Proposed Discharge of Fill Material into Waters of the U.S. to Facilitate the Construction of Huntsville Northern Bypass, Huntsville, Madison County, Alabama
Public Notice No. 17-19
Nashville District
Application No. 2012-00163
Date: September 22, 2017
Please address all comments to:
Nashville District Corps of Engineers, Western Regulatory Field Office
2424 Danville Road SW, Suite N, Decatur, AL 35603
Attn: Gary L. Davis
JOINT PUBLIC NOTICE
US ARMY CORPS OF ENGINEERS
AND
STATE OF ALABAMA
SUBJECT: Proposed Discharge of Fill Material into Waters of the U.S. to Facilitate the
Construction of Huntsville Northern Bypass, Huntsville, Madison County, Alabama
TO ALL CONCERNED: The application described below has been submitted for a Department of the Army
Permit pursuant to Section 404 of the Clean Water Act (CWA) for the discharge of fill material into
waters of the United States. Before a permit can be issued, certification must be provided by the
State of Alabama, pursuant to Section 401 (a)(1) of the CWA, that applicable water quality
standards will not be violated. By copy of this notice, the applicant hereby applies for the
required certification.
APPLICANT: The City of Huntsville
320 Fountain Circle SW
Huntsville, Alabama 35801
LEAD FEDERAL AGENCY: Alabama Department of Transportation on behalf of Federal Highways
Administration is the lead federal agency for the coordination and conduct of environmental reviews
for this proposal under the National Environmental Policy Act (NEPA), the National Historic
Preservation Act (NHPA), and the Endangered Species Act (ESA).
LOCATION: The proposed project is located approximately 1.2 miles east of the Bob Wade Lane and
Pulaski Pike intersection and ending approximately 1,500 feet east of Highway 231/432 and Bob Wade
Lane intersection in Huntsville, Madison County, Alabama. The proposed project is located on
multiple unnamed tributaries of Dry Creek which flows into Tennessee River Mile 321.0R and
Beaverdam Creek which flows into Flint River Mile 36.3R, within the Huntsville Spring Branch –
Indian Creek (HUC 0603000205) and Upper Flint River (HUC 0603000203) watersheds. The project site
may be found on the Jeff and Meridianville, AL 7.5 Minute USGS Quadrangle Maps (Latitude 34.82628°;
Longitude -86.59626°).
DESCRIPTION: The proposed project consists of the permanent discharge of fill material associated
with re-routing and permanent encapsulation of 4,878 linear feet (1,208 ephemeral, 3,420
intermittent, and 250 perennial) of stream. There would be nine streams impacted by the proposed
project. The discharge of fill would facilitate construction of the linear transportation
crossings associated with the proposed 7.8 mile Huntsville Northern Bypass. The purpose of the
project is to extend State Route 255 to reduce traffic congestion and improve traffic safety on Bob
Wade Lane and US Highway 231/431.
Plans of the proposed work are attached to this notice.
AVOIDANCE AND MINIMIZATION OF IMPACTS TO WATERS OF THE U.S.:
Avoidance and minimization factors considered in association with the project plans were presented
in the Finding of No Significant Impact (FONSI) approved by the Federal Highway Administration
(FHWA) on July 22, 2002. Given the nature and location of the project, impacts to waters of the
U.S. could not be avoided. According to the FONSI, alternate build corridors were considered for
this project. However, due to design cost constraints, relocation impacts, and potential
environmental impacts, the design referred to as Alternative 1 in the FONSI was considered the most
feasible and would impact the least amount of waters of the U.S. The proposed impacts associated
with the stream crossings would be minimized by best management practices utilized during
construction to minimize water quality impacts. In addition, culverts would be designed to handle
flow conditions and minimize flow impacts at each stream crossing.
COMPENSATORY MITIGATION: The Unified Stream Methodology of Virginia was used to assess impacts to
the stream channels and provided the basis for a compensatory mitigation debit calculation of 3,506
credits. The applicant proposed to purchase credits from the Flint River Mitigation Bank, which
currently does not have enough credits available. The applicant has proposed to provide the balance
of credits through permittee-responsible mitigation.
PUBLIC INTEREST REVIEW/CUMULATIVE EFFECTS: The decision whether to issue a permit will be based on
an evaluation of the probable impacts including cumulative impacts of the activity on the public
interest. That decision will reflect the national concern for both protection and utilization of
important resources. The benefit which reasonably may be expected to accrue from the work must be
balanced against its reasonably foreseeable detriments. All factors which may be relevant to the
work will be considered including the cumulative effects thereof; among those are conservation,
economics, aesthetics, general environmental concerns, wetlands, cultural values, fish and wildlife
values, flood hazards, floodplain values, land use, navigation, shore erosion and accretion,
recreation, water supply and conservation, water quality, energy needs, safety, food and fiber
production, mineral needs, considerations of property ownership, and, in general, the needs and
welfare of the people.
SOLICITATION OF COMMENTS: The Corps of Engineers is soliciting comments from the public; federal,
state, and local agencies and officials; Indian Tribes; and other interested parties in order to
consider and evaluate the impacts of this proposed activity. Any comments received will be
considered by the Corps of Engineers to determine whether to issue, modify, condition,
or deny a permit for this proposal. To make this decision, comments are used to assess impacts on
endangered species, historic properties, water quality, general environmental effects, and the
other public interest factors listed above. Comments are used in the preparation of an
Environmental Assessment (EA) and/or an Environmental Impact Statement pursuant to the National
Environmental Policy Act. Comments are also used to determine the need for a public hearing and to
determine the overall public interest of the proposed activity. An EA will be prepared by this
office prior to a final decision concerning issuance or denial of the requested DA Permit.
HISTORIC AND CULTURAL RESOURCES: On March 4, 2012, Alabama Department of Transportation submitted
a Phase 1 Cultural Resource Assessment of the Proposed Huntsville Northern Bypass SR 255 to Alabama
Historical Commission (AHC 01-2033). No archaeological site or buildings within the proposed
project’s footprint have been determined eligible for listing in the National Register of Historic
Places. In addition, none of the archaeological sites assessed within the project right-of-way
have been determined eligible for listing in the NRHP. A copy of this notice is being sent to the
office of the State Historic Preservation Officer (SHPO) for preliminary comments, prior to
initiating Section 106 consultation.
ENDANGERED AND THREATENED SPECIES REVIEW (Per Section 7 of the
Endangered Species Act): A review of U.S. Fish and Wildlife’s Information for Planning and
Conservation (IPaC) website (http://ecos.fws.gov/ipac/) indicated the following Threatened (T) and
Endangered (E) species that may occur or could potentially be affected by the activities in this
location:
• MAMMALS: Gray bat (Myotis grisescens) (E)
Indiana bat (Myotis sodalis) (E)
Northern
Long-Eared Bat (Myotis septentrionalis) (T)
A copy of the notice is being furnished to the United States Fish and Wildlife Service (USFWS) for
their review. This public notice serves as coordination with the USFWS pursuant to Section 7(c) of
the Endangered Species Act of 1972 (as amended). Per this notification, we request comments from
the USFWS concerning potential impacts to threatened and/or endangered species. After receipt of
comments, the USACE will evaluate the potential effects on proposed and/or listed species and their
designated critical habitat and initiate consultation with USFWS, if required.
OTHER APPROVALS: Water Quality Certification from Alabama Department of Environmental Management
(ADEM) pursuant to Section 401 (a)(1) of the CWA. Other federal, state, and/or local approvals may
be required for the proposed work.
PUBLIC HEARING REQUESTS: Any person may request, in writing, within the comment period specified
in this notice, that a public hearing be held to consider this application.
Requests for public hearings shall state, with particularity, the reasons for holding a public
hearing.
COMMENT PERIOD: Written statements received in this office on or before October 22, 2017, will
become a part of the record and will be considered in the determination. Any response to this
notice should be directed to the Western Regulatory Field Office, Attention: Gary L. Davis at the
above address, telephone (256) 350-5620, or e-mail at gary.l.davis@usace.army.mil.
If you received this notice by mail and wish to view all of the diagrams, visit our web site at:
http://www.lrn.usace.army.mil/Media/PublicNotices.aspx, or contact Mr. Gary L. Davis at the above
address or telephone number, or e-mail.
Timothy C. Wilder
Chief, West Branch
Regulatory Division
U.S. Army Corps of Engineers
.
US Army Corps of Engineers
Western Regulatory Field Office
File No. LRN-2012-00163
PN 17-19
Figure 1
Project Location
File No. LRN-2012-00163
PN 17-19
Figure 2
File No. LRN-2012-00163
PN 17-19
Figure 3
File No. LRN-2012-00163
PN 17-19
Figure 4
File No. LRN-2012-00163
PN 17-19
Figure 5
File No. LRN-2012-00163
PN 17-19
Figure 6
File No. LRN-2012-00163
PN 17-19
Figure 7
File No. LRN-2012-00163
PN 17-19
Figure 8
File No. LRN-2012-00163
PN 17-19
Figure 9
File No. LRN-2012-00163
PN 17-19
Figure 10
File No. LRN-2012-00163
PN 17-19
Figure 11
File No. LRN-2012-00163
PN 17-19
Figure 12
File No. LRN-2012-00163
PN 17-19
Figure 13
File No. LRN-2012-00163
PN17-19
Figure 14
File No. LRN-2012-00163
PN 17-19
Figure 15