The Illinois Urban Manual Standard, “Dewatering”, is being updated by the Illinois Urban Manual Technical Review Committee.
PUBLIC NOTICE
Illinois Urban Manual (IUM)
Standard Update
U.S. ArmyCorps of Engineers
Chicago District
IUM Standard NUMBERs: Dewatering Standard IUM #813
Comment Period Begins: January 8, 2018
Comment Period Expires: February 8, 2018
DESCRIPTION OF STANDARD
The Illinois Urban Manual Standard, “Dewatering”, is being updated by the Illinois Urban Manual (IUM) Technical Review Committee (TRC). The TRC is comprised of representatives of various regulatory agencies, consultants, developers, and other stakeholders. The IUM is the primary technical manual for Erosion and Sediment Control in the State of Illinois and is in the process of being updated as a result of advances in product development and associated operation and maintenance practices.
The Corps of Engineers and the IUM TRC is requesting comments from erosion and sediment control professionals, developers, engineers, contractors, and other interested parties on the enclosed attached standard. The comments will be reviewed by the TRC prior to the finalization of the IUM update. The approved standard will be incorporated into the IUM immediately upon approval by the IUM Steering Committee and Illinois Environmental Protection Agency.
Interested parties wishing to comment on the updated standard must do so in writing no later than February 8, 2018. It is presumed that all parties receiving this notice will wish to respond to this public notice; therefore, a lack of response will be interpreted as meaning that there is no objection to the "standard" as described herein.
All comments regarding the proposed standard must be submitted to the following person:
Rick McAndless
Illinois Urban Manuel Technical Review Committee Coordinator
North Cook County Soil and Water Conservation District
6640 Cosman Road
Elk Grove Village, IL 600007
Phone: (224) 875-7580
r.mcandless@northcookswcd.org
It should be noted that ALL comments received on this standard (via hard copy, or electronic) will only be accepted with the full name and address of the individual commenting.
This public notice is not a paid advertisement and is for public information only. Issuance of this notice does not imply Corps of Engineers endorsement of the standard as described.
If you have any questions regarding this public notice, please contact Kathy Chernich by telephone at (312) 846-5531, or email at kathy.g.chernich@usace.army.mil.
//ORIGINAL SIGNED//
Kathleen G. Chernich
Chief, East Section
Regulatory Branch
NOTICE TO POSTMASTERS:
It is requested that this notice be conspicuously and continuously posted until February 8, 2018.
PUBLIC NOTICE
Illinois Urban Manual (IUM)
Standard Update
U.S. ARMY
CORPS OF ENGINEERS
CHICAGO DISTRICT
IUM STANDARD NUMBERS:
Dewatering Standard IUM #813
COMMENT PERIOD BEGINS:
COMMENT PERIOD EXPIRES:
January 8, 2018
February 8, 2018
DESCRIPTION OF STANDARD
The Illinois Urban Manual Standard, "Dewatering", is being updated by the Illinois Urban
Manual (IUM) Technical Review Committee (TRC). The TRC is comprised of representatives of
various regulatory agencies, consultants, developers, and other stakeholders. The IUM is the
primary technical manual for Erosion and Sediment Control in the State of Illinois and is in the
process of being updated as a result of advances in product development and associated
operation and maintenance practices.
The Corps of Engineers and the IUM TRC is requesting comments from erosion and sediment
control professionals, developers, engineers, contractors, and other interested parties on the
enclosed attached standard. The comments will be reviewed by the TRC prior to the finalization
of the IUM update. The approved standard will be incorporated into the IUM immediately upon
approval by the IUM Steering Committee and Illinois Environmental Protection Agency.
Interested parties wishing to comment on the updated standard must do so in writing no later
than February 8, 2018. It is presumed that all parties receiving this notice will wish to respond
to this public notice; therefore, a lack of response will be interpreted as meaning that there is no
objection to the "standard" as described herein.
All comments regarding the proposed standard must be submitted to the following person:
Rick McAndless
Illinois Urban Manuel Technical Review Committee Coordinator
North Cook County Soil and Water Conservation District
6640 Cosman Road
Elk Grove Village, IL 600007
Phone: (224) 875-7580
-2r.mcandless@northcookswcd.org
It should be noted that ALL comments received on this standard (via hard copy, or
electronic) will only be accepted with the full name and address of the individual
commenting.
This public notice is not a paid advertisement and is for public information only. Issuance of this
notice does not imply Corps of Engineers endorsement of the standard as described.
If you have any questions regarding this public notice, please contact Kathy Chernich by
telephone at (312) 846-5531, or email at kathy.g.chernich@usace.army.mil.
//ORIGINAL SIGNED//
Kathleen G. Chernich
Chief, East Section
Regulatory Branch
NOTICE TO POSTMASTERS:
It is requested that this notice be conspicuously and continuously posted until February 8, 2018.
ILLINOIS URBAN MANUAL
PRACTICE STANDARD
DEWATERING
(no.)
CODE 813
(Source: Illinois Urban Manual Technical Committee)
DEFINITION
water, ground water, or other bodies of
water.
The controlled removal of water from
construction sites.
1. Where pumping operations occur.
PURPOSE
2. Where the water table is intercepted.
The purposes of this practice are as
follows:
3. Where work is performed in-stream.
4. Where collected runoff is removed
from construction sites.
1. To facilitate construction in areas
with surface water or a high water
table.
CRITERIA
2. To prevent sediment transport.
Dewatering shall consist of the removal
of surface water and/or ground water by
diverting and/or removing water from
construction sites to perform the
required construction in accordance with
the plans and specifications.
3. To provide worksite safety.
4. To prevent pollution of groundwater
or surface water from suspended soil
particles carried in construction site
dewatering operations.
Upland vegetated areas shall not be
used as a standalone sediment control
practice during dewatering operations.
5. To preserve downgradient natural
resources and property.
CONDITIONS WHERE PRACTICE
APPLIES
Construction sites, including any onsite
and offsite excavated areas, where the
presence of water creates unsafe
conditions, potential damage, or restricts
construction operations.
Construction sites where water is
present in any form, including
intermittent runoff, streams, standing
Diverting Surface Water Cofferdams,
channels, sumps, flumes, and
temporary diversions shall be built and
maintained, according to contract plans,
specifications, and respective IUM
practice standards.
Installation of cofferdams and sumps
shall follow the requirements as outlined
in practice standards COFFERDAM 803
and SUMP PIT 950.
813 - 1
Excess surface runoff shall be diverted
from the construction area as outlined in
the practice standards TEMPORARY
DIVERSION 955, TEMPORARY
SWALE 980, DIVERSION 815, and
DIVERSION DIKE 820.
A permanent stream or other
concentrated flow shall be diverted away
from the construction area as outlined in
practice standard TEMPORARY
STREAM DIVERSION 976.
Removing Water Drains, sumps,
pumps, casings, well points and all other
practices required to dewater the site
shall be furnished, installed and
maintained according to contract plans,
specifications, and respective IUM
practice standards.
Well points and deep wells shall be
placed at intervals along the
construction area as necessary to
depress the groundwater table during
construction. Monitoring wells shall be
installed where measurement of the
pumping effectiveness is required. Well
point and deep well dewatering shall be
terminated as soon as practical.
In poorly drained soil areas, or where
well dewatering is not practical, pumping
directly from construction trenches will
be permitted, provided appropriate
sediment control practices are
incorporated with the pumping activity.
Erosion and Sediment Control All
dewatering activities shall be performed
in a manner that does not negatively
impact the water quality of the water
table, cause erosion, or transport
sediment to wetlands, water bodies,
water conveyance features, etc. on or
off site.
Sediment removal shall be provided
using the following practices, or
combination of practices, depending on
the soil type, dewatering method,
location, and amount of dewatering.
Where sumps are used, they shall meet
the requirements of SUMP PIT 950. In
addition, where space is available, a
TEMPORARY SEDIMENT TRAP 960
shall be used to detain water and
remove sediment from pumping and
diversion operations. Where there is
limited space a PORTABLE SEDIMENT
TANK 895 shall be used to retain
sediment during dewatering operations.
POLYACRYLAMIDE (PAM) FOR
TURBIDITY REDUCTION AND
SEDIMENT CONTROL 894 may also be
used, as appropriate.
Where there is low, intermittent pumping
activity, pumps with sediment filter bags
shall be used. Sediment filter bags shall
be attached to pump discharges and
surrounded with a secondary
containment practice. Secondary
containment shall be used when
discharge water from a sediment filter
bag drains to any body of water,
wetland, or water conveyance feature
(ditch, swale, etc.) Secondary
containment shall be placed between
the sediment filter bag and the receiving
area and/or aquatic resource. Sediment
filter bags shall be placed on a stabilized
surface area. Sediment filter bags shall
not be placed, whole or partially, within
aquatic areas (wetlands, streams, etc.),
or water conveyance features ( ditches,
swales, etc.). Sediment filter bags shall
be raised above the supporting ground
on a surface, or material, that allows
water to flow out of the bottom of the
bag at the respective design discharge
rate for the sediment filter bag selected.
Materials, structures, etc. that are used
to ensure that water flows out of the
bottom of a sediment filter bag must
also be placed atop a stabilized surface
area ( E.g. stone).
The material for the sediment filter bag
shall meet the requirements of material
813 - 2
5. Ability to supervise pump operation.
specification 592 GEOTEXTILE, Table
2, Class I with a minimum tensile
strength of 200 lbs, or Table 1, Class 4
The sediment filter bag shall be sized
per manufacturer recommendations and
based on the size of the pump however,
the minimum bag size shall be10 foot x
15 foot with a useable surface drainage
area of 300 square feet ( 10 x 15 x 2
sides, top & bottom) The largest size
pump to be used with a sediment filter
bag shall be 4-inch diameter. Multiple
hoses/pipes shall not be attached to a
single filtration bag inlet sleeve.
Evaluate function, need, velocity control,
outlet stability, and site aesthetics. The
location and capacity of temporary
diversion and protective works should
be based on the characteristics of the
site, accessibility, and the potential
damage during development.
Winter conditions and freezing
temperatures can impact the
effectiveness and functionality of
sediment filter bags and anionic
polymers for sediment removal during
dewatering. If dewatering activities are
likely to occur over winter, dewatering
practices for sediment control should be
included in the development of the
Stormwater Pollution Prevention Plan
that can be effective in freezing
temperatures.
All outlets, and drainage pathways for
dewatering discharges shall be stable
and protected from erosion.
Removal of Dewatering Facilities - The
temporary dewatering areas shall be
removed after they have served their
purpose. The dewatering areas shall be
graded and stabilized with appropriate
erosion control practices and not create
any obstruction of normal water flow, or
any other interference with the operation
of, or access to the permanent works.
Federal, state, county and local water
quality requirements shall be followed
when choosing a dewatering method
and may include a requirement for
sampling and evaluating discharges for
clarity.
CONSIDERATIONS
Base the location, method of
dewatering, and configuration on site
conditions. The following items should
be considered when selecting the proper
dewatering method:
1. Amount of water to remove.
2. Maintenance and operation required
as a result of the construction
operations.
3. Length of time to complete the work.
4. The space available in the work
area.
An analysis of the effects of dewatering
a site should also be considered. For
example, permanent dewatering of a
site may cause subsidence of surface
areas and settlement of foundations,
Also, temporary dewatering may create
dry areas during construction but the
effect of allowing water tables to rise
after construction may result in excess
pressure on subsurface structures,
potentially causing damage and/or
excessive sump pump cycling.
PLANS AND SPECIFICATIONS
Plans and specifications for installing
and building dewatering facilities shall
be in keeping with this standard and
shall describe the requirements for
applying the practice to achieve its
intended purpose. At a minimum
include:
813 - 3
1. Approximate location and proposed
type of dewatering method shown
on plans.
2. Drawings, specifications, etc. for all
items of work as needed for
dewatering.
3. Include the dewatering plan as part
of the stormwater pollution
prevention plan (SWPPP) and/or the
erosion and sediment control plan,
detailing the location of dewatering
activities, presence of aquatic areas,
equipment, fuel storage, and
discharge point.
4. Any total maximum daily load
(TMDL) requirements for the
receiving waters or turbidity
standards shall be stated on the
plan set.
5. A brief narrative outlining a
construction sequence for the
dewatering operation.
6. Drawing details for proper
installation of the various dewatering
facilities as needed.
All plans shall include installation,
inspection, and maintenance schedules
with the responsible party identified.
Methods of dewatering shall be
constructed to meet the requirements of
construction specification REMOVAL
OF WATER 11.
OPERATION AND MAINTENANCE
The frequency of inspections shall
depend on the dewatering method,
amount of discharge, potential damage,
and quality of the receiving bodies of
water. The frequency of inspections,
responsible party and specific tasks
shall be identified.
2. Accumulated sediment shall be
removed from the flow area and
temporary diversions shall be
repaired, as required.
3. Outlet areas shall be checked and
repairs shall be made in a timely
manner, as needed.
4. Pump outlets shall be inspected for
erosion, and sumps shall be
inspected for accumulated sediment.
5. Sediment filter bags shall be
removed and replaced when half full
of sediment, or when the design
flow rate of the filter bag is no longer
being maintained.
6. If the receiving area is showing any
signs of cloudy water, erosion, or
sediment accumulation, discharges
shall be stopped immediately once
safety and property damage
concerns have been addressed.
7. Accumulated sediment from
dewatering operations shall be
disposed of in accordance with all
applicable laws and regulations.
REFERENCES
Maine Department of Environmental
Protection, Bureau of Land and Water
Quality. Maine Erosion and Sediment
Control BMPs. G-3 Construction
Dewatering. Augusta, ME. March
2003.
IDOT Erosion and Sediment Control
Field Guide for Construction Inspection,
July 1, 2010
November 2017
urbst813.doc
1. Inspections shall be conducted to
ensure proper operation and
compliance with all permits and
water quality standards.
813 - 4