The applicant proposes to excavate 1.64 acres (est. 2,650 cubic yards) of fill materials.

Full Public Notice Project Plans Mitigation Plans PROJECT DESCRIPTION: The applicant proposes to excavate 1.64 acres (est. 2,650 cubic yards) of fill materials, which will include 1.26 acres (est. 2,032 cubic yards) from wetlands and waters [1.07 acres - palustrine, emergent wetlands (PEM) and 0.19 acres – palustrine, unconsolidated bottom open waters (PUB)]. With respect to the deposition of the fill materials, 0.91 acres (~1,475 cubic yards) of in-situ material will be relocated on-site; 0.73 acres (~1,175 cubic yards) of off-site material will be placed and graded on-site; and, 0.91 acres (~1,475 cubic yards) of limestone aggregate will be deposited on-site to provide base for the tanks. The end goal will be to replace the Hurricane Ike damaged 59th Street Pump Station (a 7.5 million gallon aboveground potable water storage tank) via funding from the federal Hazard Mitigation Grant Program and Texas General Land Office’s Disaster Recovery Division CDBG program.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas