Home

New Orleans District

Run scraper

CPRA CSC Salinity Control project

Basic information

Fill out these two fields at minimum.

— or —

How Big?

Where?

Links to source documents

Raw text

You can copy from here when filling out the rest of the page.

CALCASIEU SALINITY CONTROL MEASURES PROJECT IN CALCASIEU PARISH

NAME OF APPLICANT: Louisiana Coastal Protection and Restoration Authority, Post Office Box 44027, Baton Rouge, Louisiana, 70804-4027. LOCATION: Project located at approximately Latitude 29.85861, Longitude -93.34694, on the Calcasieu Ship Channel, in the community of Lake Charles, within Calcasieu Parish, Louisiana. The Project is located within the Calcasieu Watershed, Hydrologic Unit 08080206. DESCRIPTION: The applicant proposes construction of structures designed to control saltwater entering Calcasieu Lake through the Calcasieu Ship Channel. Structures would control salinity spikes, provide storm surge benefits, and would be constructed in a manner that would allow for the continued functioning, improvement and viability of the Calcasieu Ship Channel and the Port of Lake Charles. The purpose of the proposed project is to manage the introduction of saline water from the Calcasieu Ship Channel into adjacent water bodies thereby reducing the rate of wetland loss in the project area and surrounding wetlands. To achieve, in part, the goals in the 2012 Louisiana State Master Plan, the proposed project is needed to address modifications to hydrology that have caused an increase in salinity within the project area, resulting in loss of wetlands. This project, as proposed, should achieve the following: (1) manage salinity levels in Calcasieu Lake and adjacent marshes to maintain marsh productivity and avoid marsh collapse; (2) minimize the economic impact to the navigation industry caused by potential delays in travel times resulting from any structures or modifications to the ship channel and avoid actions that cause safety issues for vessel operation; (3) achieve salinity management with minimal changes to the magnitude, frequency, duration, or extent of flood conditions in the project area. The project study area has undergone substantial land loss since 1932. The present-day Calcasieu Ship Channel cross section is more than 40 times larger than when it was first dredged for navigation in the late 1800s. This change has affected hydrology by: channeling saltwater inland into a historically low-salinity estuary; reducing freshwater residence time when the tide ebbs; and, increasing tidal amplitude through the broader waterway. Approximately 866,160 cubic yards (cy) of material would be excavated and redeposited onsite, approximately 97,791 cy of material would be excavated and hauled offsite, and approximately 1,219,246 cy of rock material would be deposited onsite for project construction. The project would potentially affect 56,244 acres of wetlands and/or waterbottoms. Approximately 6 acres of vegetated wetlands between the water’s edge and tie-in locations of adjacent spoil banks would be permanently impacted by project construction. Additionally, the project would provide 30 acres of newly constructed artificial reef and, over the life of the project, an estimated 12,000 acres of marsh would be protection and sustained.

JOINT PUBLIC NOTICE September 17, 2018 United States Army Corps of Engineers New Orleans District Regulatory Branch 7400 Leake Avenue New Orleans, LA 70118-3651

State of Louisiana Department of Environmental Quality Post Office Box 4313 Baton Rouge, La. 70821-4313 Attn: Water Quality Certifications

(504) 862-2548/ FAX (504) 862-2574 Project Manager Johnny Duplantis Permit Application Number MVN-2016-00678-WPP

(225) 219-3225/FAX (225) 325-8125 Project Manager Elizabeth Hill WQC Application Number WQC # 180911-01

Interested parties are hereby notified that a permit application has been received by the New Orleans District of the U.S. Army Corps of Engineers pursuant to: [X] Section 10 of the Rivers and Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or [X] Section 404 of the Clean Water Act (86 Stat. 816; 33 USC 1344). Application has also been made to the Louisiana Department of Environmental Quality, for a Water Quality Certification (WQC) in accordance with statutory authority contained in Louisiana Revised Statutes of 1950, Title 30, Chapter 11, Part IV, Section 2074 A(3) and provisions of Section 401 of the Clean Water Act (P.L.95-17). CALCASIEU SALINITY CONTROL MEASURES PROJECT IN CALCASIEU PARISH NAME OF APPLICANT: Louisiana Coastal Protection and Restoration Authority, Post Office Box 44027, Baton Rouge, Louisiana, 70804-4027. LOCATION: Project located at approximately Latitude 29.85861, Longitude -93.34694, on the Calcasieu Ship Channel, in the community of Lake Charles, within Calcasieu Parish, Louisiana. The Project is located within the Calcasieu Watershed, Hydrologic Unit 08080206. DESCRIPTION: The applicant proposes construction of structures designed to control saltwater entering Calcasieu Lake through the Calcasieu Ship Channel. Structures would control salinity spikes, provide storm surge benefits, and would be constructed in a manner that would allow for the continued functioning, improvement and viability of the Calcasieu Ship Channel and the Port of Lake Charles. The purpose of the proposed project is to manage the introduction of saline water from the Calcasieu Ship Channel into adjacent water bodies thereby reducing the rate of wetland loss in the project area and surrounding wetlands. To achieve, in part, the goals in the 2012 Louisiana State Master Plan, the proposed project is needed to address modifications to hydrology that have caused an increase in salinity within the project area, resulting in loss of wetlands. This project, as proposed, should achieve the following: (1) manage salinity levels in Calcasieu Lake and adjacent marshes to maintain marsh productivity and avoid marsh collapse; (2) minimize the economic impact to the navigation industry caused by potential delays in travel times resulting from any structures or modifications to the ship channel and avoid actions that cause safety issues for vessel operation; (3) achieve salinity management with minimal changes to the magnitude, frequency, duration, or extent of flood conditions in the project area. The project study area has undergone substantial land loss since 1932. The present-day Calcasieu Ship Channel cross section is more than 40 times larger than

-2when it was first dredged for navigation in the late 1800s. This change has affected hydrology by: channeling saltwater inland into a historically low-salinity estuary; reducing freshwater residence time when the tide ebbs; and, increasing tidal amplitude through the broader waterway. Approximately 866,160 cubic yards (cy) of material would be excavated and redeposited onsite, approximately 97,791 cy of material would be excavated and hauled offsite, and approximately 1,219,246 cy of rock material would be deposited onsite for project construction. The project would potentially affect 56,244 acres of wetlands and/or waterbottoms. Approximately 6 acres of vegetated wetlands between the water's edge and tie-in locations of adjacent spoil banks would be permanently impacted by project construction. Additionally, the project would provide 30 acres of newly constructed artificial reef and, over the life of the project, an estimated 12,000 acres of marsh would be protection and sustained. The comment period for the Department of the Army Permit and the Louisiana Department of Environmental Quality WQC will close 20 days from the date of this joint public notice. Written comments, including suggestions for modifications or objections to the proposed work, stating reasons thereof, are being solicited from anyone having interest in this permit and/or this WQC request and must be mailed so as to be received before or by the last day of the comment period. Letters concerning the Corps of Engineers permit application must reference the applicant's name and the Permit Application Number, and be mailed to the Corps of Engineers at the address above, ATTENTION: REGULATORY BRANCH. Similar letters concerning the Water Quality Certification must reference the applicant's name and the WQC Application number and be mailed to the Louisiana Department of Environmental Quality at the address above. The application for this proposed project is on file with the Louisiana Department of Environmental Quality and may be examined during weekdays between 8:00 a.m. and 5:00 p.m. Copies may be obtained upon payment of costs of reproduction. Corps of Engineers Permit Criteria The decision whether to issue a permit will be based on an evaluation of the probable impacts, including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people. The U.S. Army Corps of Engineers is soliciting comments from the public, federal, state, and local agencies and officials, Indian Tribes, and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the U.S. Army Corps of Engineers to determine whether to make, modify, condition, or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

-3The New Orleans District is unaware of properties listed on the National Register of Historic Places near the proposed work. The possibility exists that the proposed work may damage or destroy presently unknown archeological, scientific, pre-historical, historical sites, or data. Copies of this notice are being sent to the State Archeologist and the State Historic Preservation Officer. Our initial finding is that the proposed work would neither affect any species listed as endangered by the U.S. Departments of Interior or Commerce, nor affect any habitat designated as critical to the survival and recovery of any endangered species. Based on the South Louisiana Standard Local Operating Procedure for Endangered Species (SLOPES), as signed on October 22, 2014, between the U.S. Army Corps of Engineers, New Orleans and the U.S. Fish and Wildlife Service, it has been determined that the project is located in waters known to be utilized by the Western Indian Manatee and determined that the activity is not likely to adversely affect this species. If this permit is issued, the permittee will be required to the follow the SLOPES Manatee conditions. This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the Magnuson-Stevens Fishery Conservation and Management Act. The applicant's proposal would result in the destruction or alteration of 56,244 acre(s) of EFH utilized by various life stages of red drum and penaeid shrimp. Our initial determination is that the proposed action would not have a substantial adverse impact on EFH or federally managed fisheries in the Gulf of Mexico. Our final determination relative to project impacts and the need for mitigation measures is subject to review by and coordination with the National Marine Fisheries Service. If the proposed work involves deposits of dredged or fill material into navigable waters, the evaluation of the probable impacts will include the application of guidelines established by the Administrator of the Environmental Protection Agency. Also, a certification that the proposed activity will not violate applicable water quality standards will be required from the Department of Environmental Quality, before a permit is issued. Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. Requests for public hearings shall state, with particularity, the reasons for holding a public hearing. The applicant has certified that the proposed activity described in the application complies with and will be conducted in a manner that is consistent with the Louisiana Coastal Resources Program. The Department of the Army permit will not be issued unless the applicant received approval or a waiver of the Coastal Use Permit by the Department of Natural Resources. You are requested to communicate the information contained in this notice to any other parties whom you deem likely to have interest in the matter.

Darrell S. Barbara Chief, Western Evaluation Section Regulatory Branch Enclosures

INDEX TO SHEETS

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

DESCRIPTION TITLE SHEET GENERAL NOTES ACCESS PLAN CROSS SECTIONS A - D EAST PASS WEST PASS CROSS SECTIONS E - F JOE'S CUT LAKE WALL KEY PLAN LAKE WALL 1 OF 3 LAKE WALL 2 OF 3 LAKE WALL 3 OF 3 NINE MILE CUT SILL DETAIL 1 POB: X: N29°53'54.55" SILL DETAIL 2 Y: W93°20'16.74" FISH PASSAGE TIE-IN DETAIL 1 TIE-IN DETAIL 2 TEMPORARY ACCESS CHANNEL

PROJECT LOCATION

CALCASIEU LAKE EAST PASS LAKE WALL POE: X: N29°50'18.01" Y: W93°20'39.19"

POE: X: N29°49'55.59" Y: W93°19'47.09" POB: X: N29°50'02.31" Y: W93°20'12.77" WEST PASS POB: X: N29°49'21.66" Y: W93°21'27.33"

POB: X: N29°53'21.39" Y: W93°20'55.68" NINE MILE CUT POE: X: N29°52'53.68" Y: W93°20'55.12" JOE'S CUT POB: X: N29°51'02.65" Y: W93°21'05.35" POE: X: N29°50'33.14" Y: W93°21'07.60"

APPLICATION BY:

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DRAWN BY: SPF

POE: X: N29°49'32.42" Y: W93°21'27.20"

CALCASIEU LAKE WEST COVE

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

DESIGNED BY:

LRM

APPROVED BY: BR

PRELIMINARY - FOR PERMIT PURPOSES ONLY

SHEET NO.

STATE OF LOUISIANA INSET MAP

TITLE SHEET

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 1 OF 19

GENERAL NOTES:

CDF CL, CSC D EG EL GIWW GPS LOC MHW MLG MLW NTS POB POE R REF REQ'D SIM SLL STA SYM TYP UON VERT W/

1. 2.

CONFINED DISPOSAL FACILITY CENTER LINE CALCASIEU SHIP CHANNEL DIAMETER EXISTING GRADE ELEVATION GULF INTRACOASTAL WATERWAY GLOBAL POSITIONING SYSTEM LOCATIONS MEAN HIGH WATER MEAN LOW GULF MEAN LOW WATER NOT TO SCALE POINT OF BEGINNING POINT OF ENDING RADIUS REFERENCE REQUIRED SIMILAR STRUCTURE LIMIT LINE STATION SYMMETRICAL TYPICAL UNLESS OTHERWISE NOTED VERTICAL WITH

3.

4.

5.

6.

LEGEND: 7. ACCESS CHANNEL ACCESS CORRIDOR TEMPORARY SPOIL PLACEMENT AREA

OVERALL QUANTITY SUMMARY

BACKGROUND IMAGERY BASED ON NAIP (2015). PLANS ARE BASED ON SURVEY CONDUCTED BY LONNIE HARPER & ASSOCIATES IN 2016 AND 2017, UNLESS STATED OTHERWISE. THE HORIZONTAL DATUM IS NAD 83, LOUISIANA SOUTH ZONE-STATE PLANE COORDINATE SYSTEM. THE VERTICAL DATUM IS NAVD88, GEOID 12B. THE UNITS ARE U.S. SURVEY FEET. THERE IS NO UPLAND ACCESS TO THE PROJECT SITE. CONTRACTOR SHALL ACCESS THE PROJECT SITE FROM A NAVIGABLE WATER BODY SUCH AS THE CALCASIEU SHIP CHANNEL. TEMPORARY ACCESS/FLOTATION CHANNEL DREDGING MAY BE REQUIRED TO ACCESS THE PROJECT SITE. ALL DREDGED MATERIAL MAY BE PLACED INTO THE TEMPORARY SPOIL PLACEMENT AREAS SHOWN. THE TEMPORARY SPOILS SHALL BE BACKFILLED INTO THE TEMPORARY ACCESS CHANNEL AT THE COMPLETION OF THE PROJECT. PERMANENT NAVIGATION AIDS TO BE LOCATED AND MARKED/LIGHTED IN ACCORDANCE WITH U.S. COAST GUARD REGULATIONS. AS-BUILT DRAWINGS AND/OR PLATS SHALL HAVE WRITTEN ON THEM THE DATE OF COMPLETION OF SAID ACTIVITIES AND SHALL BE SUBMITTED TO THE LOUISIANA DEPARTMENT OF NATURAL RESOURCES, OFFICE OF COASTAL MANAGEMENT, P.O. BOX 44487, BATON ROUGE, LA 70804-4487 WITHIN 30 DAYS FOLLOWING PROJECT COMPLETION. IN ORDER TO ENSURE THE SAFETY OF ALL PARTIES, THE PERMITTEE SHALL CONTACT THE LOUISIANA ONE CALL SYSTEM (1-800-272-3020) A MINIMUM OF 48 HOURS PRIOR TO THE COMMENCEMENT OF ANY EXCAVATION (DIGGING, DREDGING, JETTING, ETC.) OR DEMOLITION ACTIVITY.

APPLICATION BY:

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DESIGNED BY:

LRM

APPROVED BY: BR

QUANTITY 28,701 LF

WALL AREA

56.04 ACRES

ROCK VOLUME

1,219,246 CY

PERMANENT DREDGE AREA

29.31 ACRES

PERMANENT DREDGE VOLUME TEMPORARY ACCESS/FLOTATION DREDGING AREA TEMPORARY ACCESS/FLOTATION DREDGING VOLUME TEMPORARY SPOIL PLACEMENT AREA TEMPORARY ACCESS CORRIDOR AREA

95,791 CY 101.61 ACRES 886,160 CY 130.42 ACRES 11.61 ACRES

OVERALL ESTIMATED IMPACT TYPE PERMANENT IMPACTED VEGETATED WETLANDS TEMPORARY IMPACTED VEGETATED WETLANDS PERMANENT IMPACTED SUBMERGED BOTTOM TEMPORARY IMPACTED SUBMERGED BOTTOM

QUANTITY 5.29 ACRES 10.96 ACRES 50.19 ACRES 232.03 ACRES

OVERALL ESTIMATED BENEFITS TYPE

QUANTITY

DIRECT BENEFITS 50-YEAR PROTECTION

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

DRAWN BY: SPF

TYPE WALL LENGTH

GENERAL NOTES

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 2 OF 19

PRELIMINARY - FOR PERMIT PURPOSES ONLY

ACRONYMS AND ABBREVIATIONS:

2.

)&0$&02D1 ,#0*-#

2.

(*55

Calcasieu Lake We s t C o v e

Source: 2017 NAIP

31'51! 5&12!%.4& $.#2!+#3-%)

'&006 +#3-%) %?9C!$>7A!#889@@ %>=@A?B8A;>=!#889@@ /?><98A!'97AB?9

APPLICATION BY:

CALCASIEU SALINITY CONTROL MEASURES

TETRA TECH 748 MAIN STREET, SUITE B BATON ROUGE, LA 70802 150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DRAWN BY: HMC

DESIGNED BY:

BR

APPROVED BY: SDG

ACCESS PLAN

STATE PROJECT NUMBER: CS-65

DATE:

FEDERAL PROJECT NUMBER:

SHEET

3

OF 18

FILL W/ STONE

COMBI WALL BEYOND, SEE SECTION B

NOTES:

24" ROCK MATTRESS

1. 2. 3.

FILTER STONE d50 = 1.6', w50 = 685#

5.0' 3.0' FISH PASSAGE AND VESSEL SILL EL -8.0 BOTTOM OF MATTRESS EL -15.0

ALL SECTIONS SYM ABOUT CL PAINT TOP 10 FEET OF PILES. REFER TO TABLE FOR PILE SECTION AND TIP ELEVATION.

20.0'

MUD LINE 4H:1V PILE SECTIONS BEDDING STONE d50 = 0.4', w50 = 7# PZC13, TIP EL -35.0

A

SILL SECTION

60"x0.875" PIPE w/ TIP EL -85.0, PZC 13 w/ TIP EL -35.0

EAST PASS REACH B, MUD LINE EL -8.0 TO -23.0

48"x0.75" PIPE w/ TIP EL -65.0, PZC 13 w/ TIP EL -35.0

EAST PASS, REACH C & D

PZC 26, TIP EL -35.0

EAST PASS REACH B, MUD LINE EL -23.0 TO -28.0

48"x0.50" PIPE w/ TIP EL -65.0, PZC 13 w/ TIP EL -35.0

EAST PASS REACH B, MUD LINE EL -8.0 TO -23.0

42"x0.50" PIPE w/ TIP EL -55.0, PZC 13 w/ TIP EL -35.0

COMBI WALL

13.0' 3.0' 3.0'

FILTER STONE d50 = 1.6', w50 = 685# TOP OF BERM EL +5.0 3H:1V 3.0' 2H:1V 3.0' MUD LINE

2.0'

BEDDING STONE d50 = 0.3', w50 = 3#

B

10.0'

PZC 26, TIP EL -35.0

JOE'S CUT, REACH B

48"x0.50" PIPE w/ TIP EL -60.0, PZC 13 w/ TIP EL -35.0

TOP OF BERM EL +5.0

3H:1V 18" ROCK MATTRESS

MUD LINE

25.0'

C

25.0'

D

SCALE: 1"=30'

APPLICATION BY:

0'

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 APPROVED BY: BR

FILTER STONE d50 = 1.6', w50 = 685#

NOTE 3

30'

LRM

MUD LINE

3.0'

BEDDING STONE d50 = 0.4', w50 = 7#

SECTION

SCALE: 1"=30'

DESIGNED BY:

10.0'

1.5' NOTE 3

SECTION

WEST PASS, REACH C & D

FILTER STONE d50 = 1.6', w50 = 685#

NOTE 3

DRAWN BY: SPF

SECTION

EAST PASS REACH B, MUD LINE EL -23.0 TO -28.0

SCALE: 1"=30'

FILL TOP 5' OF PIPE WITH CONCRETE AND REMAINING HEIGHT W/ STONE TOP OF WALL EL +5.0

FEATURE

30'

SECTION SCALE: 1"=30'

60'

CROSS SECTIONS A-D

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 4 OF 19

90'

TOS

LIMITS OF CONSTRUCTION, TYP EAST FORK OF THE A CALCASIEU RIVER

-10

0

68 8

B

-20

POINT A

B

N

TYP 2 LOCS

19

-10

-20

C

D

0

EAST PASS QUANTITY SUMMARY WALL LENGTH

1,997 LF

WALL AREA

5.15 ACRES

ROCK VOLUME

48,334 CY

PERMANENT DREDGE AREA

0.00 ACRES

PERMANENT DREDGE VOLUME

0 CY

TEMPORARY ACCESS/FLOTATION DREDGING AREA TEMPORARY ACCESS/FLOTATION DREDGING VOLUME TEMPORARY SPOIL PLACEMENT AREA TEMPORARY ACCESS CORRIDOR AREA

REACH 5, SHEET 18 5'

1.06 ACRES

D'

C'

B' POINT C

REACH D

7,690 CY

A' B'

REACH C

1.56 ACRES

C'

REACH B

3.99 ACRES

N

REACH A REACH B

EAST PASS ESTIMATED IMPACT

19

PERMANENT IMPACTED VEGETATED WETLANDS TEMPORARY IMPACTED VEGETATED WETLANDS PERMANENT IMPACTED SUBMERGED BOTTOM TEMPORARY IMPACTED SUBMERGED BOTTOM

D'

TYP 2 LOCS

QUANTITY

TYPE

5

2

QUANTITY

TYPE

APPROXIMATE SHORELINE

6 6

APPROXIMATE SHORELINE POINT B C 5 D

2.66 ACRES

REACH C

PROPOSED SALINITY BARRIER = 1,997 LINEAR FEET

REACH 5, SHEET 18

REACH D

3.99 ACRES

5'

2.49 ACRES 2.61 ACRES

MHW= +0.78 FT MLW= -0.08 FT (NAVD 88)

ALIGNMENT TABLE Point

LATITUDE

LONGITUDE

A

N29° 50' 02.31"

W93° 20' 12.77"

B

N29° 50' 02.77"

W93° 20' 07.12"

C

N29° 49' 55.62"

W93° 19' 47.16"

EAST PASS

400

800 Feet

SCALE: 1" = 400'

APPLICATION BY:

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DRAWN BY: VR

0

DESIGNED BY:

LRM

APPROVED BY: BR

EAST PASS

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 5 OF 19

LIMITS OF CONSTRUCTION, TYP

WEST FORK OF THE CALCASIEU RIVER N

APPROXIMATE SHORELINE

POINT B

B

D

D

A

4

0

0

QUANTITY

WALL LENGTH

749 LF

WALL AREA

0.97 ACRES

POINT A

ROCK VOLUME

39,613 CY

PERMANENT DREDGE AREA

0.00 ACRES

PERMANENT DREDGE VOLUME

0 CY

TEMPORARY ACCESS/FLOTATION DREDGING AREA TEMPORARY ACCESS/FLOTATION DREDGING VOLUME TEMPORARY SPOIL PLACEMENT AREA TEMPORARY ACCESS CORRIDOR AREA

APPROXIMATE SHORELINE

B

4

WEST PASS QUANTITY SUMMARY TYPE

TYP 2 LOCS

19

0

0.69 ACRES

0.79 ACRES

-10

-10

4,976 CY

1.32 ACRES

REACH B

WEST PASS ESTIMATED IMPACT

N

QUANTITY

TYPE PERMANENT IMPACTED VEGETATED WETLANDS TEMPORARY IMPACTED VEGETATED WETLANDS PERMANENT IMPACTED SUBMERGED BOTTOM TEMPORARY IMPACTED SUBMERGED BOTTOM

REACH 4, SHEET 17

19

TYP 2 LOCS

0.36 ACRES

A'

1.20 ACRES

4'

0.61 ACRES

D'

B'

REACH 4, SHEET 17

1.48 ACRES

4' D'

B' REACH D REACH D

REACH A REACH B

MHW= +0.77 FT MHW= -0.09 FT (NAVD 88)

ALIGNMENT TABLE

PROPOSED SALINITY BARRIER = 749 LINEAR FEET.

Point

LATITUDE

LONGITUDE

A

N29° 49' 21.66"

W93° 21' 27.33"

B

N29° 49' 32.05"

W93° 21' 27.21"

WEST PASS

0

200

400 Feet

SCALE: 1" = 400'

APPLICATION BY:

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DRAWN BY: VR

DESIGNED BY:

LRM

APPROVED BY: BR

WEST PASS

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 6 OF 19

NOTES: 1. 54.0'

45.0' 2. 24.0'

CHANNEL SIDE

15.0'

LAKE SIDE

SHEET PILE TOP EL +5.0

3H:1V

5.0'

TOP OF BERM EL +2.5 (NOTE 4)

3.

2H:1V

4. 5.

3H:1V MUD LINE ARMOR STONE d50 = 2.6', w50 = 2900#

3.0'

3.0'

GEOTEXTILE

FILTER STONE d50 = 1.6', w50 = 685#

3.0' 1.5' MIN (NOTE 6)

BEDDING STONE d50 = 0.3', w50 = 3#

NOTE 1

E

WALL - SECTION SCALE: 1"=20'

42.0'

29.0' 27.0'

CHANNEL SIDE

6.

REFER TO TABLE FOR SHEET PILE SECTION AND TIP ELEVATION PAINT TOP TEN FEET OF SHEET PILES. CROSS SECTIONS SHOW GEOMETRY AT END OF CONSTRUCTION. TYP TOP OF BERM EL AFTER SHORT TERM SETTLEMENT. OVERLAP GEOTEXTILE AGAINST SHEET PILE. INCREASE BEDDING STONE THICKNESS AS REQUIRED TO REACH TOP OF BERM THICKNESS.

14.0'

LAKE SIDE

SHEET PILE TOP EL +5.0 TOP OF BERM EL -1.0 (NOTE 4)

MUD LINE

1.5' MIN (NOTE 6) 2H:1V TYP GEOTEXTILE

4.5' SHEET PILE SECTIONS FEATURE

SECTION

JOE'S CUT, REACH F

PZC 18, TIP EL -22.0

EAST PASS, REACH C & D

PZC 26, TIP EL -35.0

WEST PASS, REACH C & D

PZC 26, TIP EL -35.0

LAKE WALL

PZC 18, TIP EL -26.0

NINE MILE CUT

PZC 13, TIP EL -25.0

BEDDING STONE d50 = 0.3', w50 = 3# FILTER STONE d50 = 1.6', w50 = 685#

NOTE 1

F

WALL - SECTION SCALE: 1"=20'

APPLICATION BY:

0'

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DRAWN BY: SPF

20'

DESIGNED BY:

LRM

APPROVED BY: BR

20'

40'

CROSS SECTIONS E-F

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 7 OF 19

60'

JOE'S CUT QUANTITY SUMMARY

ALIGNMENT TABLE Point

LATITUDE

LONGITUDE

A

N29° 51' 02.65"

W93° 21' 05.35"

JOE'S CUT ESTIMATED IMPACT

TYPE

QUANTITY

TYPE

WALL LENGTH

2,218 LF

WALL AREA

3.51 ACRES

PERMANENT IMPACTED VEGETATED WETLANDS TEMPORARY IMPACTED VEGETATED WETLANDS PERMANENT IMPACTED SUBMERGED BOTTOM TEMPORARY IMPACTED SUBMERGED BOTTOM

ROCK VOLUME

94,277 CY 1.39 ACRES

PERMANENT DREDGE VOLUME

5,013 CY

B

N29° 50' 53.18"

W93° 21' 07.16"

PERMANENT DREDGE AREA

C

N29° 50' 41.34"

W93° 21' 08.24"

D

N29° 50' 33.14"

W93° 21' 07.60"

TEMPORARY ACCESS/FLOTATION DREDGING AREA TEMPORARY ACCESS/FLOTATION DREDGING VOLUME TEMPORARY SPOIL PLACEMENT AREA TEMPORARY ACCESS CORRIDOR AREA

4.84 ACRES

QUANTITY 1.11 ACRES 2.76 ACRES 2.18 ACRES 11.20 ACRES

35,132 CY 6.36 ACRES 2.91 ACRES

LIMITS OF CONSTRUCTION, TYP APPROXIMATE SHORELINE

1

F

POINT B 1

A

B

POINT A

338.8'

248.8'

0

-10

B

POINT C F

-20

-10

MHW=+ 0.77 FT MLW=+ 0.03 FT (NAVD88)

0

-20 OPEN WATER

POINT D

954.8'

F'

601.0'

179.7'

1'

B'

B' 189.4'

DETAIL 1

F'

A'

REACH B

REACH F

CALCASIEU LAKE WEST COVE

1'

REACH F DETAIL 1

PROPOSED SALINITY BARRIER = 2,218 LINEAR FEET

REACH B 0

400

800 Feet

APPLICATION BY:

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DRAWN BY: VR

DESIGNED BY:

LRM

APPROVED BY: BR

JOE'S CUT

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 8 OF 19

POINT A PL

CALCASIEU LAKE PL

LIMITS OF CONSTRUCTION PL PL

POINT D

POINT E

PL

PL PL PL

PL

POINT B POINT C CSC FAIRWAY LIMIT

CSC CSC SLL 450' FROM

0

2500

5000 Feet

LAKE WALL SCALE: 1" = 2500'

PROPOSED SALINITY BARRIER = 21,830 LINEAR FEET MHW= +0.75 FT MLW= +0.02 FT (NAVD 88)

LAKE WALL QUANTITY SUMMARY QUANTITY

TYPE

ALIGNMENT TABLE Point

LATITUDE

LONGITUDE

A

N29° 53' 54.55" W93° 20' 16.74"

B

N29° 53' 03.83" W93° 20' 27.57"

C

N29° 52' 37.97" W93° 20' 29.01"

D

N29° 52' 32.03" W93° 20' 29.00"

E

N29° 50' 17.96" W93° 20' 39.20"

WALL LENGTH

21,830 LF

WALL AREA

42.50 ACRES

ROCK VOLUME

952,957 CY

PERMANENT DREDGE AREA

25.95 ACRES

PERMANENT DREDGE VOLUME

83,729 CY

TEMPORARY ACCESS/FLOTATION DREDGING AREA TEMPORARY ACCESS/FLOTATION DREDGING VOLUME TEMPORARY SPOIL PLACEMENT AREA TEMPORARY ACCESS CORRIDOR AREA

89.02 ACRES 789,928 CY 113.12 ACRES 1.51 ACRES

APPLICATION BY:

TYPE PERMANENT IMPACTED VEGETATED WETLANDS TEMPORARY IMPACTED VEGETATED WETLANDS PERMANENT IMPACTED SUBMERGED BOTTOM TEMPORARY IMPACTED SUBMERGED BOTTOM

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DRAWN BY: VR

LAKE WALL ESTIMATED IMPACT

DESIGNED BY:

LRM

APPROVED BY: BR

QUANTITY 0.53 ACRES 1.40 ACRES 41.93 ACRES 202.14 ACRES

LAKE WALL KEY PLAN

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 9 OF 19

LIMITS OF CONSTRUCTION, TYP N

APPROXIMATE SHORELINE

0

19

3

E

F

0

E

MATCHLINE (BELOW)

F

REACH E, SHEET 7 REACH E, SHEET 7

OPEN WATER

REACH F, SHEET 7

N 19

REACH F, SHEET 7

F' TIE - IN SHEET 17

CALCASIEU SHIP CHANNEL

E'

3'

0

E'

F'

400

800 Feet

DETAIL 3, SHEET 16

E

-10

3

-20

F

-20

MATCHL

F

E

N

-10

N

REACH E, SHEET 7 0

400

19

-10 800 Feet

-10 REACH F, SHEET 7

E'

3'

F'

APPLICATION BY:

F'

E' DETAIL 3, SHEET 16

CALCASIEU SALINITY CONTROL MEASURES 150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DESIGNED BY:

LRM

APPROVED BY: BR

CALCASIEU SHIP CHANNEL LAKE WALL 1 OF 3

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 10 OF 19

ET 11)

REACH F, SHEET 7

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

DRAWN BY: VR

INE (SHE

MATCHLINE (ABOVE)

19

-20

PL

PL

PL

N

2

PL

PL

PL

PL

PL PL PL

PL PL

PL

REACH F SHEET 7

883.4'

PL

REACH F 351.3'

N 19

SHEET 7

PL

2'

F'

F'

PL

CALCASIEU SHIP CHANNEL

E'

3'

0

REACH E, SHEET 7

REACH E, SHEET 7

F'

400

800 Feet

APPROXIMATE SHORELINE

CALCASIEU LAKE

N 19

E

3

F

E

REACH E, SHEET 7

SECTION F, SHEET 7

N 19

509.8'

CALCASIEU SHIP CHANNEL 1553.1'

E'

3'

E'

F'

REACH F SHEET 7

DETAIL 3 SHEET 16

LAKE WALL

0

400

800 Feet

SCALE: 1" = 400'

APPLICATION BY:

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DRAWN BY: VR

DESIGNED BY:

LRM

APPROVED BY: BR

MATCHLINE SHEET 12

MATCHLINE (ABOVE)

E'

PL

E'

DETAIL 3 SHEET 16

REACH E, SHEET 7

PL

-20

LIMITS OF CONSTRUCTION, TYP

PL

F

PL

10 MATCHLINE SHEET

F

-10

F

MATCHLINE (BELOW)

E

E

3

PL

-20

E

CALCASIEU LAKE

19

LAKE WALL 2 OF 3

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 11 OF 19

N 19

MATCHLINE BELOW 228.5'

N

OPEN WATER

REACH E SHEET 7

192+26

REACH F SHEET 7

DETAIL 3 SHEET 16

19

CALCASIEU SHIP CHANNEL

F'

E

190+26

166+96

165+56

REACH F SHEET 7

3'

LIMITS OF CONSTRUCTION, TYP

E

Z

791.1'

MATCHLINE SHEET 11

F

200.0'

2'

E'

3'

A' 0

E'

400

800

DETAIL 2 SHEET

Feet

APPROXIMATE SHORELINE

APPROXIMATE SHORELINE

N 19

MATCHLINE ABOVE

4'

LIMITS OF CONSTRUCTION, TYP

F

REACH F SHEET 7 1681.0'

228.5'

DETAIL 4 SHEET 17

N

CALCASIEU SHIP CHANNEL

F'

4'

19

0

LAKE WALL

400

800 Feet

SCALE: 1" = 400'

APPLICATION BY:

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DRAWN BY: VR

DESIGNED BY:

LRM

APPROVED BY: BR

LAKE WALL 3 OF 3

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 12 OF 19

N

CALCASIEU SHIP CHANNEL

19

LIMITS OF CONSTRUCTION, TYP 4

E

F

E

4

2

REACH F SHEET 7

0

REACH F SHEET 7

10

10

10

F

0

E' 4'

F'

2'

4'

REACH E SHEET 7

TIE IN DETAIL SHEET 17

REACH E SHEET 7

19

PROPOSED SALINITY BARRIER = 1,907 LINEAR FEET

CALCASIEU LAKE WEST COVE

DETAIL 2 SHEET 15

N

TIE IN DETAIL SHEET 17

F'

E'

MNE MILE CUT SCALE: 1" = 400'

NINE MILE CUT QUANTITY SUMMARY QUANTITY

TYPE

NINE MILE CUT ESTIMATED IMPACT TYPE

ALIGNMENT TABLE Point

LATITUDE

LONGITUDE

A

N29° 53' 21.39"

W93° 20' 55.68"

B

N29° 52' 53.68"

W93° 20' 55.12"

PERMANENT IMPACTED VEGETATED WETLANDS TEMPORARY IMPACTED VEGETATED WETLANDS PERMANENT IMPACTED SUBMERGED BOTTOM TEMPORARY IMPACTED SUBMERGED BOTTOM

QUANTITY 0.66 ACRES 1.60 ACRES 2.98 ACRES 14.60 ACRES

1,907 LF

WALL AREA

3.91 ACRES

ROCK VOLUME

84,066 CY

PERMANENT DREDGE AREA

1.97 ACRES

PERMANENT DREDGE VOLUME TEMPORARY ACCESS/FLOTATION DREDGING AREA TEMPORARY ACCESS/FLOTATION DREDGING VOLUME TEMPORARY SPOIL PLACEMENT AREA TEMPORARY ACCESS CORRIDOR AREA

APPLICATION BY:

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DESIGNED BY:

LRM

APPROVED BY: BR

MHW= +0.75 FT MLW= +0.01 FT (NAVD 88)

7,049 CY 6.00 ACRES 48,434 CY 8.60 ACRES

0

400

1.88 ACRES

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

DRAWN BY: SPF

WALL LENGTH

800 FEET

NINE MILE CUT

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 13 OF 19

A 4

SILL

B

B

4

4

60' G -

DOLPHIN, TYP

PILES AT SILL NOT SHOWN FOR CLARITY

SILL

1

SILL PLAN SCALE: 1" = 50'

G _

APPLICATION BY:

SLOPE ROCK TO MATCH

0'

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DESIGNED BY:

LRM

APPROVED BY: BR

TOP OF WALL EL +5.0

50'

100'

SILL CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

DRAWN BY: VR

50'

SECTION SCALE: 1" = 50'

EL -8.0'

SILL

SILL DETAIL 1

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 14 OF 19

150'

12" ROCK MATTRESS

SILL MATCH ADJACENT BERM NOTE 4 (TYP)

NOTES 1.

DESIGN WIDTH

CSC SIDE

40.0' TYP

2. 3.

4. MATCH ADJACENT BERM NOTE 4 (TYP)

MINIMUM SILL DEPTH (MAX EL): 60 FOOT OPENING: EL -5.0 100 FOOT OPENING: EL -8.0 DREDGE SILL AREA AS NEEDED TO REACH MINIMUM DEPTH. WHERE SILL ELEVATION IS GREATER THAN 12" ABOVE MUD LINE, FILL WITH ROCK TO 12" BELOW SILL ELEVATION. IF THE BERM ADJACENT TO THE SILL DOES NOT HAVE PILE IN IT, THEN OMIT THE 36" PIPE PILE AND SHEET PILE.

210.0'

SILL EL (NOTE 1) 3H:1V

NOTE 3

12" ROCK MATTRESS

MATCH BERM SIDE SLOPES TYP

36" X 1.00" PIPE PILE TIP EL -30 NOTE 5

BAYOU/LAKE SIDE

H

2H:1V

_

2

SILL PLAN SCALE: 1" = 40'

40'

0'

40'

APPLICATION BY:

120'

H _

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DRAWN BY: VR

80'

DESIGNED BY:

LRM

APPROVED BY: BR

ELEVATION SCALE: 1" = 40'

SILL DETAIL 2

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 15 OF 19

I -

EL +5 EL 0

A 7

EL -5

10.0' 20.0'

10.0'

10.0'

130' X 130' X 12" ROCK MATTRESS

10.0'

3H:1V ARMOR STONE

3

50'

SYM ABOUT

FISH PASSAGE SCALE: 1" = 50'

0'

EL +5 EL 0

50'

SYM ABOUT

100'

GEOTEXTILE

3.0'

12" ROCK MATTRESS

150'

I

_

20'

SECTION SCALE: 1" = 20'

1.5'

0'

CALCASIEU SALINITY CONTROL MEASURES 150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 LRM

APPROVED BY: BR

2H:1V 3.0'

3.0' MIN

APPLICATION BY:

DESIGNED BY:

EL 0 2H:1V

3.0' BERM BEYOND NOT SHOWN FOR CLARITY

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

DRAWN BY: VR

9.0'

10.0'

FILTER STONE

20'

40'

FISH PASSAGE

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 16 OF 19

60'

50.0' TRANSITION SECTION

NOTES

K _

1.

OPTIONAL SEE NOTE 1

2. 3.

J _

TIE-IN DETAIL

4

SYM ABOUT

SHEET PILE EL +5.0

15.0'

3.0' 3H:1V 2H:1V

END TIE-IN @ EG EL +7.5 (NOTE 1)

BEGIN TIE-IN REFER TO PLAN

SCALE: 1" = 50'

END SHEET PILE REFER TO PLAN

BERM SECTION PER PLAN AND PROFILE

WHERE TIE-IN ENDS AND THERE IS NO EXISTING GRADE AT OR ABOVE EL. +7.5, SLOPE DOWN ROCK AT 10H:1V. SHEET PILE TIP EL MATCHES ADJACENT BERM SECTION. REFER TO PLAN FOR THE LOCATION OF THE END OF THE SHEET PILE.

ARMOR STONE d50 = 2.3' w50 = 1899#

4.0' MIN EG

BEDDING STONE d50 = 0.4' w50 = 7#

2H:1V K _

EXCAVATE TO PROVIDE MIN ROCK THICKNESS

ELEVATION

J _

50'

SCALE: 1" = 50'

APPLICATION BY:

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DRAWN BY: VR

0'

DESIGNED BY:

LRM

APPROVED BY: BR

50'

SECTION SCALE: 1" = 50'

100'

TIE-IN DETAIL 1

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 17 OF 19

150'

ROAD/BERM

40' LONG MATTRESS TYP

PZC 26 SHEET PILE TIP EL -35 HEAD EL +8

3' OF STONE

18" ROCK MATTRESS

PLACE (2) MATS BEYOND DRIVEN SHEET PILING EL +8.0 (CDF BERM) END SHEET PILE

EL +6.0 (ROAD) EXISTING GRADE

MAT

50.0' SPLIT SHEET PILE w/ TEE CONNECTOR END ROCK BERM

R100.0'

SECTION

L _

NTS

L -

18" ROCK MATTRESS BERM WITH SHEET PILE PER PLAN

R100.0'

M

EL +8.0 (CDF BERM) EL +6.0 (ROAD)

50.0'

_

PZC 26 SHEET PILE TIP EL -35 HEAD EL +8

END SHEET PILE

5

M

TOE

TOP

TOP

TOE

PLACE (2) MATS BEYOND DRIVEN SHEET PILING _

NTS

TIE-IN DETAIL SCALE: NTS

APPLICATION BY:

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DRAWN BY: VR

SECTION

DESIGNED BY:

LRM

APPROVED BY: BR

TIE-IN DETAIL 2

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 18 OF 19

NOTE: 1.

TEMPORARY ACCESS CHANNEL AS REQUIRED FOR CONSTRUCTION ACCESS. REFER TO PLANS FOR ESTIMATED EXTENTS. REFER TO NOTE 4, SHEET 2.

EDGE OF STRUCTURE

T.O. TEMP SPOIL PLACEMENT AREA MAX EL = +6.0' TEMPORARY ACCESS CHANNEL (EXCAVATE AND BACKFILL) 20.0'

ANGLE OF REPOSE , BOTH SIDES

TEMPORARY WARNING SIGN

VARIES FROM 80' TO 110'

VARIES CAST SIDE

B.O ACCESS CHANNEL TYP EL NOT TO EXCEED -10.0'

EXISTING GROUND

MIN 20'

TYP 90.0'

TYP 120.0'

3H: 1V, TYP. BOTH SIDES

N

ACCESS CHANNEL TYPICAL SECTION SCALE: 1" = 40'

40'

APPLICATION BY:

CALCASIEU SALINITY CONTROL MEASURES

COASTAL PROTECTION AND RESTORATION AUTHORITY 150 TERRACE STREET BATON ROUGE, LA 70802

150 TERRACE STREET BATON ROUGE, LOUISIANA 70802 DRAWN BY: SPF

0'

DESIGNED BY:

LRM

APPROVED BY: BR

40'

80'

TEMPORARY ACCESS CHANNEL

STATE PROJECT NUMBER: CS-65

DATE: 20-APR-2018

FEDERAL PROJECT NUMBER:

SHEET 19 OF 19

120'

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas