Proposed discharge of approximately 8.51 acres of fill into jurisdictional waters of the United States for the widening and reconstruction of I-294

Basic information

Fill out these two fields at minimum.

— or —

How Big?

Where?

Links to source documents

Raw text

You can copy from here when filling out the rest of the page.

Proposed discharge of approximately 8.51 acres of fill into jurisdictional waters of the United States for the widening and reconstruction of I-294, for the Central Tri-State Tollway from 95th Street to Balmoral Avenue, Cook and DuPage Counties, Illinois.

PUBLIC NOTICE APPLICATION FOR PERMIT

U.S. ArmyCorps of Engineers Chicago District

Public Notice/Application Number: LRC-2016-00158

Comment Period BEGINS: 4 JUN 2018 Comment Period Expires: 3 JUL 2018

JOINT PUBLIC NOTICE U.S. Army Corps of Engineers Illinois Environmental Protection Agency

Applicant Illinois State Toll Highway Authority 2700 Ogden Avenue Downers Grove, Illinois 60515

Proposed Action Proposed discharge of approximately 8.51 acres of fill into jurisdictional waters of the United States for the widening and reconstruction of I-294, for the Central Tri-State Tollway (CTS) from milepost 17.5. (95th Street) to milepost 40.0 (Balmoral Avenue). A detailed description of this proposal is provided on page 2 of this notice.

Location of Proposed Action The project area includes the I-294 corridor from milepost 17.5 (95th Street) to milepost 40.0 (Balmoral Avenue), in Cook and DuPage Counties, Illinois (Figure 1). One omission area occurs within the project limits, between milepost 33.6 (North Avenue) to milepost 36.3 (just south of Wolf Road) (Figure 1). This omission area was previously permitted by USACE LRC under permit LRC-2007-802 in order to facilitate the connection from the Elgin O’Hare Western Access (EOWA) project to I-294.

Interested parties are hereby notified that an application has been received for a Department of the Army permit for the activity described herein and as shown on the attached drawings. You are invited to provide your comments by 3 JUL 2018 on the proposed work, which will become part of the record and will be considered in the decision. A permit will be issued or denied under Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403) and Section 404 of the Clean Water Act of 1972 (33 U.S.C. 1344).

Written comments shall be mailed to: U.S. Army Corps of Engineers Chicago District, Regulatory Branch Attn: LRC-2016-00158, Mr. Ron Abrant 231 South LaSalle Street, Suite 1500 Chicago, Illinois 60604-1437

An electronic version of this notice is available on our web page at http://www.lrc.usace.army.mil/Missions/Regulatory/PublicNotices.aspx.

It should be noted that ALL comments received by this office (via hard copy or electronic) will only be accepted with the full name and address, and email address, if available of the individual commenting, and must be received by the close of the public notice period. Electronic comments may be sent to the project manager at ron.j.abrant@usace.army.mil.

Physical copies of the application materials including wetland impact and erosion control plans are available for viewing at the Illinois Tollway Headquarters in Downers Grove and the Corps of Engineers Chicago District Office in Chicago as referenced LRC-2016-00158.

Project Description The Illinois State Toll Highway Authority is proposing the widening and reconstruction of the Central Tri-State (CTS) Tollway (I-294) from milepost 17.5 (95th Street) to milepost 40.0 (Balmoral Avenue). The CTS project area is located in Cook and DuPage Counties, Illinois and is primarily within the limits of the existing I-294 Tollway right-of-way (ROW) (Figure 1). The Central Tri-State project is a component of the overall 15-year, $12 billion capital program, Move Illinois: The Illinois Tollway Driving the Future, which is aimed at updating and enhancing the existing Illinois Tollway system.

The purpose and need of the project is to bring the CTS to a state of good repair and to replace an outdated, frequently congested roadway with a more modern, 21st Century corridor that better serves the region’s transportation network and allows customers to travel more safely, reliably and efficiently. Reducing congestion would result in a safer roadway with less fuel consumption and benefits the regional economy. Currently, the I-294 CTS Tollway consists of four mainline lanes in each direction, with auxiliary lanes at system interchanges and toll plazas. The mainline is separated by a concrete median barrier with full inside and outside shoulders. The overall scope of work includes improving capacity throughout the corridor by constructing a flex lane, a widened inside shoulder which could accommodate vehicles during peak travel times. Additionally, a fifth lane is proposed in each direction along the most congested sections of the corridor. Additional improvements include reconfigurations and improvements to the major system interchanges, new interchanges for improved local access, replacement and rehabilitation of existing bridges and improvements to toll plazas, drainage walls, retaining walls, noise abatement walls, roadway lighting, and Intelligent Transportation Systems (ITS). The largest bridge reconstructions in the CTS corridor would occur at the Mile Long Bridge/I-294 over the La Grange Road Bridge (MP 20.7 to MP 22.3) and the BNSF over I-294 Bridge (MP 26.6). The Mile Long Bridge and I-294 over the La Grange Road Bridge would be widened by one lane in each direction and would include a widened median to accommodate a 12-foot flex lane and shoulders. Replacement of these bridges would require separate northbound and southbound structures. The BNSF Bridge over I-294 would include a complete replacement of the existing structure with wider spans, raised railroad profile, and deeper superstructure to accommodate for horizontal deficiencies. CTS construction outside of all jurisdictional wetlands and waterways is anticipated to begin in in 2018 with bridge rehabilitation and utility relocation. The BNSF Bridge and Mile Long Bridge are proposed to start construction in August 2019. The BNSF Bridge would be completed in 2021, while the Mile Long Bridge construction would be completed in 2023. Construction of the mainline is anticipated to begin in 2022 and be completed in 2026. A total of 68 areas qualifying as wetlands and Waters of the United States (WOUS) under USACE jurisdiction were identified within the project area. Impacts to wetlands and WOUS were minimized throughout the design of the project. Summarily, a total of 8.51 acres of wetlands/WOUS would be impacted by the proposed project, including 4.41 acres of impact to USACE jurisdictional wetlands and 4.10 acres of impacts to jurisdictional waterways. Table 1 provides a list of all jurisdictional areas being permanently and temporarily impacted. The wetlands and WOUS that would be impacted by the project are considered low to moderate quality and would require wetland mitigation at a ratio of 1.5:1. Seven wetlands and two waterways identified within the project area are classified as High Quality Aquatic Resources (HQAR), with the wetlands being designated as HQAR due to their high Native C-Value and the waterways due to them receiving a B rating for Diversity as part of the Biological Stream Characterization study. Any impacts to HQAR wetlands and waterways would require wetland mitigation at a ratio of 3:1. A total of 7.66 acres of wetland mitigation would be required for the I-294 CTS project. Waterway impacts would be mitigated using the functional lift approach by restoring Spring Brook No. 1 Creek. In accordance with Section 404(b)(1) of the Clean Water Act, compensatory mitigation is not considered until after all appropriate and practicable steps have been taken to first avoid and then minimize adverse impacts to the aquatic ecosystem. Where possible, design alternatives were considered in order to completely avoid or greatly minimize impacts to USACE jurisdictional wetlands. The corridor wide approach generally limited impacts to within the Tollway’s existing ROW. Wetlands immediately adjacent to the existing ROW limits were taken into consideration and methods of design were applied to maximize the avoidance or minimization of impacts to these areas. Wetlands adjacent to the existing ROW have been avoided by maintaining the limits of construction inside the existing ROW to the maximum extent possible. Vertical retaining walls are also proposed along the project corridor to eliminate the need for earthen embankment slopes that would otherwise extend further from the edge of the roadway pavement into wetlands and other waters of the US. Retaining walls enable the Tollway to avoid and/or minimize impacts to wetland and water resources. The CTS is an existing roadway in a highly urbanized and restricted corridor. Limited options for modifying roadway alignments to avoid wetland and waterway impacts exist without impacting other resources (i.e. residences and businesses). Only slight modifications to the existing alignment are possible and are proposed. Alternatives with the greatest environmental impact were eliminated from further study. Drainage facilities, including stormwater detention facilities, compensatory floodplain storage, and other best management practices (BMPs) would be constructed to compensate for the increased impervious surface and loss of floodplain and to treat roadway stormwater runoff to improve water quality. Soil erosion and sediment control (SESC) measures will be designed to protect water resources from construction site runoff. Proposed additional chloride loadings will be offset through Tollway practices and partnerships with local municipalities to reduce their chloride use. The proposed BMPs include the use of naturalized stormwater management facilities and various types of vegetated bioswales. In locations where space is restricted, oil/water separators, structural grit separators will be used to improve water quality. In addition to the BMPs listed above, SESC measures for water quality protection during construction will be implemented through the use of silt fence, ditch checks, erosion control blanket and other appropriate measures. Mitigation If a permit is issued for the proposed project, the Corps will determine what is appropriate and practicable compensatory mitigation in accordance with 33 CFR Part 332. The amount of compensatory mitigation to be determined shall be commensurate with the anticipated impacts of the project. The applicant is proposing to provide wetland and WOUS mitigation at Spring Brook No. 1 Creek and Wetland Restoration Phase 2, a 116 acre site acquired by the Forest Preserve District of DuPage County. The Spring Brook No. 1 Creek and Wetland Restoration Phase 2 site is located south of Mack Road, east of Williams Road and west of Winfield Road in DuPage County (Figure 2). The Spring Brook No. 1 Creek mitigation site is located within Blackwell Forest Preserve in Warrenville, Illinois which is owned and maintained by the Forest Preserve District of DuPage County. The mitigation site would restore Spring Brook No. 1 Creek to a more naturalized state by removing a control structure and modifying the stream bed and banks to create stream meanders and wetlands on adjacent shorelines. Further, the site is anticipated to mitigate all wetland and WOUS impacts. The site is located within the Des Plaines River watershed. The Wetland Mitigation Plan is shown on Figure 3. Regulatory Authority This proposed action will be reviewed according to the provisions of Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act of 1972. Jurisdiction This application will be reviewed according to the provisions of Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act of 1972 due to placement of 8.51 acres of fill in wetlands/Waters of the U.S. Evaluation Factors The decision whether to issue a permit will be based on an evaluation of probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people. In addition, if the proposed activity involves the discharge of dredged or fill material into waters of the United States, the evaluation of the impact on the public interest will include application of Section 404(b)(1) guidelines (40 CFR 230) promulgated by the U.S. Environmental Protection Agency. The Corps of Engineers is also soliciting comments from the public, Federal, state and local agencies, Indian tribes, and other interested parties in order to consider and evaluate the potential impacts of the proposed activity. Once this office completes a review of the comments received, it will be determined whether to issue, modify, condition or deny a permit for this proposal. To prepare this decision, comments are taken into consideration to assess impacts on the public interest factors listed above, as well as endangered species, historic properties, water quality, and general environmental effects. Comments will be used in the preparation of an Environmental Assessment and/or Environmental Impact Statement pursuant to the National Environmental Policy Act. A determination concerning the need for a public hearing will also be based on the comments received. Preliminary Evaluation of Selected Factors Water Quality: The applicant will apply to the Illinois Environmental Protection Agency (IEPA) for water quality certification, or waiver thereof, for the proposed activity in accordance with Section 401 of the Clean Water Act. Certification or waiver indicates that the IEPA believes the activity will not violate applicable water quality standards. The review by the IEPA is conducted in accordance with the Illinois water quality standards under 35 Illinois Administrative Code Subtitle C by providing an antidegradation assessment, which includes an evaluation of alternatives to any proposed increase in pollutant loading that may result from this activity. The "Fact Sheet" containing the antidegradation assessment for this proposed project may be found on the IEPA's web site, at www.epa.state.il.us/public-notices/. In the event that the IEPA is unable to publish the "Fact Sheet" corresponding to the timeframe of this Joint Public Notice, a separate public notice and "Fact Sheet" will be published by the IEPA at the web site identified above. You may also obtain a copy of the "Fact Sheet" by contacting the IEPA at the address or telephone number shown below. Written comments concerning possible impacts to water quality should be addressed to the following agency, along with a copy of the comments provided to the Corps of Engineers:

Illinois Environmental Protection Agency Bureau of Water Watershed Management Section 1021 N. Grand Avenue East P.O. Box 19276 Springfield, Illinois 62794-9276

If you have any questions please contact the IEPA at (217) 782-3362.

DEPARTMENT OF NATURAL RESOURCES: The applicant will have to submit an application to the Illinois Department of Natural Resources, Office of Water Resources (IDNR-OWR) for a permit pursuant to the State of Illinois Rivers, Lakes and Streams Act (615 ILCS 5). Comments concerning the IDNR-OWR permit should be addressed to the following agency, along with a copy of the comments provided to the Corps of Engineers.

Illinois Department of Natural Resources Office of Water Resources 2050 West Stearns Road Bartlett, Illinois 60103 If you have any questions please contact the IDNR at (847) 608-3116.

Endangered and Threatened Species: A Section 7 Evaluation of federally-listed endangered or threatened species or critical habitat for any endangered or threatened species, pursuant to the Endangered Species Act of 1973, as amended (16 U.S.C. 1531 et seq.) was submitted the U.S. Fish and Wildlife Service. The project will be reviewed by the USFWS. Historic Properties/Cultural Resources: Preliminary review indicates that the proposed activity is not likely to adversely affect any historic property which is listed, or eligible for listing, on the National Register of Historic Places. The project will be reviewed by the Corps of Engineers.

Environmental Impact Statement A preliminary determination has been made that an environmental impact statement is not required for the proposed work.

Public Hearing Any person may request in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. Requests for public hearing shall state with particularity the reasons for holding a public hearing. A request for a hearing may be denied if substantive reasons for holding a hearing are not provided or if there is otherwise no valid interest to be served. It should be noted that materials submitted as part of the permit application become part of the public record and are thus available to the general public under the procedures of the Freedom of Information Act (FOIA). Individuals may submit a written request to obtain materials under FOIA or make an appointment to view the project file at the Chicago District Corps of Engineers Office of Counsel. Interested parties wishing to comment on the proposed activity must do so in writing no later than 3 JUL 2018. It is presumed that all parties receiving this notice will wish to respond to this public notice; therefore, a lack of response will be interpreted as meaning that there is no objection to the project as described. This public notice is not a paid advertisement and is for public information only. Issuance of this notice does not imply Corps of Engineers endorsement of the project as described. If you have any questions, please contact Mr. Ron Abrant of my staff by telephone at 312-846-5536, or email at Ron.J.Abrant@usace.army.mil. It should be noted that ALL comments received by this office (via hard copy or electronic) will only be accepted with the full name and address of the individual commenting. You can also visit our website at http://www.lrc.usace.army.mil/Missions/Regulatory/ for more information on our program. NOTICE TO POSTMASTERS: It is requested that this notice be conspicuously and continuously posted until 3 JUL 2018.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas