PUBLIC NOTICE: APPLICATION FOR PERMIT TO dredge 6,700 cubic yards of material from approximately 0.81 acre of Sturgeon Bay (Lake Michigan); to excavate an approximately 360 linear foot channel between Bradley Lake and Sturgeon Bay; and to discharge dredged or fill material within 20 acres of Bradley Lake in Door County, Wisconsin.
PROJECT DESCRIPTION AND PURPOSE: APPLICATION FOR PERMIT TO dredge 6,700 cubic yards of material from approximately 0.81 acre of Sturgeon Bay (Lake Michigan); to excavate an approximately 360 linear foot channel between Bradley Lake and Sturgeon Bay; and to discharge dredged or fill material within 20 acres of Bradley Lake in Door County, Wisconsin. The proposal includes the removal of material from the lake and then discharging dredged or fill material below the OHWM for lake nourishment. The project would also hydrologically connect Bradley Lake to Sturgeon Bay, increasing recreational and environmental benefits to the area.
Public Notice
APPLICANT:
City of Sturgeon Bay
ISSUED: July 26, 2018
EXPIRES: August 27, 2018
REFER TO:
2017-00290-JLK
SECTION: 404-Clean Water Act
SECTION: 10-River and Harbors Act
1. APPLICATION FOR PERMIT TO dredge 6,700 cubic yards of material from approximately
0.81 acre of Sturgeon Bay (Lake Michigan); to excavate an approximately 360 linear foot
channel between Bradley Lake and Sturgeon Bay; and to discharge dredged or fill material
within 20 acres of Bradley Lake in Door County, Wisconsin.
2. SPECIFIC INFORMATION
APPLICANT
City of Sturgeon Bay
835 North 14th Avenue
Sturgeon Bay, Wisconsin 54235
AGENT
Foth Infrastructure & Environmental
2121 Innovation Court
De Pere, Wisconsin 54235
PROJECT LOCATION: The project site includes Bradley Lake located in Section 6, Township
27 North, Range 26 East; Door County, Wisconsin. Latitude 44.84803, Longitude -87.38373.
DESCRIPTION OF PROJECT:
Bradley Lake is a 20 acre lake located east of the Bay of Sturgeon Bay and is part of Sunset
Park in the City of Sturgeon Bay, Door County, Wisconsin. Due to shallow water depths, high
nutrient loading, low dissolved oxygen, and invasive vegetation the lake is considered impaired
and not suitable for recreational activities. The proposal includes the removal of material from
the lake and then discharging dredged or fill material below the OHWM for lake nourishment.
The project would also hydrologically connect Bradley Lake to Sturgeon Bay, increasing
recreational and environmental benefits to the area.
LAKE DREDGING AND CHANNEL EXCAVATION: The first portion of the project includes the
dredging of 6,700 cubic yards of material from approximately 0.81 acre of the Bay and
excavating 20,700 cubic yards of material from upland for the construction of a 360 linear foot
channel between Bradley Lake and the Bay for the purpose of access and transporting dredged
material to a confined disposal facility located southeast of the project site. When all work is
completed, the channel would remain in place keeping the hydrologic connection, be reshaped
and graded to provide fish habitat.
LAKE AND CHANNEL NOURISHMENT: Approximately 30,000 cubic yards of dredged material
would be discharged within 20 acres of Bradley Lake and the remaining channel for the purpose
of reshaping lake grades and providing fish habitat. Additional benefits of the hydrologic
connection include increased water exchange between Bradley Lake and the Bay, improved
water quality within the lake, and easier access to the Bay. The proposed project would not
result in the loss of any aquatic resources as the area would continue to exist as lake bottom.
Regulatory Branch (2017-00290-JLK)
SOURCE OF DREDGED OR FILL MATERIAL: Material would be from on site and include
native sand and till initially dredged from the lake. A condition of any permit decision would
require dredged or fill material that is free from toxic pollutants in other than trace quantities. As
needed, engineered soil material would be obtained from an off-site source identified by the
construction contractor.
SURROUNDING LAND USE: The project area is bordered by Sunset Park and the open waters
of Sturgeon Bay to the west. Additional park property is located to the south and two-lane
roadways and residential development to the north and east.
PROJECT ALTERNATIVES: During project planning, the applicant identified and evaluated
three additional project alternatives. Two alternatives include dredging the channel at the
northeast corner of Bradley Lake. These alternatives were evaluated by the applicant for
potential adverse impacts to fish habitat located along the bay-side bank. The third alternative
includes dredging the access channel in the same location as the preferred alternative, however
then refilling the channel to original conditions after lake nourishment completion. This
alternative was re-evaluated by the applicant when the ecological benefits of maintaining a
hydrological connection was recognized.
THE FOLLOWING PRECAUTIONS TO PROTECT WATER QUALITY HAVE BEEN
DESCRIBED BY THE APPLICANT: Erosion control best management practices would be
implemented. All impacted areas would be enclosed with silt fence to prevent sediment from
eroding into adjacent properties and waters. Turbidity barriers and other physical containment
methods would be used in all work areas. All dredged material would be loaded into sealed
water-tight barges and transported through the proposed channel located at the southwest
portion of the lake and disposed of at the City's Confined Disposal Facility (CDF) located
southeast of the city of Sturgeon Bay. Additionally dredging activities would only take place
during favorable environmental conditions.
MITIGATION: No compensatory mitigation was proposed by the applicant.
3. FEDERALLY-LISTED THREATENED OR ENDANGERED WILDLIFE OR PLANTS OR
THEIR CRITICAL HABITAT
None were identified by the applicant and are known to exist in the permit area. However, Door
County is within the known or historic range of the following Federally-listed threatened (T) and
endangered (E) species:
Species
Northern long-eared bat (T)
Habitat
Hibernates in caves and mines while
swarming in surrounding wooded areas in
autumn. During summer, roosts and
forages in upland forests.
Hine's emerald dragonfly (E)
Calcareous streams and associated
wetlands overlying dolomite bedrock.
Pitcher's thistle (T)
Stabilized dunes and blowout areas.
Dwarf lake iris (T)
Partially shaded sandy-gravelly soils on
Lakeshores.
Page 2 of 4
Regulatory Branch (2017-00290-JLK)
This application is being coordinated with the U.S. Fish and Wildlife Service and consultation
under Section 7 of the Endangered Species Act (ESA) is being conducted independent of this
notice. Effects on threatened or endangered species would be resolved in accordance with
Section 7 of the ESA prior to the Corps authorization, or approval, of work in connection with
this project.
4. JURISDICTION
This application is being reviewed in accordance with the practices for documenting Corps
jurisdiction under Sections 9 & 10 of the Rivers and Harbors Act of 1899 and Section 404 of the
Clean Water Act identified in Regulatory Guidance Letter 08-02.
5. STATE SECTION 401 WATER QUALITY CERTIFICATION
WATER QUALITY CERTIFICATION. This Public Notice has been sent to the Wisconsin
Department of Natural Resources and is considered by the District Engineer to constitute valid
notification to that agency for Section 401 water quality certification. A permit will not be granted
until the Wisconsin Department of Natural Resources has issued or waived Section 401
certification.
6. HISTORICAL/ARCHAEOLOGICAL
This public notice is being sent to the National Park Service and the State Archaeologist for their
comments. The Corps will review information on known cultural resources and/or historic
property within and adjacent to the project area. The Corps will also consider the potential
effects of the project on any properties that have yet to be identified. The results of this review
and the Corps' determination of effect will be coordinated with the State Historic Preservation
Officer independently of this public notice. Any adverse effects on historic properties will be
resolved prior to the Corps authorization, or approval, of the work in connection with this project.
7.
PUBLIC HEARING REQUESTS
Any person may request, in writing, within the comment period specified in this notice, that a
public hearing be held to consider this application. Requests for public hearings shall state, in
detail, the reasons for holding a public hearing. A request may be denied if substantive reasons
for holding a hearing are not provided or if there is otherwise no valid interest to be served.
8. PUBLIC INTEREST REVIEW
The decision whether to issue a permit will be based on an evaluation of the probable impact,
including cumulative impacts, of the proposed activity on the public interest. That decision will
reflect the national concern for both protection and utilization of important resources. The benefit
which reasonably may be expected to accrue from the proposal must be balanced against its
reasonably foreseeable detriments. All factors which may be relevant to the proposal will be
considered, including the cumulative effects. Among those are conservation, economics,
aesthetics, general environmental concerns, wetlands, cultural values, fish and wildlife values,
flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion,
recreation, water supply and conservation, water quality, energy needs, safety, food and fiber
production and, in general, the needs and welfare of the people. Environmental and other
documents will be available for review in the St. Paul District Office.
Page 3 of 4
Regulatory Branch (2017-00290-JLK)
The Corps of Engineers is soliciting comments from the public; Federal, State, and local
agencies and officials; Indian tribes; and other interested parties in order to consider and
evaluate the impacts of this proposed activity. Any comments received will be considered by the
Corps of Engineers to determine whether to issue, modify, condition, or deny a permit for this
proposal. To make this decision, comments are used to assess impacts on endangered
species, historic properties, water quality, general environmental effects, and the other public
interest factors listed above. Comments are used in the preparation of an Environmental
Assessment and/or an Environmental Impact Statement pursuant to the National Environmental
Policy Act. Comments are also used to determine the need for a public hearing and to
determine the overall public interest of the proposed activity.
9.
COASTAL ZONE MANAGEMENT.
The Wisconsin Coastal Management Program (WCMP) in the Department of Administration is
inviting public comment regarding this project. The WCMP may conduct a Federal consistency
review to verify that the project will comply with State policies in Wisconsin's coastal zone.
Further information may be obtained from the Federal Consistency Coordinator at: Wisconsin
Coastal Management Program, P.O. Box 7868, Madison, WI 53707-7868; (608) 267-7982.
Any comments on whether or not this proposed project complies with the State enforceable
policies should be received within 30 days by the Federal Consistency Coordinator.
10. REPLIES/COMMENTS
Interested parties are invited to submit to this office written facts, arguments, or objections within
30 days of the date of this notice. These statements should bear upon the suitability of the
location and the adequacy of the project and should, if appropriate, suggest any changes
believed to be desirable. Comments received may be forwarded to the applicant.
Replies may be addressed to:
U.S. Army Corps of Engineers
Attn: Jessica Kempke
211 North Broadway, Suite 221
Green Bay, Wisconsin 54303
Or, IF YOU HAVE QUESTIONS ABOUT THE PROJECT, call Jessica Kempke at the Green
Bay office of the Corps, telephone number 651-290-5856.
To receive Public Notices by e-mail, go to: http://mvp-extstp/list_server/ and add your
information in the New Registration Box.
Todd Vesperman
Chief, Southeast Section
Enclosures