BULK LIQUID EXPORT TERMINAL FACILITY WITHIN AND ALONG THE MISSISSIPPI RIVER IN PLAQUEMINES PARISH

NAME OF APPLICANT: Plaquemines Port and Harbor Terminal District, c/o Coastal Engineering Solutions, Post Office Box 80735, Baton Rouge, Louisiana 70898. LOCATION OF WORK: Project site is located within and along the right descending bank of the Mississippi River, at about mile 61 above Head of Passes, at 16111 Louisiana State Highway 23, in Myrtle Grove, Louisiana, in Plaquemines Parish, as shown on the attached drawings. Latitude: 29.6611 Longitude: -89.9675 Hydrologic Unit Codes: 08090100 Lower Mississippi River - New Orleans and 080900301 East Central Louisiana Coastal. CHARACTER OF WORK: Clear, grade, excavate, and deposit fill for a 200 acre bulk liquid export terminal facility including: tank storage area/s with supporting infrastructure, dock, additional rail spurs, and rail off-loading facility. Project implementation will require excavation and deposition of 150,250 cubic yards of native material, 14,000 cubic yards of rock, 65,500 cubic yards of crushed stone or gravel, and 20 cubic yards of concrete. The proposed 200 acre parcel was originally part of Department of the Army permit authorization for RAM Terminals, LLC. Currently proposed project design would directly impact 19.6 acres of jurisdictional wetlands; 3.7 acres of the proposed direct impacts to jurisdictional wetlands have been compensated for through the previous Department of the Army authorization. The applicant proposes to contract with an approved mitigation bank in order to offset unavoidable adverse impacts to jurisdictional wetlands. The proposed liquid export facility is located in the vicinity of the Mid-Barataria Sediment Diversion proposal.

JOINT PUBLIC NOTICE September 10, 2018 United States Army Corps of Engineers New Orleans District Regulatory Branch, ODR-E Room 280 7400 Leake Avenue New Orleans, Louisiana 70118 (504) 862-1564 Stephanie.L.Castaing@usace.army.mil Project Manager Stephanie Castaing Permit Application Number MVN-2012-0123-EPP

State of Louisiana Department of Environmental Quality ATTN: Water Quality Certifications Post Office Box 4313 Baton Rouge, Louisiana 70821-4313 (225) 219-3225 Project Manager Elizabeth Hill WQC Application Number WQC 180706-01

Interested parties are hereby notified that a permit application has been received by the New Orleans District of the U.S. Army Corps of Engineers pursuant to: [X] Section 10 of the Rivers and Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or [X] Section 404 of the Clean Water Act (86 Stat. 816; 33 USC 1344). Application has also been made to the Louisiana Department of Environmental Quality, Water Quality Certifications, for a Water Quality Certification (WQC) in accordance with statutory authority contained in LRS30:2047 A(3), and provisions of Section 401 of the Clean Water Act (P.L.95-17). BULK LIQUID EXPORT TERMINAL FACILITY WITHIN AND ALONG THE MISSISSIPPI RIVER IN PLAQUEMINES PARISH NAME OF APPLICANT: Plaquemines Port and Harbor Terminal District, c/o Coastal Engineering Solutions, Post Office Box 80735, Baton Rouge, Louisiana 70898. LOCATION OF WORK: Project site is located within and along the right descending bank of the Mississippi River, at about mile 61 above Head of Passes, at 16111 Louisiana State Highway 23, in Myrtle Grove, Louisiana, in Plaquemines Parish, as shown on the attached drawings. Latitude: 29.6611

Longitude: -89.9675

Hydrologic Unit Codes: 08090100 Lower Mississippi River - New Orleans and 080900301 East Central Louisiana Coastal. CHARACTER OF WORK: Clear, grade, excavate, and deposit fill for a 200 acre bulk liquid export terminal facility including: tank storage area/s with supporting infrastructure, dock, additional rail spurs, and rail off-loading facility. Project implementation will require excavation and deposition of 150,250 cubic yards of native material, 14,000 cubic yards of rock, 65,500 cubic yards of crushed stone or gravel, and 20 cubic yards of concrete.

The proposed 200 acre parcel was originally part of Department of the Army permit authorization for RAM Terminals, LLC. Currently proposed project design would directly impact 19.6 acres of jurisdictional wetlands; 3.7 acres of the proposed direct impacts to jurisdictional wetlands have been compensated for through the previous Department of the Army authorization. The applicant proposes to contract with an approved mitigation bank in order to offset unavoidable adverse impacts to jurisdictional wetlands. The proposed liquid export facility is located in the vicinity of the Mid-Barataria Sediment Diversion proposal. The comment period for the Department of the Army Permit and the Louisiana Department of Environmental Quality WQC will close 30 days from the date of this joint public notice. Written comments, including suggestions for modifications or objections to the proposed work, stating reasons thereof, are being solicited from anyone having interest in this permit and/or this WQC request and must be mailed so as to be received before or by the last day of the comment period. Letters concerning the Corps of Engineers permit application must reference the applicant's name and the Permit Application Number, and be mailed to the Corps of Engineers at the address above, ATTENTION: REGULATORY BRANCH. The application for this proposed project is on file with the Louisiana Department of Environmental Quality and may be examined during weekdays between 8:00 a.m. and 4:30 p.m. Copies may be obtained upon payment of costs of reproduction. Corps of Engineers Permit Criteria The decision whether to issue a permit will be based on an evaluation of the probable impacts, including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people. The U.S. Army Corps of Engineers is soliciting comments from the public, federal, state, and local agencies and officials, Indian Tribes, and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the U.S. Army Corps of Engineers to determine whether to make, modify, condition, or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

The New Orleans District is aware of two sites (16PL107 and 16PL269) near the proposed work. The possibility exists that the proposed work may damage or destroy presently unknown archeological, scientific, prehistorical, historical sites, or data. Issuance of this public notice solicits input from the State Archeologist and State Historic Preservation Officer regarding potential impacts to cultural resources. The New Orleans District has determined that the proposed project is located in waters known to be utilized by the Pallid Sturgeon (Scaphirhynchus albus) and it has been determined that the proposed activity is not likely to adversely affect the species based on the Standard Local Operating Procedure for Endangered Species of Louisiana (SLOPES), dated October 22, 2014, between the U.S. Army Corps of Engineers and U.S. Fish and Wildlife Service, Ecological Services Office. Our initial finding is that the proposed work would not affect any species, nor affect any habitat designated as critical to the survival and recovery of such species, listed as endangered by the U.S. Department of Commerce. This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the MagnusonStevens Fishery Conservation and Management Act. The applicant's proposal would result in the destruction or alteration of 19.6 acres of EFH utilized by various life stages of red drum and penaeid shrimp. Our initial determination is that the proposed action would not have a substantial adverse impact on EFH or federally managed fisheries in the Gulf of Mexico. Our final determination relative to project impacts and the need for mitigation measures is subject to review by and coordination with the National Marine Fisheries Service. If the proposed work involves deposits of dredged or fill material into navigable waters, the evaluation of the probable impacts will include the application of guidelines established by the Administrator of the Environmental Protection Agency. Also, a certification that the proposed activity will not violate applicable water quality standards will be required from the Department of Environmental Quality, Water Quality Certifications, before a permit is issued. Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. Requests for public hearings shall state, with particularity, the reasons for holding a public hearing. The applicant has certified that the proposed activity described in the application complies with and will be conducted in a manner that is consistent with the Louisiana Coastal Resources Program. The Department of the Army permit will not be issued unless the applicant received approval or a waiver of the Coastal Use Permit by the Department of Natural Resources. You are requested to communicate the information contained in this notice to any other parties whom you deem likely to have interest in the matter.

Michael V. Farabee Chief, Eastern Evaluation Section

Enclosure

PLAQUEMINES LIQUID TERMINAL JOINT PERMIT APPLICATION

PLAQUEMINES PARISH, LA AUGUST 2018

N

INDEX OF SHEETS SHEET NO. 01 02 03 04 05 06 07 08 09 10 11 12 13 14

DESCRIPTION COVER SHEET VICINITY MAP BOUNDARY SURVEY SITE PLAN SITE PLAN WITH AERIAL TANK FARM CROSS SECTION LEVEE CROSSING PLAN LEVEE CROSSING SECTIONS LEVEE CRANE PAD AND TRUSS STAGING AREA DOCK PLAN VIEW DOCK APPROACH CROSS SECTION DOCK CROSS SECTION MOORING CROSS SECTION DETAILS

M:\Department 39\Admin\GIS Engineering CAD Dept\Images\Louisiana Maps\louisiana-map.GIF

PROJECT VICINITY

VICINITY MAP NOT TO SCALE

N

5000'

0'

5000'

10000'

15000'

N

PROJECT VICINITY NOT TO SCALE

REVISIONS No.

Description

Date

N

PLAQUEMINES LIQUID TERMINAL

VICINITY MAP

Project number 6000'

0'

6000'

12000'

18000'

APRIL 2018

Date Designed by Drawn by Checked by Checked by

August 29, 2018

Plot Date

2

175' (TYP.)

PHILLIPS 66

RAIL OFFLOADING FACILITY ALLIANCE REFINERY 1,460 LF x 365' LF

N

E. RAVENNA RD A

LA HWY 23

175' SETBACK

REVISIONS

RAILROAD TRACKS ( F-I)

No.

Description

Date

1,500 SETB ' ACK

CONST ACCES RUCTION x 20 LF S (4,170± LF B ROAD) DIRT PIPE (SEE RACK SHEE T 9)

CONSTRUCTION ACCESS

C

RAILROAD TRACKS (A-E)

DOCK (SEE SHEETS 10-14)

D

SECTION 10/ WETLAND IMPACT

ION

RS ION DIVE T T A N V E XCA DIM OF E AND FILL TARIA SE S T I LIM ARA

175' (TYP.)

SED ROPO

MIDB

LIMITS OF FILL

P 175' .) (TYP

PLAQUEMINES LIQUID TERMINAL

800'

0'

800'

1600'

2400'

SITE PLAN Project number

APRIL 2018

Date Designed by

*WETLAND POLYGONS IMPACTED WETLANDS

MITIGATED WETLANDS

A

11.67 AC

2.06 AC

B

1.40 AC

1.40 AC

C

0.12 AC

0.24 AC

D

6.47 AC

0.0 AC

Drawn by Checked by Checked by

August 29, 2018

Plot Date

4

175' (TYP.)

PHILLIPS 66 ALLIANCE REFINERY

RAIL OFFLOADING FACILITY 1,460 LF x 365 LF

N

E. RAVENNA RD

LA HWY 23

175' SETBACK

REVISIONS

RAILROAD TRACKS ( F-I)

No.

Description

Date

1,500 SETB ' ACK

CONST ACCES RUCTION x 20 LF S (4,170± LF ROAD) DIRT PIPE (SEE RACK SHEE T 9)

CONSTRUCTION ACCESS

RAILROAD TRACKS (A-E)

DOCK (SEE SHEETS 10-14) ION

RS ION DIVE T 175' (TYP.) T A N V E XCA DIM OF E AND FILL TARIA SE S T I RA LIM IDBA DM

OSE PROP

SECTION 10/ WETLAND IMPACT LIMITS OF FILL

175' (TYP .)

PLAQUEMINES LIQUID TERMINAL

800'

0'

800'

1600'

2400'

SITE PLAN WITH AERIAL

Project number

APRIL 2018

Date Designed by Drawn by Checked by Checked by

August 29, 2018

Plot Date

5

REVISIONS No.

Description

Date

(2) 60' X 1800' UNLOAD SHEDS (SEE SHEET 15) N

R TA RA BA ON MID RSI ED VE OS DI OP NT PR DIME SE

1,500 LF SETBACK

RAIL OFFLOADING FACILITY (1,460' X 365')

IA PLAQUEMINES LIQUID TERMINAL

E. RAVENNA RD PHILLIPS 66 ALLIANCE REFINERY

W LA H

Y 23 SITE PLAN CROSS SECTION

CONSTRUCTION ACCESS (4,170± LF x 20 LF DIRT ROAD) 1000'

0'

1000'

2000'

Project number

APRIL 2018

Date

3000'

Designed by Drawn by Checked by Checked by

EXISTING GROUND PROPOSED CONTAINMENT DIKE

ELEVATION (FT.) -2.0 +1.0

VOLUME (CUYD) 150,250

August 29, 2018

Plot Date

6

NOTE: THE IMAGE ABOVE IS A GENERAL REPRESENTATION OF THE WORK AREA, ACTUAL FIELD CONDITIONS MAY DIFFER. DATUM: NADV 88

No.

REVISIONS Description

Date

PLAQUEMINES LIQUID TERMINAL

August 29, 2018

LEVEE CROSSING PLAN

Project number Date Designed by Drawn by Checked by

Plot Date

Checked by

7

NOTE: THE IMAGE ABOVE IS A GENERAL REPRESENTATION OF THE WORK AREA, ACTUAL FIELD CONDITIONS MAY DIFFER. DATUM: NADV 88

No.

REVISIONS Description

Date

PLAQUEMINES LIQUID TERMINAL

August 29, 2018

LEVEE CROSSING SECTIONS Project number Date Designed by Drawn by Checked by

Plot Date

Checked by

8

REVISIONS No.

Description

Date

PLAQUEMINES LIQUID TERMINAL

LEVEE CRANE PAD AND TRUSS STAGING AREAS Project number Date

NOTE: THE IMAGE ABOVE IS A GENERAL REPRESENTATION OF THE WORK AREA, ACTUAL FIELD CONDITIONS MAY DIFFER. DATUM: NADV 88

Designed by Drawn by Checked by Checked by

August 29, 2018

Plot Date

9

REVISIONS No.

Description

Date

THIS DOCUMENT IS THE PROPERTY OF GRAND ISLE SHIP YARD ("GISY"). IT MAY CONTAIN INFORMATION DESCRIBING TECHNOLOGY OWNED BY GISY AND DEEMED TO BE COMMERCIALLY SENSITIVE. IT IS TO BE USED ONLY IN CONNECTION WITH WORK BEING PERFORMED BY GISY OR APPROVED CONTRACTOR. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN WORK PERFORMED BY GISY OR APPROVED CONTRACTOR IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF GISY. IT IS TO BE SAFEGUARDED AGAINST BOTH DELIBERATE AND INADVERTENT DISCLOSURE TO ANY THIRD PARTY.

PLAQUEMINES LIQUID TERMINAL

DOCK PLAN

39145-1104

Project number

APRIL 2018

Date

NOTE: THE IMAGE ABOVE IS A GENERAL REPRESENTATION OF THE WORK AREA, ACTUAL FIELD CONDITIONS MAY DIFFER. DATUM: NADV 88

Designed by

GIS

Drawn by

GIS

Checked by

BJ

Checked by

ST August 30, 2018

Plot Date

10

REVISIONS No.

Description

Date

PLAQUEMINES LIQUID TERMINAL

DOCK APPROACH CROSS SECTION Project number Date

NOTE: THE IMAGE ABOVE IS A GENERAL REPRESENTATION OF THE WORK AREA, ACTUAL FIELD CONDITIONS MAY DIFFER. DATUM: NADV 88

Designed by Drawn by Checked by Checked by

August 29, 2018

Plot Date

11

NOTE: THE IMAGE ABOVE IS A GENERAL REPRESENTATION OF THE WORK AREA, ACTUAL FIELD CONDITIONS MAY DIFFER. DATUM: NADV 88

13-190

No.

REVISIONS Description

Date

PLAQUEMINES LIQUID TERMINAL

August 29, 2018

DOCK CROSS SECTION

Project number Date Designed by Drawn by Checked by

Plot Date

Checked by

12

REVISIONS No.

Description

Date

PLAQUEMINES LIQUID TERMINAL

MOORING CROSS SECTION Project number Date

NOTE: THE IMAGE ABOVE IS A GENERAL REPRESENTATION OF THE WORK AREA, ACTUAL FIELD CONDITIONS MAY DIFFER. DATUM: NADV 88

Designed by Drawn by Checked by Checked by

August 29, 2018

Plot Date

13

REVISIONS No.

Description

Date

PLAQUEMINES LIQUID TERMINAL

REVETMENT REPAIR DETAILS Project number

APRIL 2018

Date Designed by Drawn by Checked by Checked by

August 29, 2018

Plot Date

14

REVISIONS No.

Date

N

(2) 60' X 1800' UNLOAD SHEDS (SEE SHEET 15)

Description

R TA RA BA ON MID RSI ED VE OS DI OP NT PR DIME SE

1,500 LF SETBACK RAIL OFFLOADING FACILITY

IA

E. RAVENNA RD PHILLIPS 66 ALLIANCE REFINERY

LA H

3

WY 2

CONSTRUCTION ACCESS (4,170± LF x 20 LF DIRT ROAD) 1000'

0'

1000'

2000'

3000'

PLAQUEMINES LIQUID TERMINAL

RAIL CROSS SECTION

Project number

APRIL 2018

Date Designed by Drawn by Checked by Checked by

August 30, 2018

Plot Date

15

REVISIONS No.

Description

Date

PLAQUEMINES LIQUID TERMINAL

TYPICAL RAIL DETAILS Project number

APRIL 2018

Date

NOTE: THE IMAGE ABOVE IS A GENERAL REPRESENTATION OF THE WORK AREA, ACTUAL FIELD CONDITIONS MAY DIFFER.

Designed by Drawn by Checked by Checked by

August 29, 2018

Plot Date

16

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas