Extension of comment period for proposed anchor structures, dredging, and discharge at the Enbridge Line 5 pipeline in the Straits of Mackinac, Michigan

Please open the attachment to view the full Public Notice.

US Army Corps of Engineers

Public Notice

Detroit District Applicant:

Enbridge Pipelines (Lakehead), LLC

In Reply Refer To:

Corps File No. LRE-2010-00463-56-N18

Date: June 29, Expires: August 7,

2018 2018

Extension of comment period for proposed anchor structures, dredging, and discharge at the Enbridge Line 5 pipeline in the Straits of Mackinac, Michigan We have elected to extend the comment period for the public notice an additional 20 days. Details on the proposed project and information on how to submit comments are in the attached public notice.

FOR THE DISTRICT ENGINEER:

Kerrie E. Kuhne Chief, Permit Evaluation Western Branch Regulatory Office

NOTICE TO POSTMASTERS: We request that the above notice be conspicuously and continuously posted for the time period of this notice.

US Army Corps of Engineers

Public Notice

Detroit District Applicant:

Enbridge Pipelines (Lakehead), LLC

In Reply Refer To:

Corps File No. LRE-2010-00463-56-N18

Date: June Expires: July

29, 2018 18, 2018

Proposed anchor structures, dredging, and discharge at the Enbridge Line 5 pipeline in the Straits of Mackinac, Michigan

Applicant: Enbridge Pipelines (Lakehead) LLC 26 East Superior Street, Suite 309, Duluth, MN 55802 Project Location: The site is located in the Straits of Mackinac between Point LaBarbe and McGulpin Point, Emmet and Mackinac Counties, Michigan. Federal Authority: The applicant has applied for a Department of the Army permit under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act. State Authority: Section 401 of the Clean Water Act requires that all discharges of dredged or fill material must be certified by the State as complying with applicable effluent limitations and water quality standards. Coastal Zone Management Certification (or waiver thereof) is required from the State of Michigan if this proposed activity would occur within the designated coastal zone. Project Description: As shown on the attached plans, the applicant proposes to install 48 helical anchor structures on the existing pipeline. Anchors would consist of a helical anchoring system with saddle mounts. The anchors would be augured into the lakebed to a depth of approximately 10 feet. Work would be conducted from a barge with diver assistance. A total of up to 10 cubic yards of material would be dredged from an area approximately 4 feet long, 2 feet wide, and 1 foot deep, if needed to accommodate anchor saddle installation at some proposed anchor locations. A total of up to 5 cubic yards of material would be dredged from a similar sized area at 4 locations where anchors were authorized in 2017 but have not yet been installed. The dredged material would be discharged on the lakebed adjacent to the dredge area. The applicant further proposes to dredge and discharge lakebed sediment in association with the inspection of 128 existing pipeline anchor structures. A total of up to 300 cubic yards of sediment would be dredged from an area up to 40 feet long, 5 feet wide, and 2 feet deep at up to 128 anchor sites by pumping, water jetting, and

File No. LRE-2010-00463-56-N18

June 29, 2018

hand excavation to expose the pipeline for inspection, if needed. If coating repairs are needed in close proximity to an anchor, approximately 4 cubic yards of grout bags would be temporarily placed in a 6-foot by 6-foot area underneath the pipeline to support it as the anchor is removed and replaced following coating repair. The purpose of the proposed work is to maintain the existing pipeline in accordance with state and federal requirements. Avoidance & Minimization: The applicant has stated the following concerning avoidance and minimization of impacts to Waters of the United States: "Enbridge has sought to minimize impacts to waters of the United States by limiting the extent of bottom disturbance to the minimal amount necessary to safely complete the proposed work activities. The extent of bottom disturbance described in our application is the maximum potential. The actual amount of bottom disturbance is anticipated to be significantly less." The Corps has not verified the adequacy of the applicant's avoidance and minimization statement at this time. Compensatory Mitigation: The applicant has stated the following concerning compensatory mitigation for unavoidable impacts to Waters of the United States: "Enbridge believes compensatory mitigation should not be required for the work activities described in our applications due to the minimal footprint of bottom disturbance, all of which qualify under the nationwide permits." The Corps has not verified the adequacy of this mitigation proposal at this time. Other Authorizations: A permit is required from the Michigan Department of Environmental Quality under applicable provisions of the Natural Resources and Environmental Protection Act (NREPA), 1994 PA 451. The State file number is 24Enbridge Energy, LP - Straits of Mackinac Comments: We are publishing this notice in compliance with Title 33 Code of Federal Regulations Parts 320-332. Comments on the project should be submitted in writing and postmarked or delivered by the expiration date of this public notice. Comments of a positive or negative nature may be submitted. All responses must refer to file number LRE-2010-00463-56-N18. We will interpret a lack of response as meaning that there is no objection to the permit application. Comments should be filed with: Kerrie E. Kuhne Chief, Permit Evaluation Western Branch Regulatory Office Detroit District, Corps of Engineers 477 Michigan Avenue Detroit, Michigan 48226-2550 Comments may be e-mailed to: Katie.L.Otanez@usace.army.mil but must include a name and mailing address. 2

File No. LRE-2010-00463-56-N18

June 29, 2018

Public Hearing: Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. Requests for public hearings shall state, with particularity, the reasons for holding a public hearing. Evaluation: The decision whether to issue the Department of the Army permit will be based on evaluation of the probable impacts of the proposed activity on the public interest. That decision will reflect the national concerns for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership, and, in general, the needs and welfare of the people. The Corps of Engineers is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps of Engineers to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. This activity involves the discharge of dredged or fill material into waters of the United States. Therefore, the U.S. Army Corps of Engineers' evaluation of the impact of the activity on the public interest will include application of the guidelines promulgated by the Administrator of the Federal Environmental Protection Agency, under the authority of Section 404(b)(1) of the Clean Water Act. Endangered Species: We will review this application for the potential impact on threatened or endangered species pursuant to Section 7 of the Endangered Species Act as amended. We are not aware of the presence of any listed species or critical habitat at or in the vicinity of the proposed worksite. We invite information and/or comments regarding the potential presence of, or impacts to, any listed species or critical habitat. 3

File No. LRE-2010-00463-56-N18

June 29, 2018

Cultural Resources: The District Staff has reviewed existing information on historic properties potentially affected by the proposed project, including the National Register of Historic Places. There are no recorded historic properties within the permit area. The proposed work is of such a limited nature and extent that little likelihood exists for the project to impinge upon an unrecorded historic property. The District Engineer invites responses to this public notice from federal, state and local agencies, historical and archaeological societies, Indian tribes, and other parties likely to have knowledge of or concerns with historic properties in the area. Additional Information: This public notice and drawings are also available for viewing/printing at: http://www.lre.usace.army.mil/Missions/RegulatoryProgramandPermits/PublicNotices.as px. Questions concerning this application may be directed to Katie Otanez at the Corps of Engineers address listed above, or telephone number (313) 226-5479. FOR THE DISTRICT ENGINEER:

Kerrie E. Kuhne Chief, Permit Evaluation Western Branch Regulatory Office

NOTICE TO POSTMASTERS: We request that the above notice be conspicuously and continuously posted for the time period of this notice.

4

Supplemental Information Enbridge Pipelines (Lakehead) L.L.C. 2018 Line 5 Anchor Installation Project Mackinac and Emmet Counties, Michigan

PROJECT SUMMARY 3 ­ Proposed Activities and Construction Methods Enbridge Pipelines (Lakehead) L.L.C. (Enbridge) is planning to conduct maintenance on the existing dual 20-inch-diameter pipelines beneath the Straits of Mackinac. Enbridge is proposing to install pipeline anchors at 48 locations to comply with federal consent decree (Case 1:16-cv-00914, ECF No. 3 filed 7/20/16) condition 68. These pipeline anchors are in addition to the 22 anchors applied for in 2017 (submission number 2RD-DFDK-Y35G). Enbridge, considering the history of previous pipeline anchor installation work, is seeking authorization to complete this project from the Michigan DEQ under Act 451, Section 325 and from USACE under Nationwide Permit 12. Project activities will involve the installation of pipeline anchors which consist of a helical anchoring system with saddle mounts around the pipeline at each of the proposed locations. The 48 anchors will be augured directly into the lake bed. Each anchor uses two 10-inch-diameter by 10-foot long screws. The total lake bottom impact from the anchors will be approximately 20 cubic yards with a total footprint of about 53 ft2. The proposed locations for installation of the anchors are provided in Attachment A. Attachment B contains typical drawings depicting the auguring apparatus, as well as equipment that will be used for installation. Attachment C contains the anchor installation procedure. A marine infrastructure and utility contractor, Ballard Marine Construction, will work from barges to complete the anchor installation. No new on-land staging, temporary workspaces, or new access routes will be required for the Project. The Project is scheduled to begin in July 2018. Ballard Marine Construction will maintain a safety plan and an environmental protection plan for this work activity (Attachment D). In the unlikely event of pipeline damage during this project, Enbridge will implement a repair plan. If a release were to occur from the pipeline during this project, Enbridge would respond following the company Integrated Contingency Plan and Straits Tactical Response Plan. 4 ­ Project Purpose, Use and Alternatives The installation of 48 pipeline anchors is being proposed to comply with federal consent decree (Case 1:16-cv-00914, ECF No. 3 filed 7/20/16) condition 68. This Project is pipeline maintenance and is not associated with a new utility installation. The proposed activities are for the sole purpose of maintaining the previously authorized 1

Canada

WI

Michigan IL

IN

OH

WAP-1 WAP-2

WAP-6 WAP-7 WAP-8 WAP-9 WAP-10 WAP-11 WAP-12 WAP-13 WAP-14 WAP-15 WAP-16 WAP-17 WAP-18 WAP-19 WAP-20

EAP-6 EAP-7 EAP-8 EAP-9 EAP-10 EAP-11 EAP-12 EAP-13 EAP-14 EAP-15 EAP-16 EAP-17 EAP-18 EAP-19 EAP-20 EAP-21 EAP-22 EAP-23 EAP-24 EAP-25 EAP-26 EAP-27 EAP-28

Copyright:© 2013 National Geographic Society, i-cubed 0

0.5

1 Miles

1 inch = 1 miles

Figure 1a

Line 5 Straits of Mackinac Enbridge Pipelines (Lakehead) L.L.C. 2018 Proposed Anchor Locations

For Environmental Review Purposes Only

2018 Proposed Anchor Locations Line 5

Source: Z:\Clients\E_H\Enbridge\Line_5_Straits_of_Mackinac\Permitting\Maintenance\201802\L5_Straits_of_Mackinac_2018_Anchors_Overview_Topo.mxd

WAP-5

Date: (2/14/2018)

WAP-3 WAP-4

EAP-1 EAP-2 EAP-3 EAP-4 EAP-5

Supplemental Information Enbridge Pipelines (Lakehead) L.L.C. 2018 Line 5 Anchor Installation Project Mackinac and Emmet Counties, Michigan pipelines, and are consistent with those activities authorized under Nationwide Permit 12. The method of anchor installation is anticipated to incur no environmental impacts.

2

Supplemental Information Enbridge Pipelines (Lakehead) L.L.C. 2018 Line 5 Anchor Installation Project Mackinac and Emmet Counties, Michigan

3

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas