The 2017 Nationwide Permit (NWP) Regional Conditions for the Honolulu District (the District) were approved by the Pacific Ocean Division Commander on March 10, 2017 and went into effect on March 19, 2017. The District is proposing a change to regional condition 3 – Acreage Limitation as described below.
The 2017 Nationwide Permit (NWP) Regional Conditions for the Honolulu District (the
District) were approved by the Pacific Ocean Division Commander on March 10, 2017
and went into effect on March 19, 2017. The District is proposing a change to regional
condition 3 – Acreage Limitation as described below.
1) Regional Condition 3 – Acreage Limitation
Approved regional condition 3 currently states:
“The maximum acreage of permanent loss to wetlands, other special aquatic sites
and other waters for a single project may not exceed 0.10-acre resulting from any
discharge of dredged or fill material.”
The District is proposing to revise regional condition 3 to read as follows:
“The maximum acreage of permanent loss to wetlands and other special aquatic
sites for a single project may not exceed 0.10-acre resulting from any discharge of
dredged or fill material.”
Rationale: Regional condition 3 as currently written is having the unintended
consequence of increasing the number of projects reviewed under our highest level of
review, the Individual Permit (IP), without a demonstrated benefit to the environment or
the public interest. Projects that propose to impact “other waters” and result in no more
than minimal environmental impacts, individually and cumulatively, are required to be
reviewed under IPs rather than NWPs. This more rigorous review process has resulted
in longer permit decision timelines (delays) and an additional burden on the regulated
public in terms of information needed to process an IP. Removing the wording “and
other waters” would provide clarity and allow for a more expedient permit review
process, while maintaining the focus on protection of wetlands and other special aquatic
sites.
The effect of the change is that some permanent losses of up to 0.5-acre of
jurisdictional aquatic resources (i.e. streams and open water) would be authorized by
NWP as long as the proposed activities otherwise satisfy the terms and conditions of
those NWPs. However, under such circumstances, the District would retain its ability to
require compensatory mitigation for unavoidable impacts to “other waters” when
appropriate and practicable. The District Engineer would also retain the discretionary
authority to review any activity authorized by NWP to determine whether the activity
complies with the NWP or whether the prospective permittee should apply for an IP.
We believe that in the vast majority of cases, with the terms and conditions currently in
effect, proposed actions that would result in the permanent loss of 0.5-acre or less of
“other waters” (i.e., streams and/or open waters) would have no more than minimal
individual and cumulative adverse effects on the aquatic environment. While
ephemeral, intermittent and perennial streams in the District’s area of responsibility
provide functions and services that contribute to the biological, chemical and physical
integrity of traditional navigable waters, these aquatic resources generally do not have
the same sensitivity as wetlands and other special aquatic sites, like coral reefs, riffle
and pool complexes, and submerged aquatic vegetation. Verification of activities under
a NWP would not preclude the need for applicants to avoid and minimize impacts nor
limit the District’s discretion to include special conditions, such as best management
practices or restricting the timing of work to occur only during the “dry” season and/or
under low tide conditions.
COMMENT AND REVIEW PERIOD: The District is seeking written comments on the proposed revision to the approved regional condition 3 as described above. Conventional mail or e-mail comments on this public notice received during the comment period will be made part of the record and will be considered in determining whether to revise the District’s regional condition 3. In order to be accepted, e-mail comments must originate from the author’s e-mail account and must include on the subject line of the e-mail message “RC 3”.
All e-mail comments should be sent to: tunis.w.mcelwain@usace.army.mil
Conventional mail comments should be sent to:
U.S. Army Corps of Engineers
Honolulu District, Regulatory Branch
Building 230 (Attn: CEPOH-RB)
Fort Shafter, Hawaii 96858-5440
Comments must reach this office no later than the expiration date of this public notice to become part of the record and be considered in the decision.
This public notice is issued by the Chief, Regulatory Office.