DREDGING FOR HYDROCARBON EXPLORATION WELL SITE AND PROPOSED FLOWLINES IN LAKE VERRET IN ASSUMPTION PARISH
NAME OF APPLICANT: Hilcorp Energy Company, c/o Tim Morton & Associates, Attn: Jarrod Grandon, 730 East Kaliste Saloom, Lafayette, Louisiana 70508.
LOCATION OF WORK: Located in Lake Verret, in Section 23, Township 14 South, Range 13 East, west of Labadieville, Louisiana, located in Assumption Parish, as shown on the enclosed drawings (Latitude 29.8499 N Longitude -90.1103 W). This project is located in the Terrebonne Basin (West Central Louisiana Coastal HUC 08090302).
CHARACTER OF WORK: The applicant is requesting a Department of the Army permit authorization for the dredging for access and well location for the installation and maintenance of a drilling barge and appurtenances to drill the Mallard Prospect Well in Lake Verret. The proposed project also includes the installation and maintenance of one 3-inch flowline and one 4-inch flowline to serve the proposed well site. Approximately 58,645 cubic yards of non-vegetated waterbottoms would be directly impacted as a result of propwashing (access channel, and well location) and jetting (3-inch and 4-inch flowlines) as a result of project implementation. Approximately 23.49 acres of jurisdictional waterbottoms would be impacted by the dredging portions of this project. The applicant has claimed that the project has been designed to avoid and minimize direct and secondary adverse wetland impacts to the maximum extent practicable. The applicant is proposing to utilize best management practices during and after the construction phase of the project. The proposed project will not directly impact any jurisdictional wetlands and compensatory mitigation is not anticipated.
JOINT PUBLIC NOTICE
September 17, 2018
United States Army
Corps of Engineers
New Orleans District
Regulatory Branch
7400 Leake Avenue
New Orleans, Louisiana 70118
State of Louisiana
Department of Environmental Quality
Water Permits Division
Post Office Box 4313
Baton Rouge, Louisiana 70821-4313
(504) 862-1217
Project Manager
Kenny Blanke
Kenneth.G.Blanke@usace.army.mil
MVN 2018-0642-CQ
(225) 219-3225
Project Manager
Ms. Elizabeth Hill
WQC Application Number
WQC 180815-04
Interested parties are hereby notified that a permit application has been received by the
New Orleans District of the U.S. Army Corps of Engineers pursuant to: [X] Section 10 of the
Rivers and Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or [X] Section 404
of the Clean Water Act (86 Stat. 816; 33 USC 1344).
Application has also been made to the Louisiana Department of Environmental Quality,
Office of Environmental Services, for a Water Quality Certification (WQC) in accordance with
statutory authority contained in LRS30:2074 A(3), and provisions of Section 401 of the Clean
Water Act (P.L.95-17).
DREDGING FOR HYDROCARBON EXPLORATION WELL SITE AND PROPOSED
FLOWLINES IN LAKE VERRET IN ASSUMPTION PARISH
NAME OF APPLICANT: Hilcorp Energy Company, c/o Tim Morton & Associates, Attn: Jarrod
Grandon, 730 East Kaliste Saloom, Lafayette, Louisiana 70508.
LOCATION OF WORK: Located in Lake Verret, in Section 23, Township 14 South, Range 13
East, west of Labadieville, Louisiana, located in Assumption Parish, as shown on the enclosed
drawings (Latitude 29.8499 N Longitude -90.1103 W). This project is located in the Terrebonne
Basin (West Central Louisiana Coastal HUC 08090302).
CHARACTER OF WORK: The applicant is requesting a Department of the Army permit
authorization for the dredging for access and well location for the installation and maintenance
of a drilling barge and appurtenances to drill the Mallard Prospect Well in Lake Verret. The
proposed project also includes the installation and maintenance of one 3-inch flowline and one
4-inch flowline to serve the proposed well site. Approximately 58,645 cubic yards of nonvegetated waterbottoms would be directly impacted as a result of propwashing (access channel,
and well location) and jetting (3-inch and 4-inch flowlines) as a result of project implementation.
Approximately 23.49 acres of jurisdictional waterbottoms would be impacted by the dredging
portions of this project. The applicant has claimed that the project has been designed to avoid
and minimize direct and secondary adverse wetland impacts to the maximum extent
practicable. The applicant is proposing to utilize best management practices during and after
the construction phase of the project. The proposed project will not directly impact any
jurisdictional wetlands and compensatory mitigation is not anticipated.
The comment period for the Department of Army Permit and the Louisiana Department
of Environmental Quality will close in 20 days from the date of this joint public notice. Written
comments, including suggestions for modifications or objections to the proposed work, stating
reasons thereof, are being solicited from anyone having interest in this permit and/or this WQC
request and must be mailed so as to be received before or by the last day of the comment
period. Letters concerning the Corps of Engineers permit application must reference the
applicant's name and the Permit Application Number, and be mailed to the Corps of Engineers
at the address above, ATTENTION: REGULATORY BRANCH. Similar letters concerning the
Water Quality Certification must reference the applicant's name and the WQC application
number and be mailed to the Louisiana Department of Environmental Quality at the address
above. Individuals or parties may request an extension of time in which to comment on the
proposed work by writing or e-mailing the Corps of Engineers Project Manager listed above.
Any request must be specific and substantively supportive of the requested extension, and
received by this office prior to the end of the initial comment period. The Section Chief will
review the request and the requestor will be promptly notified of the decision to grant or deny
the request. If granted, the time extension will be continuous to the initial comment period and,
inclusive of the initial comment period, will not exceed a total of 30 calendar days.
The application for this proposed project is on file with the Louisiana Department of
Environmental Quality and may be examined during weekdays between 8:00 a.m. and 4:30
p.m. Copies may be obtained upon payment of costs of reproduction.
Corps of Engineers Permit Criteria
The decision whether to issue a permit will be based on an evaluation of the probable
impacts, including cumulative impacts of the proposed activity on the public interest. That
decision will reflect the national concern for both protection and utilization of important
resources. The benefit which reasonably may be expected to accrue from the proposal must be
balanced against its reasonably foreseeable detriments. All factors which may be relevant to
the proposal will be considered including the cumulative effects thereof; among those are
conservation, economics, aesthetics, general environmental concerns, wetlands, historic
properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation,
shoreline erosion and accretion, recreation, water supply and conservation, water quality,
energy needs, safety, food and fiber production, mineral needs, considerations of property
ownership and, in general, the needs and welfare of the people.
The US Army Corps of Engineers is soliciting comments from the public, federal, state,
and local agencies and officials, Indian Tribes, and other interested parties in order to consider
and evaluate the impacts of this proposed activity. Any comments received will be considered
by the US Army Corps of Engineers to determine whether to make, modify, condition, or deny a
permit for this proposal. To make this decision, comments are used to assess impacts on
endangered species, historic properties, water quality, general environmental effects, and other
public interest factors listed above. Comments are used in the preparation of an Environmental
Assessment and/or an Environmental Impact Statement pursuant to the National Environmental
Policy Act. Comments are also used to determine the need for a public hearing and to
determine the overall public interest of the proposed activity.
The New Orleans District is unaware of properties listed on the National Register of
Historic Places near the proposed work. The possibility exists that the proposed work may
damage or destroy presently unknown archeological, scientific, prehistorical, historical sites, or
data. Copies of this notice are being sent to the State Archeologist and State Historic
Preservation Officer.
Our initial finding is that the proposed work would neither affect any species listed as
endangered by the U.S. Departments of Interior or Commerce, nor affect any habitat
designated as critical to the survival and recovery of any endangered species. Utilizing
Standard Local Operating Procedure for Endangered Species in Louisiana (SLOPES), dated
October 22, 2014, between the U.S. Army Corps of Engineers, New Orleans and U.S. Fish and
Wildlife Service, Ecological Services Office, the Corps has determined that with the inclusion of
special conditions, the proposed activity is not likely adversely affect the West Indian manatee
(Trichechus manatus).
This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the
Magnuson-Stevens Fishery Conservation and Management Act. The applicant's proposal
would result in the destruction or alteration of N/A acres of EFH utilized by various life stages of
red drum and penaeid shrimp. Our initial determination is that the proposed action would not
have a substantial adverse impact on EFH or federally managed fisheries in the Gulf of Mexico.
Our final determination relative to project impacts and the need for mitigation measures is
subject to review by and coordination with the National Marine Fisheries Service.
If the proposed work involves deposits of dredged or fill material into navigable waters,
the evaluation of the probable impacts will include the application of guidelines established by
the Administrator of the Environmental Protection Agency. Also, a certification that the
proposed activity will not violate applicable water quality standards will be required from the
Department of Environmental Quality, Office of Environmental Services, before a permit is
issued.
Any person may request, in writing, within the comment period specified in this notice,
that a public hearing be held to consider this application. Requests for public hearings shall
state, with particularity, the reasons for holding a public hearing. You are requested to
communicate the information contained in this notice to any other parties whom you deem likely
to have interest in the matter.
The applicant has certified that the proposed activity described in the application
complies with and will be conducted in a manner that is consistent with the Louisiana Coastal
Resources Program. The Department of the Army permit will not be issued unless the applicant
received approval or a waiver of the Coastal Use Permit by the Department of Natural
Resources.
JOHN M. HERMAN
Chief, Central Evaluation Section
Regulatory Branch
Enclosure
As-built drawings and/or plats shall have written on them the date of completion of said
activities and shall be submitted to the Louisiana Department of Natural Resources, Office
of Coastal Management, P.O. Box 44487, Baton Rouge, LA 70804-4487 within 30 days
following project completion.
AREA OF
PROPOSED WORK
All structures built under the authorization and conditions of this permit shall be removed
from the site within 120 days of abandonment of the facilities for the herein permitted use,
or when these structures fall into a state of disrepair such that they can no longer function
as intended. This condition does not preclude the necessity for revising the current permit
or obtaining a separate Coastal Use Permit, should one be required, for such removal
activities.
Structures must also be marked / lighted in accordance with U.S Coast Guard regulations.
REPRODUCED FROM STATE HIGHWAY MAP
5
0
5
10
15
MILES
In order to ensure the safety of all parties, the permittee shall contact Louisiana One Call
System (1-800-272-3020) a minimum of 48 hours prior to the commencement of any
excavation (digging, dredging, jetting, etc.) or demolition activity.
2
40
39
3
31
41
81
1
GU
4
10
12
11
37
15
NAD27
LA SOUTH ZONE
LAMBERT GRID NORTH
18
17
T14S-R14E
PROPOSED FLOWLINES
SEE PLAN 3 SHEET 4 OF 6
0"
H2
OUT
LF S
T14S-R13E
31
32
14
39
13
16
24
20
PROPOSED PROP WASH & LOCATION
SEE PLAN 1 & 2 SHEETS 2 & 3 OF 6
17
21
19
40
22
23
20
THESE PLANS WERE PREPARED FOR THE EXCLUSIVE
USE OF OBTAINING REGULATORY PERMIT(S) AND ARE
NOT TO BE USED TO ACQUIRE RIGHT-OF-WAY,
SERVITUDE OR EASEMENT FROM PROPERTY OWNERS,
NOR DO THEY PURPORT TO SHOW ALL PIPELINE
CROSSINGS OR OTHER ENCUMBRANCES.
50
26
27
4,000
25
0
4,000
8,000
U.S. SURVEY FEET (1"=4,000')
PROPOSED PROP WASH, LOCATION, & F/L
MALLARD PROSPECT
Lake Verret Area
Assumption Parish, Louisiana
PREPARED
BY:
OCEANEERING INTERNATIONAL, INC.
730 E. KALISTE SALOOM RD.
LAFAYETTE, LA 70508
(337) 210-0000
LA Reg. No. 747
JOB: 190459
DRW: REP
CKD: WPB
APP: REP
DOC: 190459-OII-DRW-COE-001-01
DATE: MAY 21, 2018
SHEET 1 of 6
REV.
0
1,15
5'
1,20
3'
1,5
73'
1,5
64'
1,1
1,1
49
'
NAD83
LA SOUTH ZONE
LAMBERT GRID NORTH
MATCH
LINE
76
'
Proposed Prop Wash
Average Wash = 1.0'
30,497 cu.yds.
18.90 acres
PLAN 1
PLAN 2
A'
A
2 ,7
20'
55'
2 ,7
'
770
2,071,729' (27)
421,768'
'
X=
Y=
740
3,352,529' (83)
482,474'
249'
220'
BEGIN PROP WASH
X=
Y=
6'
48
3'
'
1,372
482'
'
504'
'
378
1'
3'
1,369
56
54
70'
2'
82
82
9'
49
'
413
PLAN 1
1,000
0
1,000
U.S. SURVEY FEET (1"=1,000')
PROPOSED PROP WASH, LOCATION, & F/L'S
MALLARD PROSPECT
Lake Verret Area
Assumption Parish, Louisiana
PREPARED
BY:
OCEANEERING INTERNATIONAL, INC.
730 E. KALISTE SALOOM RD.
LAFAYETTE, LA 70508
(337) 210-0000
LA Reg. No. 747
JOB: 190459
DRW: REP
CKD: WPB
APP: REP
DOC: 190459-OII-DRW-COE-002-01
DATE: MAY 21, 2018
SHEET 2 of 6
REV.
0
PLAN 2
1,000
0
1,000
U.S. SURVEY FEET (1"=1,000')
X=
Y=
3,351,519' (83)
491,109'
X=
Y=
2,070,719' (27)
430,403'
345'
160'
B'
Proposed Prop Wash
Average Wash = 3.5'
25,914 cu.yds.
4.59 acres
1,895'
2,379'
12
7'
B
1,15
5'
1,20
3'
1,5
73'
1,5
64'
1,1
76
'
1,1
49
'
NAD83
LA SOUTH ZONE
LAMBERT GRID NORTH
MATCH
LINE
Proposed Prop Wash
Average Wash = 1.0'
30,497 cu.yds.
18.90 acres
PLAN 1
PLAN 2
A'
A
55'
2,7
20'
2,7
PROPOSED PROP WASH, LOCATION, & F/L'S
MALLARD PROSPECT
Lake Verret Area
Assumption Parish, Louisiana
PREPARED
BY:
OCEANEERING INTERNATIONAL, INC.
730 E. KALISTE SALOOM RD.
LAFAYETTE, LA 70508
(337) 210-0000
LA Reg. No. 747
JOB: 190459
DRW: REP
CKD: WPB
APP: REP
DOC: 190459-OII-DRW-COE-002-02
DATE: MAY 21, 2018
SHEET 3 of 6
REV.
0
A
70'
0
WATER LINE +1.0'
40
U.S. SURVEY FEET (1"=40')
VERTICAL
8'
TYPICAL
SECTIONS
HORIZONTAL
A'
Proposed Prop Wash
0
20
Prop. Bottom -7.0'
1.0'
B
U.S. SURVEY FEET (1"=20')
B'
Proposed Prop Wash
160'
WATER LINE +1.0'
8'
MHW +1.5'
MLW +1.0'
Prop. Bottom -7.0'
3.5'
TYPICAL
DIESEL POWERED DRILL BARGE
100
0
ELEVATION
100
ELEV. APPROX. 179'
US SURVEY FEET (1"=100')
WELL LOCATION
57' CLEAR
PLAN
TYPICAL DRILL BARGE
900 HP TUG
KEYWAY
8' X 16'
6 - 30' PILES
=
NOTE:
8 TEMPORARY 3 PILE CLUSTER TO BE
DRIVEN TO ASSIST IN REMOVING DRILL BARGE
FROM LOC'N. TEMPORARY CLUSTERS TO BE
PULLED WHEN PERMANENT WELL GUARD
IS INSTALLED.
WATER LINE +1.0'
MUD LINE
TYPICAL
WELL HEAD PROTECTOR
5
0
NAVIGATIONAL
LIGHT
EL. = VARIES
WELL
WELL
5
SIDE VIEW
4'
US SURVEY FEET (1"=5')
TOP VIEW
BATTERY
BOX
NAVIGATIONAL LIGHT
(TIMBER STRUCTURE)
4'
10" X 30' PILINGS
WELL
7'
DRAFT
6.0'
DRAFT
7.5'
WATER
8.0'
MHW +1.5'
MLW +1.0'
WELL
WATER LINE +1.0'
8'
WELL
16'
MUD LINE
PROPOSED PROP WASH, LOCATION, & F/L'S
MALLARD PROSPECT
Lake Verret Area
Assumption Parish, Louisiana
PREPARED
BY:
OCEANEERING INTERNATIONAL, INC.
730 E. KALISTE SALOOM RD.
LAFAYETTE, LA 70508
(337) 210-0000
LA Reg. No. 747
JOB: 190459
DRW: REP
CKD: WPB
APP: REP
DOC: 190459-OII-DRW-COE-002-03
DATE: JUNE 6, 2018
SHEET 4 of 6
REV.
0
"
RO
MA
6
CH
U
F SO
GUL
PROPOSED 3" & 4"
0"
TH 2
BEARING
COURSE
1
2
3
4
DISTANCE
NORTH
WEST
120'
100'
2,964'
14,028'
00+00' P.O.B.
172+12' E.O.L.
EXISTING SSTI
X=
Y=
3,337,232' (83)
499,283'
PR
X=
Y=
OP
OS
2,056,432' (27)
438,577'
4
ED
3"
&
X=
Y=
3,351,519' (83)
491,109'
X=
Y=
2,070,719' (27)
430,403'
4"
NAD83
LA SOUTH ZONE
LAMBERT GRID NORTH
2
1
3
PLAN 3
2,000
0
2,000
U.S. SURVEY FEET (1"=2,000')
JOB: 190459
REV:
PREPARED BY:
0
DATE: MAY 21, 2018
PROPOSED PROP WASH, LOCATION, & F/L'S
SHEET 5 of 6
OCEANEERING INTERNATIONAL, INC.
730 E. KALISTE SALOOM RD.
LAFAYETTE, LA 70508
(337) 210-0000
LA Reg. No. 747
MALLARD PROSPECT
DRW: REP
CKD: WPB APP: REP DOC:
190459-OII-DRW-COE-003-01
Lake Verret Area
Assumption Parish, Louisiana
APPROX. 2.4 CU. YDS. OF MATERIAL TO BE
DISPLACED BY JETTING OPERATIONS.
APPROX. 2,231 CU. YDS. OF MATERIAL TO BE
DISPLACED BY JETTING OPERATIONS.
TIE-IN IS TO BE BACKFILLED BY NATURALLY
OCCURING SEDIMENTATION.
3.5'
3'
MIN.
DITCH IS TO BE BACKFILLED BY NATURALLY
OCCURING SEDIMENTATION.
PROP.
FLOWLINES
(17,212')
TYPICAL JETTING DITCH
NOT TO SCALE
900 HP TUG
BARGE
BARGE
MHW +1.5'
MLW +1.0'
WATER LINE +1.0'
DRAFT
MUD LINE
DRAFT
PROPOSED PROP WASH, LOCATION, & F/L'S
MALLARD PROSPECT
Lake Verret Area
Assumption Parish, Louisiana
PREPARED
BY:
OCEANEERING INTERNATIONAL, INC.
730 E. KALISTE SALOOM RD.
LAFAYETTE, LA 70508
(337) 210-0000
LA Reg. No. 747
JOB: 190459
DRW: REP
CKD: WPB
APP: REP
DOC: 190459-OII-DRW-COE-003-02
DATE: MAY 21, 2018
SHEET 6 of 6
REV.
0