Mountains Restoration Trust In-Lieu Fee Program Amendment 1
The review of the MRT Development, Interim Management and Long-Term Management Plans (ILF Project Plans) in Cold Creek and Amendment No. 1 to the MRT ILF Instrument related to the ILF Project in the Cold Creek, Calabasas, Los Angeles County California. The review of the MRT Development, Interim Management and Long-Term Management Plans (ILF Project Plans) in Cold Creek and Amendment No. 1 to the MRT ILF Instrument related to the ILF Project in the Cold Creek, Calabasas, Los Angeles County California.
SPECIAL PUBLIC NOTICE
_________________________________________________________________________________________
U.S. ARMY CORPS OF ENGINEERS
BUILDING STRONG®
LOS ANGELES DISTRICT
Mountains Restoration Trust
In-Lieu Fee Program, Amendment 1
Calabasas, Los Angeles County, CA
Public Notice/Application No.: SPL-2004-00121-JWM
Comment Period: April 13, 2018 through May 18, 2018 [30-day comment period]
Project Manager: Stephen Estes; 213-452-3660; Stephen.M.Estes@usace.army.mil
Applicant
Debra Sharpton
MRT
23075 Mulholland HWY
Calabasas, California 91302
Contact
Debra Sharpton
MRT
23075 Mulholland HWY
Calabasas, California 91302
Location
The location of the proposed In-Lieu Fee Project (ILF Project) is located in Cold Creek which is a
tributary within the Santa Monica watershed in northwestern Los Angeles County, California (see
attached vicinity map). The property is generally located near Cold Canyon Road in the Monte Nido
neighborhood of unincorporated Calabasas.
Activity
The review of the MRT Development, Interim Management and Long-Term Management Plans
(ILF Project Plans) in Cold Creek and Amendment No. 1 to the MRT ILF Instrument related to the ILF
Project in the Cold Creek, Calabasas, Los Angeles County California. For more information see page
3 of this notice.
Interested parties are hereby notified that the ILF Project Plans have been received to establish an
ILF Project to comply with the framework of the established MRT ILF Program. Interested parties are
invited to provide their views on the proposed ILF Project Plans, which will become a part of the
record and will be considered in the decision to authorize or not authorize the ILF Project. Comments
should be mailed to:
Department of the Army
U.S. Army Corps of Engineers Regulatory Division
Los Angeles District
ATTN: Stephen Estes (SPL-2004-121-PKK)
915 Wilshire Boulevard
Los Angeles, California 90017
Alternatively, comments can be sent electronically to: Stephen.M.Estes@usace.army.mil
Evaluation Factors
The Corps of Engineers is soliciting comments from the public; Federal, state, and local agencies
and officials; Indian tribes; and other interested parties in order to consider and evaluate the impacts
of this First Amendment. The District Engineer (DE) will review the comments received in response to
this notice and make a written initial evaluation as to the potential of the proposed First Amendment to
help provide compensatory mitigation opportunities within the Santa Monica Watershed. To make this
decision, comments are used to assess impacts on endangered species, historic properties, water
quality, general environmental effects, and the other public interest factors listed above. In addition,
all comments will be distributed to the members of the Interagency Review Team (IRT) and the MRT
within 15 days of the close of the comment period. The DE and the IRT members will also have the
opportunity to comment to the MRT. After considering comments from the DE, the IRT, and the public,
if the MRT chooses to proceed with the First Amendment, the MRT will submit the Amendment to the
DE.
Background
On April 10, 2008, the Corps of Engineers and the Environmental Protection Agency published the
Final Rule on Compensatory Mitigation for Losses of Aquatic Resources ("Mitigation Rule"), which
went into effect June 9, 2008. The rule replaced most previous guidance concerning compensatory
mitigation, including the previous ILF guidance of 2000. The new rule includes requirements that
prospective ILF program providers meet substantially the same standards as mitigation banks and
undergo the same IRT review and approval process as mitigation banks.
The MRT, a non-profit entity, wishes to implement an ILF Project consistent with the existing MRT
ILF Program Instrument, previously reviewed under the Mitigation Rule. The Mitigation Rule allows
ILF Projects associated with approved ILF programs and Instruments to provide compensatory
mitigation for DA permits. Consistent with the requirements of the rule at 33 CFR § 332.8(d), MRT
has submitted the ILF Project Plans to the Corps for the purpose of implementing and managing an
ILF Project. The Corps seeks comments from interested parties on the ILF Project Plans.
2
This public notice provides a summary of the ILF Project Plans submitted by MRT. The full ILF
Project Plans may be obtained from the Corps by contacting Stephen Estes at
Stephen.M.Estes@usace.army.mil, or by viewing the ILF Project Plans at the following website:
https://ribits.usace.army.mil/ribits_apex/f?p=107:378:3080285866991::NO::P378_PROGRAM_ID:1261
And following these steps:
1. Expand Santa Monica Bay Watershed Folder
2. Expand Cold Creek Folder
3. Expand Steelhead Barrier Folder
4. Expand Steelhead Barrier Development Plan
5. Click on the file to download the Plan
Objectives of the Project and Location
The ILF Project Plans were developed to comply with MRT's In-Lieu Fee Program to be used for
the enhancement of approximately 2.20 acres of riparian areas, rehabilitation and enhancement of
approximately 0.97 acre within the perennial Cold Creek, and enhancement of 0.06 acre of wetland
within Cold Creek, located on MRT property (the "ILF Project") in Cold Creek subwatershed of the
Santa Monica Watershed.
The purpose of the mitigation is to restore the functions and values of the Cold Creek watershed
lost due to impacts from human activities by restoring and enhancing degraded areas where the ILF
Project is to be located. The ILF Project Plans consider both the ecological and geomorphologic
functions of the mitigation site in order to confirm that the functions of the restoration will exceed those
of the existing habitat.
The objective of the ILF Project is to restore the ILF Project area to provide for stable communities
and ecosystems which will require little or no support once established. This will be fulfilled by using
plant materials that have originated from the local Eco region and that will provide improved food,
cover and reproductive opportunities for wildlife.
The service area will continue to be the same as in the approved MRT ILF Program, which is the
Santa Monica Watershed. The ILF Project site currently consists of dense stands of willow, California
wildrose, and rough sedge. Invasive species found on site consist of smilo grass, water bentgrass,
fennel, umbrella sedge, and clustered dock. The ILF project site contains a concrete barrier which
spans the Cold Creek creating an artificial impoundment upstream of the barrier. MRT has completed
and submitted to the ACOE a proposed preliminary concept plan referred to as the Development
Plan. The Project was selected because the property is owned by MRT and would result in a high
amount of improvement in the multiple functions described in the Prioritization and Compensation
Planning Framework found in Exhibit B of the executed MRT ILF Instrument. MRT is requesting
approximately 3.23 of ILF Program credits which equates to approximately 3.23 acres of land that will
be rehabilitated, enhanced or used for a buffer area. The ILF Project site will be protected in
perpetuity by a restrictive covenant and be managed with endowment funds.
Qualifications of the Sponsor
MRT has successfully managed many restoration projects including the removal of channels,
culvert and bridge supports from streams, and the re-contouring of stream beds. Additional
information about the qualifications of MRT were documented in the ILF Program Prospectus and
Instrument.
3
For additional information please call Stephen Estes of my staff at 213-452-3660 or via e-mail at
Stephen.M.Estes@usace.army.mil. This public notice is issued by the Chief, Regulatory Division.
Regulatory Program Goals:
To provide strong protection of the nation's aquatic environment, including wetlands.
To ensure the Corps provides the regulated public with fair and reasonable decisions.
To enhance the efficiency of the Corps' administration of its regulatory program.
__________________________________________________________
DEPARTMENT OF THE ARMY
LOS ANGELES DISTRICT, U.S. ARMY CORPS OF ENGINEERS
Los Angeles District
915 Wilshire Boulevard
Los Angeles, California 90017
WWW.SPL.USACE.ARMY.MIL/MISSIONS/REGULATORY
4
Figure 1:
Vicinity Map
Project Boundary
Project Location
µ
0
0.05 0.1
0.2 Miles
1:10,000
Coordinate System: NAD 1983
UTM Zone 11N
Basemap: USGS 7.5-Minute Malibu
Beach Quadrangle (2015)
This map contains data from various
federal, state, and local sources. MRT is
not responsible for the accuracy of data
presented herein. Use for general
planning purposes only.
Created by: Kevin Gaston
Date: 11/17/2017