You can copy from here when filling out the rest of the page.
LETTER OF PERMISSION: The purpose of the proposed project is to provide access to the applicant’s property for the construction of a
driveway and home. The applicant has determined that 0.61 acres of fill in wetlands is the minimum necessary required to allow access to the site and provide a minimal amount of fill for the building site. Therefore, the applicant has requested authorization to retain 0.61 acres of fill in forested wetlands.
PROJECT DESCRIPTION AND PURPOSE:The purpose of the proposed project is to provide access to the applicant’s property for the construction of a driveway and home. The applicant has determined that 0.61 acres of fill in wetlands is the minimum necessary required to allow access to the site and provide a minimal amount of fill for the building site. Therefore, the applicant has requested authorization to retain 0.61 acres of fill in forested wetlands.
Information for File # 2016-02183-LSP
Applicant: Duane Sellen
Corps Contact: Lawrence Puchalski
Address: 4111 Technology Drive, Suite 295, Bemidji, Minnesota 56601
E-Mail: Lawrence.S.Puchalski@usace.army.mil
Phone: (651) 290-5339
Primary County: Lake of the Woods
Section: 34
Township: 168N
Range: 34W
Information Complete On: September 22, 2016.
Posting Expires On: November 3, 2017.
Authorization Type: LOP-05-MN(B)
This application is being reviewed in accordance with the practices for documenting Corps
jurisdiction under Sections 9 & 10 of the Rivers and Harbor Act of 1899 and Section 404 of the
Clean Water Act identified in Regulatory Guidance Letter 07-01. We have made a preliminary
determination that the aquatic resources that would be impacted by the proposed project are
regulated by the Corps of Engineers under Section 404 of the Clean Water Act. Our
jurisdictional review and final jurisdictional determination could result in modifications to the
scope of the project's regulated water body/wetland impacts and compensatory mitigation
requirements identified above. An approved jurisdictional determination will be made prior to
reaching a permit decision, and will be posted on the St. Paul District web page at
http://www.mvp.usace.army.mil/.
Project
PROJECT NAME: Duane Sellen Fill for Road Access and Home.
PROJECT DESCRIPTION AND PURPOSE: The purpose of the proposed
project is to provide access to the applicant's property for the construction of a
driveway and home.
This is an after the fact permit to retain fill that was placed without authorization
from the Corps of Engineers. In the summer of 2016, the Corps was notified that
approximately 1.6 acres of forested wetlands had been filled to construct an
access road and building site without Corps authorization. At that time, the
applicant had also constructed a house at the site. Upon notice of the
unauthorized activity, the applicant worked with both state and federal agencies
to find a solution. The applicant was ordered by the state to remove as much fill
from wetlands as possible which has been accomplished.
1
The applicant has determined that 0.61 acres of fill in wetlands is the minimum
necessary required to allow access to the site and provide a minimal amount of
fill for the building site. Therefore, the applicant has requested authorization to
retain 0.61 acres of fill in forested wetlands.
The location of the work proposed is shown on the included drawings labeled
2016-02183-LSP Page 1 of 2 though Page 2 of 2. The proposed work will
include retained fill for the construction of an access road and fill for a building
site at the location. These areas are shown on the drawings.
NAME, AREA AND TYPES OF WATERS (INCLUDING WETLANDS) SUBJECT
TO LOSS: There will be a total of 0.61 acres of forested wetlands lost by
permanent fill as a result of this project.
ALTERNATIVES CONSIDERED: As this is an after the fact application, the
applicant did not explore alternatives that would have eliminated or reduced the
amount of fill at the site. As part of the restoration order, the applicant was
required to minimize fill to the greatest extent possible while allowing the use of
his property. The driveway was narrowed and the amount of fill at the
homestead was reduced to the greatest extent possible. The minimum amount
of fill needed is 0.61 acres.
COMPENSATORY MITIGATION: The applicant will be required to purchase
mitigation credits from a Corps approved wetland bank to offset unavoidable
impacts to the forested wetlands at the site.
Drawings
See attached.
2
MVP-2016-02183-LSP Page 1 of 2
Angle Inlet, Lake of the Woods
Dawson Road NW
Approximate
Sellen Property
Boundary
0
485 970
1,940
2,910
Feet
3,880
±
Figure 1. USGS Topographic Map (1:24000 scale) that depicts approximate location of the Sellen Property
(data obtained from Minnesota Geospatial Image Service)
MVP-2016-02183-LSP Page 2 of 2
To Youngs Bay
To Jim's Corner
Remote Border Area Station
(1.25 miles west of access easement)
Dawson Road NW
Approximate Access
Easement Location
Approximate Sellen
Property Boundary
0
240 480
960
1,440
Feet
1,920
±
Figure 2. Aerial image with approximate locations of access easement and Sellen Property