You can copy from here when filling out the rest of the page.
Proposal for the redevelopment of a lot in the southwest corner of the Motorola Campus, at the Southwest corner of the Motorola Campus in Schaumburg, located south of Algonquin Road and west of Meacham Road in Cook County, Illinois.
PUBLIC NOTICE
APPLICATION FOR PERMIT
U.S. ArmyCorps of Engineers
Chicago District
Public Notice/Application Number: LRC-2017-00407
Comment Period BEGINS: May 11, 2018
Comment Period Expires: Jun 11, 2018
U.S. Army Corps of Engineers
Applicant
Jim Wells
TUF Partners, LLC
401 West Superior Street
Chicago, Illinois 60654
Proposed Action
Proposal for the redevelopment of a lot in the southwest corner of the Motorola Campus (See attached drawings). A detailed description of this proposal is provided on page 2 of this notice.
Location of Proposed Action
Southwest corner of the Motorola Campus in Schaumburg located south of Algonquin Road and west of Meacham Road in Cook County, Illinois (Latitude 42.066131, Longitude -88.049872).
Interested parties are hereby notified that an application has been received for a Department of the Army permit for the activity described herein and as shown on the attached drawings. You are invited to provide your comments by June 11, 2018 on the proposed work, which will become part of the record and will be considered in the decision. A permit will be issued or denied under Section 404 Action of the Clean Water Act of 1972(33 U.S.C. 1344).
Written comments shall be mailed to:
U.S. Army Corps of Engineers
Chicago District, Regulatory Branch
Attn: LRC-2017-00407, Mr. Soren Hall
231 South LaSalle Street, Suite 1500
Chicago, Illinois 60604-1437
It should be noted that ALL comments received by this office (via hard copy or electronic) will only be accepted with the full name and address, and email address, if available of the individual commenting, and must be received by the close of the public notice period. Electronic comments may be sent to the project manager at Soren.G.Hall@usace.army.mil.
Project Description
The purpose of the proposed project, South Pond Modifications at Veridian, is to redevelop the stormwater management facilities of an existing corporate campus and restructure the buildable space as part of a redevelopment of the property. The south pond is proposed to be reconfigured and enlarged to meet the current stormwater requirements of the Metropolitan Water Reclamation District and the Village of Schaumburg.
The existing 30-acre site contains two buildings, roadways, parking lots, sidewalks, mowed turf grass, forested areas, a 6.89 acre open water pond, and a 0.18 acre wetland (Wetland 3). Both the pond and wetland were determined to be under the jurisdiction of this office. Wetland 3 has native mean C value of 2.00 and native FQI of 2.83. This wetland will be completely filled with no remaining portion. The open water pond is currently vegetated with turf grass on the side slopes, so no mean C or FQI were calculated.
The proposed project includes the demolition of the existing two buildings, parking, and other associated features on site and reconfiguration of the existing pond. A new building pad would be constructed in the northeast portion of the site and include the construction of a 7-story office building, parking garage, sidewalks, and a reconfigured access drive. According to the application materials, the current site configuration is not adequate to support the desired development type, necessitating the reconfiguration of the existing detention pond.
The project would include filling or otherwise modifying 4.52 acres of the existing pond. And 0.18 acres of wetland. Mitigation for filling a portion of the pond is proposed at a 1:1 ratio and would include the construction of 4.53 acres of new or reconfigured pond. Mitigation for the wetland impact is proposed at a ratio of 1.5:1 and would be fulfilled by purchasing 0.27 acres of wetland mitigation credits for a Corps approved wetland mitigation bank.
The western portion of the pond would be a wetland vegetated pond with three deeper pools. The central portion of the pond would be reconfigured with native vegetation along the edge and open water in the middle. The easternmost portion of the pond would remain unchanged with the exception of a native vegetated fringe along the north side. The proposed planting plan is included as an attachment to this notice.
Proposed post-construction stormwater best management practices (BMPs) include the construction of two rain gardens to be located south of the proposed building. These rain gardens would capture rainwater from the turf grass area and paths in front of the proposed building. The location of the rain gardens is depicted on the attached site development plan exhibit.
Avoidance & Minimization
The applicant has stated the following concerning avoidance and minimization of impacts to Waters of the United States: The configuration of the existing two buildings, parking lot, sidewalks, and stormwater management facility are not conducive for the economic redevelopment that the developer and the Village of Schaumburg have planned. The existing site lacks accessibility and connectivity for commercial development. In order to create a more function space for commercial use with vehicular access, the site needs to be reconfigured.
Mitigation
The applicant has stated the following concerning compensatory mitigation for unavoidable impacts to Waters of the United States: Mitigation is proposed at 1:1 on-site for the reconfiguration of the existing pond. Mitigation credits are proposed at 1.5:1 for the impacts to Wetland 3.
The Corps has not verified the adequacy of this mitigation proposal at this time and will make the final determination on whether the proposed mitigation is appropriate and practicable in accordance with 33 CFR Part 332.
Regulatory Authority
This proposed action will be reviewed according to the provisions of Section 404 of the Clean Water Act of 1972.
Jurisdiction
This application will be reviewed according to the provisions of Section 404 of the Clean Water Act of 1972 due to placement of 4.70 acres of fill in waters of the U.S. Both the pond and Wetland 3 were determined to be under Corps jurisdictional based on an approved jurisdictional determination dated June 8, 2017.
Evaluation Factors
The decision whether to issue a permit will be based on an evaluation of probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments.
All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people. In addition, if the proposed activity involves the discharge of dredged or fill material into waters of the United States, the evaluation of the impact on the public interest will include application of Section 404(b)(1) guidelines (40 CFR 230) promulgated by the U.S. Environmental Protection Agency.
The Corps of Engineers is also soliciting comments from the public, Federal, state and local agencies, Indian tribes, and other interested parties in order to consider and evaluate the potential impacts of the proposed activity. Once this office completes a review of the comments received, it will be determined whether to issue, modify, condition, or deny a permit for this proposal.
To prepare this decision, comments are taken into consideration to assess impacts on the public interest factors listed above, as well as endangered species, historic properties, water quality, and general environmental effects. Comments will be used in the preparation of an Environmental Assessment and/or Environmental Impact Statement pursuant to the National Environmental Policy Act. A determination concerning the need for a public hearing will also be based on the comments received.
Preliminary Evaluation of Selected Factors
Water Quality:
The applicant has applied to the Illinois Environmental Protection Agency (IEPA) for water quality certification, or waiver thereof, for the proposed activity in accordance with Section 401 of the Clean Water Act. Certification or waiver indicates that the IEPA believes the activity will not violate applicable water quality standards. The review by the IEPA is conducted in accordance with the Illinois water quality standards under 35 Illinois Administrative Code Subtitle C by providing an antidegradation assessment, which includes an evaluation of alternatives to any proposed increase in pollutant loading that may result from this activity.
The "Fact Sheet" containing the antidegradation assessment for this proposed project may be found on the IEPA's web site, at www.epa.state.il.us/public-notices/. In the event that the IEPA is unable to publish the "Fact Sheet" corresponding to the timeframe of this Joint Public Notice, a separate public notice and "Fact Sheet" will be published by the IEPA at the web site identified above. You may also obtain a copy of the "Fact Sheet" by contacting the IEPA at the address or telephone number shown below.
Written comments concerning possible impacts to water quality should be addressed to the following agency, along with a copy of the comments provided to the Corps of Engineers:
Illinois Environmental Protection Agency
Bureau of Water
Watershed Management Section
1021 N. Grand Avenue East
P.O. Box 19276
Springfield, Illinois 62794-9276
If you have any questions please contact the IEPA at (217) 782-3362.
Department of Natural Resources:
The applicant may have to submit an application to the Illinois Department of Natural Resources, Office of Water Resources (IDNR-OWR) for a permit pursuant to the State of Illinois Rivers, Lakes and Streams Act (615 ILCS 5). Comments concerning the IDNR-OWR permit should be addressed to the following agency, along with a copy of the comments provided to the Corps of Engineers:
Illinois Department of Natural Resources
Office of Water Resources
2050 West Stearns Road
Bartlett, Illinois 60103
If you have any questions please contact the IDNR at (847) 608-3116.
Endangered and Threatened Species:
The Corps of Engineers has determined that the proposed activity would not affect any federally-listed endangered or threatened species or critical habitat for any endangered or threatened species, pursuant to the Endangered Species Act of 1973, as amended (16 U.S.C. 1531 et seq.). Therefore, consultation with the U.S. Fish and Wildlife Service pursuant to Section 7 of the Endangered Species Act does not appear to be warranted at this time.
Historic Properties/Cultural Resources:
Preliminary review indicates that the proposed activity is not likely to adversely affect any historic property which is listed, or eligible for listing, on the National Register of Historic Places.
Environmental Impact Statement
A preliminary determination has been made that an environmental impact statement is not required for the proposed work.
Public Hearing
Any person may request in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. Requests for public hearing shall state with particularity the reasons for holding a public hearing. A request for a hearing may be denied if substantive reasons for holding a hearing are not provided or if there is otherwise no valid interest to be served.
It should be noted that materials submitted as part of the permit application become part of the public record and are thus available to the general public under the procedures of the Freedom of Information Act (FOIA). Individuals may submit a written request to obtain materials under FOIA or make an appointment to view the project file at the Chicago District Corps of Engineers Office of Counsel.
Interested parties wishing to comment on the proposed activity must do so in writing no later than June 11, 2018. It is presumed that all parties receiving this notice will wish to respond to this public notice; therefore, a lack of response will be interpreted as meaning that there is no objection to the project as described.
This public notice is not a paid advertisement and is for public information only. Issuance of this notice does not imply Corps of Engineers endorsement of the project as described.
If you have any questions, please contact Mr. Soren Hall of my staff by telephone at (312) 846-5532, or email at Soren.G.Hall@usace.army.mil. It should be noted that ALL comments received by this office (via hard copy or electronic) will only be accepted with the full name and address of the individual commenting. You can also visit our website at http://www.lrc.usace.army.mil/Missions/Regulatory.aspx for more information on our program.
FOR THE DISTRICT COMMANDER:
Original Signed
Kathleen G. Chernich
Chief, East Section
Regulatory Branch