The applicant proposes to discharge 17,114 cubic yards of concrete as road base, 3,318 cubic yards of bridge shafts, and 3,000 cubic yards of rip-rap.

Full Public NoticeProject Plans PROJECT DESCRIPTION: The applicant proposes to discharge 17,114 cubic yards of concrete as road base, 3,318 cubic yards of bridge shafts, and 3,000 cubic yards of rip-rap into 11.28 acres of jurisdictional waters of the United States, during fill activities associated with roadway widening and the installation of bridge pilings. The proposed project activities are associated with the widening of a 4-lane divided roadway to a 6- to 12-lane freeway, with grade separations at major intersections.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas