You can copy from here when filling out the rest of the page.
WATER CONTROL STRUCTURE IN CAMERON PARISH
[EXPIRATION DATE EXTENDED TO 8/27/2018 DUE TO TECHNICAL DIFFICULTIES WITH POSTING]
NAME OF APPLICANT: D.P. Land, c/o C.H. Fenstermaker and Associates, 135 Regency Square, Lafayette, Louisiana 70508.
LOCATION OF WORK: Existing Canal, located approximately 3.8 miles southwest of Johnsons Bayou, in Cameron Parish, Louisiana, as shown on the enclosed drawings.
Location: Latitude: 29°49ʹ40.16ʺ N / Longitude: -93°39ʹ17.61ʺ W, Hydrologic Unit Code: 08080206 – Calcasieu Basin.
CHARACTER OF WORK: Conduct excavating operations within an existing levee area and install a six 42-inch wide by 20-foot long barrel flap gate style barrels within a new 53-foot wide by 78-foot long water control structure, two approximately 115-foot long temporary cofferdams, construct a 40-foot wide by 125-foot long temporary equipment staging area, two 40-foot wide by 60-foot long loading and unloading zone areas, two approximately 40-foot wide by 119-foot long temporary work areas, and place 878 cubic yards of dredged material within two 40-foot wide by 42-foot long temporary spoil placement areas. Approximately 0.60 of an acre of emergent wetlands would be temporarily impacted via project implementation. The applicant will be required to restore all temporarily impacted wetlands to be verified after one growing season from project completion, and will compensate for any unrepairable wetland impacts through acquisition of in-kind credits at a Department of the Army approved mitigation bank, should a DA permit be granted.
[EXPIRATION DATE EXTENDED TO 8/27/2018 DUE TO TECHNICAL DIFFICULTIES WITH POSTING]
JOINT PUBLIC NOTICE
July 30, 2018
United States Army
Corps of Engineers
New Orleans District
Regulatory Branch
7400 Leake Avenue
New Orleans, Louisiana 70118-3651
State of Louisiana
Department of Environmental Quality
ATTN: Water Quality Certifications
Post Office Box 4313
Baton Rouge, Louisiana 70821-4313
(504) 862-2284
Sara.B.Fortuna@usace.army.mil
Project Manager
Sara Fortuna
Permit Application Number
MVN-2018-00472-WKK
(225) 219-3225
Elizabeth.Hill@la.gov
Project Manager
Elizabeth Hill
WQC Application Number
WQC 180502-01
Interested parties are hereby notified that a permit application has been received by the New
Orleans District of the U.S. Army Corps of Engineers pursuant to: [X] Section 10 of the Rivers and
Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or [X] Section 404 of the Clean
Water Act (86 Stat. 816; 33 USC 1344).
Application has also been made to the Louisiana Department of Environmental Quality, Water
Quality Certifications, for a Water Quality Certification (WQC) in accordance with statutory authority
contained in LRS30:2047 A(3), and provisions of Section 401 of the Clean Water Act (P.L.95-17).
WATER CONTROL STRUCTURE IN CAMERON PARISH
NAME OF APPLICANT: D.P. Land, c/o C.H. Fenstermaker and Associates, 135 Regency Square,
Lafayette, Louisiana 70508.
LOCATION OF WORK: Existing Canal, located approximately 3.8 miles southwest of Johnsons
Bayou, in Cameron Parish, Louisiana, as shown on the enclosed drawings.
Location: Latitude: 29°4940.16 N / Longitude: -93°3917.61 W, Hydrologic Unit Code: 08080206
Calcasieu Basin.
CHARACTER OF WORK: Conduct excavating operations within an existing levee area and install a
six 42-inch wide by 20-foot long barrel flap gate style barrels within a new 53-foot wide by 78-foot
long water control structure, two approximately 115-foot long temporary cofferdams, construct a 40foot wide by 125-foot long temporary equipment staging area, two 40-foot wide by 60-foot long
loading and unloading zone areas, two approximately 40-foot wide by 119-foot long temporary work
areas, and place 878 cubic yards of dredged material within two 40-foot wide by 42-foot long
temporary spoil placement areas. Approximately 0.60 of an acre of emergent wetlands would be
temporarily impacted via project implementation. The applicant will be required to restore all
temporarily impacted wetlands to be verified after one growing season from project completion, and
will compensate for any unrepairable wetland impacts through acquisition of in-kind credits at a
Department of the Army approved mitigation bank, should a DA permit be granted.
-2The comment period for the Department of the Army Permit and the Louisiana Department of
Environmental Quality WQC will close 20 days from the date of this joint public notice. Written
comments, including suggestions for modifications or objections to the proposed work, stating
reasons thereof, are being solicited from anyone having interest in this permit and/or this WQC
request and must be mailed so as to be received before or by the last day of the comment period.
Letters concerning the Corps of Engineers permit application must reference the applicant's name
and the Permit Application Number, and be mailed to the Corps of Engineers at the address above,
ATTENTION: REGULATORY BRANCH. Similar letters concerning the Water Quality
Certification must reference the applicant's name and the WQC Application number
and be mailed to the Louisiana Department of Environmental Quality at the address above.
Individuals or parties may request an extension of time in which to comment on the proposed work
by writing or e-mailing the Corps of Engineers Project Manager listed above. Any request must be
specific and substantively supportive of the requested extension, and received by this office prior to
the end of the initial comment period. The Section Chief will review the request and the requestor will
be promptly notified of the decision to grant or deny the request. If granted, the time extension will be
continuous to the initial comment period and, inclusive of the initial comment period, will not exceed a
total of 30 calendar days.
The application for this proposed project is on file with the Louisiana Department of Environmental
Quality and may be examined during weekdays between 8:00 a.m. and 4:30 p.m. Copies may be
obtained upon payment of costs of reproduction.
Corps of Engineers Permit Criteria
The decision whether to issue a permit will be based on an evaluation of the probable impacts,
including cumulative impacts of the proposed activity on the public interest. That decision will reflect
the national concern for both protection and utilization of important resources. The benefit which
reasonably may be expected to accrue from the proposal must be balanced against its reasonably
foreseeable detriments. All factors which may be relevant to the proposal will be considered including
the cumulative effects thereof; among those are conservation, economics, aesthetics, general
environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards,
floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and
conservation, water quality, energy needs, safety, food and fiber production, mineral needs,
considerations of property ownership and, in general, the needs and welfare of the people.
The U.S. Army Corps of Engineers is soliciting comments from the public, federal, state, and local
agencies and officials, Indian Tribes, and other interested parties in order to consider and evaluate
the impacts of this proposed activity. Any comments received will be considered by the U.S. Army
Corps of Engineers to determine whether to make, modify, condition, or deny a permit for this
proposal. To make this decision, comments are used to assess impacts on endangered species,
historic properties, water quality, general environmental effects, and other public interest factors listed
above. Comments are used in the preparation of an Environmental Assessment and/or an
Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are
also used to determine the need for a public hearing and to determine the overall public interest of the
proposed activity.
The New Orleans District is unaware of properties listed on the National Register of Historic
Places near the proposed work. The possibility exists that the proposed work may damage or
destroy presently unknown archeological, scientific, prehistorical, historical sites, or data. Copies of
this public notice are being sent to the State Archeologist and State Historic Preservation Officer
regarding potential impacts to cultural resources.
-3The New Orleans District has determined that 0.60 of an acre of the project footprint is in waters
known to be utilized by the West Indian Manatee (Trichechus manatus) and determined the activity is
not likely to adversely affect this species based on the Standard Local Operating Procedure for
Endangered Species in Louisiana (SLOPES), dated October 22, 2014, between the U.S. Army Corps
of Engineers, New Orleans and U.S. Fish and Wildlife Service, Ecological Services Office. If this
permit modification/time extension is issued, the applicant has agreed to follow the Standard Manatee
Conditions for In-Water Activities.
This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the MagnusonStevens Fishery Conservation and Management Act. The applicant's proposal would result in the
destruction or alteration of 0.60 of an acre of EFH utilized by various life stages of red drum and
penaeid shrimp. Our initial determination is that the proposed action would not have a substantial
adverse impact on EFH or federally managed fisheries in the Gulf of Mexico. Our final determination
relative to project impacts and the need for mitigation measures is subject to review by and
coordination with the National Marine Fisheries Service.
If the proposed work involves deposits of dredged or fill material into navigable waters, the
evaluation of the probable impacts will include the application of guidelines established by the
Administrator of the Environmental Protection Agency. Also, a certification that the proposed activity
will not violate applicable water quality standards will be required from the Department of
Environmental Quality, Water Quality Certifications, before a permit is issued.
Any person may request, in writing, within the comment period specified in this notice, that a
public hearing be held to consider this application. Requests for public hearings shall state, with
particularity, the reasons for holding a public hearing.
The applicant has certified that the proposed activity described in the application complies with
and will be conducted in a manner that is consistent with the Louisiana Coastal Resources Program.
The Department of the Army permit will not be issued unless the applicant received approval or a
waiver of the Coastal Use Permit by the Department of Natural Resources.
You are requested to communicate the information contained in this notice to any other parties
whom you deem likely to have interest in the matter.
Darrell S. Barbara
Chief, Western Evaluation Section
Regulatory Branch
Enclosure
AREA OF
PROPOSED
WORK
Approx. 3.8 miles Southwesterly
from "JOHNSONS BAYOU,
LOUISIANA"
Sec. 17
Sec. 16
Sec. 15
VICINITY MAP
NOT TO SCALE
Sec. 20
Sec. 19
Sec. 30
PROPOSED SIX BARREL
WATER CONTROL STRUCTURE
Lat. 29°49'40.16"
Long. 93°39'17.61"
(NAD 83)
SEE PLAN VIEW SHEET 2
Sec. 21
Sec. 29
Sec. 22
Sec. 27
Sec. 28
Marsh Buggy Access
2000'
0
1000'
2000'
NAD 27 LA. SOUTH ZONE
Scale: 1" = 2000'
NOTE: THESE PLANS ARE INTENDED
EXCLUSIVELY FOR THE PURPOSE OF
OBTAINING ENVIRONMENTAL
COMPLIANCE PERMITS AND ARE NOT
TO BE USED FOR CONSTRUCTION,
BIDDING, RECORDATION, CONVEYANCE,
SALES OR ENGINEERING DESIGN.
Not to be used for construction,
bidding, recordation, conveyance,
sales, or engineering design.
PRELIMINARY
Robert L. Lastrapes
Professional Land Surveyor
Registration No. 4717
DORE ENERGY
SIX BARREL WATER CONTROL STRUCTURE
Cameron Meadows Marsh Creation
Section 20, T14S-R13W
Cameron Parish, Louisiana
DRAWN BY: KJD
C. H. Fenstermaker & Associates, L.L.C.
135 Regency Sq. Lafayette, LA 70508
Ph. 337-237-2200 Fax. 337-232-3299
www.fenstermaker.com
PROJ. MGR.: CL
REVISED:
DATE: 01/16/2018
SHEET 1 OF 6
FILENAME: T:\2016\2164927\DWG\PERMIT PLANS_6 Barrel Structure.dwg
SHEETS
-6
.
-6
.
0
0
Temporary staging
area for barge with
marsh buggy
40'
.0
0
-6
0
-6
.
'
-5
.
Temporary Equipment
'
Staging Area
125
0
-5
.
0
Loading &
Unloading Zone
-5
.
0
40'
66
Canal
0
Existing
-6
.
-6
.
0
B
A
-6
.
0
R 13 W
-5
.
60'
-5
.
0
8'
-5
.
0
14
40'
115'
.0
-5
.0
-5
.
0
-5
'
60
-6
.
40
.0
C'
-3
-3 .0 4.
0
119
-4
78'
.0
53'
-4 .0 4.
0
-4
.0
42'
-3
.0
.0
-4
Temporary Proposed
Coffer Dam For
Construction
-4
.0
-5
.0
-2 -3.
-3
.5 0
.0 4.0
.0
.0
-4
-3
.
0
-5
.
0
-5
-5
.0
-3
.0
-4
.0
-2
.0
.5
.0
Temporary
Fill Placement
B'
-4
.0
-4
A'
-2
.0
40'
73'
-1
-4 -3. -3
.0 0 .0
42'
Temporary
Fill Placement
Temporary
Work Area
-2
.0
-3
.0
49'
40'
Typical 6 Barrel
Structure
(See Sheet 4)
73'
-1
Temporary
Work Area
Loading &
Unloading Zone
'
0
.0
-5
.
117'
111'
Sec. 20 C
'
.0
-4
0
Temporary Proposed
Coffer Dam For
Construction
T
14
S
60'
0
30'
60'
NAD 27 LA. SOUTH ZONE
Scale: 1" = 60'
NOTE: THESE PLANS ARE INTENDED
EXCLUSIVELY FOR THE PURPOSE OF
OBTAINING ENVIRONMENTAL
COMPLIANCE PERMITS AND ARE NOT
TO BE USED FOR CONSTRUCTION,
BIDDING, RECORDATION, CONVEYANCE,
SALES OR ENGINEERING DESIGN.
Not to be used for construction,
bidding, recordation, conveyance,
sales, or engineering design.
PRELIMINARY
Robert L. Lastrapes
Professional Land Surveyor
Registration No. 4717
DORE ENERGY
SIX BARREL WATER CONTROL STRUCTURE
Cameron Meadows Marsh Creation
Section 20, T14S-R13W
Cameron Parish, Louisiana
DRAWN BY: KJD
C. H. Fenstermaker & Associates, L.L.C.
135 Regency Sq. Lafayette, LA 70508
Ph. 337-237-2200 Fax. 337-232-3299
www.fenstermaker.com
PROJ. MGR.: CL
REVISED:
DATE: 01/16/2018
SHEET 2 OF 6
FILENAME: T:\2016\2164927\DWG\PERMIT PLANS_6 Barrel Structure.dwg
SHEETS
Temporary
Coffer Dam
Temporary
Coffer Dam
Proposed
Excavation
+0.5' MHWL
+0.15' MHWL
+0.5' MLWL
-1.85' MLWL
39'
CROSS SECTION A-A'
Horizontal Scale: 1"=50'
Vertical Scale: 1"=20'
Temporary
Coffer Dam
Temporary
Coffer Dam
Proposed
Excavation
+0.5' MHWL
+0.15' MHWL
-0.5' MLWL
-1.85' MLWL
49'
CROSS SECTION B-B'
Horizontal Scale: 1"=50'
Vertical Scale: 1"=20'
Temporary
Spoil Placement
40'
Proposed
Excavation
7.1'
7.1'
40'
76'
CROSS SECTION C-C'
Horizontal Scale: 1"=50'
Vertical Scale: 1"=20'
NOTE: THESE PLANS ARE INTENDED
EXCLUSIVELY FOR THE PURPOSE OF
OBTAINING ENVIRONMENTAL
COMPLIANCE PERMITS AND ARE NOT
TO BE USED FOR CONSTRUCTION,
BIDDING, RECORDATION, CONVEYANCE,
SALES OR ENGINEERING DESIGN.
Not to be used for construction,
bidding, recordation, conveyance,
sales, or engineering design.
PRELIMINARY
Robert L. Lastrapes
Professional Land Surveyor
Registration No. 4717
DORE ENERGY
SIX BARREL WATER CONTROL STRUCTURE
Cameron Meadows Marsh Creation
Section 20, T14S-R13W
Cameron Parish, Louisiana
DRAWN BY: KJD
C. H. Fenstermaker & Associates, L.L.C.
135 Regency Sq. Lafayette, LA 70508
Ph. 337-237-2200 Fax. 337-232-3299
www.fenstermaker.com
PROJ. MGR.: CL
REVISED:
DATE: 01/16/2018
SHEET 3 OF 6
FILENAME: T:\2016\2164927\DWG\PERMIT PLANS_6 Barrel Structure.dwg
SHEETS
Existing Marsh
Elevation +1'
Front Stoplog Bay
4'
Riser Height
5'
3/8" x 12" Wide
Flange
(Each Side &
Bottom)
Top of Riser
Elev. +1'
Riser Length
As Required
Sheet Pile
Side Stoplog Bay
5'
4' - 9'
Riser Width As Required
Timber Pile
Supports
6'x6' Post
Side Plate Height
2.5'
P.O.B. Top of Pipe
-2.0' Elevation
Proposed Back Fill
Min. 2' Cover
Sheet Pile
P.O.E. Top of Pipe
-2.5' Elevation
Corrugated Aluminum Pipe Length
Varmit
Shield
20'
12 Ga. 3" x 1" Corrugations
Drill 5/8" Dia. Holes
1/4" Aluminum Plate
Equally Spaced
Sides & Bottom
(11 Req'd Front & Back Flange) -4' at or just
above water
SIDE VIEW
FRONT ELEVATION
bottom
Top of Pipe
+1.5'
Aluminum
Flap Gate
-5' at or just
above water
bottom
5'
Timber Pile
Supports
6'x6' Post
Weld Pipe To Riser
With Continuous Weld
Weld Flap Gate
To Pipe
Varmit
Shield
5'
Timber Pile
Supports
6'x6' Post
Timber Pile
Supports
6'x6' Post
3/8" x 12" Wide Flange Req'd
(Front & Back)
3 BAY ALUMINUM RISER STRUCTURE
No Scale
In-Situ Fill (Type)
Min. 2' Cover Over
Pipe
42" Wide Corrugated
Aluminum Pipe
Existing
Ground
4" x 12' x 6'
Timber
Anchors
EL. Varies With
Slope of Pipe
Timber Pile
Supports
8.5' (TYP.)
TYPICAL 6 BARREL STRUCTURE
No Scale
NOTE: THESE PLANS ARE INTENDED
EXCLUSIVELY FOR THE PURPOSE OF
OBTAINING ENVIRONMENTAL
COMPLIANCE PERMITS AND ARE NOT
TO BE USED FOR CONSTRUCTION,
BIDDING, RECORDATION, CONVEYANCE,
SALES OR ENGINEERING DESIGN.
Not to be used for construction,
bidding, recordation, conveyance,
sales, or engineering design.
PRELIMINARY
Robert L. Lastrapes
Professional Land Surveyor
Registration No. 4717
DORE ENERGY
SIX BARREL WATER CONTROL STRUCTURE
Cameron Meadows Marsh Creation
Section 20, T14S-R13W
Cameron Parish, Louisiana
DRAWN BY: KJD
C. H. Fenstermaker & Associates, L.L.C.
135 Regency Sq. Lafayette, LA 70508
Ph. 337-237-2200 Fax. 337-232-3299
www.fenstermaker.com
PROJ. MGR.: CL
REVISED:
DATE: 01/16/2018
SHEET 4 OF 6
FILENAME: T:\2016\2164927\DWG\PERMIT PLANS_6 Barrel Structure.dwg
SHEETS
DPL Operational Plan
Cameron Meadows West
CS-66 Six Barrel Structure Operation Plan
Maintenance Phase
Flap Gates Position
Dates
Stop Log Setting
Feb 1 - July 31
Open
Open
August 1 - Jan 31
Open
6" Below Marsh
Elevation
Drawdown Phase *
Flap Gates Position
Dates
Jan 16 - May 31
Stop Log Setting
Flapping
Open
Jun 1 - Oct 31
Open
Open
Nov 1 - Jan 15
Open
6" Below Marsh
Elevation
*No more than one attempt every three years
Additional Provisions
1. Maximum stop log elevation may not exceed 6" below marsh elevation.
2. Flap gates are closed only when salinity as measured inside each structure exceeds 6 ppt.
3. In the event of an impending extreme rainfall, tropical storm or hurrucane, all flap gates may be
raised and all stop logs may be removed. Normal structure operation may may resume once
salinity and water levels return to normal seasonal conditions.
4. If water salinty inside the management unit exceeds ssalinity outside the unit for greater than two
weeks, the structures should be opened.
5. If water level inside the management unit exceeds marsh level by 6" for more than 14 consecutive
days, the structures should be configured to evacuate excess water. ANormal structure operation
may resume once water levels inside the management unit equilibrate to outside the unit.
6. All elevations are shown in NAVD 88.
NOTE: THESE PLANS ARE INTENDED
EXCLUSIVELY FOR THE PURPOSE OF
OBTAINING ENVIRONMENTAL
COMPLIANCE PERMITS AND ARE NOT
TO BE USED FOR CONSTRUCTION,
BIDDING, RECORDATION, CONVEYANCE,
SALES OR ENGINEERING DESIGN.
Not to be used for construction,
bidding, recordation, conveyance,
sales, or engineering design.
PRELIMINARY
Robert L. Lastrapes
Professional Land Surveyor
Registration No. 4717
DORE ENERGY
SIX BARREL WATER CONTROL STRUCTURE
Cameron Meadows Marsh Creation
Section 20, T14S-R13W
Cameron Parish, Louisiana
DRAWN BY: KJD
C. H. Fenstermaker & Associates, L.L.C.
135 Regency Sq. Lafayette, LA 70508
Ph. 337-237-2200 Fax. 337-232-3299
www.fenstermaker.com
PROJ. MGR.: CL
REVISED:
DATE: 01/16/2018
SHEET 5 OF 6
FILENAME: T:\2016\2164927\DWG\PERMIT PLANS_6 Barrel Structure.dwg
SHEETS
TOTAL EXCAVATION REQUIRED FOR 6 BARREL STRUCTURE . . . . . . . . . . . 878 CU. YDS.
TEMPORARY IMPACTS, LOADING & UNLOADING AREAS,
WORK AREAS AND FILL PLACEMENT AREAS . . . . . . . . . . . . . . . . . . . . . . . . 0.09 ACRES
Tug
WATERLINE
6' Draft
MUDLINE
TYPICAL BACKHOE/MARSH BUGGY
TYPICAL TUG BOAT
No Scale
No Scale
NOTES:
1. All structures and/or facilities occurring in open
water and/or Jurisdictional Wetlands shall be removed
when all de-watering processes have been completed
and no additional salt water will be added to the marsh
for the herein permitted use unless prior written
approval to leave such structures in place is received
from the Coastal Management Division. This condition
does not preclude the necessity for revising the current
permit or obtaining a separate Coastal Use Permit,
should one be required for such activities.
Proposed
40' x 75'
Temporary Pulling
Barge with Winch
Approx. 6' Draft
0.0' NAVD 88
2. As-built drawings shall be submitted within 30 days
of completion of this project to the Louisiana
Department of Natural Resources, Coastal
Management Division, P.O. Box 44487, Baton
Rouge, LA 70804-4487.
3. In order to ensure the safety of all parties, the
permittee shall contact the Louisiana ONE CALL
System (1-800-272-3020), a minimum of 48 hours
prior to the commencement of any excavation
(Digging, Dredging, Jetting, etc.) or demolition
activity.
Mudline
TYPICAL PULLING BARGE
Proposed
3-Pile Cluster
No Scale
4. Structures will also be marked/lighted in accordance
with U.S. Coast Guard regulations.
5. The entire proposed protection levee will be degraded
to the marsh elevation of the adjacent marsh.
NOTE: THESE PLANS ARE INTENDED
EXCLUSIVELY FOR THE PURPOSE OF
OBTAINING ENVIRONMENTAL
COMPLIANCE PERMITS AND ARE NOT
TO BE USED FOR CONSTRUCTION,
BIDDING, RECORDATION, CONVEYANCE,
SALES OR ENGINEERING DESIGN.
Not to be used for construction,
bidding, recordation, conveyance,
sales, or engineering design.
PRELIMINARY
Robert L. Lastrapes
Professional Land Surveyor
Registration No. 4717
DISCLAIMER: At this time, C. H. Fenstermaker & Associates, L.L.C. has not performed
nor was asked to perform any type of engineering, hydrological modeling, flood plain, or
"No Rise" certification analyses, including but not limited to determining whether the
project will impact flood hazards in connection with federal/FEMA, state, and/or local
laws, ordinances and regulations. Accordingly, Fenstermaker makes no warranty or
representation of any kind as to the foregoing issues, and persons or entities using this
information shall do so at their own risk.
DORE ENERGY
SIX BARREL WATER CONTROL STRUCTURE
Cameron Meadows Marsh Creation
Section 20, T14S-R13W
Cameron Parish, Louisiana
DRAWN BY: KJD
C. H. Fenstermaker & Associates, L.L.C.
135 Regency Sq. Lafayette, LA 70508
Ph. 337-237-2200 Fax. 337-232-3299
www.fenstermaker.com
PROJ. MGR.: CL
REVISED:
DATE: 01/16/2018
SHEET 6 OF 6
FILENAME: T:\2016\2164927\DWG\PERMIT PLANS_6 Barrel Structure.dwg
SHEETS