The Wyoming Water Development Office has requested authorization to expand Leavitt Reservoir on Bureau of Land Management (BLM) lands and private property in Big Horn County at latitude 44.64, longitude -107.87. The project purpose is to expand the water storage capacity of Leavitt Reservoir to provide late season supplemental irrigation water to irrigated lands in the Beaver Creek and Shell Creek drainages to reduce irrigation water shortages. The attached map shows the project location in Section 24, Township 54 North, Range 92 West, Big Horn County, Wyoming.
The Wyoming Water Development Office has requested authorization to expand Leavitt Reservoir on Bureau of Land Management (BLM) lands and private property in Big Horn County at latitude 44.64, longitude -107.87. The project purpose is to expand the water storage capacity of Leavitt Reservoir to provide late season supplemental irrigation water to irrigated lands in the Beaver Creek and Shell Creek drainages to reduce irrigation water shortages. The attached map shows the project location in Section 24, Township 54 North, Range 92 West, Big Horn County, Wyoming.
PUBLIC NOTICE
Application No.: NWO-2016-00623
Applicant: Wyoming Water Development Office
Waterway: Leavitt Reservoir, Beaver Creek, Unnamed
ephemeral draw along Beaver Creek, and wetlands adjacent to these resources
Issue Date: September 18, 2018
Expiration Date: October 17, 2018
30 DAY NOTICE
Wyoming Regulatory Office
2232 Dell Range Blvd., Suite 210
Cheyenne, Wyoming 82009
JOINT NOTICE OF PERMIT PENDING
U.S. ARMY CORPS OF ENGINEERS
AND
WYOMING DEPARTMENT OF ENVIRONMENTAL QUALITY
The application of Wyoming Water Development Office (WWDO), 6920 Yellowtail Road, Cheyenne,
Wyoming, 82002 is being considered by the District Engineer, U.S. Army Corps of Engineers, Omaha,
Nebraska, for approval of plans and issuance of a permit under the authority of the Secretary of the Army. A
permit, if issued, will be under the provisions of Section 404 of the Clean Water Act of 1972, as amended.
The applicant has requested authorization to expand Leavitt Reservoir on Bureau of Land Management
(BLM) lands and private property in Big Horn County at latitude 44.64, longitude -107.87. The project
purpose is to expand the water storage capacity of Leavitt Reservoir to provide late season supplemental
irrigation water to irrigated lands in the Beaver Creek and Shell Creek drainages to reduce irrigation water
shortages. The attached map shows the project location in Section 24, Township 54 North, Range 92 West,
Big Horn County, Wyoming.
The existing earthen dam embankment will be removed and a new embankment will be constructed. The
reservoir expansion of 5,962 acre feet (AF) would bring the total storage capacity to 6,604 AF to reduce
drought vulnerability and irrigation shortages. Storage in the expanded Leavitt Reservoir would include the
existing 643 AF; 1,500 AF for minimum environmental/recreation pool; and 4,461 AF for a supplemental
irrigation supply. The reservoir would be filled from a new Beaver Creek diversion and 2-mile long, buried
supply line. A new Beaver Creek transfer diversion and 3-mile long, buried pipeline would convey reservoir
releases to existing irrigation ditches. The new earthen embankment contains approximately 1.42 million
cubic yards (CY) of fill and has a crest length of approximately 1,800 feet with a maximum height of 80 feet.
The expanded reservoir surface area at the normal high water line is approximately 203 acres. The project
also includes improvements to existing roads, new access road construction, recreational facilities, and
constructed wetlands.
Removal of the dam embankment and construction of the new embankment will disturb approximately 45
acres resulting in a loss of approximately 0.92 acre of wetlands. Approximately 17.15 acres of wetlands will
be permanently impacted and 3.3 acres of wetlands will be temporarily impacted due to excavation and
construction of the entire reservoir, including the inundation of the reservoir once filled.
The applicant has proposed compensatory mitigation for permanent wetland loss resulting from Leavitt
Reservoir Expansion Project (LREP). WWDO has identified three potential areas (North, South, and Rim
wetlands areas) and an additional area that may be used for either wetland mitigation or recreation. The
combined areas are likely to be more than sufficient to mitigate for wetland impacts. The final areas and
configurations will depend on mitigation requirements determined by the United States Army Corps of
Engineers (USACE) once a determination is made on the least environmentally damaging practicable
alternative (LEDPA). Wetlands would be replaced at a minimum of 1.5:1 ratio at any or all of the three
mitigation sited identified on the attached figure WM-1 (Conceptual Wetland Mitigation Locations). The
three locations are also attached as figures WM-2, WM-3, and WM-4. The applicant will mitigate for all
permanent impacts to wetlands within the project area. All mitigation will be "on-site" located on lands
owned by the BLM and or private inholdings and establishment would be "in-kind".
The U.S. Army Corps of Engineers is soliciting comments from the public; federal, state, and local agencies;
Tribes; and other interested parties in order to consider and evaluate impacts of the project. Any comments
received will be considered by the Corps to determine whether to issue, modify, condition or deny a permit
for the project. To make this decision, comments are used to assess impacts on endangered species, historic
properties, water quality, general environmental affects, and other public interest factors. Comments are also
used to determine the need for a public hearing and to determine the overall public interest of the project.
Any person may request, in writing and within the comment period specified in this notice, that a public
hearing be held for the purpose of gathering additional information. Requests for public hearings must be
identified as such and shall state specifically the reasons for holding a public hearing and shall identify what
additional information would be obtained. The request must be submitted to the address shown above.
Any interested party (particularly officials of any town, county, state, federal agency, or local association
whose interests may be affected by the project) is invited to submit to this office written facts, arguments, or
objections on or before the expiration date of this notice. Any agency or individual having an objection to the
project should specifically identify it as an objection with clear and specific reasons. Comments, both
favorable and unfavorable, will be accepted, made a part of the record and will receive full consideration in
subsequent actions on this application. All replies to the public notice should be mailed to the address listed
above. Mr. Michael Stanley may be contacted for additional information by telephone at (307) 772-2300 or
by electronic mail at michael.g.stanley@usace.army.mil
The Wyoming Department of Environmental Quality (WDEQ), Water Quality Division, 200 West 17th
Street, Cheyenne, Wyoming 82002, will review the application and comments with intent to certify in
accordance with provisions of Section 401 of the Clean Water Act of 1972, as amended. The certification, if
issued, will express the state's opinion that construction of the project will not result in a violation of
applicable water quality standards. The WDEQ hereby incorporates this public notice as its own public
notice and procedures by reference thereto.
The BLM is the lead federal agency responsible for ensuring compliance with the National Historic
Preservation Act of 1966 and the Endangered Species Act of 1973 through the EIS process as stated in the
Memorandum of Understanding dated April 5, 2016 between the United State Army Corps of Engineers and
the BLM. As the lead federal agency, the BLM retains final responsibility for the content of all planning and
NEPA documents, which include the Draft EIS, the Final EIS, any Supplemental Drafts, and the BLM's
Record of Decision (ROD). BLM published the Draft EIS on August 31, 2018. This draft can be reviewed in
further detail at https://go.usa.gov/xUsa7.
The decision whether to issue a permit will be based on an evaluation of the probable impacts, including
cumulative impacts, of the project on the public interest. That decision will reflect the national concern for
both protection and utilization of important resources. The benefits which reasonably may be expected to
accrue from the project must be balanced against its reasonably foreseeable detriments. All factors which
may be relevant to the proposal will be considered, including the cumulative effects thereof; among those are
conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and
wildlife, flood plains, land use, navigation, shoreline erosion and accretion, recreation, water supply and
conservation, water quality, energy needs, safety, food and fiber production, mineral needs, and
considerations of property ownership. In addition, the evaluation will include application of the guidelines
promulgated by the Administrator, Environmental Protection Agency, under the authority of Section 404 (b)
of the Clean Water Act of 1972, as amended (40 C.F.R.; Part 230).
Comments received after the expiration date of this public notice will not be considered.
Public Notices issued by the Wyoming Regulatory Office can also be obtained by visiting its web site at