City of Lincoln - Grade, pave, and widen Rokeby Road between South 70th Street and South 84th Street to urban standards, including curb and gutters with enclosed storm sewers; Improve the South 70th Street and South 84th Street intersections with Rokeby Road; Construct new intersections at Rokeby Road and South 73rd Street, South 77th Street, and South 80th Street; and Install storm water management facilities, sanitary sewer, water lines, and a trail crossing within the right-of-way of the road.
City of Lincoln - Grade, pave, and widen Rokeby Road between South 70th Street and South 84th Street to urban standards, including curb and gutters with enclosed storm sewers; Improve the South 70th Street and South 84th Street intersections with Rokeby Road; Construct new intersections at Rokeby Road and South 73rd Street, South 77th Street, and South 80th Street; and Install storm water management facilities, sanitary sewer, water lines, and a trail crossing within the right-of-way of the road.
PUBLIC NOTICE
Application No: NWO-2015-01247-WEH
Applicant: Craig Aldridge, City of Lincoln, Nebraska,
Public Works and Utilities Department
Waterway: Tributaries to Salt Creek, Beal Slough,
Wagon Train Creek, and Adjacent/Abutting Wetlands
Issue Date: November 15, 2017
Expiration Date: December 6, 2017
21 DAY NOTICE
Reply To:
NEBRASKA REGULATORY OFFICE
8901 SOUTH 154TH STREET, SUITE 1, OMAHA, NEBRASKA 68138-3635
JOINT PUBLIC NOTICE: This public notice is issued jointly by the U.S. Army Corps of
Engineers, Omaha District, and the Nebraska Department of Environmental Quality (NDEQ), P.O.
Box 98922, State House Station, Lincoln, Nebraska 68509. NDEQ will review the proposed
project for state certification in accordance with the provisions of Section 401 of the Clean Water
Act. NDEQ hereby incorporates this public notice as its own public notice and procedures by
reference thereto. For the purposes of NDEQ, this public notice will expire 30 days from the issue
date shown above.
AUTHORITY: Section 404 of the Clean Water Act (33 USC 1344).
APPLICANT: Craig Aldridge, City of Lincoln Public Works and Utilities Department, 901 West
Bond, Lincoln, Nebraska 68521
PROJECT LOCATION: Sections 27, 28, 33 and 34 , Township 9 North, Range 7 East, City of
Lincoln, Lancaster County, Nebraska; 40.712017° North, -96.617626° West.
PROJECT DESCRIPTION: The City of Lincoln is proposing the following:
x
x
x
Grade, pave, and widen Rokeby Road between South 70th Street and South 84th Street to
urban standards, including curb and gutters with enclosed storm sewers;
Improve the South 70th Street and South 84th Street intersections with Rokeby Road;
Construct new intersections at Rokeby Road and South 73rd Street, South 77th Street, and
South 80th Street; and
1
x
Install storm water management facilities, sanitary sewer, water lines, and a trail crossing
within the right-of-way of the road.
Basic Project Purpose: The basic project purpose, as defined by the Corps, is road construction.
Applicant's Project Purpose: The project purpose, as stated by the applicant, is as follows:
"The purpose of the proposed improvements is to:
x
x
x
x
Safely and effectively accommodate increased traffic volumes;
Provide a planned rural to urban transition of paving and upgrading roads in urbanizing
areas as the City annexes parts of the County;
Concurrently construct other urban utilities and infrastructure at the same time as the road
improvements to minimize expense, disruption, and impacts; these will include storm water
management, sanitary sewer and water lines; and
Provide for pedestrian and bicycle trail connectivity as shown in the City-County
Comprehensive Plan (2017) and Lincoln MPO 2040 Long Range Transportation Plan
(2017)."
Overall Project Purpose: The overall project purpose, as defined by the Corps, is to upgrade an
existing segment of Rokeby Road between South 70th Street and South 84th Street from rural gravel
road to urban roadway design and safety standards and to accommodate city-provided
infrastructure.
SPECIAL AQUATIC SITES: The proposed project would result in the discharge of fill material
into Waters of the U.S., thus impacting 0.94 acre of PEMA/C floodplain depressional wetlands,
0.33 acre PFOA floodplain depressional wetlands, and 0.24 acre of PSSA floodplain depressional
wetland.
Proposed impacts to three, R4SB un-named tributaries total 255 linear feet.
AVOIDANCE, MINIMIZATION, AND MITIGATION:
Avoidance and Minimization: The applicant has considered alternatives to avoid, minimize, and
mitigate impacts to waters of the U.S. Project impacts on wetlands and waters of the United States
are unavoidable. Minimization measures included the use of roundabout intersections, use of
vertical headwalls, modification of trail clearance standards, and minimization of the trail
embankment.
Mitigation: Permittee-required mitigation is being proposed at the City of Lincoln Wetland
Mitigation Bank. Mitigation credits have not yet been determined.
CULTURAL RESOURCES: The Corps of Engineers, Omaha District, will comply with the
National Historic Preservation Act of 1966 and amendments, and the procedures set forth in 33
CFR 325, Appendix C. We have checked the National Register of Historic Places, and any
2
available site database information, and there are no known National Register sites in the vicinity.
We will evaluate input by the State Historic Preservation Office, Tribes, and the public in response
to this public notice, and we may conduct or require a survey of the permit area to check for
unknown historic or prehistoric properties, if warranted.
ENDANGERED SPECIES: Pursuant to the Endangered Species Act, a preliminary
determination has been made that the described work may affect but is not likely to adversely
affect species designated as threatened or endangered or adversely affect critical habitat.
May affect, not likely to adversely affect: Northern Long-Eared Bat;
No effect: Least Tern; Piping Plover, Whooping Crane, Pallid Sturgeon, Western Prairie Fringed
Orchid, Salt Creek Tiger Beetle.
In order to complete our evaluation of this activity, comments are solicited from the U.S. Fish and
Wildlife Service and other interested agencies and individuals.
FLOODPLAIN: This activity is being reviewed in accordance with Executive Order 11988,
Floodplain Management, which discourages direct or indirect support of floodplain development
whenever there is a practicable alternative. By this notice, comments are requested from
individuals and agencies that believe the described work will adversely impact the floodplain.
WATER QUALITY CERTIFICATION: Section 401 of the Clean Water Act (33 USC 1341)
requires that all discharges of fill material must be certified by the appropriate state agency as
complying with applicable effluent limitations and water quality standards. This public notice
serves as an application to the state in which the discharge site is located for certification of the
discharge. The discharge must be certified before a Department of the Army permit can be issued.
Certification, if issued, expresses the state's opinion that the discharge will not violate applicable
water quality standards.
PUBLIC INTEREST REVIEW: The decision whether to issue the Corps' permit will be based
on an evaluation of the probable impacts including cumulative impacts of the proposed / completed
activity on the public interest. That decision will reflect the national concern for both protection
and utilization of important resources. The benefits, which reasonably may be expected to accrue
from the proposal, must be balanced against their reasonably foreseeable detriments. All factors
which may be relevant to the proposal will be considered including the cumulative effects thereof;
among those are conservation, economics, aesthetics, general environmental concerns, wetlands,
historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation,
shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy
needs, safety, food and fiber production, mineral needs, considerations of property ownership and,
in general, the needs and welfare of the people. In addition, the evaluation of the impact of the
work on the public interest will include application of the guidelines promulgated by the
Administrator, Environmental Protection Agency, under authority of Section 404(b) of the Clean
Water Act (40 CFR Part 230).
3
COMMENTS: The Corps of Engineers is soliciting comments from the public, Federal, State,
and Local agencies and officials, Indian Tribes and other interested parties in order to consider and
evaluate the impacts of this activity. Any comments received will be considered by the Corps of
Engineers to determine whether to issue, modify, condition or deny a permit for this project. To
make this decision, comments are used to assess impacts on endangered species, historic
properties, water quality, general environmental effects, and the other public interest factors listed
above. Comments are used in the preparation of an Environmental Assessment and/or an
Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments
are also used to determine the need for a public hearing and to determine the overall public interest
of the activity.
Anyone whose interests may be affected by the proposed / completed work is invited to submit
favorable or unfavorable written comments to the Nebraska Regulatory Office, 8901 South 154th
Street, Suite 1, Omaha, NE 68138-3635. The District Engineer is particularly interested in
receiving comments related to the proposal's probable impacts on the affected aquatic system's
functional values, cumulative and secondary effects, and endangered species. All comments
received will be considered public information; copies of all comments, including names and
addresses of commenters, may be provided to the applicant unless confidentiality is requested.
Comments must be submitted on or before the expiration date (located at the top of the first page)
of this notice to be considered in the subsequent actions on this application.
PUBLIC HEARING: Before the expiration date of this notice, anyone may request, in writing,
that a public hearing be held to consider this application. Requests shall specifically state the
reason(s) for holding a public hearing. If the District Engineer determines that the information
received in response to this notice is inadequate for thorough evaluation, a public hearing may be
warranted. If a public hearing is warranted, interested parties will be notified of the time, date,
and location.
ADDITIONAL INFORMATION: Additional information about this application may be
obtained by writing to Ms. Laura Banker at the address shown on page one, or by calling (402)
896-0896. You can also e-mail Ms. Banker at Laura.Banker@usace.army.mil.
REQUEST TO POSTMASTERS: Please post this notice conspicuously and continuously until
the expiration date specified at the top of page one.
NOTICE TO EDITORS: This notice purpose is provided as background information for your
use in formatting news stories. This notice is not a contract for classified display advertising.
4