INSTALL AND MAINTAIN RESIDENTIAL HOMES, STREETS, AND DETENTION PONDS FOR THE ROBINDALE SUBDIVISION IN SAINT TAMMANY PARISH
NAME OF APPLICANT: Steadfast Development, LLC c/o J. V. Burkes and Associates, Inc., Barbara Zelenka, 1805 Shortcut Highway, Slidell, Louisiana 70458.
LOCATION OF WORK: Section 35, Township 6 South, Range 11 East, in Covington, Louisiana, in Saint Tammany Parish, as shown on the attached drawings.
HUC: 08090201: Liberty Bayou – Tchefuncte River
Latitude: 30.487147 Longitude: -90.056178
CHARACTER OF WORK: Approximately 10,000 cubic yards of sandy clay, 3,200 cubic yards of concrete, and 1,050 cubic yards of asphalt will be deposited for the installation and maintenance of residential homes, roadways, detention ponds, and appurtenant structures in the Robindale Subdivision, in Covington, Louisiana. Approximately 17.8 acres of pine savannah/flatwood wetlands would be impacted.
The current applicant has recently secured the original Department of the Army permit (authorized on May 14, 2007) from the previous holder and is requesting a time extension to complete the project. The work has been started, but not completed. Compensatory mitigation requirements of the original permit are outstanding. The applicant stated their intent to bring the project into compliance by securing the original compensatory mitigation requirements of 24.0 acres of pine savannah/flatwood mitigation at the Bayou Lacombe mitigation bank.
JOINT PUBLIC NOTICE
February 5, 2018
United States Army
Corps of Engineers
New Orleans District
Regulatory Branch
7400 Leake Avenue
New Orleans, Louisiana 70118
State of Louisiana
Department of Environmental Quality
Attn: Water Quality Certifications
Post Office Box 4313
Baton Rouge, Louisiana 70821-4313
(504) 862-2259
Project Manager
Scott N. Kennedy
scott.n.kennedy@usace.army.mil
Permit Application Number
MVN 2004-02863 EMM
(225) 219-3225
Project Manager
Elizabeth Hill
WQC Application Number
WQC 180129-01
Interested parties are hereby notified that a permit application has been received by the New Orleans
District of the U.S. Army Corps of Engineers pursuant to: [ ] Section 10 of the Rivers and Harbors Act of
March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or [X] Section 404 of the Clean Water Act (86 Stat. 816;
33 USC 1344).
Application has also been made to the Louisiana Department of Environmental Quality, Water
Quality Certifications, for a Water Quality Certification (WQC) in accordance with statutory authority
contained in LRS 30:2074 A(3) and provisions of Section 401 of the Clean Water Act.
INSTALL AND MAINTAIN RESIDENTIAL HOMES, STREETS, AND DETENTION PONDS
FOR THE ROBINDALE SUBDIVISION IN SAINT TAMMANY PARISH
NAME OF APPLICANT: Steadfast Development, LLC c/o J. V. Burkes and Associates, Inc., Barbara
Zelenka, 1805 Shortcut Highway, Slidell, Louisiana 70458.
LOCATION OF WORK: Section 35, Township 6 South, Range 11 East, in Covington, Louisiana, in
Saint Tammany Parish, as shown on the attached drawings.
HUC: 08090201: Liberty Bayou Tchefuncte River
Latitude: 30.487147 Longitude: -90.056178
CHARACTER OF WORK: Approximately 10,000 cubic yards of sandy clay, 3,200 cubic yards of
concrete, and 1,050 cubic yards of asphalt will be deposited for the installation and maintenance of
residential homes, roadways, detention ponds, and appurtenant structures in the Robindale Subdivision, in
Covington, Louisiana. Approximately 17.8 acres of pine savannah/flatwood wetlands would be impacted.
The current applicant has recently secured the original Department of the Army permit (authorized on
May 14, 2007) from the previous holder and is requesting a time extension to complete the project. The
work has been started, but not completed. Compensatory mitigation requirements of the original permit
are outstanding. The applicant stated their intent to bring the project into compliance by securing the
original compensatory mitigation requirements of 24.0 acres of pine savannah/flatwood mitigation at the
Bayou Lacombe mitigation bank.
-2The comment period for the Department of the Army Permit and the Louisiana Department of
Environmental Quality WQC will close 20 days from the date of this joint public notice. Written
comments, including suggestions for modifications or objections to the proposed work, stating reasons
thereof, are being solicited from anyone having interest in this permit and/or this WQC request and must
be mailed so as to be received before or by the last day of the comment period. Letters concerning the
Corps of Engineers permit application must reference the applicant's name and the Permit Application
Number, and be mailed to the Corps of Engineers at the address above, ATTENTION:
REGULATORY BRANCH. Similar letters concerning the Water Quality Certification must reference
the applicant's name and the WQC Application number and be mailed to the Louisiana Department of
Environmental Quality at the address above. Individuals or parties may request an extension of time in
which to comment on the proposed work by writing or e-mailing the Corps of Engineers Project Manager
listed above. Any request must be specific and substantively supportive of the requested extension, and
received by this office prior to the end of the initial comment period. The Section Chief will review the
request and the requestor will be promptly notified of the decision to grant or deny the request. If granted,
the time extension will be continuous to the initial comment period and, inclusive of the initial comment
period, will not exceed a total of 30 calendar days.
The application for this proposed project is on file with the Louisiana Department of
Environmental Quality and may be examined weekdays between 8:00 a.m. and 4:30 p.m. Copies may be
obtained upon payment of costs of reproduction.
Corps of Engineers Permit Criteria
The decision whether to issue a permit will be based on an evaluation of the probable impacts,
including cumulative impacts of the proposed activity on the public interest. That decision will reflect the
national concern for both protection and utilization of important resources. The benefit which reasonably
may be expected to accrue from the proposal must be balanced against its reasonably foreseeable
detriments. All factors which may be relevant to the proposal will be considered including the cumulative
effects thereof; among those are conservation, economics, aesthetics, general environmental concerns,
wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use,
navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality,
energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and,
in general, the needs and welfare of the people.
The U.S. Army Corps of Engineers is soliciting comments from the public, federal, state, and local
agencies and officials, Indian Tribes, and other interested parties in order to consider and evaluate the
impacts of this proposed activity. Any comments received will be considered by the U.S. Army Corps of
Engineers to determine whether to make, modify, condition, or deny a permit for this proposal. To make
this decision, comments are used to assess impacts on endangered species, historic properties, water
quality, general environmental effects, and other public interest factors listed above. Comments are used
in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant
to the National Environmental Policy Act. Comments are also used to determine the need for a public
hearing and to determine the overall public interest of the proposed activity.
The New Orleans District is unaware of properties listed on the National Register of Historic
Places near the proposed work. The possibility exists that the proposed work may damage or destroy
presently unknown archeological, scientific, prehistorical, historical sites, or data. Issuance of the public
notice solicits input from the State Archeologist and State Historic Preservation Office regarding potential
impacts to cultural resources.
-3The New Orleans District has determined that the proposed work would neither affect any species
or critical habitat listed as endangered by the U.S. Department of Commerce.
Utilizing Standard Local Operating Procedure for Endangered Species in Louisiana (SLOPES),
dated October 22, 2014, between the U.S. Army Corps of Engineers, New Orleans and U.S. Fish and
Wildlife Service, Ecological Services Office, the Corps has determined that the proposed activity would
have no effect on any listed species.
This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the MagnusonStevens Fishery Conservation and Management Act. The applicant's proposal would result in the
destruction or alteration of up to N/A acres of EFH utilized by various life stages of red drum and penaeid
shrimp. Our initial determination is that the proposed action would not have a substantial adverse impact
on EFH or federally managed fisheries in the Gulf of Mexico. Our final determination relative to project
impacts and the need for mitigation measures is subject to review by and coordination with the National
Marine Fisheries Service.
If the proposed work involves deposits of dredged or fill material into navigable waters, the
evaluation of the probable impacts will include the application of guidelines established by the
Administrator of the Environmental Protection Agency. Also, a certification that the proposed activity
will not violate water quality standards will be required from the Department of Environmental Quality,
Water Quality Certifications, before a permit is issued.
Any person may request, in writing, within the comment period specified in this notice, that a
public hearing be held to consider this application. Requests for public hearings shall state, with
particularity, the reasons for holding a public hearing.
You are requested to communicate the information contained in this notice to any other parties
whom you deem likely to have interest in the matter.
Michael Farabee
Chief, Eastern Evaluation Section
Enclosures
Current Construction (Dashed Area)
FOR SEC 404 PERMITTING ONLY This
document is not to be used for construction,
bidding, recordation, conveyance or sales.
Project Limits
Total Site Acreage 37.1 Acres
Wetland Acreage 17.8 Acres
Excavation:
NOT A PART
+/-10,000 cy clean sandy clay fill
+/- 3,201 cy concrete
+/- 1,050 cy asphalt
Note: Site to be selectively cleared and graded.
Best Management Practices (BMPs) during
Construction would be utilized to reduce
sedimentation and erosion potential. Removed
soils would be hauled off to a commercial disposal
facility. All hauled in soils would be free of
contaminants. Central Sewer and Water system
to be installed
Detention Pond
Constructed
Project Limits
ROAD BASE PREVIOUSLY CONSTRUCTED
Fill:
NONWET UNDER CONSTRUCTION
+/-11,700 cy onsite soils
A
Wetland 17.8 acres pine flatwood/savanna
(includes previously constructed areas)
FINISHING ROAD CONSTRUCTION
Previously
Constructed
NONWET UNDER CONSTRUCTION
NOT A PART
NOT A PART
Detention Pond Constructed
Previously Constructed
Scale:
0
200'
SITE PLAN Steadfast Development, LLC
Date: 12-19-17
Portions of Sq 7, 8. 9, 11, 13, 14, and 15 Robindale S/D,
St. Tammany Parish, Louisiana
Scale: 1" = 200'