ANNOUNCEMENT OF TIME EXTENSION AND REVISIONS TO GENERAL PERMIT GP-20 FOR HAZARDOUS CONDITION RESPONSE ACTIVITIES WITHIN THE NEW ORLEANS DISTRICT
The New Orleans District, Corps of Engineers is hereby issuing a public notice announcing a time extension for GP-20. This general permit authorized hazardous condition response activities within the New Orleans District. The proposed time extension and revision was advertised for public comment on June 19, 2017. All available information and comments were considered in determining whether the overall public interest would be best served by revising and extending this general permit. A copy of the extended general permit is attached.
We have reserved the right to modify, suspend, or revoke this general permit any time we determine it is in the public’s interest to do so. Interested parties are invited to submit written comments or suggestions for modifications or improvement of this general permit to the Regulatory Branch of this district at any time.
DEPARTMENT OF THE ARMY
CORPS OF ENGINEERS, NEW ORLEANS DISTRICT
7400 LEAKE AVENUE
NEW ORLEANS, LOUISIANA 70118
REPLY TO
ATTENTION OF
Operations Division
Regulatory Branch
SUBJECT:
CEMVN-OD-S
MVN-1997-04840-MG
(General Permit) GP-20
DEPARTMENT OF THE ARMY GENERAL PERMIT FOR HAZARDOUS CONDITION
RESPONSE ACTIVITIES WITHIN THE NEW ORLEANS DISTRICT
AUTHORIZATION NO.:
INITIAL EFFECTIVE DATE:
EXPIRATION DATE:
(General Permit) GP-20
November 1, 1982
November 30, 2022
Under authorization granted by Part 325.8(b) of Title 33, Code of Federal
Regulations, the District Commander at New Orleans has granted this general permit
for discharge of dredge and fill material and other work to address the performance of
certain activities in response to hazardous conditions. This permit authorizes work and
structures under the following legislation:
a. Section 10 of the Rivers and Harbors Act of March 3, 1899 (33 USC 403).
b. Section 404 of the Clean Water Act (33 USC 1344).
This permit does not authorize any work under Section 9 of the Rivers and Harbors
Act of March 3, 1899 (33 USC 404) or Section 103 of the Marine Protection, Research
and Sanctuaries Act of 1972 (33 USC 1413).
This permit is applicable only within the boundaries of the New Orleans District of the
U.S. Army Corps of Engineers.
Work authorized by this general permit is the minimum amount necessary to respond
to oil or gas well blowouts, pipeline explosions or ruptures, explosions, fires, oil or
hazardous materials spills, shipwrecks or sinking of vessels in navigation channels,
pipeline damage, flood and storm events, or similar situations which would result in an
imminent safety and/or environmental hazard.
-2Work authorized under this general permit is considered temporary. After the
immediate situation has been addressed, the permittee must either restore the site to
its pre-project conditions, or must apply for a permit to maintain the work or portions of
work initially authorized under this general permit. Permit applications to maintain work
initially authorized under this general permit will be processed in the appropriate
manner, to potentially include an agency or public notice, water quality certification
from the Louisiana Department of Environmental Quality, and Coastal Use Permit or
other authorizations from the Louisiana Department of Natural Resources, Office of
Coastal Management (OCM).
The activities authorized by this general permit include, but are not limited to:
a. Placement of a drilling rig in open waters to drill a relief well.
b. Placement of fill to provide access to a location for placement of drilling rigs to
drill relief wells.
c. Dredging and disposal of dredged material for movement of equipment to
evacuate personnel, fight fires, shutoff blow-out wells, install and service pollution
control equipment, and repair ruptured pipelines.
d. Dredging and placement of fill and/or structures to collect and confine oil or
hazardous materials.
e. Dredging and deposition of dredged material to remove or re-float grounded,
wrecked, burned out or sunken vessels and/or structures obstructing navigation
channels and resulting in a hazard to public navigation.
f. Dredging and the placement of fill associated with emergency response to specific
storm and/or flood events.
g. Dredging and the deposition of material for emergency pipeline anomaly repairs
and access.
In addition to the applicable conditions of our standard permit form (copy
enclosed), the following conditions apply to this general permit:
a. Dredging and other activities will be the minimum necessary to address safety
and environmental hazards.
b. Work performed under this general permit must be completed within 120 days of
the date that the specific authorization was granted. If work is not completed within this
time-frame, the permittee may request additional time to complete the work. The
District Commander will consider granting any requests for a time-extension on a caseby-case basis.
-3c. Restoration is required in accordance with the following:
(1) Restoration plans must be submitted to the Regulatory Branch of this district
within 30 days of the date when the authorization was granted by the New Orleans
District under the general permit.
(2) The District Commander will consult with appropriate federal, state, and local
agencies prior to authorization of restoration plans.
(3) The restoration work must begin within 30 days of the date of authorization of
the restoration plan or lesser time when so specified by the District Commander or his
representative, unless a specific time extension is granted by the New Orleans District.
(4) Once begun, restoration work will be diligently prosecuted until completed.
(5) Disturbed wetland areas shall be restored to pre-project conditions, to the
greatest extent practicable.
d. In appropriate cases when it may be in the public interest to allow maintenance of
structures, fill areas, and/or dredged areas installed under this general permit
authorization, permittees must apply for and receive a Department of the Army permit. If
the permit application is denied, restoration will proceed in accordance with condition c.,
immediately above.
e. Applications to maintain facilities authorized by this general permit must be
submitted within 30 days of the date the authorization was granted by the New Orleans
District for work under this general permit, unless a specific time extension is granted by
the New Orleans District. Permit applications will be processed using appropriate
procedures, including a public notice where applicable.
f. Requests to maintain facilities located outside the Louisiana Coastal Zone and
authorized under this general permit, must include a completed Department of the Army
application form (4345), along with appropriate letter-sized drawings and scope of the
work, and be mailed to the USACE, New Orleans District, Regulatory Branch at the
letterhead address above. For work located within the Louisiana Coastal Zone, a Joint
permit application shall be submitted through DNR/OCM.
g. This general permit may be modified, suspended, or revoked by the District
Commander any time it is found to be in the public interest to do so.
h. Authorizations under this general permit do not relieve permittees from obtaining
permits or other authorizations from any required state or local agency, or the consent
of the landowner. For response activities within the Louisiana Coastal Zone, applicants
must also contact OCM at (225) 342-7591 for state authorization before performing the
work.
i. Other permit conditions may be added in individual authorizations for work under
this general permit to address site specific conditions or situations.
-4Procedures to be followed in administering this general permit are as follows:
a. The initial contact may be made in person or via one of the following:
(1) Electronic mail: CEMVNRegulatoryApplication@usace.army.mil
Please include "HCRA, the Parish where the project is proposed, and the
Applicant" in the subject line of the electronic mail.
(2) Regulatory Branch
(504) 862-2255
(3) Eastern Evaluation Section
(504) 862-2292
(4) Central Evaluation Section
(504) 862-1581
Archer/x2046
(5) Western Evaluation Section
(504) 862-2261
b. For work within the Louisiana Coastal Zone also contact the OCM at (225)
342-7591.
c. If a permission from the Corps pursuant to 33 U.S.C.408 is required, final action
on the HCRA cannot be made until the Section 408 permission is granted.
d. If the proposed work is located with any known sensitive/critical areas (e.g. TES
habitat, EFH habitat, refuges, cultural sites, etc.), we may request an emergency review
from the appropriate resource agency, as determined necessary.
e. Authorization under this general permit may be granted upon initial contact
provided the requester can present sufficient information on the location, nature, and
extent of the work to establish that the safety or environmental hazard exists. When
necessary, immediate verbal authorization may be granted to perform the work.
However, in other cases, a written request describing the need for the work may be
needed to establish that the project qualifies for authorization under the provisions of
this general permit. Please provide the following if available:
(1) Copies of any original Department of the Army (DA) permit for the
structure/site if available, or any relevant DA permit number(s) if available, or
the approximate time the original project/structure was constructed.
(2) Clear description of the hazardous situation, to include but not limited to: any
work initiated and/or proposed, description of the structure and/or site and its
current condition, machinery used, time frames for start and completion of
work, anticipated wetland impacts through filling, excavating or mechanized