PUBLIC NOTICE
Application No: NWO-2017-00703-WEH
Applicant: Carol White, Lyman Richey Corp.
Waterway: Platte River and Adjacent/Abutting Wetlands
Issue Date: December 13, 2017
Expiration Date: December 28, 2017
15 DAY NOTICE
Reply To:
NEBRASKA REGULATORY OFFICE
8901 SOUTH 154TH STREET, SUITE 1, OMAHA, NEBRASKA 68138-3635
JOINT PUBLIC NOTICE: This public notice is issued jointly by the U.S. Army Corps of
Engineers, Omaha District, and the Nebraska Department of Environmental Quality (NDEQ), P.O.
Box 98922, State House Station, Lincoln, Nebraska 68509. NDEQ will review the proposed
project for state certification in accordance with the provisions of Section 401 of the Clean Water
Act. NDEQ hereby incorporates this public notice as its own public notice and procedures by
reference thereto. For the purposes of NDEQ, this public notice will expire 30 days from the issue
date shown above.
AUTHORITY: Section 404 of the Clean Water Act (33 USC 1344).
APPLICANT: Carol White, Lyman-Richey Corp., 2625 South 158th Plaza, Omaha, Nebraska
68130.
PROJECT LOCATION: Sections 24 and 19 , Township 15 North, Range 10 East, Douglas
County, Nebraska; 41.2511376° North, -96.3413903° West.
PROJECT DESCRIPTION: This public notice reflects an increase in impacts to waters of the
United States previously reported in the Public Notice issued on October 19, 2017. Changes
are in red text.
Lyman Richey Corporation proposes to expand Pit 40 to the south. The proposed expansion would
occur within five, 5-year phases and result in the discharge of fill material into waters of the United
States as follows:
· Phase 1 is years one through five and will impact 7.5 acres of L1UB open water; 0.66 acre
of PEMA/C riverine floodplain wetland; 0.89 acre of PEMA/C lacustrine fringe wetland;
0.38 acre of PSSA lacustrine fringe wetland; 0.29 acre of PEMF riverine floodplain
wetland; and 1.51 acres of PEMA/C agricultural riverine floodplain wetland.
1
· Phase 2 is years six through ten and will impact 0.75 acre of PEMA/C riverine floodplain
wetland; 0.52 acre of PEMA/C lacustrine fringe wetland; 0.05 acre of PEMA/C riverine
channel wetland; 0.23 acre of PEMF riverine floodplain wetland; and 3.07 acres of
PEMA/C agricultural riverine floodplain wetland.
· Phase 3 is years eleven through fifteen and will impact 3,005 linear feet of R2UBH stream
channel; 0.19 acre of PEMA/C riverine floodplain wetland; 0.50 acre of PEMA/C riverine
channel wetland; 1.99 acres of PSSA riverine channel wetland; 1.03 acres of PFOA
riverine channel wetland; 0.10 acre of PEMF riverine channel wetland; and 3.0 acres of
PEMA/C agricultural riverine floodplain wetland.
· Phase 4 is years sixteen through twenty and will impact 1,241 linear feet of R2UBH stream
channel; 1.53 acres of PEMA/C riverine floodplain wetland; 0.03 acre of PEMA/C riverine
channel wetland; 0.67 acre of PSSA riverine channel wetland; 0.43 acre of PEMF riverine
channel wetland; and 3.43 acres of PEMA/C agricultural riverine floodplain wetland.
· Phase 5 is years twenty-one through twenty-three and will impact 257 linear feet of
R2UBH stream channel; 0.17 acre of PEMA/C riverine floodplain wetland; 0.09 acre of
PSSA riverine channel wetland; 0.05 acre of PFOA riverine channel wetland; 0.04 acre of
PEMF riverine channel wetland; and 5.44 acres of PEMA/C agricultural riverine
floodplain wetland.
If issued, the permit will be evaluated every 5 years in order to address any changes to the project,
impacts, mitigation, endangered species, or jurisdiction.
Basic Project Purpose: The basic project purpose, as defined by the Corps, is sand and gravel mining.
Applicant's Project Purpose: The project purpose, as stated by the applicant, is as follows:
"The purpose of the project is to expand an existing sand and gravel mine to extract sand and
gravel for commercial sale in the market service area from approximately Nebraska Highway 36
(N-36) to the Elkhorn River confluence."
Overall Project Purpose: The overall project purpose, as defined by the Corps, is to dredge sand
and gravel to provide aggregate for use in concrete-related construction.
SPECIAL AQUATIC SITES: The proposed project would result in the discharge of fill material
into Waters of the U.S., thus impacting 3.30 acres of PEMA/C riverine floodplain wetlands,
0.58 acre of PEMA/C riverine channel wetlands, 1.41 acres of PEMA/C lacustrine fringe wetlands,
2.75 acres of PSSA riverine channel wetlands, 0.38 acre of PSSA lacustrine fringe wetland, 0.52
acre of PEMF riverine floodplain wetland, 0.57 acre of PEMF riverine channel wetland, 1.08 acres
of PFOA riverine channel wetland, and 16.45 acres of PEMA/C agricultural riverine floodplain
wetlands. Total wetland impacts are 27.04 acres. Impacts would result from excavation and
from the deposition of unusuable overburden and fine sands and gravel.
Proposed impacts to open water total 7.5 acres. Proposed impacts to a perennial, R2UBH unnamed tributary to the Elkhorn River total 4,503 linear feet.
2
AVOIDANCE, MINIMIZATION, AND MITIGATION:
Avoidance and Minimization: The applicant has considered alternatives to avoid, minimize, and
mitigate impacts to waters of the U.S. Project impacts on wetlands and waters of the United States
are unavoidable. Expansion of the site in each cardinal direction was assessed for levels of impact
to certify the minimization of impacts to the greatest extent possible.
Mitigation: Permittee-required mitigation at an off-site location within the same 8-digit hydrologic
unit will be developed for unavoidable impacts associated with Phase 1 expansion and operation
of Plant 40. Mitigation for subsequent phases will be determined and coordinated with the U. S.
Army Corps of Engineers before each phase is initiated.
The applicant has not provided a mitigation plan. A final mitigation plan, completed in accordance
with the 2008 Mitigation Rule and using the Nebraska Stream Assessment Protocol (NeSCAP)
dated 10 October, 2016, will be required to be submitted by the applicant and approved by the
U. S. Army Corps of Engineers prior to any permit issuance.
Mitigation Banks or In-Lieu Fee Programs: The project is located in the service area of the
following wetland mitigation banks:
·
·
·
Bundy Bank Phase I
Bundy Bank Phase II
Bundy Bank Phase III
Private Commercial
Private Commercial
Private Commercial
CULTURAL RESOURCES: The Corps of Engineers, Omaha District, will comply with the
National Historic Preservation Act of 1966 and amendments, and the procedures set forth in 33
CFR 325, Appendix C. We have checked the National Register of Historic Places, and any
available site database information, and there are no known National Register sites in the vicinity.
We will evaluate input by the State Historic Preservation Office, Tribes, and the public in response
to this public notice, and we may conduct or require a survey of the permit area to check for
unknown historic or prehistoric properties, if warranted.
ENDANGERED SPECIES: Pursuant to the Endangered Species Act, a preliminary
determination has been made that the described work may affect but is not likely to adversely
affect species designated as threatened or endangered or adversely affect critical habitat.
May affect, not likely to adversely affect: Northern Long-Eared Bat; Least Tern; Piping Plover,
Western Prairie Fringed Orchid, Pallid Sturgeon.
In order to complete our evaluation of this activity, comments are solicited from the U.S. Fish and
Wildlife Service and other interested agencies and individuals.
3
FLOODPLAIN: This activity is being reviewed in accordance with Executive Order 11988,
Floodplain Management, which discourages direct or indirect support of floodplain development
whenever there is a practicable alternative. By this notice, comments are requested from
individuals and agencies that believe the described work will adversely impact the floodplain.
WATER QUALITY CERTIFICATION: Section 401 of the Clean Water Act (33 USC 1341)
requires that all discharges of fill material must be certified by the appropriate state agency as
complying with applicable effluent limitations and water quality standards. This public notice
serves as an application to the state in which the discharge site is located for certification of the
discharge. The discharge must be certified before a Department of the Army permit can be issued.
Certification, if issued, expresses the state's opinion that the discharge will not violate applicable
water quality standards.
PUBLIC INTEREST REVIEW: The decision whether to issue the Corps' permit will be based
on an evaluation of the probable impacts including cumulative impacts of the proposed / completed
activity on the public interest. That decision will reflect the national concern for both protection
and utilization of important resources. The benefits, which reasonably may be expected to accrue
from the proposal, must be balanced against their reasonably foreseeable detriments. All factors
which may be relevant to the proposal will be considered including the cumulative effects thereof;
among those are conservation, economics, aesthetics, general environmental concerns, wetlands,
historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation,
shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy
needs, safety, food and fiber production, mineral needs, considerations of property ownership and,
in general, the needs and welfare of the people. In addition, the evaluation of the impact of the
work on the public interest will include application of the guidelines promulgated by the
Administrator, Environmental Protection Agency, under authority of Section 404(b) of the Clean
Water Act (40 CFR Part 230).
COMMENTS: The Corps of Engineers is soliciting comments from the public, Federal, State,
and Local agencies and officials, Indian Tribes and other interested parties in order to consider and
evaluate the impacts of this activity. Any comments received will be considered by the Corps of
Engineers to determine whether to issue, modify, condition or deny a permit for this project. To
make this decision, comments are used to assess impacts on endangered species, historic
properties, water quality, general environmental effects, and the other public interest factors listed
above. Comments are used in the preparation of an Environmental Assessment and/or an
Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments
are also used to determine the need for a public hearing and to determine the overall public interest
of the activity.
Anyone whose interests may be affected by the proposed / completed work is invited to submit
favorable or unfavorable written comments to the Nebraska Regulatory Office, 8901 South 154th
Street, Suite 1, Omaha, NE 68138-3635. The District Engineer is particularly interested in
receiving comments related to the proposal's probable impacts on the affected aquatic system's
functional values, cumulative and secondary effects, and endangered species. All comments
4
received will be considered public information; copies of all comments, including names and
addresses of commenters, may be provided to the applicant unless confidentiality is requested.
Comments must be submitted on or before the expiration date (located at the top of the first page)
of this notice to be considered in the subsequent actions on this application.
PUBLIC HEARING: Before the expiration date of this notice, anyone may request, in writing,
that a public hearing be held to consider this application. Requests shall specifically state the
reason(s) for holding a public hearing. If the District Engineer determines that the information
received in response to this notice is inadequate for thorough evaluation, a public hearing may be
warranted. If a public hearing is warranted, interested parties will be notified of the time, date,
and location.
ADDITIONAL INFORMATION: Additional information about this application may be
obtained by writing to Ms. Laura Banker at the address shown on page one, or by calling (402)
896-0896. You can also e-mail Ms. Banker at Laura.Banker@usace.army.mil.
REQUEST TO POSTMASTERS: Please post this notice conspicuously and continuously until
the expiration date specified at the top of page one.
NOTICE TO EDITORS: This notice purpose is provided as background information for your
use in formatting news stories. This notice is not a contract for classified display advertising.
5
LEGEND
King Lake
Valley
Plant 40 Project Area
County Boundary
City Boundary
64
¬
«
O
0
Miles
1
Waterloo
275
£
¤
Yutan
Venice
92
¬
«
Saunders
Douglas
Sarpy
PROJECT LOCATION
LYMAN-RICHEY CORPORATION: PLANT 40
FIGURE A1
PATH: Z:\PROJECTS\LYMAN_RICHEY\10056607_WATERLOO_PIT_40_IP\MAP_DOCS\DRAFT\IP_PROJECT_LOCATION.MXD - USER: BFISHER - DATE: 10/18/2017
INDIVIDUAL PERMIT APPLICATION