The applicant proposes to discharge 186,274 cubic yards of fill material.

Full Public Notice Project Plans PROJECT DESCRIPTION: The applicant proposes to discharge 186,274 cubic yards of fill material into 5.10 acres of jurisdictional waters of the United States (U.S.), during excavation and fill activities associated with creating detention basins. The proposed project activities are associated with the widening of the Sam Houston Tollway (East) from IH-45 South to SH-225. Such activities include the construction of detention basins occurring within the boundaries of eight separate subject properties, totaling 30.76 combined acres in size. Refer to the table 1 below for more information.

Table 1. No. Waters Name Name Latitude Longitude Impacts (Acres) 1 Area A PSS 29.7025247 -95.151805 4.88 2 Area C PEM 29.6787926 -95.15335 0.04 3 Area D PEM 29.6285618 -95.169396 0.03 4 Area E PUB 29.6123125 -95.20027 0.01 5 Area G PEM 29.7011804 -95.152777 0.00 6 Area I PEM 29.7021059 -95.150231 0.00 7 Area J PEM 29.6896664 -95.151579 0.02 8 Area K PEM 29.6782908 -95.154099 0.00 9 Area L PEM 29.6781739 -95.154108 0.00 10 Area M PEM 29.62904 -95.169811 0.10

Total Wetland Impacts 5.08

No. Waters Name Name Latitude Longitude Impacts (Acres) 1 Area B (HCFCD Drainage Unit No. G105 03 00) Intermittent 29.6891807 -95.1513413 0 2 Area H (HCFCD Drainage Unit No. G105-01-00) Intermittent 29.70067 -95.1528755 0 3 Area F Ephemeral 29.6126281 -95.1994388 0.02

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas