Eversource Energy of Westwood, MA, has submitted a permit application to work within Boston Harbor

Eversource Energy of Westwood, MA, has submitted a permit application to work within Boston Harbor between Conley Terminal and Deer Island. The work will consist of installing a replacement 115k V cable from K Street to the Deer Island wastewater treatment facility. Removal or abandonment of the existing cable will be addressed in a separate action.