In accordance with Section 404 of the Clean Water Act (33 U.S.C. 1344) and Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403), the U.S. Army Corps of Engineers (Corps) hereby authorizes certain limited discharges of dredged and fill material associated with stream stabilization in the State of Colorado. The purpose of this Regional General Permit (RGP) is to authorize stream bed and bank stabilization activities.
Regional General Permit 37
STREAM STABILIZATION PROJECTS
IN COLORADO
EFFECTIVE DATE: October 20, 2017
EXPIRATION DATE: October 20, 2022
In accordance with Section 404 of the Clean Water Act (33U.S.C. 1344) and Section 10 of the
Rivers and Harbors Act of 1899 (33 U.S.C. 403), the U.S. Army Corps of Engineers (Corps)
hereby authorizes certain limited discharges of dredged and fill material associated with stream
stabilization in the State of Colorado. The purpose of this Regional General Permit (RGP) is to
authorize stream bed and bank stabilization activities.
LOCATION: This RGP is applicable to waters of the United States within the State of
Colorado, including Tribal Lands.
SCOPE OF WORK: This RGP authorizes stream stabilization activities necessary for erosion
control or prevention, such as vegetative stabilization, bioengineering, sills, rip rap, revetment,
barbs, jetties, weirs, or combinations of bank stabilization techniques, provided the activity
meets all of the following criteria:
1. No material is placed in excess of the minimum needed for erosion protection;
2. The activity is no more than 1,000 feet in length along the bank;
3. The activity will not exceed an average of two cubic yard per running foot, as measured
along the length of the treated bank, below the plane of the ordinary high water mark
(OHWM), unless the district engineer waives this criterion by making a written determination
concluding that the discharge will result in no more than minimal adverse environmental
effects;
4. The average stream width measured at the OHWM is no less than
20 feet; and
5. The activity will not exceed 0.5 acre of permanent impacts to wetlands.
NOTIFICATION AND APPROVAL PROCEDURES:
Written notification requesting approval and concurrence with the requirements of the RGP must
be sent to the Corps office that services the area of the project location. For assistance in
determining the appropriate regulatory office, please contact one of the Regulatory offices below
or visit the Colorado Regulatory website at http://www.nwo.usace.army.mil/Missions/
RegulatoryProgram/Colorado/GeographicResponsibility.aspx.
Denver Regulatory Office
(Omaha District)
9307 South Wadsworth Blvd.
Grand Junction Regulatory Office
(Sacramento District)
400 Rood Ave., Room 224
Regional General Permit 37
Stream Stabilization Projects in Colorado
Littleton, CO 80128-6901
Phone: (303) 979-4120
Grand Junction, CO 81501-2563
Phone: (970) 243-1199
Southern Colorado Regulatory Office
(Albuquerque District)
200 S. Santa Fe Ave., Suite 301
Pueblo, CO 81003
Phone: (719) 543-9459
Durango Regulatory Office
(Albuquerque & Sacramento Districts)
1970 E 3rd Ave., Suite 109
Durango, CO 81301
Phone: (970) 259-1764
This RGP does not authorize activities that would adversely affect important spawning areas,
including Gold Medal Waters, or that would be conducted in these waters during designated
spawning seasons. In order to determine if projects would result in adverse effects to important
spawning areas, the Corps will consult with Colorado Parks and Wildlife (CPW) for all projects
proposed in Gold Medal Waters and other fisheries of concern identified by CPW on a case-bycase basis. Pre-application consultation with CPW, preferably on-site, is highly recommended.
Providing documentation of pre-application consultation with CPW and their response(s) will
satisfy the coordination requirements of this permit resulting in quicker processing times. For
assistance in determining the appropriate CPW office and point-of-contact, please visit the
following state website to determine the appropriate office for coordination:
http://wildlife.state.co.us, or call one of the following:
Northeast Region Manager
6060 Broadway
Denver, CO 80216
(303) 291-7227
Northwest Region Manager
711 Independent Ave.
Grand Junction, CO 81505
(970) 255-6100
Southeast Region Manager
4255 Sinton Rd.
Colorado Springs, CO 80907
(719) 227-5200
Southwest Region Manager
415 Turner Dr.
Durango, CO 81303
(970) 375-6702
The applicant must first notify the Corps in writing according to the Notification procedures of the
RGP as described below. Work cannot proceed until the Corps has provided written approval to
the applicant. The applicant must provide the following information:
1. Name, address and telephone number of the applicant responsible for the work, the owner
of the affected lands (if different than the applicant), and the contractor(s) that will be
performing the work, if applicable. The applicant must provide written permission allowing
the Corps, CPW, and/or tribal representative to enter upon and perform work on property
not belonging to the applicant. The applicant should be the entity retaining long-term
maintenance responsibility for constructed features. The notification must include a letter,
signed and dated by the applicant, stating that they certify that the information in the
notification is complete and accurate and that they will abide by the terms and conditions of
this permit;
2. A description of the project location including section, township, range, and coordinates
(latitude/longitude, UTM, etc.) at both ends of the work area;
Page 2 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
3. A written well-defined purpose and need for the work, including a description/assessment of
the existing stream conditions (i.e., baseline information) and an explanation for why the
project is needed, including a description of how the project will result in bank stabilization;
4. Quantity of waters of the U.S to be impacted by the proposed activity in terms of wetlands
and other aquatic resources. Units of measure should be provided in acres or square feet,
and also linear feet, if appropriate;
5. If the proposed activity will result in the loss of greater than 1/10-acre of wetlands, the
prospective permittee must submit a proposal describing how the wetland loss will be
mitigated, or explaining why the adverse environmental effects are no more than minimal
and why compensatory mitigation should not be required. As an alternative, the prospective
permittee may submit a conceptual or detailed mitigation plan;
6. Pre-construction photos depicting the physical setting (to be compared to post-construction
site conditions from the same photo points). Photos should contain figure labels with time,
date, bearing, and a general description of the site;
7. A set of drawings per established standards and guidelines for maps and drawings (refer to
the map standards located at http://www.spd.usace.army.mil/Portals/13/docs/regulatory
/standards/MapStand020816.pdf). Additionally, the drawings must include the following
elements:
a. Location map, including name of the waterway, nearest town, county, and coordinates
(NAD83) of each structure and at both ends of the work area;
b. Plan view of all work, including staging area(s) and access point(s), clearly identifying
types and locations of structures/impacts, along with dimensions, a scale bar, a north
arrow, and approximate extent of aquatic resources within the project area. To aid in
visual understanding, this plan can be overlaid on a recent aerial image of the project
site;
c. Cross-sectional and profile views to scale of the existing stream channel and the
proposed structures, including dimensions (length, width and height of the structures or
work), and clear delineation of the limits of the OHWM; and
d. A delineation of the OHWM and all special aquatic sites at the project site, including
wetlands and riffle and pool complexes. The aquatic resource delineation report must be
submitted in accordance with the wetland delineations protocols for the individual Corps
District that covers the project area;
8. A complete description of the work, including the composition, source, and volume in cubic
yards of all material to be placed or redistributed in waters of the U.S. The description
should contain a proposed procedure to be taken to reduce sedimentation and the basis
used in determining the volume of fill to be placed or redistributed in waters of the U.S.:
a. For projects involving grade control, the project description must also include a detailed
explanation and criteria for the following design features:
(1) Number and spacing of structures;
Page 3 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
(2) Any changes in base flow elevations; and
(3) For projects located in perennial streams, a justification for any structure heights that
exceed 18 inches and/or do not include a fish passage element with a maximum
drop of 12 inches;
b. For projects that involve deflectors, such as jetties and weirs, the project description
must also include a detailed explanation and criteria for the following design features:
(1) Height: Deflectors are generally designed to be exposed during low flows and
submerged during high flows. Depending on the site and the project goals, deflectors
may be constructed with the height of the structure at the stream bank equal to the
bankfull elevation sloping down to the low flow elevation at the toe or end of the
structure;
(2) Length: The maximum extension of any deflector into a waterway generally should
not exceed of the channel width as measured at bankfull elevation (approximately
1-2 year event);
(3) Angle: Deflectors are designed to redirect flows away from the stream bank and back
toward the center of the channel. In order to best accomplish this goal, the angle of
deflectors is generally perpendicular to the desired direction of flow downstream of
the deflector. Incorrect deflector angles can result in scouring behind the structure,
particularly during low flow conditions, or erosion of the opposite stream bank. In
most cases, the angle of the deflector should be between 0 and 30 degrees
upstream from perpendicular to the stream bank; and
(4) Spacing: In many cases, a series of deflectors are designed to work together as a
single unit. In such applications, deflectors should be spaced appropriately along the
bank in order to prevent scouring or scalloping of the bank between the structures;
c. For projects involving work on multiple reaches or sections of stream, the project
description must also include detailed explanation of the independent utility of each
section of work; and
d. If the proposal does not incorporate bioengineering techniques, the project description
must also include a discussion on the alternative techniques that were considered and
why they were found not to be practicable. The description of the proposed activity and
any proposed mitigation measures should be sufficiently detailed to allow the District
Engineer to determine that the adverse environmental effects of the activity will be no
more than minimal and to determine the need for compensatory mitigation or other
mitigation measures;
9. If the project is located on the following Indian Lands, the applicant must obtain an individual
water quality certification (WQC) under Section 401 of the Clean Water Act and provide a
copy of the WQC to the Corps (see also General Condition 20):
a. Southern Ute Indian Lands. WQCs for projects located on Southern Ute Indian Lands
must be obtained from the U.S. Environmental Protection Agency (EPA). For assistance,
contact the EPA at: EPA, EPR-EP, Aquatic Resources Protection and Accountability
Page 4 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
Unit, 1595 Wynkoop Street, Denver, Colorado 80202-1129, 303-312-6909, or visit the
webpage: http://www.epa.gov/region8/water/wqc.html; or
b. Ute Mountain Ute Indian Lands. WQCs for projects located on Ute Mountain Ute Indian
Lands must be obtained from the Ute Mountain Ute Tribe. For assistance, contact the
Ute Mountain Ute Environmental Programs Department, 520 Sunset Blvd. or P.O. Box
448, Towoac, Colorado 81334, 970-564-5430 (fax 970-565-2651), or visit the webpage:
http://www.utemountainuteenvironmental.org;
10. For non-federal permittees, if any listed species or designated critical habitat might be
affected or is in the vicinity of the activity, or if the activity is located in designated critical
habitat, the notification package must include the name(s) of those endangered or
threatened species that might be affected by the proposed activity or utilize the designated
critical habitat that might be affected by the proposed activity. Federal permittees must
provide documentation demonstrating compliance with the Endangered Species Act (see
General Condition 16);
11. For non-federal permittees, if the RGP activity may have the potential to cause effects to a
historic property listed on, determined to be eligible for listing on, or potentially eligible for
listing on, the National Register of Historic Places, the notification package must state which
historic property may have the potential to be affected by the proposed activity or include a
vicinity map indicating the location of the historic property. Federal permittees must provide
documentation demonstrating compliance with Section 106 of the National Historic
Preservation Act (see General Condition 18); and
12. Applicants are encouraged to provide the Corps with electronic files to expedite agency
coordination and permit review. Such submittals may be limited by size so the applicant
should request confirmation of delivery receipt.
The information should reference "Regional General Permit No. 37" and be sent to the
appropriate Corps office. The Corps will review the applicant's request for authorization under
this RGP and will inform the applicant in writing that the work may proceed. The applicant may
not start work until notified by the Corps. If the work is not authorized under this RGP, the
applicant must apply to the Corps for a Standard Individual Permit or other appropriate
Department of the Army permit(s).
For projects located within tribal trust lands, coordination is required with the appropriate tribal
entity. Pre-application consultation with the tribe, preferably on-site, is highly recommended.
For projects that have the potential to impact vested water rights, it is recommended that the
applicant provide evidence or coordination with the local Water Commissioner. For assistance,
contact the Colorado Division of Water Resources (DWR), 1313 Sherman St., Suite 821,
Denver, CO 80203, (303) 866-3581, or you may contact the appropriate Water Commissioner
using the directory found at: http://water.state.co.us/DivisionsOffices/Pages/default.aspx.
GENERAL CONDITIONS: To qualify for this RGP authorization, the prospective permittee
must comply with the following general conditions (GC), in addition to any regional or casespecific conditions imposed by the Division Engineer or District Engineer:
Page 5 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
1. Upon receiving approval to perform work under this RGP, the permittee will have three years
to complete the work or until the permit expires or is revoked, unless specified otherwise in a
Corps verification letter. If the permittee commenced work on the authorized activity or is
under contract to commence work when the permit expires or is revoked, the permittee will
have one more year or until the original expiration, whichever is less, to complete the
construction. Upon completion of the work, the permittee shall submit a signed Certification
of Compliance form to the Corps;
2. For all projects that include a design-build component, the permittee shall submit a complete
set of as-built drawings to the Corps within 90 days following the completion of work;
3. Structures or fill authorized by this permit shall not impede waterborne navigation, including
rafting and canoeing, or create a hazard to navigation in waterways. Any interference with
navigation may require removal or modification of the structure at the permittee's expense;
4. Activities authorized by this permit shall be designed to withstand expected high flows and
maintain preconstruction surface flow rates from the site to the maximum extent practicable;
5. This RGP does not authorize stream stabilization projects that are a necessary component
of residential, commercial, and institutional developments;
6. The construction of recreational features (e.g., water parks, kayak courses) and flood control
projects are not authorized by this permit;
7. Material may not be placed in any location or manner that will impair surface water flows into
or out of any special aquatic sites. The permittee must take precautions to avoid and
minimize temporary impacts and protect wetlands and riffle-pool complexes from damage
during access and construction. Temporary fills must be removed in their entirety and the
affected areas returned to pre-construction conditions, including the revegetation of affected
areas, as appropriate. This permit does not authorize the loss of greater than 0.5 acre of
wetland;
8. The activity must comply with applicable FEMA-approved state or local floodplain
management requirements;
9. Heavy equipment working in wetlands or mudflats must be placed on mats, or other
measures must be taken to minimize soil disturbance;
10. The District Engineer may designate, after notice and opportunity for public comment,
additional waters officially designated by the State of Colorado as having particular
environmental or ecological significance, such as outstanding national resource waters or
state natural heritage sites. The District Engineer may also designate additional critical
resource waters after notice and opportunity for public comment;
11. The District Engineer may determine on a case-by-case basis that compensatory mitigation
is required to ensure that the activity results in no more than minimal adverse environmental
effects. The District Engineer will consider the following factors when determining
appropriate and practicable mitigation necessary to ensure that the individual and
cumulative adverse environmental effects are no more than minimal:
Page 6 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
a. The activity must be designed and constructed to avoid and minimize adverse effects,
both temporary and permanent, to waters of the United States to the maximum extent
practicable at the project site (i.e., on site);
b. Mitigation in all its forms (avoiding, minimizing, rectifying, reducing, or compensating for
resource losses) will be required to the extent necessary to ensure that the individual
and cumulative adverse environmental effects are no more than minimal;
c. Compensatory mitigation plans for RGP activities in or near streams or other open
waters will normally include a requirement for the restoration or enhancement,
maintenance, and legal protection (e.g., conservation easements) of riparian areas next
to open waters. In some cases, the restoration of riparian areas may be the only
compensatory mitigation required. Restored riparian areas should consist of native
species. The width of the required riparian area will address documented water quality or
aquatic habitat loss concerns. Normally, the riparian area will be 25 to 50 feet wide on
each side of the stream, but the District Engineer may require slightly wider riparian
areas to address documented water quality or habitat loss concerns. Where both
wetlands and open waters exist on the project site, the District Engineer will determine
the appropriate compensatory mitigation (e.g., riparian areas and/or wetlands
compensation) based on what is best for the aquatic environment on a watershed basis.
In cases where riparian areas are determined to be the most appropriate form of
compensatory mitigation, the District Engineer may waive or reduce any requirement to
provide wetland compensatory mitigation for wetland losses;
d. Compensatory mitigation projects provided to offset losses of aquatic resources must
comply with the applicable provisions of 33 CFR part 332;
(1) The prospective permittee is responsible for proposing an appropriate compensatory
mitigation option if compensatory mitigation is necessary to ensure that the activity
results in no more than minimal adverse environmental effects;
(2) If permittee-responsible mitigation is the proposed option, the prospective permittee
is responsible for submitting a mitigation plan. A conceptual or detailed mitigation
plan may be used by the District Engineer to make the decision on the RGP
verification request, but a final mitigation plan that addresses the applicable
requirements of 33 CFR parts 332.4(c)(2) (14) must be approved by the District
Engineer before the permittee begins work in waters of the United States, unless the
District Engineer determines that prior approval of the final mitigation plan is not
practicable or not necessary to ensure timely completion of the required
compensatory mitigation (see 33 CFR part 332.3(k)(3));
(3) If mitigation bank or in-lieu fee program credits are the proposed option, the
mitigation plan only needs to address the baseline conditions at the impact site and
the number of credits to be provided; and
(4) Compensatory mitigation requirements (e.g., resource type and amount to be
provided as compensatory mitigation, site protection, ecological performance
standards, monitoring requirements) may be added through special conditions added
to the RGP authorization;
Page 7 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
e. Compensatory mitigation will not be used to increase the acreage losses allowed by the
acreage limits of this RGP. For example, RGP 37 cannot be used to authorize any
activity resulting in permanent impacts to greater than 0.5 acre of wetlands, even if
compensatory mitigation is provided to replace or restore some of the lost waters.
However, compensatory mitigation can and should be used, as necessary, to ensure
that an activity already meeting the established acreage limits also satisfies the no more
than minimal impact requirement for this RGP; and
f.
Permittees may propose the use of mitigation banks, in-lieu fee programs, or permitteeresponsible mitigation. For permittee-responsible mitigation, the special conditions of the
RGP verification must clearly indicate the party or parties responsible for the
implementation and performance of the compensatory mitigation project, and, if
required, its long-term management.
When mitigation is required, no work in waters of the United States may occur until the
District Engineer has approved a specific mitigation plan or has determined that prior
approval of a final mitigation plan is not practicable or not necessary to ensure timely
completion of the required compensatory mitigation. For projects requiring compensatory
mitigation, please refer to the Mitigation and Monitoring Guidelines located at:
http://www.spd.usace.army.mil/Portals/13/docs/regulatory/mitigation/MitMon.pdf;
12. No activity may substantially disrupt the necessary life cycle movements of those species of
aquatic life indigenous to the waterbody, including those species that normally migrate
through the area;
13. Destruction of riparian or riverine vegetation, especially mature cottonwoods, shall be
avoided to the maximum extent practicable. The permittee is cautioned that cottonwoods
may be locally very important for several protected species, including the yellow-billed
cuckoo, and bald eagles, which are protected under the Bald and Golden Eagle Act. If the
authorized work causes damage to riparian vegetation that is not directly covered by a
permanent feature, these scarred areas shall be replanted with a mixture of native trees,
shrubs, forbs and grasses. Seeding, sprigging, or other means of planting native woody and
herbaceous plants is highly recommended and advantageous to further stabilize stream
banks. For further information on planting, please contact the local Natural Resources
Conservation Service or Corps office;
14. Appropriate soil erosion and sediment controls must be used and maintained in effective
operating condition during construction, and all exposed soil and other fills, as well as any
work below the OHWM, must be permanently stabilized at the earliest practicable date.
Erosion control fabrics/blankets may be required on a case-by-case basis. All disturbed
areas, including the riparian and upland buffer zones, shall be revegetated with native
species to prevent erosion. These areas shall be monitored and maintained to ensure
vegetative success;
15. Activities in breeding areas for migratory waterfowl must be avoided to the maximum extent
practicable. On a case-by-case basis, the Corps may restrict the timing of construction in
order to avoid and minimize impacts to migratory waterfowl during the breeding season;
16. Endangered Species:
Page 8 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
a. No activity is authorized under any RGP which is likely to directly or indirectly jeopardize
the continued existence of a threatened or endangered species or a species proposed
for such designation, as identified under the Federal Endangered Species Act (ESA), or
which will directly or indirectly destroy or adversely modify the critical habitat of such
species. No activity is authorized under any RGP which ``may affect'' a listed species or
critical habitat, unless ESA section 7 consultation addressing the effects of the proposed
activity has been completed. Direct effects are the immediate effects on listed species
and critical habitat caused by the RGP activity. Indirect effects are those effects on listed
species and critical habitat that are caused by the RGP activity and are later in time, but
still are reasonably certain to occur;
b. Federal agencies should follow their own procedures for complying with the
requirements of the ESA. The federal permittee must provide the district engineer with
the appropriate documentation to demonstrate compliance with those requirements. The
district engineer will verify that the appropriate documentation has been submitted. If the
appropriate documentation has not been submitted, additional ESA section 7
consultation may be necessary for the activity and the respective federal agency would
be responsible for fulfilling its obligation under section 7 of the ESA;
c. For activities that might affect federally-listed endangered or threatened species or
designated critical habitat, the non-federal applicant's notification must include the
name(s) of the endangered or threatened species that might be affected by the
proposed activity or that utilize the designated critical habitat that might be affected by
the proposed activity. The district engineer will determine whether the proposed activity
``may affect'' or will have ``no effect'' to listed species and designated critical habitat and
will notify the non-federal applicant of the Corps' determination within 45 days of receipt
of a complete notification. In cases where the non-federal applicant has identified listed
species or critical habitat that might be affected or is in the vicinity of the activity, and has
so notified the Corps, the applicant shall not begin work until the Corps has provided
notification that the proposed activity will have ``no effect'' on listed species or critical
habitat, or until ESA section 7 consultation has been completed;
d. As a result of formal or informal consultation with the FWS the district engineer may add
species specific permit conditions to the RGP;
e. Authorization of an activity by the RGP does not authorize the ``take'' of a threatened or
endangered species as defined under the ESA. In the absence of separate authorization
(e.g., an ESA Section 10 Permit, a Biological Opinion with ``incidental take'' provisions,
etc.) from the FWS or the NMFS, the Endangered Species Act prohibits any person
subject to the jurisdiction of the United States to take a listed species, where ``take''
means to harass, harm, pursue, hunt, shoot, wound, kill, trap, capture, or collect, or to
attempt to engage in any such conduct. The word ``harm'' in the definition of ``take''
means an act which actually kills or injures wildlife. Such an act may include significant
habitat modification or degradation where it actually kills or injures wildlife by significantly
impairing essential behavioral patterns, including breeding, feeding or sheltering;
f.
If the non-federal permittee has a valid ESA section 10(a)(1)(B) incidental take permit
with an approved Habitat Conservation Plan for a project or a group of projects that
includes the proposed RGP activity, the non-federal applicant should provide a copy of
that ESA section 10(a)(1)(B) permit with the notification required by paragraph (c) of this
Page 9 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
general condition. The district engineer will coordinate with the agency that issued the
ESA section 10(a)(1)(B) permit to determine whether the proposed RGP activity and the
associated incidental take were considered in the internal ESA section 7 consultation
conducted for the ESA section 10(a)(1)(B) permit. If that coordination results in
concurrence from the agency that the proposed RGP activity and the associated
incidental take were considered in the internal ESA section 7 consultation for the ESA
section 10(a)(1)(B) permit, the district engineer does not need to conduct a separate
ESA section 7 consultation for the proposed RGP activity. The district engineer will notify
the non-federal applicant within 45 days of receipt of a complete pre-construction
notification whether the ESA section 10(a)(1)(B) permit covers the proposed RGP
activity or whether additional ESA section 7 consultation is required; and
g. Information on the location of threatened and endangered species and their critical
habitat can be obtained directly from the offices of the FWS or their World Wide Web
pages at http://www.fws.gov/ or http://www.fws.gov/ipac;
17. The permittee is responsible for ensuring their action complies with the Migratory Bird Treaty
Act and the Bald and Golden Eagle Protection Act. The permittee is responsible for
contacting appropriate local office of the USFWS to determine applicable measures to
reduce impacts to migratory birds or eagles, including whether "incidental take" permits are
necessary and available under the Migratory Bird Treaty Act or Bald and Golden Eagle
Protection Act for a particular activity;
18. Historic Properties:
a. In cases where the District Engineer determines that the activity may affect properties
listed, or eligible for listing, in the National Register of Historic Places, the activity is not
authorized, until the requirements of Section 106 of the National Historic Preservation
Act (NHPA) have been satisfied;
b. Federal permittees should follow their own procedures for complying with the
requirements of Section 106 of the National Historic Preservation Act. Federal
permittees must provide the District Engineer with the appropriate documentation to
demonstrate compliance with those requirements. The District Engineer will verify that
the appropriate documentation has been submitted. If the appropriate documentation is
not submitted, then additional consultation under Section 106 may be necessary. The
respective federal agency is responsible for fulfilling its obligation to comply with Section
106;
c. Non-federal permittees must identify in their notification which historic properties may be
affected by the proposed work or include a vicinity map indicating the location of the
historic properties or the potential for the presence of historic properties.
Assistance regarding information on the location of or potential for the presence of
historic resources can be sought from the State Historic Preservation Officer or Tribal
Historic Preservation Officer, as appropriate, and the National Register of Historic Places
(see 33 CFR part 330.4(g)). When reviewing notification packages, District Engineers
will comply with the current procedures for addressing the requirements of Section 106
of the National Historic Preservation Act. The District Engineer shall make a reasonable
and good faith effort to carry out appropriate identification efforts, which may include
Page 10 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
background research, consultation, oral history interviews, sample field investigation,
and field survey. Based on the information submitted and these efforts, the District
Engineer shall determine whether the proposed activity has the potential to cause an
effect on the historic properties. Where the non-federal applicant has identified historic
properties on which the activity may have the potential to cause effects and so notified
the Corps, the non-federal applicant shall not begin the activity until notified by the
District Engineer either that the activity has no potential to cause effects or that
consultation under Section 106 of the NHPA has been completed;
d. The District Engineer will notify the prospective permittee within 45 days of receipt of a
complete notification package whether NHPA Section 106 consultation is required.
Section 106 consultation is not required when the Corps determines that the activity
does not have the potential to cause effects on historic properties (see 36 CFR part
800.3(a)). If NHPA Section 106 consultation is required and will occur, the District
Engineer will notify the non-federal applicant that he or she cannot begin work until
Section 106 consultation is completed. If the non-federal applicant has not heard back
from the Corps within 45 days, the applicant must still wait for notification from the
Corps; and
e. Prospective permittees should be aware that Section 110k of the NHPA (16 U.S.C.
470h-2(k)) prevents the Corps from granting a permit or other assistance to an applicant
who, with intent to avoid the requirements of Section 106 of the NHPA, has intentionally
significantly adversely affected a historic property to which the permit would relate, or
having legal power to prevent it, allowed such significant adverse effect to occur, unless
the Corps, after consultation with the Advisory Council on Historic Preservation (ACHP),
determines that circumstances justify granting such assistance despite the adverse
effect created or permitted by the applicant. If circumstances justify granting the
assistance, the Corps is required to notify the ACHP and provide documentation
specifying the circumstances, the degree of damage to the integrity of any views
obtained from the applicant, SHPO/THPO, appropriate Indian tribes if the undertaking
occurs on or affects historic properties on tribal lands or affects properties of interest to
those tribes, and other parties known to have a legitimate interest in the impacts to the
permitted activity on historic properties.
If any previously unknown historic, cultural or archeological remains and artifacts are
discovered while accomplishing the activity authorized by this permit, the permittee must
immediately notify the District Engineer of what was found, and to the maximum extent
practicable, avoid construction activities that may affect the remains and artifacts until
the required coordination has been completed. The District Engineer will initiate the
federal, tribal and state coordination required to determine if the items or remains
warrant a recovery effort or if the site is eligible for listing in the National Register of
Historic Places;
19. To ensure that all structures are safely designed, the District Engineer may require nonfederal applicants to demonstrate that the structures have been designed by qualified
persons. The District Engineer may also require documentation that the design has been
independently reviewed by similarly qualified persons, and appropriate modifications made
to ensure safety;
Page 11 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
20. If a conditioned water quality certification is issued for the project, (i.e., for projects located
on Southern Ute or Ute Mountain Ute Tribal Lands) the permittee must comply with the
conditions specified in the certification as special conditions to this permit. In Colorado,
excluding Indian lands, regional general permits are unconditionally certified by statute;
21. This permit does not authorize discharges of dredged or fill material associated with
channelization, ditching, mechanized land clearing, cutting off meanders, or blocking off
channels;
22. All construction debris (including excess dredged or fill materials, wood, cleared vegetation,
concrete, and all other materials not specifically authorized by the permit) shall be disposed
of in an upland area in such a manner that it cannot enter a waterway or wetland;
23. Dredged or fill material shall not consist of unsuitable material (e.g., trash, debris, waste
metal products, asphalt, car bodies, tires, etc.) and must be free from toxic pollutants in toxic
amounts (see Section 307 of the Clean Water Act);
24. The use of grout is not allowed by this permit unless, after a case-by-case review, the Corps
makes a written determination that the use of grout would not cause more than minor
impacts to the aquatic resource;
25. Activities that result in the physical destruction (e.g., through excavation, fill, or downstream
smothering by substantial turbidity) of an important spawning area are not authorized by this
RGP;
26. Discharges of dredged or fill material shall not occur in the proximity of a water supply
intake, shall not limit the ability of any existing diversion structure to appropriate water, shall
not impair the ability to deliver vested water rights, and shall not adversely impact a stream
gauging station;
27. Activities shall not impair reserved tribal rights including, but not limited to, reserved water
rights and treaty fishing and hunting rights;
28. National Wild and Scenic River System:
a. No activity may occur in a component of the National Wild and Scenic River System, or
in a river officially designated by Congress as a "study river" for possible inclusion in the
system while the river is in an official study status, unless the appropriate federal agency
with direct management responsibility for such river, has determined in writing that the
proposed activity will not adversely affect the Wild and Scenic River designation or study
status;
b. If a proposed RGP activity will occur in a component of the National Wild and Scenic
River System, or in a river officially designated by Congress as a "study river" for
possible inclusion in the system while the river is in an official study status, the District
Engineer will coordinate with the federal agency with direct management responsibility
for that river. The permittee shall not begin the RGP activity until notified by the District
Engineer that the federal agency with direct management responsibility for that river has
determined in writing that the proposed RGP activity will not adversely affect the Wild
and Scenic River designation or study status; and
Page 12 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
c. Information on Wild and Scenic Rivers may be obtained from the appropriate federal
land management agency responsible for the designated Wild and Scenic River or study
river (e.g., National Park Service, U.S. Forest Service, Bureau of Land Management,
U.S. Fish and Wildlife Service). Information on these rivers is also available at:
http://www.rivers.gov/;
29. The permittee must allow representatives from the Corps to inspect the authorized work at
any time deemed necessary to ensure that it is being or has been accomplished in
compliance with the terms and conditions of the permit;
30. The permittee shall maintain the activity authorized by this permit in good condition and in
conformance with the terms and conditions of this permit, including maintenance to ensure
public safety and compliance with applicable RGP general conditions, as well as any
activity-specific conditions added by the District Engineer to an RGP authorization. The
permittee is not relieved of this requirement if construction of the permitted activity is
abandoned, although the permittee may make a good faith transfer to a third party in
compliance with General Condition 31 below. Should the permittee wish to cease
maintenance of the authorized activity, or should the permittee desire to abandon it without
a good faith transfer, the permittee shall obtain a modification of the permit from the Corps,
which may require restoration of the area; and
31. If the permittee sells the property associated with the permit verification, the permittee may
transfer the permit verification to the new owner by submitting a letter to the Corps to
validate the transfer. A copy of the permit verification must be attached to the letter, and the
letter must contain the following statement and signature: "When the structures or work
authorized by this permit are still in existence at the time the property is transferred, the
terms and conditions of this permit, including any special conditions, shall continue to be
binding on the new property owner(s). To validate the transfer of this permit and the
liabilities associated with compliance with its terms and conditions, have the transferee sign
and date below."
BEST MANAGEMENT PRACTICES:
1. In order to prevent the spread of invasive and/or nuisance species (e.g., Asian Clam, Grand
Valley Asian Tapeworm, Green River Mud Snail, New Zealand Mud Snail), the permittee is
strongly encouraged to clean heavy equipment prior to and after construction if the
equipment was previously used in another stream, river, lake, pond, or wetland within 10
days of initiating work. The following are recommended methods for preventing the spread
of invasive aquatic organisms:
a. Remove all mud and debris from equipment (tracks, turrets, buckets, drags, teeth, etc.)
and spray/soak equipment with a 1:15 solution of disinfection solution containing the
following ingredients:
(1) Dialkyl dimethyl ammonium chloride (5-10% by weight);
(2) Alkyl dimethyl benzyl ammonium chloride (5-10% by weight);
(3) Nonyl phenol ethoxylate (5-10% by weight);
Page 13 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
(4) Sodium sesquicarbonate (1-5%); and
(5) Tetrasodium ethylene diaminetetraacetate (1-15%); and
b. The equipment should be kept moist for at least 10 minutes, and rinsate should be
managed as a solid waste in accordance with local, county, state, or federal regulations.
Alternately, equipment, hand tools, boots and any other equipment that was previously
used in a river, stream, lake, pond, or wetland prior to moving the equipment to another
water body may be disinfected using either of the following methods:
(1) Spray/soak equipment with water greater than 140 degrees Fahrenheit for at least 10
minutes; or
(2) Sanitize water suction hoses and water transportation tanks (using methods
described above) and discard rinse water at an appropriately permitted disposal
facility; and
2. No petroleum products, chemicals, or other deleterious materials should be allowed to enter
or be disposed of in such a manner in which they could enter the waterway or adjacent
wetlands. Accordingly, it is recommended that oil absorbent "booms" be installed
downstream of the project site during construction activities.
DEFINITIONS:
Bankfull: Bankfull, as defined by Dunne and Leopold (1978), is the stream stage corresponding to the
discharge at which channel maintenance is most effective. That is, the discharge at which moving
sediment, forming or removing bars, forming or changing bends and meanders, and generally doing work
that result in the average morphological characteristics of channels.
Best management practices (BMPs): Policies, practices, procedures, or structures implemented to
mitigate the adverse environmental effects on surface water quality resulting from development. BMPs
are categorized as structural or non-structural.
Bioengineering Techniques: The combination of biological, mechanical, and ecological concepts to
control erosion and stabilize soil through the use of native vegetation or a combination of vegetative and
traditional construction materials. Bioengineering techniques include both living and non-living plants.
Non-living plants (trees, logs, etc.) are used as construction materials, similar to or in combination with
engineered materials. Planted vegetation controls erosion, stabilizes soil, and serves as wildlife and
fisheries habitat in riparian areas, between the stream channel and adjacent upland habitats.
Compensatory mitigation: The restoration (re-establishment or rehabilitation), establishment (creation),
enhancement, and/or in certain circumstances preservation of aquatic resources for the purposes of
offsetting unavoidable adverse impacts which remain after all appropriate and practicable avoidance and
minimization has been achieved.
Direct effects: Effects that are caused by the activity and occur at the same time and place.
Discharge: The term "discharge" means any discharge of dredged or fill material into waters of the
United States.
Enhancement: The manipulation of the physical, chemical, or biological characteristics of an aquatic
resource to heighten, intensify, or improve a specific aquatic resource function(s). Enhancement results in
Page 14 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
the gain of selected aquatic resource function(s), but may also lead to a decline in other aquatic resource
function(s). Enhancement does not result in a gain in aquatic resource area.
Ephemeral stream: An ephemeral stream has flowing water only during, and for a short duration after,
precipitation events in a typical year. Ephemeral stream beds are located above the water table yearround. Groundwater is not a source of water for the stream. Runoff from rainfall is the primary source of
water for stream flow.
Establishment (creation): The manipulation of the physical, chemical, or biological characteristics
present to develop an aquatic resource that did not previously exist at an upland site. Establishment
results in a gain in aquatic resource area.
Historic Property: Any prehistoric or historic district, site (including archaeological site), building,
structure, or other object included in, or eligible for inclusion in, the National Register of Historic Places
maintained by the Secretary of the Interior. This term includes artifacts, records, and remains that are
related to and located within such properties. The term includes properties of traditional religious and
cultural importance to an Indian tribe or Native Hawaiian organization and that meet the National Register
criteria (36 CFR part 60).
Independent utility: A test to determine what constitutes a single and complete non-linear project in the
Corps Regulatory Program. A project is considered to have independent utility if it would be constructed
absent the construction of other projects in the project area. Portions of a multi-phase project that depend
upon other phases of the project do not have independent utility. Phases of a project that would be
constructed even if the other phases were not built can be considered as separate single and complete
projects with independent utility.
Indirect effects: Effects that are caused by the activity and are later in time or farther removed in
distance, but are still reasonably foreseeable.
Intermittent stream: An intermittent stream has flowing water during certain times of the year, when
groundwater provides water for stream flow. During dry periods, intermittent streams may not have
flowing water. Runoff from rainfall is a supplemental source of water for stream flow.
Loss of waters of the United States: Waters of the United States that are permanently adversely
affected by filling, flooding, excavation, or drainage because of the regulated activity. Permanent adverse
effects include permanent discharges of dredged or fill material that change an aquatic area to dry land,
increase the bottom elevation of a waterbody, or change the use of a waterbody. The acreage of loss of
waters of the United States is a threshold measurement of the impact to jurisdictional waters for
determining whether a project may qualify for a general permit; it is not a net threshold that is calculated
after considering compensatory mitigation that may be used to offset losses of aquatic functions and
services. The loss of stream bed includes the acres or linear feet of stream bed that are filled or
excavated as a result of the regulated activity. Waters of the United States temporarily filled, flooded,
excavated, or drained, but restored to pre-construction contours and elevations after construction, are not
included in the measurement of loss of waters of the United States. Impacts resulting from activities that
do not require Department of the Army authorization, such as activities eligible for exemptions under
section 404(f) of the Clean Water Act, are not considered when calculating the loss of waters of the
United States.
Navigable waters: Waters subject to section 10 of the Rivers and Harbors Act of 1899. These waters are
defined at 33 CFR part 329.
Open water: For purposes of this general permit, an open water is any area that in a year with normal
patterns of precipitation has water flowing or standing above ground to the extent that an OHWM can be
determined. Aquatic vegetation within the area of flowing or standing water is either non-emergent,
Page 15 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
sparse, or absent. Vegetated shallows are considered to be open waters. Examples of "open waters"
include rivers, streams, lakes, and ponds.
Ordinary High Water Mark: An OHWM is a line on the shore established by the fluctuations of water and
indicated by physical characteristics, or by other appropriate means that consider the characteristics of
the surrounding areas.
Perennial stream: A perennial stream has flowing water year-round during a typical year. The water
table is located above the stream bed for most of the year. Groundwater is the primary source of water for
stream flow. Runoff from rainfall is a supplemental source of water for stream flow.
Preservation: The removal of a threat to, or preventing the decline of, aquatic resources by an action in
or near those aquatic resources. This term includes activities commonly associated with the protection
and maintenance of aquatic resources through the implementation of appropriate legal and physical
mechanisms. Preservation does not result in a gain of aquatic resource area or functions.
Re-establishment: The manipulation of the physical, chemical, or biological characteristics of a site with
the goal of returning natural/historic functions to a former aquatic resource. Re-establishment results in
rebuilding a former aquatic resource and results in a gain in aquatic resource area and functions.
Rehabilitation: The manipulation of the physical, chemical, or biological characteristics of a site with the
goal of repairing natural/historic functions to a degraded aquatic resource. Rehabilitation results in a gain
in aquatic resource function, but does not result in a gain in aquatic resource area.
Restoration: The manipulation of the physical, chemical, or biological characteristics of a site with the
goal of returning natural/historic functions to a former or degraded aquatic resource. For the purpose of
tracking net gains in aquatic resource area, restoration is divided into two categories: re-establishment
and rehabilitation.
Riffle and pool complex: Riffle and pool complexes are special aquatic sites under the 404(b)(1)
Guidelines. Riffle and pool complexes sometimes characterize steep gradient sections of streams. Such
stream sections are recognizable by their hydraulic characteristics. The rapid movement of water over a
course substrate in riffles results in a rough flow, a turbulent surface, and high dissolved oxygen levels in
the water. Pools are deeper areas associated with riffles. A slower stream velocity, a streaming flow, a
smooth surface, and a finer substrate characterize pools.
Riparian areas: Riparian areas are lands next to streams, lakes, and estuarine-marine shorelines.
Riparian areas are transitional between terrestrial and aquatic ecosystems, through which surface and
subsurface hydrology connects riverine, lacustrine, estuarine, and marine waters with their adjacent
wetlands, non-wetland waters, or uplands. Riparian areas provide a variety of ecological functions and
services and help improve or maintain local water quality. (See general condition 23.)
Single and complete project: For non-linear projects, such as those activities authorized by this RGP,
the term "single and complete project" is defined at 33 CFR 330.2(i) as the total project proposed or
accomplished by one owner/developer or partnership or other association of owners/developers. A single
and complete non-linear project must have independent utility (see definition of "independent utility").
Single and complete non-linear projects may not be "piecemealed" to avoid the limits in this general
permit.
Stream bed: The substrate of the stream channel between the OHWMs. The substrate may be bedrock
or inorganic particles that range in size from clay to boulders. Wetlands contiguous to the stream bed, but
outside of the OHWMs, are not considered part of the stream bed.
Page 16 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
Stream channelization: The manipulation of a stream's course, condition, capacity, or location that
causes more than minimal interruption of normal stream processes. A channelized stream remains a
water of the United States.
Structure: An object that is arranged in a definite pattern of organization. Examples of structures include,
without limitation, any pier, boat dock, boat ramp, wharf, dolphin, weir, boom, breakwater, bulkhead,
revetment, riprap, jetty, artificial island, artificial reef, permanent mooring structure, power transmission
line, permanently moored floating vessel, piling, aid to navigation, or any other manmade obstacle or
obstruction.
Tribal lands: Any lands title to which is either: 1) held in trust by the United States for the benefit of any
Indian tribe or individual; or 2) held by any Indian tribe or individual subject to restrictions by the United
States against alienation.
Tribal rights: Those rights legally accruing to a tribe or tribes by virtue of inherent sovereign authority,
unextinguished aboriginal title, treaty, statute, judicial decisions, executive order or agreement, and that
give rise to legally enforceable remedies.
Waterbody: For purposes of this general permit, a waterbody is a jurisdictional water of the United
States. If a wetland is adjacent to a waterbody determined to be a water of the United States, that
waterbody and any adjacent wetlands are considered together as a single aquatic unit (see 33 CFR
328.4(c)(2)). Examples of "waterbodies" include streams, rivers, lakes, ponds, and wetlands.
FURTHER INFORMATION:
1. District Engineers have authority to determine if an activity complies with the terms and
conditions of a RGP;
2. Congressional Authorities. This permit authorizes work in accordance with:
a. Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403); and
b. Section 404 of the Clean Water Act (33 U.S.C. 1344);
3. Limits of this authorization:
a. This permit does not obviate the need to obtain other federal, state, or local
authorizations required by law;
b. This permit does not grant any property rights or exclusive privileges; and
c. This permit does not authorize interference with any existing or proposed federal
projects;
4. Limits of Federal Liability. In issuing this permit, the federal government does not assume
any liability for the following:
a. Damages to the permitted project, or uses thereof, as a result of other permitted or
unpermitted activities or from natural causes;
b. Damages to the permitted project, or uses thereof, as a result of current or future
activities undertaken by or on behalf of the United States in the public interest;
Page 17 of 18
Regional General Permit 37
Stream Stabilization Projects in Colorado
c. Damages to persons, property, or other permitted or unpermitted activities or structures
caused by the activity authorized by this permit;
d. Design or construction deficiencies associated with the permitted work; and
e. Damage claims associated with any future modification, suspension, or revocation of this
permit;
5. Reliance on applicant's data. The determination by the Corps that a verification based upon
this permit is not contrary to the public interest will be made in reliance on the information
provided by the applicant;
6. Re-evaluation of permit decisions. The Corps may reevaluate its decision on this permit at
any time the circumstances warrant (33 CFR 325.7(a)). Circumstances that could require a
reevaluation include, but are not limited to, the following:
a. Failure to comply with the terms and conditions of this permit;
b. The information provided by you in support of your permit application proves to have
been false, incomplete, or inaccurate; or
c. Significant new information surfaces that the Corps did not consider before verifying that
the project is authorized by this permit.
Such re-evaluation may result in a determination that it is appropriate to use the suspension,
modification, and revocation procedures contained in 33 CFR 325.7 or enforcement
procedures such as those contained in 33 CFR 326.4 and 326.5. The referenced
enforcement procedures provide for the issuance of an administrative order requiring the
permittee to comply with the terms and conditions of the permit and for the initiation of legal
action where appropriate;
7. Extensions. General Condition 1 establishes a time limit for the completion of the activity
authorized by this permit. Unless there are circumstances requiring either a prompt
completion of the authorized activity or a reevaluation of our decision, the Corps will
normally give favorable consideration to a request for an extension of this time limit; and
8. Renewal of the RGP: This RGP may be reviewed for reissuance prior to its expiration date.
Any reissuance will be processed in accordance with 33 CFR 325.2 including a public notice
and environmental procedures and documentation required by the national Environmental
Policy Act of 1969.
This permit becomes effective when the federal official, designated to act for the Sacramento,
Albuquerque, and Omaha District Engineers, has signed below.
STEINLE.ALLAN.ED
WARD.1231814503
Digitally signed by
STEINLE.ALLAN.EDWARD.1231814503
DN: c=US, o=U.S. Government, ou=DoD,
ou=PKI, ou=USA,
cn=STEINLE.ALLAN.EDWARD.1231814503
Date: 2017.10.20 14:35:09 -06'00'
__________________________________
Allan Steinle, Chief
Albuquerque District Regulatory Division
Page 18 of 18
20 October 2017
_________________________
DATE