INSTALL AND MAINTAIN A PIER, BOATHOUSE, AND DECK IN THE GEOGHEGAN CANAL IN SAINT TAMMANY PARISH
NAME OF APPLICANT: Robert Bordlee, 24 Watters Court, River Ridge, Louisiana 70123; Lamulle Construction, 4978 Pontchartrain Drive, Slidell Louisiana 70458.
LOCATION OF WORK: Geoghegan Canal, Section 37, Township 10 South, Range 15 East, in Slidell, Louisiana, in Saint Tammany Parish, as shown on the attached drawings.
HUC: 08090201: Liberty Bayou – Tchefuncta
Latitude: 30.183581 Longitude: -89.718933
CHARACTER OF WORK: Install and maintain a 120’ fiberglass pier at the end of an existing wooden pier and a 42’ x 36’ boathouse and deck at the end of the fiberglass pier in Slidell, Louisiana. The applicant contends jurisdictional wetlands will not be impacted, as such compensatory mitigation is not anticipated at this time.
DEPARTMENT OF THE ARMY
CORPS OF ENGINEERS, NEW ORLEANS DISTRICT
7400 LEAKE AVENUE
NEW ORLEANS, LOUISIANA 70118
REPLY TO
ATTENTION OF
Operations Division
Eastern Evaluation Section
February 20, 2018
Project Manager
Scott Kennedy
(504) 862-2259
Scott.N.Kennedy@usace.army.mil
SUBJECT: MVN-2010-01462 EMM
PUBLIC NOTICE
Interested parties are hereby notified that a permit application has been received by
the New Orleans District of the U.S. Army Corps of Engineers pursuant to: [X] Section
10 of the Rivers and Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or
[ ] Section 404 of the Clean Water Act (86 Stat. 816; 33 USC 1344).
INSTALL AND MAINTAIN A PIER, BOATHOUSE, AND DECK
IN THE GEOGHEGAN CANAL IN SAINT TAMMANY PARISH
NAME OF APPLICANT: Robert Bordlee, 24 Watters Court, River Ridge, Louisiana
70123; Lamulle Construction, 4978 Pontchartrain Drive, Slidell Louisiana 70458.
LOCATION OF WORK: Geoghegan Canal, Section 37, Township 10 South, Range 15
East, in Slidell, Louisiana, in Saint Tammany Parish, as shown on the attached
drawings.
HUC: 08090201: Liberty Bayou Tchefuncta
Latitude: 30.183581 Longitude: -89.718933
CHARACTER OF WORK: Install and maintain a 120' fiberglass pier at the end of an
existing wooden pier and a 42' x 36' boathouse and deck at the end of the fiberglass
pier in Slidell, Louisiana. The applicant contends jurisdictional wetlands will not be
impacted, as such compensatory mitigation is not anticipated at this time.
The comment period will close 15 days from the date of this public notice. Written
comments, including suggestions for modifications or objections to the proposed work,
stating reasons thereof, are being solicited from anyone having interest in this permit
and must be mailed so as to be received before or by the last day of the comment
period. Letters concerning the Corps of Engineers permit application must reference
the applicant's name and the Permit Application Number, and be mailed to the Corps of
Engineers at the address above, ATTENTION: REGULATORY BRANCH. Individuals
or parties may request an extension of time in which to comment on the proposed work
by writing or e-mailing the Corps of Engineers Project Manager listed above. Any
-2-
request must be specific and substantively supportive of the requested extension, and
received by this office prior to the end of the initial comment period. The Section Chief
will review the request and the requestor will be promptly notified of the decision to
grant or deny the request. If granted, the time extension will be continuous to the initial
comment period and, inclusive of the initial comment period, will not exceed a total of 30
calendar days.
Corps of Engineers Permit Criteria
The decision whether to issue a permit will be based on an evaluation of the impact
of the proposed work on navigation and national security.
The U.S. Army Corps of Engineers is soliciting comments from the public, federal,
state, and local agencies and officials, Indian Tribes, and other interested parties in
order to consider and evaluate the impacts of this proposed activity. Any comments
received will be considered by the U.S. Army Corps of Engineers to determine whether
to make, modify, condition, or deny a permit for this proposal. To make this decision,
comments are used to assess impacts on endangered species, historic properties,
water quality, general environmental effects, and other public interest factors listed
above. Comments are used in the preparation of an Environmental Assessment and/or
an Environmental Impact Statement pursuant to the National Environmental Policy Act.
Comments are also used to determine the need for a public hearing and to determine
the overall public interest of the proposed activity.
The New Orleans District is unaware of properties listed on the National Register of
Historic Places near the proposed work. The possibility exists that the proposed work
may damage or destroy presently unknown archeological, scientific, prehistorical,
historical sites, or data. Issuance of this public notice solicits input from the State
Archeologist and the State Historic Preservation Officer regarding potential impacts to
cultural resources.
Our initial finding is that the proposed work would neither affect critical habitat nor
any species listed as endangered by the U.S. Department of Commerce.
Utilizing Standard Local Operating Procedure for Endangered Species in Louisiana
(SLOPES), dated October 22, 2014, between the U.S. Army Corps of Engineers, New
Orleans and U.S. Fish and Wildlife Service, Ecological Services Office, the Corps has
determined that the proposed activity would have no effect on any listed species.
This notice initiates the Essential Fish Habitat (EFH) consultation requirements of
the Magnuson-Stevens Fishery Conservation and Management Act. The applicant's
proposal would result in the destruction or alteration of n/a acres of EFH utilized by
various life stages of red drum and penaeid shrimp. Our initial determination is that the
proposed action would not have a substantial adverse impact on EFH or federally
managed fisheries in the Gulf of Mexico. Our final determination relative to project
impacts and the need for mitigation measures is subject to review by and coordination
with the National Marine Fisheries Service.
-3-
If the proposed work involves deposits of dredged or fill material into navigable
waters, the evaluation of the probable impacts will include the application of guidelines
established by the Administrator of the Environmental Protection Agency. Also, a
certification that the proposed activity will not violate applicable water quality standards
will be required from the Department of Environmental Quality before a permit is issued.
The applicant has certified that the proposed activity described in the application
complies with and will be conducted in a manner that is consistent with the Louisiana
Coastal Resources Program. The Department of the Army permit will not be issued
unless the applicant received approval or a waiver of the Coastal Use Permit by the
Department of Natural Resources.
Any person may request, in writing, within the comment period specified in this
notice, that a public hearing be held to consider this application. Requests for public
hearings shall state, with particularity, the reasons for holding a public hearing.
You are requested to communicate the information contained in this notice to any
other parties whom you deem likely to have interest in the matter.
Michael Farabee
Chief, Eastern Evaluation Section
Attachments