Programmatic General Permit (18-PGP-01) for Minor Structures, Work, and Associated Minor Activities Located in the Tennessee Valley Authority Reservoirs and Slackwaters within the states of Alabama, Kentucky, Mississippi, Tennessee, and Virginia
Public Notice No. 18-13
Nashville District
Date: March 30, 2018;Expires: April 30, 2018
Please address all comments to:
Nashville District Corps of Engineers
Regulatory Division (Attn: Aurora Scott),
3701 Bell Road, Nashville, TN 37214
PROPOSED PROGRAMMATIC GENERAL PERMIT
TO ALL CONCERNED: Interested parties are hereby notified that in accordance with 33 CFR 325.2(e)(2) and 325.3(b), the Nashville District of the U.S. Army Corps of Engineers (Corps) is proposing to issue a programmatic general permit (PGP), described herein, pursuant to Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (CWA). A provisional determination (copy available from this office for review) has been made that the individual activities proposed for issuance under the PGP comply with the requirements for issuance of general permits as required by 33 CFR 325.3(b).
This permit would be valid for a period of 5 years, to expire in 2023. If unforeseen adverse impacts result from the issuance of this PGP, it may be modified or terminated. However, before this PGP can be issued, certification must be provided, pursuant to Section 401(a)(1) of the CWA, that applicable water quality standards would not be violated for proposed Clean Water Act activities, from the following agencies:
• State of Alabama, Department of Environmental Management
• Commonwealth of Kentucky, Natural Resources and Environmental Protection Cabinet
• Commonwealth of Virginia, Department of Environmental Quality
• State of Mississippi, Department of Environmental Quality
• State of Tennessee, Department of Environment and Conservation
By copy of this notice, the Corps hereby applies for the required certifications.
PERMIT NUMBER: 18-PGP-01
PERMIT TITLE: Programmatic General Permit (18-PGP-01) for Minor Structures, Work, and Associated Minor Activities Located in the Tennessee Valley Authority Reservoirs and Slackwaters within the states of Alabama, Kentucky, Mississippi, Tennessee,and Virginia
ISSUING OFFICE: U.S. Army Corps of Engineers, Nashville District
Regulatory Division
3701 Bell Road
Nashville, TN 37214
Purpose: In recognition of the fact that both TVA and the Corps have related authorities and permitting responsibilities for regulating waters of the US, specifically navigable waters within TVA reservoir boundaries, and in order to improve agency cooperation, consultation, and efficiency, the Corps is considering the issuance of the subject PGP. Issuance of this PGP would reduce and/or eliminate overlapping environmental reviews and permitting actions taken by both agencies within the Nashville District Regulatory boundaries.
Separate but Similar Roles and Responsibilities of TVA and Corps. TVA manages reservoir shoreline development along the Tennessee River and its slack waters through their Section 26a permit, which regulates the construction of shoreline structures and other related activities. The Corps has related responsibilities under Section 10 of the Rivers and Harbors Act and Section 404 of the CWA. Section 26a of the TVA Act (US Congress, 1933) requires that TVA approval be obtained prior to construction, operation, or maintenance of any activity, appurtenant works, or other obstruction affecting navigation, flood control, public lands, or reservations along or in the Tennessee River or its tributaries.
Location of Activities: The TVA reservoir boundary is defined as the extent to which the US owns reservoir property entrusted to TVA (including both fee-owned land and flowage easements). On TVA reservoirs, jurisdiction typically extends to the 500-year floodplain or to the upper limits of the 100-year floodplain. In particular situations, jurisdiction may extend to higher elevations.
The PGP would be applicable to the TVA reservoir boundary, which specifically includes the Tennessee River navigable and slack waters of Kentucky Lake, Pickwick Lake, Wilson Lake, Wheeler Lake, Guntersville Lake, Tims Ford Lake, Upper Bear Creek Lake, Little Bear Creek Lake, Cedar Creek, Lake, Fort Loudon Lake, Watts Bar Lake, Douglas Lake, Norris Lake, Cherokee Lake, South Holston Lake, Ft. Patrick Henry Lake, Boone Lake, Watauga Lake, Chickamauga Lake, Tellico Lake, Melton Lake, and Nickajack Lake.
Activities to be Covered: This PGP would apply to the following activities:
a. Docks, Piers, Boathouses, and Other Water Use Facilities. Construction, modification, and maintenance of fixed and floating docks, piers, and boathouses; steps leading to the reservoir; walkways leading to dock facilities; water intakes, geothermal heat exchange units or electrical lines attached to dock facilities; and other associated structures. (Section 10)
b. New Work Channel Excavation. Excavation of material from the reservoir bottom to create sufficient depth for mooring and navigation of vessels. Dredging of no more than 150 cubic yards below the normal full pool elevation of the reservoir. Excavation shall only be performed between the reservoir shoreline and surface of the lake, when the reservoir is below full pool elevation; referred to as work in the dry. Excavated material shall be disposed of in a confined upland
disposal site located above the 100- year floodplain. The discharge of effluent from a confined upland disposal site is not authorized. (Sections 10 and 404)
NOTE: Maintenance excavation of previously authorized facilities is not authorized by 18-PGP-01. An application must be submitted to the Corps to conduct maintenance excavation in a facility with a valid 26.a Permit.
c. Shoreline Stabilization. Shoreline stabilization necessary for erosion control. All fill and excavation work shall be performed in the dry. (Sections 10 and 404)
d. Boat Ramps and Other Recreation Watercraft Launching Facilities. The discharge of the fill material and/or the excavation of material necessary for the construction, improvement, expansion, or maintenance of boat ramps, or other recreational watercraft launching facilities. Only clean, inert material shall be used for fill
material. Excavated material not used for boat ramp construction will be disposed of in a confined upland disposal site located above the 100-year floodplain. All fill and excavation work shall be performed in the dry. The discharge of effluent from a confined upland disposal site is not authorized. (Sections 10 and 404)
Activities excluded from PGP. Activities that exceed the thresholds of the PGP, have more than minimal impacts to the aquatic environment, and/or have unacceptable impacts on the public interest would not be authorized under the PGP. This PGP would exclude work or structures located within areas previously identified to be potentially hazardous to commercial navigation, and/or within wetlands or areas designated as a special aquatic site. The TVA and the Corps will coordinate, as appropriate, on proposed activities located in sections of the river with navigation restrictions.
Lead Agency Role between the TVA and Corps: Lead agency roles and responsibilities under NEPA are as described in Sections 1501, 1504, 1506 and 1508 of the CEQ’s regulations. Section 501 provides that if more than one federal agency is involved in the same action, or is involved in a group of actions directly related to each other because of their geographical proximity, then one agency may act as lead. Section 1508 defines the lead agency as the agency taking primary responsibility for conducting and preparing environmental impact reviews pursuant to NEPA. The lead agency is responsible for initiating and directing the conduct of all NEPA consultations and coordination.
Recently the Corps and TVA revisited their 1985 Memorandum of Understanding (MOU) for the purpose of reducing agency separate, and overlapping, coordination and conduct of environmental reviews for the permit applications. Since both the Corps and TVA have related jurisdiction and responsibilities for regulating activities within the project boundaries of TVA reservoirs, the agencies re-established that TVA will serve as the lead federal agency on permit applications and projects within the Tennessee River reservoir boundaries and whenever US property in TVA custody or control is involved. The Corps will serve as the lead federal agency in all other cases (off Tennessee River reservoir) unless otherwise agreed to by TVA and Corps.
Procedures for Use of the PGP: Under the PGP procedures, a permit applicant would apply to TVA for authorizations under both TVA’s and the Corps’ permit programs. TVA, as lead agency, will determine if the activities are consistent with TVA’s procedures and permitting regulations, and are in procedural or substantive compliance with NEPA and any other Federal laws (i.e., the Endangered Species Act, the Clean Water Act, the National Historic Preservation Act). TVA will coordinate with the Corps if appropriate, but not normally. An individual activity/activities proposed for authorization under 18-PGP-01 will automatically be authorized under 18-PGP-01 if/when TVA issues a 26a permit for the proposed activities, and no further coordination or notification to the Corps would normally be required.
TVA’s 26a permit documentation to the permittee will provide a statement that the activities also meet the criteria of Corps 18-PGP-01, and notification to the Corps would not be required.
Likewise, any activity that is denied a permit from TVA would not be eligible for verification under 18-PGP-01.
Issuance of the PGP would not relieve the applicant of the necessity of obtaining other federal, state, or local permits, licenses, or authorizations required. Activities requiring DA authorization that are not specifically covered by the PGP would be prohibited unless authorized by a separate permit. Work or structures that would have more than minimal impacts to the aquatic environment and/or unacceptable impacts on the public interest would not be authorized and may require an individual permit.
Cultural Resources Assessment: The proposed PGP would not authorize activities which would adversely affect properties registered or listed as eligible for inclusion in the National Register of Historic Places. Presently unknown archaeological, scientific, prehistorical, or historical data may be located within the areas of consideration and could be affected by the proposed work. The TVA, as lead Federal agency, will determine if the specific activities proposed by applicants are
in compliance with the National Historic Preservation Act.
Endangered Species: The Endangered Species Act of 1973 (ESA), as amended, requires all federal agencies to consult with the National Marine Fisheries Service (NMFS) and/or U.S. Fish and Wildlife Service (USFWS), pursuant to Section 7 of the ESA, on any action, or proposed action, permitted, funded, or undertaken by the agency that may affect a species listed as threatened or endangered under the ESA, or its designated critical habitat. The TVA, as lead Federal agency, will determine if the specific activities proposed by applicants are in compliance with the Endangered Species Act.
Public Interest Review: The decision whether to issue the PGP would be based on an evaluation of the probable impacts including cumulative impacts of the activity on the public interest. That decision would reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the work
must be balanced against its reasonably foreseeable detriments. All factors which may be relevant
to the work would be considered including the cumulative effects; conservation, economics, aesthetics, general environmental concerns, wetlands, cultural values, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shore erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership, and in general the needs and welfare of the people. The PGP will be issued unless the District Engineer determines it would be contrary to public interest.
Consideration of Public Comments: The Corps is soliciting comments from the public; federal, state, and local agencies and officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps of Engineers to determine whether to issue, modify, condition, or deny
a permit for this PGP. To make this decision, comments are used to assess impacts on endangered
species, historic properties, water quality, general environmental effects, and other public interest factors listed above.
Comments will be used in the preparation of an EA and/or an Environmental Impact Statement, if required, pursuant to NEPA. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the activity.
Application of Section 404(b)(1) Guidelines: Certain activities that would be authorized by 18-PGP-01 could involve the discharge of dredged or fill material into the waters of the United States. The Nashville District's evaluation of the impact of the activity on the public interest will include application of the guidelines promulgated by the Administrator, Environmental Protection Agency, under the authority of Section 404(b) of the Clean Water Act.
Public Hearing: Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider the issuance of 18-PGP-01. Requests for public hearings shall state, with particularity, the reasons for requesting a public hearing. The decision whether to hold a public hearing is at the discretion of the District Engineer, or his designated appointee, based on the need for additional substantial information necessary in evaluating the proposed PGP.
Comment Period: Written statements received in this office on or before April 30, 2018, become a part of the record and would be considered in the determination. Any response to this notice should refer to Public Notice Number 18-13 and be directed to the Regulatory Division, Attention: Aurora Scott, at the above address, email Aurora.C.Scott@usace.army.mil, or telephone (615) 369-7520.
For additional information about our Regulatory Program, please visit our web site at www.lrn.usace.army.mil, and please take a moment to complete our customer satisfaction survey while you are there. Your response is appreciated and will allow us to improve our services.
BY:
/s/
Casey H. Ehorn
Chief, East Branch
Regulatory Division
U.S. Army Corps of Engineers