SPECIAL PUBLIC NOTICE: This public notice announces the St. Paul District Corps of Engineers Regulatory Branch (Corps) modification of regional general permit (RGP) GP-004-WI. This modification has been implemented to address the duration of authorization after GP-004-WI expires, and extend the expiration date of GP-004-WI from December 31, 2017 through January 7, 2018.
PROJECT DESCRIPTION AND PURPOSE: This public notice announces the St. Paul District Corps of Engineers Regulatory Branch (Corps) modification of regional general permit (RGP) GP-004-WI. This modification has been implemented to address the duration of authorization after GP-004-WI expires, and extend the expiration date of GP-004-WI from December 31, 2017 through January 7, 2018.
MODIFICATION OF
REGIONAL GENERAL
PERMIT GP-004-WI
REFER TO: 2012-01421-DJM
Public Notice
ISSUED: October 18, 2017
Section 404, Clean Water Act
Section 10, Rivers and Harbors Act
1. PROPOSED ACTION: This public notice announces the St. Paul District Corps of Engineers
Regulatory Branch (Corps) modification of regional general permit (RGP) GP-004-WI. This
modification has been implemented to address the duration of authorization after GP-004-WI expires,
and extend the expiration date of GP-004-WI from December 31, 2017, through January 7, 2018.
General Condition 1 (Duration of Authorization) in GP-004-WI is modified to allow all activities
authorized that have commenced construction, or are under contract to commence construction, to
remain authorized provided the activity is completed within 12 months of the date of the GP-004-WI
expiration, suspension, or revocation; whichever is sooner.
In addition, the Corps has extended the expiration date of GP-004-WI from December 31, 2017, to
January 7, 2018. By regulation, Corps RGP's may not be valid for more than 5 years without a reevaluation and re-issuance. The proposed extension would optimize this five year window. No other
portions of the current GP-004-WI have been modified.
2. PURPOSE OF THE PROPOSED ACTION: Separate from this proposed action, the Corps
issued a public notice on July 11, 2017, announcing its intent to develop several new regional general
permits, which would replace the current suite of general permits, including GP-004-WI. This
initiative remains the overarching goal of the Corps. Information regarding the new proposed regional
general permits is available under separate notices.
The Corps has modified GP-004-WI to minimize any potential gap in general permit coverage during
development of the new regional general permits.
3. FINAL ACTION: The final version of GP-004-WI is available for review from the Corps website
at: http://www.mvp.usace.army.mil/Missions/Regulatory/Permitting-Process-Procedures/.
Questions regarding GP-004-WI may be addressed to Rebecca Graser in our Brookfield office at (651)
290-5728, or via email at Rebecca.m.graser@usace.army.mil.
FOR THE DISTRICT COMMANDER:
Chad Konickson
Chief, Regulatory Branch