate letter.
2
ESSENTIAL FISH HABITAT (EFH): This notice initiates consultation with the National
Marine Fisheries Service on EFH as required by the Magnuson-Stevens Fishery
Conservation and Management Act 1996. The proposal would impact approximately
0.14 acres of sand, silt, algae, and crushed shell bottom utilized by various life stages of
penaeid shrimp complex, reef fish, stone crab, spiny lobster, migratory/pelagic fish, and
snapper/grouper complex. Our initial determination is that the proposed action would
not have a substantial adverse impact on EFH or Federally managed fisheries in the
South Atlantic Region. Our final determination relative to project impacts and the need
for mitigation measures is subject to review by and coordination with the National
Marine Fisheries Service.
NAVIGATION: Based on the Florida State Plane coordinates provided by the applicant,
the waterward edge of the proposed structure is 112.51 feet away from the near bottom
edge of the Intracoastal Waterway Federal channel.
NOTE: This public notice is being issued based on information furnished by the
applicant. This information has not been verified or evaluated to ensure compliance
with laws and regulation governing the regulatory program. The jurisdictional line
[has/has not] been verified by Corps personnel.
AUTHORIZATION FROM OTHER AGENCIES: Water Quality Certification may be
required from the Florida Department of Environmental Protection and/or one of the
state Water Management Districts.
COMMENTS regarding the potential authorization of the work proposed should be
submitted in writing to the attention of the District Engineer through the Palm Beach
Gardens Permits Section, 4400 PGA Boulevard, Suite 500, Palm Beach Gardens, FL
33410 within 21 days from the date of this notice.
The decision whether to issue or deny this permit application will be based on the
information received from this public notice and the evaluation of the probable impact to
the associated wetlands. This is based on an analysis of the applicant's avoidance and
minimization efforts for the project, as well as the compensatory mitigation proposed.
QUESTIONS concerning this application should be directed to the project manager,
Kelly Egan, in writing at the Palm Beach Gardens Permits Section, 4400 PGA
Boulevard, Suite 500, Palm Beach Gardens, FL 33410; by electronic mail at
Kelly.Egan@usace.army.mil; or, by telephone at (561) 472-3514.
IMPACT ON NATURAL RESOURCES: Coordination with U.S. Fish and Wildlife
Service, Environmental Protection Agency (EPA), the National Marine Fisheries
Services, and other Federal, State, and local agencies, environmental groups, and
concerned citizens generally yields pertinent environmental information that is
instrumental in determining the impact the proposed action will have on the natural
resources of the area.
3
EVALUATION: The decision whether to issue a permit will be based on an evaluation of
the probable impact including cumulative impacts of the proposed activity on the public
interest. That decision will reflect the national concern for both protection and utilization
of important resources. The benefits, which reasonably may be expected to accrue from
the proposal, must be balanced against its reasonably foreseeable detriments. All
factors which may be relevant to the proposal will be considered including cumulative
impacts thereof; among these are conservation, economics, esthetics, general
environmental concerns, wetlands, historical properties, fish and wildlife values, flood
hazards, floodplain values, land use, navigation, shoreline erosion and accretion,
recreation, water supply and conservation, water quality, energy needs, safety, food,
and fiber production, mineral needs, considerations of property ownership, and in
general, the needs and welfare of the people. Evaluation of the impact of the activity on
the public interest will also include application of the guidelines promulgated by the
Administrator, EPA, under authority of Section 404(b) of the Clean Water Act or the
criteria established under authority of Section 102(a) of the Marine Protection Research
and Sanctuaries Act of 1972. A permit will be granted unless its issuance is found to be
contrary to the public interest.
The US Army Corps of Engineers (Corps) is soliciting comments from the public;
Federal, State, and local agencies and officials; Indian Tribes; and other Interested
parties in order to consider and evaluate the impacts of this proposed activity. Any
comments received will be considered by the Corps to determine whether to issue,
modify, condition, or deny a permit for this proposal. To make this determination,
comments are used to assess impacts to endangered species, historic properties, water
quality, general environmental effects, and the other public interest factors listed above.
Comments are also used to determine the need for a public hearing and to determine
the overall public interest of the proposed activity.
COASTAL ZONE MANAGEMENT CONSISTENCY: In Florida, the State approval
constitutes compliance with the approved Coastal Zone Management Plan. In Puerto
Rico, a Coastal Zone Management Consistency Concurrence is required from the
Puerto Rico Planning Board. In the Virgin Islands, the Department of Planning and
Natural Resources permit constitutes compliance with the Coastal Zone Management
Plan.
REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The
request must be submitted in writing to the District Engineer within the designated
comment period of the notice and must state the specific reasons for requesting the
public hearing.
4
NORTH
8.8'
35.0'
6.2'
61.6'
6.2'
57.3'
6.0'
58.3'
6.0'
58.0'
6.1'
57.0'
6.1'
58.2'
6.1'
57.7'
5.7'
50.9'
56.7'
80.4'
80.4'
80.6'
80.8'
80.8'
80.8'
89.6'
A
EXISTING SUBMERGED
LAND LEASE (91,269 SQ.FT.)
80.7'
80.7'
80.7'
30
29
28
SCALE
1"= 60'
67.1'
B
41
42
43
40
33
34
35
36
37
38
39
31
32
27
26
25
±8.8'
576.6'
EAST R/W LINE
A
APPROXIMATE RIPARIAN RIGHTS LINE
7.2'
71.9'
23
33.1'
43
5.9'
EXISTING SLIPS
THIS DRAWING AND ALL APPURTENANT MATTER CONTAINS
INFORMATION PROPRIETARY TO THE CHAPPELL GROUP, INC.
AND IS LOANED SUBJECT TO RETURN UPON DEMAND AND
MUST NOT BE REPRODUCED, COPIED, LOANED, REVEALED,
NOR LISTED FOR ANY PURPOSE OTHER THAN THAT FOR
714 East McNab Road
WHICH IT IS SPECIFICALLY FURNISHED WITHOUT EXPRESSED
Pompano Beach, Florida 33060
WRITTEN CONSENT OF THE CHAPPELL GROUP, INC.
tel. 954.782.1908
© THE CHAPPELL GROUP, INC. 2017
fax. 954.782.1108
24
25.6'
19
50.7'
37.9'
4.0'
Chappell
39.8'
3.9'
18
17
38.0'
16
40.5'
3.9'
15
37.8'
14
40.5'
3.8'
· Environmental Consultants
· Marina & Wetland Permitting
· Mitigation Design & Monitoring
GROUP
· T&E Species Surveys
www.thechappellgroup.com · Phase I ESAs
INC.
LEGEND
20
21
22
59.1'
50.6'
13
37.3'
12
11
9
50.7'
50.7'
39.8'
3.9'
10
40.5'
3.8'
41.8'
3.4'
8
7
6
5
38.1'
50.5'
39.8'
3.9'
4
3
50.1'
39.7'
3.9'
HALL OF FAME MARINA
PREPARED FOR:
WESTREC MARINAS
2
1
44.8'
3.5'
MOFL-EXISTING
Sheet :
Date:
3/13/2017
Proj No.:
06-0012.003
of :
1
2
8.8'
±18.6'
NORTH
44
35.0'
EXISTING TRIPLE PILE
CLUSTERS TO REMAIN
EXISTING SUBMERGED
LAND LEASE (91,269 SQ.FT.)
A
10.0'
6.0'
EAST R/W LINE
156.0'
43
6.0'
58.0'
6.1'
57.0'
6.1'
58 2'
70.0'
70.0'
U
OW
6.1'
57.7'
5.7'
50.9'
56.7'
155.0'
SCALE
1"= 60'
70.0'
PROPOSED
TRIPLE PILE
CLUSTER 42
80.7'
80.7'
30
29
28
6
5
B
10.0'
41
80.4'
80.4'
80.6'
80.6'
80.7'
35
36
37
38
39
40
33
34
±8 8
576.6'
35.0'
155.0'
31
32
67.1'
27
26
25
±8 8'
378.2'
APPROXIMATE RIPARIAN RIGHTS LINE
A
5'X15' GANGWAY (TYP.)
23
LEGEND
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
4
3
2
1
PROPOSED SLIPS
24
THIS DRAWING AND ALL APPURTENANT MATTER CONTAINS
INFORMATION PROPRIETARY TO THE CHAPPELL GROUP, INC.
AND IS LOANED SUBJECT TO RETURN UPON DEMAND AND
MUST NOT BE REPRODUCED, COPIED, LOANED, REVEALED,
NOR LISTED FOR ANY PURPOSE OTHER THAN THAT FOR
714 East McNab Road
WHICH IT IS SPECIFICALLY FURNISHED WITHOUT EXPRESSED
Pompano Beach, Florida 33060
WRITTEN CONSENT OF THE CHAPPELL GROUP, INC.
tel. 954.782.1908
© THE CHAPPELL GROUP, INC. 2017
fax. 954.782.1108
Chappell
· Environmental Consultants
· Marina & Wetland Permitting
· Mitigation Design & Monitoring
GROUP
· T&E Species Surveys
www.thechappellgroup.com · Phase I ESAs
INC.
44
HALL OF FAME MARINA
PREPARED FOR:
WESTREC MARINAS
MOFL-PROPOSED
Sheet :
Date:
3/13/2017
Proj No.:
06-0012.003
of :
2
2