You can copy from here when filling out the rest of the page.
Proposal to retain previously authorized temporary fill in Lake Michigan on a permanent basis, in Lake Michigan on the shoreline of the Naval Station Great Lakes harbor north of the inlet of Pettibone Creek, in unincorporated Great Lakes, Lake County, Illinois.
PUBLIC NOTICE
APPLICATION FOR PERMIT
U.S. Army
Corps of Engineers
Chicago District
Public Notice/Application Number: LRC-2006-1319
Comment Period BEGINS: July 9, 2018
Comment Period Expires: August 8, 2018
U.S. Army Corps of Engineers
Illinois Environmental Protection Agency
Applicant
Department of the Navy
Naval Station Great Lakes
2601 E. Paul Jones Street, Building 1
Great Lakes, IL 60088
Proposed Action
Proposal to retain previously authorized temporary fill in Lake Michigan on a permanent basis. (See attached drawings). A detailed description of this proposal is provided on page 2 of this notice.
Location of Proposed Action
In Lake Michigan on the shoreline of the Naval Station Great Lakes harbor north of the inlet of Pettibone Creek, in unincorporated Great Lakes, Lake County, Illinois, (NE Quarter of Section 9, Township 44 N, Range 12 E; 42.307933, -87.829699).
Interested parties are hereby notified that an application has been received for a Department of the Army permit for the activity described herein and as shown on the attached drawings. You are invited to provide your comments by August 8, 2018 on the proposed work, which will become part of the record and will be considered in the decision. A permit will be issued or denied under Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403) and Section 404 Action of the Clean Water Act of 1972(33 U.S.C. 1344).
Comments should be emailed to Michael.J.Murphy@usace.army.mil or written comments can be mailed to:
U.S. Army Corps of Engineers
Chicago District, Regulatory Branch
Attn: LRC-2006-1319, Michael Murphy
231 South LaSalle Street, Suite 1500
Chicago, Illinois 60604-1437
It should be noted that ALL comments received by this office (via hard copy or electronic) will only be accepted with the full name and address, and email address, if available, of the individual commenting, and must be received by the close of the public notice period. Electronic comments may be sent to the project manager at Michael.J.Murphy@usace.army.mil.
Project Description
The applicant was authorized to construct a temporary cofferdam structure and backfill in the Naval Station Great Lakes harbor to facilitate unloading of dredge spoils for upland disposal during harbor dredging operations. The original permit was issued in November of 2009 and modified in May of 2010. This permit will expire in November of 2019. The applicant has requested authorization under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act to keep this structure and associated backfill in place on a permanent basis (see attached drawings). No new fill is requested under this current request, only the permanent retention of the fill placed in 2010.
The cofferdam and fill were constructed in May of 2010 (see original site layout drawing attached) partly in wetland fringe vegetation and partly in waters of Lake Michigan (Naval Station Great Lakes Harbor). The vegetative community prior to construction was (and the adjacent area still is) dominated by a monotypic stand of Common Reed (Phragmities australis). The area filled totals 0.18 acres and has subsequently been vegetated by turf grass over the dredge material (sand) used to fill the cofferdam.
The applicant proposes to keep the cofferdam and fill in place to facilitate future dredge operations in the harbor and to facilitate the use of the area as part of emergency spill response plans within the harbor. While no dredge work is currently scheduled for the harbor, dredging in the future is anticipated and a structure similar in size and position to the current cofferdam will be required to facilitate offloading of dredge spoils. The applicant proposes to minimize overall disturbance by maintaining and mitigating for the permanent retention of the existing structure.
In addition to the anticipated need for future dredging, the current cofferdam structure has become part of the harbors overall hazardous spill response plans. The area became part of the spill response plan in 2016 and is considered a critical part of the harbor spill response plans, being used for staging and pumpout of skimmed materials. The applicant has stated that while alternatives can be found, this is an ideal location for these activities and removal of the existing structure and fill would impair future emergency operations.
The applicant has proposed compensatory mitigation for the 0.18 acres of fill should they be authorized to retain it permanently. The impact was not mitigated for at the time of construction because the fill was intended to be temporary, lasting at most until the expiration of the original permit. As part of this request the applicant has proposed to buy 0.45 acre of wetland mitigation credit from a wetland mitigation bank for a proposed mitigation ratio of 2.5:1. There are currently no wetland mitigation banks in the Chicago District that serve the Michigan watershed.
Avoidance & Minimization
The applicant has stated the following concerning avoidance and minimization of impacts to Waters of the United States: Applicant made the structure as small as possible to operate as a offloading point for dredge spoils.
Mitigation
The applicant has stated the following concerning compensatory mitigation for unavoidable impacts to Waters of the United States: Applicant proposes to purchase of 0.45 acres of wetland mitigation credit from a wetland mitigation bank. The proposed mitigation ratio is 2.5:1. There is currently no mitigation bank in the Chicago District serving the Lake Michigan watershed.
The Corps has not verified the adequacy of this mitigation proposal at this time and will make the final determination on whether the proposed mitigation is appropriate and practicable in accordance with 33 CFR Part 332.
Regulatory Authority
This proposed action will be reviewed according to the provisions of Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act of 1972.
Jurisdiction
This application will be reviewed according to the provisions of Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act of 1972 due to placement of fill into Lake Michigan, a navigable water of the United States under the jurisdiction of the Department of the Army.
Evaluation Factors
The decision whether to issue a permit will be based on an evaluation of probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments.
All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people. In addition, if the proposed activity involves the discharge of dredged or fill material into waters of the United States, the evaluation of the impact on the public interest will include application of Section 404(b)(1) guidelines (40 CFR 230) promulgated by the U.S. Environmental Protection Agency.
The Corps of Engineers is also soliciting comments from the public, Federal, state and local agencies, Indian tribes, and other interested parties in order to consider and evaluate the potential impacts of the proposed activity. Once this office completes a review of the comments received, it will be determined whether to issue, modify, condition, or deny a permit for this proposal.
To prepare this decision, comments are taken into consideration to assess impacts on the public interest factors listed above, as well as endangered species, historic properties, water quality, and general environmental effects. Comments will be used in the preparation of an Environmental Assessment and/or Environmental Impact Statement pursuant to the National Environmental Policy Act. A determination concerning the need for a public hearing will also be based on the comments received.
Preliminary Evaluation of Selected Factors
Water Quality:
The applicant has applied to the Illinois Environmental Protection Agency (IEPA) for water quality certification, or waiver thereof, for the proposed activity in accordance with Section 401 of the Clean Water Act. Certification or waiver indicates that the IEPA believes the activity will not violate applicable water quality standards. The review by the IEPA is conducted in accordance with the Illinois water quality standards under 35 Illinois Administrative Code Subtitle C by providing an antidegradation assessment, which includes an evaluation of alternatives to any proposed increase in pollutant loading that may result from this activity.
The "Fact Sheet" containing the antidegradation assessment for this proposed project may be found on the IEPA's web site, at www.epa.state.il.us/public-notices/. In the event that the IEPA is unable to publish the "Fact Sheet" corresponding to the timeframe of this Joint Public Notice, a separate public notice and "Fact Sheet" will be published by the IEPA at the web site identified above. You may also obtain a copy of the "Fact Sheet" by contacting the IEPA at the address or telephone number shown below.
Written comments concerning possible impacts to water quality should be addressed to the following agency, along with a copy of the comments provided to the Corps of Engineers:
Illinois Environmental Protection Agency
Bureau of Water
Watershed Management Section
1021 N. Grand Avenue East
P.O. Box 19276
Springfield, Illinois 62794-9276
If you have any questions please contact the IEPA at (217) 782-3362.
Department of Natural Resources:
The applicant has applied to the Illinois Department of Natural, Office of Water Resources (IDNR-OWR) for a permit pursuant to the State of Illinois Rivers, Lake and Streams Act (615 ILCS 5). Comments concerning the IDNR-OWR permit should be addressed to the following agency, along with a copy of the comments provided to the Corps of Engineers:
Illinois Department of Natural Resources
Office of Water Resources
Michael A. Bilandic Building
160 N. LaSalle Street, Suite S-700
Chicago, IL 60601
If you have any questions please contact the IDNR at (312) 793-5947.
Endangered and Threatened Species:
The Corps of Engineers has determined that the proposed activity would not affect any federally-listed endangered or threatened species or critical habitat for any endangered or threatened species, pursuant to the Endangered Species Act of 1973, as amended (16 U.S.C. 1531 et seq.). Therefore, consultation with the U.S. Fish and Wildlife Service pursuant to Section 7 of the Endangered Species Act does not appear to be warranted at this time.
Historic Properties/Cultural Resources:
Preliminary review indicates that the proposed activity is not likely to adversely affect any historic property which is listed, or eligible for listing, on the National Register of Historic Places.
Environmental Impact Statement
A preliminary determination has been made that an environmental impact statement is not required for the proposed work.
Public Hearing
Any person may request in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. Requests for public hearing shall state with particularity the reasons for holding a public hearing. A request for a hearing may be denied if substantive reasons for holding a hearing are not provided or if there is otherwise no valid interest to be served.
It should be noted that materials submitted as part of the permit application become part of the public record and are thus available to the general public under the procedures of the Freedom of Information Act (FOIA). Individuals may submit a written request to obtain materials under FOIA or make an appointment to view the project file at the Chicago District Corps of Engineers Office of Counsel.
Interested parties wishing to comment on the proposed activity must do so in writing no later than August 8, 2018. It is presumed that all parties receiving this notice will wish to respond to this public notice; therefore, a lack of response will be interpreted as meaning that there is no objection to the project as described.
This public notice is not a paid advertisement and is for public information only. Issuance of this notice does not imply Corps of Engineers endorsement of the project as described.
If you have any questions, please contact Michael Murphy of my staff by telephone at (312) 846-5538, or email at Michael.J.Murphy@usace.army.mil. It should be noted that ALL comments received by this office (via hard copy or electronic) will only be accepted with the full name and address of the individual commenting. You can also visit our website at http://www.lrc.usace.army.mil/Missions/Regulatory.aspx for more information on our program.
FOR THE DISTRICT COMMANDER:
Original Signed
Kathleen G. Chernich
Chief, East Section
Regulatory Branch
PUBLIC NOTICE
APPLICATION FOR PERMIT
U.S. ARMY
CORPS OF ENGINEERS
CHICAGO DISTRICT
PUBLIC NOTICE/APPLICATION NUMBER: LRC-2006-1319
COMMENT PERIOD BEGINS: July 9, 2018
COMMENT PERIOD EXPIRES: August 8, 2018
U.S. Army Corps of Engineers
Illinois Environmental Protection Agency
APPLICANT
Department of the Navy
Naval Station Great Lakes
2601 E. Paul Jones Street, Building 1
Great Lakes, IL 60088
PROPOSED ACTION
Proposal to retain previously authorized temporary fill in Lake Michigan on a permanent basis.
(See attached drawings). A detailed description of this proposal is provided on page 2 of this
notice.
LOCATION OF PROPOSED ACTION
In Lake Michigan on the shoreline of the Naval Station Great Lakes harbor north of the inlet of
Pettibone Creek, in unincorporated Great Lakes, Lake County, Illinois, (NE Quarter of Section
9, Township 44 N, Range 12 E; 42.307933, -87.829699).
Interested parties are hereby notified that an application has been received for a Department of
the Army permit for the activity described herein and as shown on the attached drawings. You
are invited to provide your comments by August 8, 2018 on the proposed work, which will
become part of the record and will be considered in the decision. A permit will be issued or
denied under Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403) and Section 404
Action of the Clean Water Act of 1972(33 U.S.C. 1344).
Comments should be emailed to Michael.J.Murphy@usace.army.mil or written comments can be
mailed to:
-2U.S. Army Corps of Engineers
Chicago District, Regulatory Branch
Attn: LRC-2006-1319, Michael Murphy
231 South LaSalle Street, Suite 1500
Chicago, Illinois 60604-1437
It should be noted that ALL comments received by this office (via hard copy or electronic) will
only be accepted with the full name and address, and email address, if available, of the individual
commenting, and must be received by the close of the public notice period. Electronic comments
may be sent to the project manager at Michael.J.Murphy@usace.army.mil.
PROJECT DESCRIPTION
The applicant was authorized to construct a temporary cofferdam structure and backfill in the
Naval Station Great Lakes harbor to facilitate unloading of dredge spoils for upland disposal
during harbor dredging operations. The original permit was issued in November of 2009 and
modified in May of 2010. This permit will expire in November of 2019. The applicant has
requested authorization under Section 10 of the Rivers and Harbors Act of 1899 and Section 404
of the Clean Water Act to keep this structure and associated backfill in place on a permanent
basis (see attached drawings). No new fill is requested under this current request, only the
permanent retention of the fill placed in 2010.
The cofferdam and fill were constructed in May of 2010 (see original site layout drawing
attached) partly in wetland fringe vegetation and partly in waters of Lake Michigan (Naval
Station Great Lakes Harbor). The vegetative community prior to construction was (and the
adjacent area still is) dominated by a monotypic stand of Common Reed (Phragmities australis).
The area filled totals 0.18 acres and has subsequently been vegetated by turf grass over the
dredge material (sand) used to fill the cofferdam.
The applicant proposes to keep the cofferdam and fill in place to facilitate future dredge
operations in the harbor and to facilitate the use of the area as part of emergency spill response
plans within the harbor. While no dredge work is currently scheduled for the harbor, dredging in
the future is anticipated and a structure similar in size and position to the current cofferdam will
be required to facilitate offloading of dredge spoils. The applicant proposes to minimize overall
disturbance by maintaining and mitigating for the permanent retention of the existing structure.
In addition to the anticipated need for future dredging, the current cofferdam structure has
become part of the harbors overall hazardous spill response plans. The area became part of the
spill response plan in 2016 and is considered a critical part of the harbor spill response plans,
being used for staging and pumpout of skimmed materials. The applicant has stated that while
alternatives can be found, this is an ideal location for these activities and removal of the existing
structure and fill would impair future emergency operations.
-3The applicant has proposed compensatory mitigation for the 0.18 acres of fill should they be
authorized to retain it permanently. The impact was not mitigated for at the time of construction
because the fill was intended to be temporary, lasting at most until the expiration of the original
permit. As part of this request the applicant has proposed to buy 0.45 acre of wetland mitigation
credit from a wetland mitigation bank for a proposed mitigation ratio of 2.5:1. There are
currently no wetland mitigation banks in the Chicago District that serve the Michigan watershed.
AVOIDANCE & MINIMIZATION
The applicant has stated the following concerning avoidance and minimization of impacts to
Waters of the United States: Applicant made the structure as small as possible to operate as a
offloading point for dredge spoils.
MITIGATION
The applicant has stated the following concerning compensatory mitigation for unavoidable
impacts to Waters of the United States: Applicant proposes to purchase of 0.45 acres of wetland
mitigation credit from a wetland mitigation bank. The proposed mitigation ratio is 2.5:1. There
is currently no mitigation bank in the Chicago District serving the Lake Michigan watershed.
The Corps has not verified the adequacy of this mitigation proposal at this time and will make
the final determination on whether the proposed mitigation is appropriate and practicable in
accordance with 33 CFR Part 332.
REGULATORY AUTHORITY
This proposed action will be reviewed according to the provisions of Section 10 of the Rivers
and Harbors Act of 1899 and Section 404 of the Clean Water Act of 1972.
JURISDICTION
This application will be reviewed according to the provisions of Section 10 of the Rivers and
Harbors Act of 1899 and Section 404 of the Clean Water Act of 1972 due to placement of fill
into Lake Michigan, a navigable water of the United States under the jurisdiction of the
Department of the Army.
EVALUATION FACTORS
The decision whether to issue a permit will be based on an evaluation of probable impact
including cumulative impacts of the proposed activity on the public interest. That decision will
reflect the national concern for both protection and utilization of important resources. The
benefit which reasonably may be expected to accrue from the proposal must be balanced against
its reasonably foreseeable detriments.
All factors which may be relevant to the proposal will be considered including the cumulative
effects thereof; among those are conservation, economics, aesthetics, general environmental
concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values,
land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation,
water quality, energy needs, safety, food and fiber production, mineral needs, considerations of
property ownership and, in general, the needs and welfare of the people. In addition, if the
proposed activity involves the discharge of dredged or fill material into waters of the United
-4States, the evaluation of the impact on the public interest will include application of Section
404(b)(1) guidelines (40 CFR 230) promulgated by the U.S. Environmental Protection Agency.
The Corps of Engineers is also soliciting comments from the public, Federal, state and local
agencies, Indian tribes, and other interested parties in order to consider and evaluate the potential
impacts of the proposed activity. Once this office completes a review of the comments received,
it will be determined whether to issue, modify, condition, or deny a permit for this proposal.
To prepare this decision, comments are taken into consideration to assess impacts on the public
interest factors listed above, as well as endangered species, historic properties, water quality, and
general environmental effects. Comments will be used in the preparation of an Environmental
Assessment and/or Environmental Impact Statement pursuant to the National Environmental
Policy Act. A determination concerning the need for a public hearing will also be based on the
comments received.
PRELIMINARY EVALUATION OF SELECTED FACTORS
WATER QUALITY:
The applicant has applied to the Illinois Environmental Protection Agency (IEPA) for water
quality certification, or waiver thereof, for the proposed activity in accordance with Section 401
of the Clean Water Act. Certification or waiver indicates that the IEPA believes the activity will
not violate applicable water quality standards. The review by the IEPA is conducted in
accordance with the Illinois water quality standards under 35 Illinois Administrative Code
Subtitle C by providing an antidegradation assessment, which includes an evaluation of
alternatives to any proposed increase in pollutant loading that may result from this activity.
The "Fact Sheet" containing the antidegradation assessment for this proposed project may be
found on the IEPA's web site, at www.epa.state.il.us/public-notices/. In the event that the IEPA
is unable to publish the "Fact Sheet" corresponding to the timeframe of this Joint Public Notice, a
separate public notice and "Fact Sheet" will be published by the IEPA at the web site identified
above. You may also obtain a copy of the "Fact Sheet" by contacting the IEPA at the address or
telephone number shown below.
Written comments concerning possible impacts to water quality should be addressed to the
following agency, along with a copy of the comments provided to the Corps of Engineers:
Illinois Environmental Protection Agency
Bureau of Water
Watershed Management Section
1021 N. Grand Avenue East
P.O. Box 19276
Springfield, Illinois 62794-9276
If you have any questions please contact the IEPA at (217) 782-3362.
-5DEPARTMENT OF NATURAL RESOURCES:
The applicant has applied to the Illinois Department of Natural, Office of Water Resources
(IDNR-OWR) for a permit pursuant to the State of Illinois Rivers, Lake and Streams Act (615
ILCS 5). Comments concerning the IDNR-OWR permit should be addressed to the following
agency, along with a copy of the comments provided to the Corps of Engineers:
Illinois Department of Natural Resources
Office of Water Resources
Michael A. Bilandic Building
160 N. LaSalle Street, Suite S-700
Chicago, IL 60601
If you have any questions please contact the IDNR at (312) 793-5947.
ENDANGERED AND THREATENED SPECIES:
The Corps of Engineers has determined that the proposed activity would not affect any federallylisted endangered or threatened species or critical habitat for any endangered or threatened
species, pursuant to the Endangered Species Act of 1973, as amended (16 U.S.C. 1531 et seq.).
Therefore, consultation with the U.S. Fish and Wildlife Service pursuant to Section 7 of the
Endangered Species Act does not appear to be warranted at this time.
HISTORIC PROPERTIES/CULTURAL RESOURCES:
Preliminary review indicates that the proposed activity is not likely to adversely affect any
historic property which is listed, or eligible for listing, on the National Register of Historic
Places.
ENVIRONMENTAL IMPACT STATEMENT
A preliminary determination has been made that an environmental impact statement is not
required for the proposed work.
PUBLIC HEARING
Any person may request in writing, within the comment period specified in this notice, that a
public hearing be held to consider this application. Requests for public hearing shall state with
particularity the reasons for holding a public hearing. A request for a hearing may be denied if
substantive reasons for holding a hearing are not provided or if there is otherwise no valid
interest to be served.
It should be noted that materials submitted as part of the permit application become part of the
public record and are thus available to the general public under the procedures of the Freedom of
Information Act (FOIA). Individuals may submit a written request to obtain materials under
FOIA or make an appointment to view the project file at the Chicago District Corps of Engineers
Office of Counsel.
-6Interested parties wishing to comment on the proposed activity must do so in writing no later
than August 8, 2018. It is presumed that all parties receiving this notice will wish to respond to
this public notice; therefore, a lack of response will be interpreted as meaning that there is no
objection to the project as described.
This public notice is not a paid advertisement and is for public information only. Issuance of this
notice does not imply Corps of Engineers endorsement of the project as described.
If you have any questions, please contact Michael Murphy of my staff by telephone at (312) 8465538, or email at Michael.J.Murphy@usace.army.mil. It should be noted that ALL comments
received by this office (via hard copy or electronic) will only be accepted with the full name
and address of the individual commenting. You can also visit our website at
http://www.lrc.usace.army.mil/Missions/Regulatory.aspx for more information on our program.
FOR THE DISTRICT COMMANDER:
ORIGINAL SIGNED
Kathleen G. Chernich
Chief, East Section
Regulatory Branch
Path: S:\PT\T\TTLAS\139194\3-env-stdy-regs\32-permit\GIS\Fig1_Topo_Loc.mxd
Location of
Cofferdam
0
500
1,000 Feet
3535 VADNAIS CENTER DR.
ST. PAUL, MN 55110
PHONE: (651) 490-2000
FAX: (651) 490-2150
WATTS: 800-325-2055
www.sehinc.com
Project: TTLAS 139194
Print Date: 11/8/2016
Map by: ebudrow
Projection: UTM NAD 83 Zone 16 N
Source: SEHinc, ESRI, USGS, USDA
SITE LOCATION AND TOPOGRAPHY
NAVAL STATION GREAT LAKES COFFERDAM
North Chicago, Illinois
Figure
1
This map is neither a legally recorded map nor a survey map and is not intended to be used as one. This map is a compilation of records, information, and data gathered from various sources listed on this map and is to be used for reference purposes only. SEH does not warrant that the Geographic Information System (GIS) Data used to prepare this map are error free, and SEH does not represent that
the GIS Data can be used for navigational, tracking, or any other purpose requiring exacting measurement of distance or direction or precision in the depiction of geographic features. The user of this map acknowledges that SEH shall not be liable for any damages which arise out of the user's access or use of data provided.
Path: S:\PT\T\TTLAS\139194\3-env-stdy-regs\32-permit\GIS\Fig2_Aerial.mxd
Location of
Cofferdam
0
150
300 Feet
3535 VADNAIS CENTER DR.
ST. PAUL, MN 55110
PHONE: (651) 490-2000
FAX: (651) 490-2150
WATTS: 800-325-2055
www.sehinc.com
Project: TTLAS 139194
Print Date: 11/8/2016
Map by: ebudrow
Projection: UTM NAD 83 Zone 16 N
Source: SEHinc, ESRI, USGS, USDA
2014 AERIAL PHOTOGRAPH
NAVAL STATION GREAT LAKES COFFERDAM
North Chicago, Illinois
Figure
2
This map is neither a legally recorded map nor a survey map and is not intended to be used as one. This map is a compilation of records, information, and data gathered from various sources listed on this map and is to be used for reference purposes only. SEH does not warrant that the Geographic Information System (GIS) Data used to prepare this map are error free, and SEH does not represent that
the GIS Data can be used for navigational, tracking, or any other purpose requiring exacting measurement of distance or direction or precision in the depiction of geographic features. The user of this map acknowledges that SEH shall not be liable for any damages which arise out of the user's access or use of data provided.
Legend
Cofferdam
Wetland Impacts
0
10
20 Feet
Path: S:\PT\T\TTLAS\139194\3-env-stdy-regs\32-permit\GIS\Fig3_Impac.mxd
Total Permanent
Impact: 0.18 acres
3535 VADNAIS CENTER DR.
ST. PAUL, MN 55110
PHONE: (651) 490-2000
FAX: (651) 490-2150
WATTS: 800-325-2055
www.sehinc.com
Project: TTLAS 139194
Print Date: 11/8/2016
Map by: ebudrow
Projection: UTM NAD 83 Zone 16 N
Source: SEHinc, ESRI, USGS, USDA
WELTAND IMPACT AREA
NAVAL STATION GREAT LAKES COFFERDAM
North Chicago, Illinois
Figure
3
This map is neither a legally recorded map nor a survey map and is not intended to be used as one. This map is a compilation of records, information, and data gathered from various sources listed on this map and is to be used for reference purposes only. SEH does not warrant that the Geographic Information System (GIS) Data used to prepare this map are error free, and SEH does not represent that
the GIS Data can be used for navigational, tracking, or any other purpose requiring exacting measurement of distance or direction or precision in the depiction of geographic features. The user of this map acknowledges that SEH shall not be liable for any damages which arise out of the user's access or use of data provided.