This notice announces a Prospectus that has been submitted for the development of the Redstone Arsenal Mitigation Bank pursuant to 33 CFR 332, Compensatory Mitigation for Losses of Aquatic Resources (Federal Register: April 10, 2008, effective June 9, 2008).

Public Notice No. 18-38 Nashville District Date: September 13, 2018 Application No. LRN-2018-00664

Please address comments to: Nashville District Corps of Engineers, Regulatory Division

3701 Bell Road, Nashville, TN 37214-2660 SUBJECT: This notice announces a Prospectus that has been submitted for the development of the Redstone Arsenal Mitigation Bank pursuant to 33 CFR 332, Compensatory Mitigation for Losses of Aquatic Resources (Federal Register: April 10, 2008, effective June 9, 2008).

BANK SPONSOR: U.S. Army Garrison, Redstone Arsenal

ATTN: Jeff Duke - CEC, Inc. 325 Seaboard Ln, Ste. 170

Franklin, TN 37067

LOCATION: The proposed mitigation bank is located on Redstone Arsenal, a 37,910-acre federally owned facility in Huntsville, Madison County, Alabama (Latitude N 34.586516, Longitude W -86.675226). The proposed mitigation bank would rehabilitate 3,765 linear feet of unnamed tributaries to the Tennessee River, and enhance and preserve 121.38 acres of wetlands adjacent to the Tennessee River.

PURPOSE: The Redstone Arsenal Mitigation Bank proposes to provide compensatory stream and wetland mitigation credits for permitted impacts within a primary service area comprised of the Redstone Arsenal Base within the Wheeler Lake watershed (HUC 06030002). The Bank has not proposed a

secondary service area.

GENERAL INFORMATION: Mitigation banks are defined as a site, or suite of sites, where aquatic resources (e.g., wetlands, streams, riparian areas) are restored, established, enhanced, and/or preserved for the purpose of providing compensatory mitigation for impacts authorized by Department of the Army (DA) permits pursuant to Section 10 of the Rivers and Harbors Act of 1899 and/or Section 404 of the Clean Water Act. In general, units of restored, established, enhanced or preserved wetlands or streams are expressed as “credits” which may subsequently be withdrawn to offset “debits” incurred at a permitted project site. In this way, a permit requirement to provide compensatory mitigation can be transferred to the mitigation bank sponsor. The operation and use of a mitigation bank are governed by an approved mitigation banking instrument (MBI). The MBI is the legal document for the establishment, operation and use of a mitigation bank. This bank is intended to be a private commercial bank. The sponsor would be responsible for the successful development of the mitigation bank including monitoring and reporting requirements.

A group of federal and state regulatory and resource agency representatives known as the Interagency Review Team (IRT) would oversee the establishment and management of the bank. The IRT is chaired by the US Army Corps of Engineers, Nashville District (USACE). The primary role of the IRT is to facilitate establishment of the mitigation bank through the development of a MBI. The IRT will review the prospectus, instrument, and other appropriate documents and provide comments to the USACE.

Approval of the use of the bank for specific projects is the decision of the USACE pursuant to Section 10 of the Rivers and Harbors Act of 1899 and/or Section 404 of the Clean Water Act and/or the Alabama Department of Environmental Management (ADEM) pursuant to Section 401 of the CWA and/or applicable state of Alabama statute(s) and regulation(s). The USACE and ADEM provide no guarantee that any particular individual or general permit would be authorized to use the bank for compensation.

PROJECT DESCRIPTION: A portion of the Redstone Arsenal Mitigation Bank was originally permitted as a compensatory mitigation site for wetland impacts associated with improvements to Martin Road, and an Advanced Credit Wetland Mitigation Site for future impacts that may occur in association with

Redstone Arsenal. The site was constructed, but following completion of construction and planting, no subsequent monitoring or maintenance was performed, which resulted in no generation of future credits and a cease in operation of the Advanced Credit Wetland Mitigation Site.

The goal of the Redstone Arsenal Mitigation Bank is to bring the original compensatory mitigation site into compliance with the 2008 Compensatory Mitigation Rule and create a single-user mitigation bank for Redstone Arsenal. This will involve new hydrologic modifications and replanting of some areas with appropriate species based on proposed habitat types. This modification will capture additional areas of stream restoration and wetland enhancement that

were not included in the original permit.

Stream functional uplift is proposed to be provided through improvement of stream hydrology, reduction of streambank erosion, improvement to aquatic and terrestrial habitat, and improvement to riparian stream buffers. Wetland functional uplift is proposed to be provided through restoration of wetland hydrology and improvement to aquatic habitat. The proposed stream mitigation approach involves restoration of 3,765 linear feet of stream channel. The proposed wetland mitigation approach involves enhancement of 44.33 acres of wetland and preservation of 77.05 acres of wetland.

Details of the mitigation plan are contained in the Prospectus for Redstone Arsenal Mitigation Bank dated July 2018. The plan can be viewed by emailing Ms. Peyton Abernathy at: Peyton.S.Abernathy@usace.army.mil.

HISTORIC AND CULTURAL RESOURCES: A search of the National Register returned no findings of historic properties currently listed on the National Register of Historic Places within the project area. A Phase I cultural/archaeological survey has not been conducted for the site. At this early stage in the regulatory process, no project design plans have been submitted; therefore, USACE cannot yet complete an effects determination for historic and cultural resources. The USACE invites responses to this public notice from American Indian Tribes or tribal governments; Federal, State, and local agencies; historical and archeological societies; and other parties likely to have knowledge or concerns regarding historic properties and cultural significance at or near the

project area. Upon submittal of the design plans, USACE would evaluate the design plans along with any substantive comments from this public notice to determine the potential to effect historic and cultural resources in compliance with Section 106 of the National Historic Preservation Act. If USACE determines that consultation is required, consultation with the Alabama Historic Commission State Historic Preservation Officer (SHPO), and American Indian Tribes will follow, as appropriate.

ENDANGERED/THREATENED SPECIES REVIEW: A review of the United States Fish and Wildlife Service (USFWS) website, http://ecos.fws.gov/ipac identified the following federally-listed species that are known to occur or believed to occur in Madison County, Alabama:

Species Nomenclature

Federal Status

Mammals

Indiana Bat (Myotis sodalist)

Endangered

Gray Bat (Myotis grisescens)

Endangered

Northern Long-eared Bat (Myotis septentrionalis)

Threatened

Clams

Pink Mucket (pearlymussel) (Lampsilis abrupta)

Endangered

Rough Pigtoe (Pleurobema plenum)

Endangered

Sheepnose Mussel (Plethobasus cyphyus)

Endangered

Snuffbox Mussel (Epioblasma triquetra)

Endangered

Spectaclecase (mussel) (Cumberlandia monodonta)

Endangered

Crustaceans

Alabama Cave Shrimp (Palaemonias alabamae)

Endangered

Flowering Plants

Price's Potato-bean (Apios priceana)

Threatened

A copy of this notice is being furnished to USFWS for their review. After receipt of any comments, the USACE will evaluate the potential effects to proposed and/or listed species and their designated critical habitat, and initiate consultation with the U.S. Fish & Wildlife Service, if required.

COMMENT PERIOD: Written statements received in this office within 30 days from the date of this notice will become part of the record and will be considered in the determination. Any response to this notice should be directed to the Nashville District Corps of Engineers, Regulatory Division, Attention: Peyton S. Abernathy at the above address or via email: Peyton.S.Abernathy@usace.army.mil.

\s\

Joshua W. Frost

Chief, Technical Services Branch Regulatory Division

U.S. Army Corps of Engineers

\\SVR-NASH\ P:\2017\173-738\-GIS\Maps\Final_Maps\173-738_Fig_1_Land_Ownership.mxd (4/24/2018 10:29:04 AM)

Public Notice 18-38 File No. LRN-2018-00664 Exhibit A

NOTE: ALL SURROUNDING LAND IS OWNED BY THE U.S. GOVERNMENT.

LEGEND

Conservation Easement Boundary

REDSTONE ARSENAL MITIGATION BANK MODIFIED PROSPECTUS HUNTSVILLE, MADISON COUNTY, AL

SCALE IN FEET 0

REFERENCE

1,000

2,000

325 Seaboard Lane, Suite 170 Franklin,Tennessee 37067 615-333-7797 800-763-2326 www.cecinc.com

ESRI WORLD IMAGERY / ARCGIS MAP SERVICE: HTTP://GOTO.ARCGISONLINE.COM/MAPS/W ORLD_IMAGERY, DRAWN BY: ACCESSED 4/24/2018, DATE:

BCL 4/24/2018

CHECKED BY: SCALE:

CAD 1 " = 1,000 '

LAND OWNERSHIP MAP APPROVED BY: PROJECT NO:

JTD

* Hand signature on file

173-738

FIGURE NO:

1

Public Notice 18-38 File No. LRN-2018-00664 Exhibit B

Existing Stream ~3,593 ft.

Existing Culvert

Second Growth Forest/ Scrub-Shrub Wetland Mix ~30.07 ac. Failed Water Control Structure

( &

(4) Spoil Piles ~0.25 ac

Emergent Wetland ~1.04 ac

Upland Buffer ~90.22 ac

Open Water ~9.31 ac

Emergent Wetland ~8.06 ac.

Tupelo Gum Swamp ~63.87 ac

Spoil Pile Forested Wetland

Forested Wetland ~6.99 ac

Emergent Wetland Open Water Road

Failed Water Control Structure

Second Growth Forested/Scrub-Shrub Mix

( &

Tupelo Gum Swamp

Open Water ~6.71 ac.

Upland Existing Stream Existing Culvert

( &

Water Control Structure

Water Control Structure

Scrub-Shrub Wetland ~7.77 ac

M "& J

Conservation Easement Boundary

Emergency Spillway

Upland Island ~0.57 ac

Existing Road Crossing

Forested Wetland Emergent Wetland

Existing Earthen Berm

Scrub-Shrub Wetland Upland Island

Emergent Wetland ~0.59 ac

Upland Buffer Existing Ditch

Forested Wetland ~20.72 ac

Existing Earthen Berm

Existing Ditch

Existing Road crossing

" J M &

Emergency Spillway Water Control Structure

REDSTONE ARSENAL MITIGATION BANK MODIFIED PROSPECTUS HUNTSVILLE, MADISON COUNTY, AL

SCALE IN FEET 0

1,000

2,000

325 Seaboard Lane, Suite 170 Franklin,Tennessee 37067 615-333-7797 800-763-2326 www.cecinc.com ESRI WORLD IMAGERY / ARCGIS MAP SERVICE: HTTP://GOTO.ARCGISONLINE.COM/MAPS/WORLD_IMAGERY, DRAWN BY: ACCESSED 7/2/2018, DATE:

BCL 7/2/2018

CHECKED BY: SCALE:

CAD 1 " = 1,000 '

EXISTING AQUATIC RESOURCES MAP APPROVED BY: PROJECT NO:

JTD

* Hand signature on file

173-738

FIGURE NO:

Public Notice 18-38 File No. LRN-2018-00664 Exhibit C

Conservation Easement Boundary

Ad - Abernathy-Emory Silt Loam (Non-Hydric) Al - Allen Clay Loam (Hydric Inclusion) Cb - Captina and Capshaw Silt Loam (Hydric Inclusion) De - Decatur Silty Clay (Non-Hydric) Eg - Egam Silty Clay Loam (Hydric Inclusion) Ex - Etowah Silt Loam (Hydric Inclusion) Ey - Etowah Silty Clay Loam (Hydric Inclusion) Hz - Huntington Silt Loam (Hydric Inclusion) Lk - Lindside Silty Clay Loam (Hydric Inclusion) Me - Melvin Silty Clay Loam (Hydric) Op - Ooltewah Silt Loam (Hydric) Pr - Prader Fine Sandy Loam (Hydric) Ro - Robertsville Silt Loam (Hydric) Tu - Tupelo Silt Loam (Hydric Inclusion) Wo; Wp - Wolftever Silt Loam (Hydric Inclusion) W - Water

REDSTONE ARSENAL MITIGATION BANK MODIFIED PROSPECTUS HUNTSVILLE, MADISON COUNTY, AL

SCALE IN FEET 0

1,000

2,000

ESRI WORLD IMAGERY / ARCGIS MAP SERVICE: HTTP://GOTO.ARCGISONLINE.COM/MAPS/W ORLD_IMAGERY, ACCESSED 4/24/2018, NRCS WEB SOIL SURVEY. ACCESSED 4/24/2018,

325 Seaboard Lane, Suite 170 Franklin,Tennessee 37067 615-333-7797 800-763-2326 www.cecinc.com DRAWN BY: DATE:

BCL 4/24/2018

CHECKED BY: SCALE:

CAD 1 " = 1,000 '

NRCS SOILS MAP APPROVED BY:JTD PROJECT NO:

* Hand signature on file

173-738

FIGURE NO:

Public Notice 18-38 File No. LRN-2018-00664 Exhibit D

Conservation Easement Boundary Estuarine and Marine Deepwater Estuarine and Marine Wetland Freshwater Emergent Wetland Freshwater Forested/Shrub Wetland Freshwater Pond Lake Other Riverine SCALE IN FEET 0

1,000

REDSTONE ARSENAL MITIGATION BANK MODIFIED PROSPECTUS HUNTSVILLE, MADISON COUNTY, AL

2,000

325 Seaboard Lane, Suite 170 Franklin,Tennessee 37067 615-333-7797 800-763-2326 www.cecinc.com

ESRI WORLD IMAGERY / ARCGIS MAP SERVICE: HTTP://GOTO.ARCGISONLINE.COM/MAPS/W ORLD_IMAGERY, ACCESSED 4/24/2018, U.S. FISH & WILDLIFE SERVICE NATIONAL WETLANDS INVENTORY (NWI) MAP. ACCESSED 4/24/2018,

DRAWN BY: DATE:

BCL 4/24/2018

CHECKED BY: SCALE:

CAD 1 " = 1,000 '

NATIONAL WETLANDS INVENTORY MAP APPROVED BY:JTD PROJECT NO:

* Hand signature on file

173-738

FIGURE NO:

Public Notice 18-38 File No. LRN-2018-00664 Exhibit E

Proposed Low-ford Crossing

Stream Restoration ~3,765 ft.

Wetland Enhancement Area-4 ~26.44 ac.

Upland Buffer Preservation ~90.22 ac

Open Water Preservation ~9.31 ac

Wetland Habitat Enhancement Area-3 ~8.06 ac.

Tupelo Gum Swamp Preservation ~63.87 ac

Wetland Enhancement Area-2 ~3.12 ac.

Forested Wetland Preservation ~3.87 ac Wetland Enhancement Area-1 ~6.71 ac.

Proposed Scrub-Shrub

Tupelo ~8.07 ac

Proposed Supplemental Oak and Hickory Planting

Earthen Berm Elevation: 560.5'

Proposed Tupelo Forested Wetland to Remain

Earthen Berm Elevation: 562'

Scrub-Shrub ~0.93 ac

Upland Buffer Preservation

Upland Island ~0.57 ac

Repair Existing Road Crossing

Upland Buffer Hardwood Planting Upland Island to Remain

Supplemental Oak and Hickory Planting ~6.65 ac

Proposed Low-ford Crossing

Upland Buffer Hardwoods Planting ~1.74 ac

Wetland Enhancement Wetland Preservation

Fill Existing Ditch

Forested Wetland to Remain ~20.72 ac

Upland Buffer Preservation Proposed Stream Restoration 25 ft. Stream Buffer Conservation Easement Boundary

REDSTONE ARSENAL MITIGATION BANK MODIFIED PROSPECTUS HUNTSVILLE, MADISON COUNTY, AL

SCALE IN FEET 0

1,000

2,000

325 Seaboard Lane, Suite 170 Franklin,Tennessee 37067 615-333-7797 800-763-2326 www.cecinc.com USGS TOPOGRAPHIC MAP/ ARCGIS MAP SERVICE: HTTP://GOTO.ARCGISONLINE.COM/MAPS/USA_TOPO_MAPS, ACCESSED 7/3/2018

DRAWN BY: DATE:

BCL 7/3/2018

CHECKED BY: SCALE:

CAD 1 " = 1,000 '

CONCEPTUAL MITIGATION TOPOGRAPHIC MAP APPROVED BY: PROJECT NO:

JTD

* Hand signature on file

173-738

FIGURE NO:

Public Notice 18-38 File No. LRN-2018-00664 Exhibit F

Proposed Low-ford Crossing

Stream Restoration ~3,765 ft.

Wetland Enhancement Area-4 ~26.44 ac.

Upland Buffer Preservation ~90.22 ac

Open Water Preservation ~9.31 ac

Wetland Habitat Enhancement Area-3 ~8.06 ac.

Tupelo Gum Swamp Preservation ~63.87 ac

Wetland Enhancement Area-2 ~3.12 ac.

Forested Wetland Preservation ~3.87 ac Wetland Enhancement Area-1 ~6.71 ac.

Proposed Scrub-Shrub

Tupelo ~8.07 ac

Proposed Supplemental Oak and Hickory Planting

Earthen Berm Elevation: 560.5'

Proposed Tupelo Forested Wetland to Remain

Earthen Berm Elevation: 562'

Scrub-Shrub ~0.93 ac

Upland Buffer Preservation

Upland Island ~0.57 ac

Repair Existing Road Crossing

Upland Buffer Hardwood Planting Upland Island to Remain

Supplemental Oak and Hickory Planting ~6.65 ac

Proposed Low-ford Crossing

Upland Buffer Hardwoods Planting ~1.74 ac

Wetland Enhancement Wetland Preservation

Fill Existing Ditch

Forested Wetland to Remain ~20.72 ac

Upland Buffer Preservation Proposed Stream Restoration 25 ft. Stream Buffer Conservation Easement Boundary

REDSTONE ARSENAL MITIGATION BANK MODIFIED PROSPECTUS HUNTSVILLE, MADISON COUNTY, AL

SCALE IN FEET 0

1,000

2,000

325 Seaboard Lane, Suite 170 Franklin,Tennessee 37067 615-333-7797 800-763-2326 www.cecinc.com ESRI WORLD IMAGERY / ARCGIS MAP SERVICE: HTTP://GOTO.ARCGISONLINE.COM/MAPS/WORLD_IMAGERY, DRAWN BY: ACCESSED 7/3/2018, DATE:

BCL 7/3/2018

CHECKED BY: SCALE:

CAD 1 " = 1,000 '

CONCEPTUAL MITIGATION AERIAL MAP APPROVED BY: PROJECT NO:

JTD

* Hand signature on file

173-738

FIGURE NO:

Public Notice 18-38 File No. LRN-2018-00664 Exhibit G

_ ^

_ ^

Site Location Service Area

ESRI WORLD STREET MAP / ARCGIS MAP SERVICE: HTTP://GOTO.ARCGISONLINE.COM/MAPS/WORLD_STREET_MAP, ACCESSED 6/29/2018, IMAGERY DATE: 2014.

REDSTONE ARSENAL WETLAND MITIGATION BANK HUNTSVILLE, MADISON COUNTY, ALABAMA 325 Seaboard Lane, Ste. 170 Franklin, Tennessee 615-333-7797 800-763-2326 www.cecinc.com DRAWN BY: DATE:

BCL CHECKED BY: 6/29/2018 SCALE:

SERVICE AREA MAP JTD APPROVED BY: CEC

1 " = 3 miles

PROJECT NO:

* Hand signature on file

174-738

FIGURE NO:

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas