Proposed Discharge of Fill Material into Waters of the U.S. Associated with Construction of a Barge Dock and Mooring Cells in Decatur, Morgan County, Alabama
Public Notice No. 17-29
Date: December 28, 2017
Application No. 2017-00675
JOINT PUBLIC NOTICE: US ARMY CORPS OF ENGINEERS, TENNESSEE VALLEY AUTHORITY, AND THE STATE OF ALABAMA
SUBJECT: Proposed Discharge of Fill Material into Waters of the U.S. Associated with Construction of a Barge Dock and Mooring Cells in Decatur, Morgan County, Alabama
TO ALL CONCERNED: The application described below has been submitted for a Department of the Army Permit pursuant to Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (CWA) for the discharge of fill material into waters of the United States. Before a permit can be issued, certification must be provided by the State of Alabama, pursuant to Section 401 (a)(1) of the CWA, that applicable water quality standards will not be violated. By copy of this notice, the applicant hereby applies for the required certification.
APPLICANT: AGRI-AFC
Paul Thompson
P.O. Box 2227
Decatur, Alabama 35602
LEAD FEDERAL AGENCY: The USACE and Tennessee Valley Authority (TVA) have a Memorandum of Understanding that designates TVA as the lead Federal Agency for conducting environmental reviews under the National Environmental Policy Act (NEPA) and other applicable federal laws and regulations (e.g., the National Historic Preservation Act (NHPA) and the Endangered Species Act (ESA)) for proposed work that may occur on property which is under TVA custody or control.
LOCATION: The proposed project is located on Wheeler Lake at Tennessee River Mile 305.1, Left Bank, in Decatur, Morgan County, Alabama. The project site may be found on the Decatur, AL 7.5 Minute USGS Quadrangle Map (Latitude 34.61082°; Longitude -86.9732°).
DESCRIPTION: The proposed work consists of the discharge of fill material into Tennessee River (Wheeler Lake) for the construction of a dock and mooring cells to facilitate the loading and unloading of barges. The 58-foot wide dock would extend 80 linear feet lakeward, incorporate two 24-foot diameter mooring cells on either side of the face of the dock, and include a conveyor belt system to transport the material from the barges to the warehouse. Two additional 24-foot diameter mooring cells would be located approximately 70 feet from the dock, one upstream and the other downstream. Approximately 2,038 cubic feet of fill material would be used to construct the dock and mooring cells. Fill material consisting of soil, limestone aggregate, and concrete would be placed within sheet piles during installation. The mooring cell located on the west side of the dock would be capped with concrete; the remaining cells would have an aggregate cap. Approximately 75 linear feet of vegetated shoreline would be cleared to allow for the construction of the dock. An 18’ x 4’ grouted rip-rap flume would be constructed below an existing 24-inch steel drainage pipe and extend to the water’s edge to protect the shoreline. An existing set of steps and platforms located on the shoreline within this area would be removed.
Plans of the proposed work are attached to this notice.
AVOIDANCE AND MINIMIZATION OF IMPACTS TO WATERS OF THE U.S.: This area is currently used for loading and unloading materials from barges and because of the nature of the work impacts to all waters of the U.S. (WOUS) could not be avoided. To minimize impacts to WOUS, the width of the dock was reduced from 100’ to 60’, but was extended lakeward to provide navigational depth for barges and to avoid the need for dredging.
COMPENSATORY MITIGATION: The applicant does not propose any compensatory mitigation for impacts to waters of the U.S.
PUBLIC INTEREST REVIEW/CUMULATIVE EFFECTS: The decision whether to issue a permit will be based on an evaluation of the probable impacts including cumulative impacts of the activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the work must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the work will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, cultural values, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shore erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership, and, in general, the needs and welfare of the people.
SOLICITATION OF COMMENTS: The Corps of Engineers is soliciting comments from the public; federal, state, and local agencies and officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps of Engineers to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment (EA) and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. An EA will be prepared by this office prior to a final decision concerning issuance or denial of the requested DA Permit.
HISTORIC AND CULTURAL RESOURCES: A review of National Register of Historic Places (http://nrhp.focus.nps.gov/natreghome.do?searchtype=natreghome) identified 11 historic properties in Morgan County, AL within one mile of the project site: Albany Heritage Neighborhood Historic District, Bank Street Historic District, Bank Street-Old Decatur Historic District (Boundary Increase), Cotaco Opera House, Col. Francis Dancy House, New Decatur Albany Historic District, New Decatur—Albany Historic District (Boundary Increase),
New Decatur—Albany Residential Historic District (Boundary Increase), Rhea-McEntire House,
Southern Railway Depot, and the State Bank Building. The USACE invites responses to this public notice from American Indian Tribes or tribal governments; Federal, State, and local agencies; historical and archeological societies; and other parties likely to have knowledge of or concerns regarding historic properties and areas of cultural significance at or near the project area. USACE would consider any substantive comments to determine the potential of impacts of the project to historic properties and would initiate any required consultation with the Tennessee Historic Commission (SHPO) and American Indian Tribes in accordance with Section 106 of the National Historic Preservation Act.
ENDANGERED AND THREATENED SPECIES REVIEW (Per Section 7 of the Endangered Species Act): A review of U.S. Fish and Wildlife’s Information for Planning and Conservation (IpaC) website (http://ecos.fws.gov/ipac/) on December 4, 2017 indicated the following Threatened (T) and Endangered © species that may occur or could potentially be affected by the activities in this location:
MAMMALS: Gray bat (Myotis grisescens) ©; Indiana bat (Myotis odalist) ©; Northern Long-Eared Bat (Myotis septentrionalis) (T)
CLAMS: Pink Mucket (pearlymussel) (Lampsilis abrupta) ©; Rough Pigtoe (Pleurobema plenum) ©; Sheepnose Mussell (Plethobasus cyphyus) ©; Snuffbox Mussel (Epioblasma triquetra) ©; Spectaclecase (mussel) (Cumberlandia monodonta) ©
A copy of the notice is being furnished to the United States Fish and Wildlife Service (USFWS) for their review. This public notice serves as coordination with the USFWS pursuant to Section 7© of the Endangered Species Act of 1972 (as amended). Per this notification, we request comments from the USFWS concerning potential impacts to threatened and/or endangered species. After receipt of comments, the USACE will evaluate the potential effects on proposed and/or listed species and their designated critical habitat and initiate consultation with USFWS, if required.
OTHER APPROVALS: In addition to the DA permit, other federal, state, and/or local approvals may be required for the proposed work is as follows:
Water Quality Certification from Alabama Department of Environmental Management (ADEM) pursuant to Section 401 (a)(1) of the CWA is required for the proposed project.
TVA approval is required under Section 26a of the TVA Act for all work that may occur on property that is under TVA control or custody and would be processed separately.
PUBLIC HEARING REQUESTS: Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. Requests for public hearings shall state, with particularity, the reasons for holding a public hearing.
COMMENT PERIOD: Written statements received in this office on or before January 28, 2018, will become a part of the record and will be considered in the determination. Any response to this notice should be directed to the Western Regulatory Field Office, Attention: Gary L. Davis at the above address, telephone (270) 702-1312, or email at gary.l.davis@usace.army.mil.
If you received this notice by mail and wish to view all of the diagrams, visit our web site at: http://www.lrn.usace.army.mil/Media/PublicNotices.aspx, or contact Mr. Gary L. Davis at the above address or telephone number, or email.
/s/
Timothy C. Wilder
Chief, West Regulatory Branch
Regulatory Division