LETTER OF PERMISSION: The applicant proposes to construct an expansion of their current facility. The expansion would take place on farm
land immediately to the west of the current Digi Key facility.
PROJECT DESCRIPTION AND PURPOSE: The applicant proposes to construct an expansion of their current facility. The expansion would take place on farm land immediately to the west of the current Digi Key facility. The project would involve the construction of an approximately 1,000,000 square foot warehouse and distribution center. Two entrance roads from County State Aid Highway 16 would also be constructed for vehicle entrance and exit from the new facility. An entrance would also be constructed on the north end of the proposed facility from Barzen Avenue.
Information for File # MVP-2017-03282-LSP
Applicant: Digi Key Electronics Rick Harris
Corps Contact: Lawrence Puchalski
Address: 4111 Technology Drive, Suite 295, Bemidji, Minnesota 56601
E-Mail: Lawrence.S.Puchalski@usace.army.mil
Phone: (651) 290-5339
Primary County: Pennington
Sections: 32
Township: 154N
Range: 43W
Information Complete On: 21 February 2018.
Posting Expires On: 18 April 2018.
Authorization Type: LOP-05-MN(B)
This application is being reviewed in accordance with the practices for documenting Corps
jurisdiction under Sections 9 & 10 of the Rivers and Harbor Act of 1899 and Section 404 of the
Clean Water Act identified in Regulatory Guidance Letter 07-01. We have made a preliminary
determination that the aquatic resources that would be impacted by the proposed project are
regulated by the Corps of Engineers under Section 404 of the Clean Water Act. Our
jurisdictional review and final jurisdictional determination could result in modifications to the
scope of the project's regulated water body/wetland impacts and compensatory mitigation
requirements identified above. An approved jurisdictional determination will be made prior to
reaching a permit decision, and will be posted on the St. Paul District web page at
http://www.mvp.usace.army.mil/.
Project
PROJECT DESCRIPTION AND PURPOSE: The applicant proposes to construct
an expansion of their current facility. The expansion would take place on farm
land immediately to the west of the current Digi Key facility. The project would
involve the construction of an approximately 1,000,000 square foot warehouse
and distribution center. Two entrance roads from County State Aid Highway 16
would also be constructed for vehicle entrance and exit from the new facility. An
entrance would also be constructed on the north end of the proposed facility from
Barzen Avenue. Four storm water ponds will also be constructed on site. The
proposed project is shown on the attached drawings labeled MVP-2017-03282LSP Page 1 of 4 through Page 4 of 4.
This project would require the removal of 2.0 acres of mature trees which could
be utilized by Northern Long Eared Bats during portions of the year. This project
is being coordinated with the U.S. Fish and Wildlife Service for potential impacts
to the Northern Long Eared Bat.
1
NAME, AREA AND TYPES OF WATERS (INCLUDING WETLANDS) SUBJECT
TO LOSS: The applicant conducted a delineation of aquatic resources in the
project location. A total of 15 wetlands were identified and are shown on the
attached drawings.
The Corps of Engineers provided a combined approved jurisdictional
determination and preliminary jurisdictional determination to the applicant which
identified four wetlands which are subject to Corps of Engineers jurisdiction.
These wetlands are identified on the attached drawings as Wetland 2, Wetland 3,
Wetland Ditch 10 and Wetland Ditch 11. This project would impact
approximately 0.94 acres of jurisdictional wetlands.
ALTERNATIVES CONSIDERED:
The applicant conducted an analysis for their projected needs and determined
that an additional 1,000,000 square foot warehouse and associated infrastructure
was required to meet business needs.
An alternatives analysis was conducted by the applicant and was submitted with
the application. A description of the alternatives studied are described below.
Option 1: The applicant studied a no-build alternative. This alternative would
avoid all wetland impacts, but would not meet the needs of the applicant for
additional warehouse space to expand their business.
Option 2: Total avoidance of wetland impacts on the target property could be
achieved by rearranging the site layout. The proposed warehouse would need to
be split into three separate buildings connected by overhead walkways and
conveyor systems. The overall warehouse would be reduced by approximately
230,000 sq. ft. to avoid all wetland impacts. The parking lots and loading dock
areas would need to be separated to avoid wetland impacts. The proposed
stormwater ponds would need to be reduced in size or not constructed to avoid
all wetland impacts. Single arch culverts would be installed along the roadways
at all wetland ditch crossings.
Option 3: Total avoidance of wetland impacts could potentially be achieved by
constructing the proposed project at Offsite Alternative 4 which is described in
the application. This property is located adjacent southwest of the project area.
Avoiding all wetland impacts would require separating the proposed warehouse
into separate buildings. Utilities are located within ½ mile of this site and could
be extended to the project area. The applicant does not currently own this
property and the property is not currently for sale. This property is not currently
located within the city limits and is not zoned for the proposed project.
Offsite Locations: Offsite alternative sites were explored within the vicinity of
the project area. According to the applicant, many sites found near the project
area were not large enough to complete the proposed project. Five offsite
locations were selected and analyzed for their ability to meet project
requirements. Each of the offsite alternatives are described in detail in an
appendix to the application.
Onsite Alternatives: One additional alternative site layout was completed for
the target property. This alternative would reduce wetland impacts by 0.70 acres
compared to the Applicant's Preferred Alternative. The west parking lot and
loading dock were separated to reduce wetland impacts. Single arch culverts
2
would be installed at roadway crossings impacting wetlands. The proposed
stormwater pond expansion on the south side of the project area was removed.
The loading dock area would need to be accessed from Barzen Avenue and
County Highway 16, which would create traffic issues.
COMPENSATORY MITIGATION: The applicant has proposed to purchase
credits from an approved wetland bank to offset unavoidable wetland losses
associated with this project.
Drawings
See attached.
3
MVP-2017-03282-LSP Page 1 of 4
PROJECT
LOCATION
IMAGE: UNITED STATES DEPARTMENT OF THE INTERIOR - GEOLOGICAL SURVEY
© 2018 WIDSETH SMITH NOLTING
ROSEAU
MARSHALL
KOOCHICHING
PENNINGTON
RED LAKE
ER
CLEARWAT
N
ME
NO
ST. LOUIS
MILLE LACS
KA
NAB
EC
G
WAD
WIN
PINE
WRIGHT
LE
MCLEOD CARVER
RENVILLE
SIBLEY
REDWOOD
NICOLLET
BROWN
LE
DAKOTA
SCOTT
R
GOODHUE
EU
RICE
SU
WABASHA
CA
ELE
SE
ROCK NOBLES JACKSON
WA
WAT
ON
EARTH
ON BLUE
WO
WAN
OD
STE
CO
TT
U.S.G.S. QUADRANGLE MAPS:
HENNEPIN
AR
IP
QU
MEEKER
ANOKA
RA
MSE
Y
WASHINGTO
N
TRAV
IYO
ISANTI
O
C
ND
CHIPPEWA KA
SHER
BU
RNE
HI
LA
STON LINCOLN
E
CARLTON
ISAG
STEARNS
SWIFT
YELLOW MEDIC
INE
PIPE
AITKIN
CR
MORRISON
BENTON
STEVENS POPE
STO
MU
( IN FEET )
RD
A
EN
ERSE
TODD
RRAY
4000
OW
WILKIN
OTTER TAIL
LYON
2000
CASS
GRANT DOUGLAS
NE
0
HU
BB
A
BECKER
CH
BIG
LAKE
ITASCA
H
MA
CLAY
COOK
BELTRAMI
POLK
NORMAN
NORTH
KITTSON
LAKE OF THE WOODS
AREA LOCATION
DODGE OLMSTED WINONA
MARTIN FARIBAULT FREEBORN MOWER
FILLMORE HOUSTON
THIEF RIVER FALLS, THIEF RIVER FALLS NW
PUBLISHED: 1961, 1961
PHOTOREVISED: 1976, 1976
DATE:
DIGI-KEY JOINT APPLICATION
DIGI-KEY CORPORATION
FEBRUARY 2018
JOB No.
FIGURE
THIEF RIVER FALLS, MN
SITE LOCATION MAP
0680C0945.004
01
MVP-2017-03282-LSP Page 2 of 4
WETLAND DITCH 3
AREA = 3,040FT²
WETLAND DITCH 4
AREA = 25,156FT²
EXISTING 24" RCP CULVERT
WETLAND DITCH 10
AREA = 24,340FT²
WETLAND DITCH 7
AREA = 20,181FT²
COUNTY HIGHWAY No. 16
WETLAND DITCH 2
AREA = 2,084FT²
COUNTY DITCH No. 70
WETLAND DITCH 9
AREA = 18,043FT²
SP-1A
WETLAND DITCH 6
AREA = 9,806FT²
WETLAND 2
AREA = 5,165FT²
SP-5A
SP-1B
SP-5B
WETLAND 1
AREA = 4,041FT²
WETLAND 3
AREA = 29,662FT²
SP-4A
WETLAND DITCH 1
AREA = 10,897FT²
SP-4B
BARZEN AVENUE
WETLAND DITCH 8
AREA = 16,640FT²
ARCTIC CAT
SP-2B
DIGI-KEY
PARKING LOT
SP-2A
SP-3B
SP-3A
EXISTING STORMWATER POND
CONSTRUCTED IN 2017
WETLAND DITCH 11
AREA = 4,705FT²
DIGI-KEY
ST
WETLAND DITCH 5
AREA = 9,139FT²
LEGEND
ST
DENOTES PROJECT AREA
WETLAND DITCH 12
AREA = 3,455FT²
SP
DENOTES DELINEATED
INCIDENTAL WETLANDS
DENOTES DELINEATED WETLAND
DITCH
DENOTES SOIL TEST PIT
LOCATION
160TH STREET
NORTH
© 2017 WIDSETH SMITH NOLTING
IMAGE: ESRI, INC.
0
250
( SCALE IN FEET )
DIGI-KEY JOINT APPLICATION
DIGI-KEY CORPORATION
THIEF RIVER FALLS, MN
EXISTING CONDITIONS MAP
DATE:
FEBRUARY 2018
JOB No.
0680C0945.004
FIGURE
02
MVP-2017-03282-LSP Page 3 of 4
PROPOSED
STORMWATER POND
PROPOSED
PARKING AREA
PROPOSED WAREHOUSE
PROPOSED
PARKING AREA
PROPOSED LOADING
DOCK ACCESS ROAD
BARZEN AVENUE
COUNTY HIGHWAY No. 16
PROPOSED
CITY ROAD
PROPOSED
STORMWATER PONDS
PROPOSED
ACCELERATION LANE
PROPOSED
BYPASS LANE
ARCTIC CAT
PROPOSED
SIDEWALK(S)
PROPOSED
OVERHEAD CONVEYOR
PROPOSED
LOADING DOCK
PROPOSED STORMWATER
POND EXTENSION
DIGI-KEY
PROPOSED
TURN LANE
EXISTING STORMWATER POND
CONSTRUCTED IN 2017
LEGEND
DENOTES PROJECT AREA
DENOTES CONSTRUCTION LIMITS
DENOTES DELINEATED
INCIDENTAL WETLANDS
DENOTES DELINEATED WETLAND
DITCH
160TH STREET
NORTH
© 2017 WIDSETH SMITH NOLTING
IMAGE: ESRI, INC.
0
250
( SCALE IN FEET )
DIGI-KEY JOINT APPLICATION
DIGI-KEY CORPORATION
THIEF RIVER FALLS, MN
PROPOSED CONDITIONS MAP
DATE:
FEBRUARY 2018
JOB No.
0680C0945.004
FIGURE
03
COUNTY HIGHWAY No. 16
MVP-2017-03282-LSP Page 4 of 4
AREA A - FIGURE 04A
AREA B - FIGURE 04B
BARZEN AVENUE
ARTIC CAT
AREA C - FIGURE 04C
AREA D - FIGURE 04D
DIGI-KEY
PROPOSED STORMWATER
POND EXTENSION
LEGEND
DENOTES PROJECT AREA
EXISTING STORMWATER POND
CONSTRUCTED IN 2017
DENOTES CONSTRUCTION LIMITS
DENOTES DELINEATED
INCIDENTAL WETLANDS
DENOTES DELINEATED WETLAND
DITCH
DENOTES INCIDENTAL WETLAND
IMPACTS - FILL
DENOTES WETLAND DITCH
IMPACTS - FILL
DENOTES WETLAND DITCH
IMPACTS - CUT
AREA E - FIGURE 04E
DENOTES STORM SEWER
160TH STREET
NORTH
© 2017 WIDSETH SMITH NOLTING
IMAGE: ESRI, INC.
0
250
( SCALE IN FEET )
DIGI-KEY JOINT APPLICATION
DIGI-KEY CORPORATION
THIEF RIVER FALLS, MN
DATE:
FEBRUARY 2018
JOB No.
FIGURE
WETLAND IMPACT MAP - OVERVIEW0680C0945.004 04