NOTICE OF PROPOSED INTENT TO ACCEPT FUNDS FROM THE STATE OF LOUISIANA, COASTAL PROTECTION & RESTORATION AUTHORITY FOR EXPEDITING DEPARTMENT OF THE ARMY PERMISSION AND PERMIT APPLICATIONS
NOTICE OF PROPOSED INTENT TO ACCEPT FUNDS FROM THE STATE OF LOUISIANA, COASTAL PROTECTION & RESTORATION AUTHORITY FOR EXPEDITING DEPARTMENT OF THE ARMY PERMISSION AND PERMIT APPLICATIONS
This Special Public Notice announces the proposed intent of the United States Army Corps of Engineers (“USACE”), New Orleans District (“CEMVN”), to accept and expend funds from the State of Louisiana, Coastal Protection and Restoration Authority (“CPRA”) for the purpose of providing expedited review, evaluation, and processing of Department of the Army (“DA”) permission requests and permit applications to be submitted by CPRA for their proposed Calcasieu Salinity Control Measures (“Project”).
This Special Public Notice solicits comments from the general public, concerned agencies, and organizations on the subject of the acceptance and expenditure of funds to be contributed by CPRA to expedite the evaluation of DA permission and permit requests pursuant to 33 U.S.C Section 2352, also referred to as Section 214 of the Water Resources Development Act of 2000, (“Section 214”), as amended by Section 1006 of the Water Resources Reform and Development Act of 2014. The public comment period under this Special Public Notice is twenty (20) calendar days.
SPECIAL PUBLIC NOTICE
______________________________________________________________________________
U. S. ARMY CORPS OF ENGINEERS
BUILDING STRONG®
NEW ORLEANS DISTRICT
NOTICE OF PROPOSED INTENT TO ACCEPT FUNDS FROM THE
STATE OF LOUISIANA, COASTAL PROTECTION & RESTORATION AUTHORITY
FOR EXPEDITING DEPARTMENT OF THE ARMY
PERMISSION AND PERMIT APPLICATIONS
Public Notice Issue Date: October 11, 2018
Comment Period Expiration Date: October 31, 2018
This Special Public Notice announces the proposed intent of the United States Army
Corps of Engineers ("USACE"), New Orleans District ("CEMVN"), to accept and expend
funds from the State of Louisiana, Coastal Protection and Restoration Authority ("CPRA")
for the purpose of providing expedited review, evaluation, and processing of Department
of the Army ("DA") permission requests and permit applications to be submitted by CPRA
for their proposed Calcasieu Salinity Control Measures ("Project").
This Special Public Notice solicits comments from the general public, concerned
agencies, and organizations on the subject of the acceptance and expenditure of funds
to be contributed by CPRA to expedite the evaluation of DA permission and permit
requests pursuant to 33 U.S.C Section 2352, also referred to as Section 214 of the Water
Resources Development Act of 2000, ("Section 214"), as amended by Section 1006 of
the Water Resources Reform and Development Act of 2014. The public comment period
under this Special Public Notice is twenty (20) calendar days.
CPRA intends to submit a request for permission for the Project under Section 14 of the
Rivers and Harbors Appropriation Act of 1899, as amended (33 U.S.C. 408) (hereinafter
"Section 408"). Section 408 provides authority to the Secretary of the Army ("Secretary")
to grant permission for the alteration or modification of USACE federal civil works projects
when, in the judgment of the Secretary, the alteration or modification will not be injurious
to the public interest and will not impair the usefulness of a USACE project. In addition,
CPRA previously submitted a Joint DA Permit Application for the Project under the
provisions of Section 404 of the Clean Water Act (33 U.S.C. 1344) (hereinafter "Section
404"), and Section 10 of the Rivers and Harbors Appropriation Act of 1899, as amended
(33 U.S.C. 403) ("Section 10") which may be collectively referred to as "Section 10/404"
herein.
1
The proposed Project consists of 5 project features designed to reduce salinity in
Calcasieu Lake and the Calcasieu-Sabine Basin. These features largely consist of steel
sheet pile (some of which is pile supported) supported by rock with the inclusion of
navigation sills in each feature. The two southernmost features are on East Pass and
West Pass and will reduce the cross-sectional area of these passes. There are 3 project
features to the north of these along the Calcasieu Ship Channel.
Name of the Funding Entity.
The Funding Entity is the State of Louisiana, Coastal Protection and Restoration
Authority, a non-federal public entity. The term "non-federal public entity" is limited to
governmental agencies or governmental public authorities, including governments of
federally recognized Indian Tribes. Non-federal public entities include, but are not limited
to, port authorities; state, local or tribal local transportation departments/agencies; flood
and storm water management agencies; and public infrastructure departments that have
the desire to expedite the permitting and permission processes either programmatically
or for a specific project.
Funding can only be accepted and expended pursuant to Section 214 if the proposed
project serves a public purpose. CPRA, as non-federal public entity, is the proponent of
the proposed regulatory permits and Section 408 request. District Commanders have the
discretion to determine whether a single or complete project has a public purpose and
therefore, may be reviewed under a Funding Agreement with a non-federal public entity.
It is not acceptable for private entities to provide funds to a non-federal public entity to
expedite a private project. No funds provided by a federal agency to CPRA under the
Funding Agreement may be accepted by USACE unless CPRA forwards to USACE, a
written confirmation from the disbursing federal agency, that the use of the funds to
expedite the evaluation of the requested permits and Section 408 permission is
acceptable. In this case, the Department of the Treasury is disbursing funds to CPRA. By
letter dated August 22nd, 2018, the Department of the Treasury has given permission for
CPRA to use federal funding for Section 214 activities.
Statutory Authority to Accept and Expend the Funds.
Pursuant to Section 214 and all applicable guidance and regulations
(Available here:
https://www.usace.army.mil/Missions/Civil-Works/Regulatory-Program-andPermits/Section-214/ ) the Secretary after public notice, may accept and expend funds
contributed by a non-federal public entity, to expedite the evaluation of applications for
permits and requests for permissions of that entity related to a project or activity, for a
public purpose under the jurisdiction of the Department of the Army, including Section 10,
Section 404, and Section 408. The Secretary must ensure that the use of such funds will
not impact impartial decision making with respect to permits and permissions, either
substantively or procedurally. The Secretary has delegated decision-making
responsibility on the acceptance of funds under Section 214 to the Chief of Engineers
and his authorized representatives, including District Commanders of USACE.
2
Reason for the Contribution of Funds.
By correspondence dated 31 August, 2018, CPRA has requested CEMVN to expedite
the evaluation of a Joint DA Section 10/404 Permit Application and a Section 408
permission request to be submitted by CPRA for the Project, and has stated CPRA's
intent to provide the funds necessary to expedite the permit and permission evaluations
and processing.
How the District's Acceptance of Funds Will Expedite the Process.
Funds received from CPRA will be used by CEMVN in accordance with the provisions of
Section 214, and all applicable USACE guidance and regulations. Activities conducted in
accordance with the Funding Agreement must expedite the review process, and may
include generally shorter review times as compared to typical review times, facilitation of
a smoother review process through improved coordination and communication, and/or
the development or use of programmatic agreements or standard operating procedures.
The District Commander shall designate a Section 408 Coordinator responsible for
ensuring the processes set forth in applicable USACE regulations are met, and that the
proper coordination occurs among all necessary CEMVN elements, including but not
limited to, regulatory, real estate, office of counsel, planning, engineering, programs and
project management, and/or operations. CEMVN shall expedite the evaluation of the
Section 408 request in accordance with the terms and conditions of the Funding
Agreement to be executed by CEMVN and CPRA.
Types of Activities on Which the Funds Will Be Expended.
Prior to expending funds on any activity, CEMVN shall determine that the activity
contributes to meeting the specific purpose of the appropriate authorities (i.e., Section
10/404 and Section 408). Funds provided by CPRA will be primarily expended on direct
labor, salaries, and overhead for CEMVN personnel performing expedited Section 10/404
and Section 408 permitting and permission processing activities for the Project. Examples
of CEMVN tasks and activities for which the funds may be expended include, but are not
limited to: application intake review, permit database entry, jurisdictional determinations,
jurisdictional delineation verifications, functional or conditional assessment verifications,
public scoping meetings, preparation of public notices, drafting of correspondence,
conducting the public interest review, meetings with CPRA, preparation of draft permit
decision documents, engineering, technical, policy analyses, real estate evaluation, risk
analysis, District-led Agency Technical Review, technical writing, copying and other
clerical/support tasks, site visits, travel, coordination activities, training, field office set up
costs, technical contracting, programmatic tool development and improvement,
acquisition of geographic information system data, additional personnel (including
support/clerical staff), contracting support for technical services and environmental
reviews and the filing of the environmental compliance documents, early coordination
activities such as National Environmental Policy Act ("NEPA")/404 synchronization
procedures, and any other permit evaluation related activities that are mutually agreed
upon in writing by the parties.
3
Funds may be used to contract discrete tasks to inform decisions or conduct
administrative actions. If contracts are used to develop decision documents or other
NEPA documentation, such documents must be drafts only, and shall be reviewed and
evaluated independently by the USACE decision-maker to determine whether it is
appropriate before Section 408 and Section 10/404 decisions can be made. Funds may
be used to contract discrete tasks to inform decisions or conduct administrative
actions. Funds may also be expended for administrative tasks associated with
maintaining and tracking the work completed under the Funding Agreement.
The funds provided shall not be used to cover administrative expenses related to the
issuance of real property instruments required if the Section 408 permission is granted.
Those administrative costs for drafting, negotiating, or issuing any necessary real estate
instruments, may be accepted under the provisions of 10 U.S.C. 2695.
No funds will be used by the Division or District Commanders for their review,
recommendation, or decision concerning Section 408 or Section 10/404 requests. Funds
will not be expended for review of the decision-maker's decision.
CEMVN will provide an annual report on the Funding Agreement to CECW-CO-R as
required by USACE Guidance.
Procedures to Ensure Funds Will Not Impact the District's Impartial Decision
Making.
In order to ensure the funds accepted from CPRA are expended for the intended purposes,
CEMVN shall establish a separate account for expenditures for the Joint DA Section
10/404 permit application processing, and a separate account for expenditures for the
Section 408 permission request processing, in the USACE Financial Management
System to track the acceptance and expenditure of funds in acco rda nce with the
USA CE cu rrent f isc a l yea r bud get e xe cut io n guidan ce. CE MV N personnel
accomplishing the technical and administrative tasks required to expedite the evaluation
of the Joint DA Section 10/404 permit application and the Section 408 request shall
charge their time against the specific applicable account when working on those requests.
Regulatory funds can only be used for Section 10/404 actions, which may include actions
associated with the Section 408 request. Regulatory staff can use Regulatory funds to
participate in joint meetings and internally coordinated portions of shared documents
when the Section 408 request also requires a Section 10/404 action. Regulatory funds
cannot be used to develop or coordinate any components of the Section 408 request
independent of a Section 10/404 action. If the Section 408 request requires Division or
HQUSACE coordination and/or review, no Section 10/404 permit decision documentation
will be forwarded to Division or HQUSACE in order to preserve the independent decisionmaking authority of CEMVN and Division Commander. If the Section 408 request requires
Division or HQUSACE coordination and/or review, no Section 10/404 permit decision
documentation will be forwarded to Division or HQUSACE in order to preserve the
independent decision-making authority of CEMVN and Division Commander; however,
the coordination/review materials will clearly articulate that the Section 10/404 permit
decision is also required for this project.
4
The Section 408 Coordinator shall ensure that the processes in USACE regulations are
met and that the proper coordination occurs among all necessary CEMVN elements. The
Section 408 Coordinator will track CEMVN expenditures, including funding provided by
CPRA for expediting the processing of the Section 408 request by federal fiscal year basis
by funding source. The District Commander, or his authorized designee, shall designate
a Regulatory Project Manager to oversee the Section 10/404 permit application
processed by CEMVN to ensure that USACE regulations are met and that proper
coordination occurs among CEMVN elements. The Regulatory Project Manager will
coordinate as necessary with the Section 408 Coordinator, throughout their respective
evaluations.
HQUSACE maintains a Regulatory Section 214 informational web page at
https://www.usace.army.mil/Missions/Civil-Works/Regulatory-Program-andPermits/Section-214/ that includes a copy of all approved 214 Funding Agreements by
State, a link to all permit decisions made under those Funding Agreements, and general
information about Funding Agreements. CEMVN also provides a link to the HQUSACE
Regulatory Section 214 informational web page from the CEMVN permitting web page
located at http://www.mvn.usace.army.mil/Missions/Regulatory/Permits/
The permission request and permit application reviews conducted by CEMVN shall follow
the same procedures for decisions that would otherwise be required for the evaluation of
permits and permissions for similar projects or activities not carried out using funds
authorized under Section 214. CEMVN shall not eliminate any procedures or decisions
that would otherwise be required for the Project and reviews under consideration, and
shall comply with all applicable laws, regulations, policies, and guidance. However,
process improvements that are developed by CEMVN can be shared in order for all
members of the general public to benefit. No prescribed procedures, analyses,
decisions, or other activities will be eliminated, curtailed, or omitted by CEMVN for
purposes of expediency.
All final permit and permission decision documents, including all reporting and state
programmatic permit verifications, shall be reviewed and approved in writing by a
responsible official, at least one level above the decision maker. The decision maker is
the person that has been delegated signature authority. The one-level-above review must
be a position that is not partially or fully funded by the same funding entity. For example,
if the decision maker is a Regulatory Section Chief, then the one-level-above reviewer
may be the Regulatory Chief or Deputy Chief. Team leaders are appropriate one-level
above reviewers provided signature authority has been delegated to the project manager
level.
If the Section 408 approval authority is at the level of the USACE Director of Civil Works,
CEMVN through the Mississippi Valley Division, shall provide sufficient information to
assure the decision maker that the acceptance and expenditure of funds by CEMVN
under the Funding Agreement has not affected the District's or the Division's evaluation
of the Section 408 request, either substantively, or procedurally. Draft technical
documents or draft decision documents shall be reviewed and signed by unfunded
reviewers prior to consideration by the Division or District Commander. No funds received
5
shall be expended for the District Commander's consideration and recommendation to
the Director of Civil Works regarding CPRA's Section 408 request.
All preliminary jurisdictional determinations and any approved jurisdictional
determinations where funds are used must have documentation that a non-funded
regulator conducted a review of the determination.
Funds will not be used under the Funding Agreement for enforcement activities. However,
funds received under the Funding Agreement may be used for compliance activities
including monitoring of mitigation sites and compliance inspections. If the district
determines that a permittee has violated the terms or conditions of the permit and that the
violation is sufficiently serious to require an enforcement action, funds provided under the
agreement must not be used to address the enforcement action.
Impacts of the Proposed Funding Agreement on the District's Civil Works
Program.
CEMVN does not expect the Funding Agreement and the expedited review of the CPRA
Section 10/404 permit application and the Section 408 permission request to negatively
impact the District's Civil Works Program, or to increase the time for evaluations of other
projects submitted to CEMVN by the general public.
Impacts of the Proposed Funding Agreement on the District's Ability to Review
Other Section 408 Requests.
Activities conducted under the Funding Agreement will not result in an adverse effect on
the timeframes for review of other Section 408 requests within the New Orleans District,
when considered collectively. The Funding Agreement will not negatively impact
CEMVN's ability to review other Section 408 requests nor will it increase the time frames
for evaluations of Section 408 requests submitted to CEMVN by the general public.
Impacts of the Proposed Funding Agreement on the District's Regulatory
Program.
CEMVN does not expect the Funding Agreement to negatively impact the CEMVN's
Regulatory Program, or to increase the time frames for evaluations of applications for
the general public with CEMVN. CEMVN anticipates that the benefits of implementing
this expedited review process will result in an enhanced evaluation capability for all
participants.
Consideration of Comments.
This Special Public Notice has been issued, posted, and published on the CEMVN
webpages:
http://www.mvn.usace.army.mil/Missions/214Agreement/214PublicNotices.aspx
and
http://www.mvn.usace.army.mil/Missions/Regulatory/Public-Notices/
and has also been distributed to concerned agencies, and organizations, and the
interested public. There is a twenty (20) calendar day public comment period pursuant
to this Public Notice. Comments will be made part of the Administrative Record and
6
considered in determining whether it would be in the public interest to proceed with this
action. If the CEMVN District Commander determines, after considering the public
comments, that the acceptance and expenditure of the funds is appropriate and in
compliance with Section 214 and it is not otherwise contrary to the public interest, the
CEMVN District Commander will document the decision in a Memorandum for Record
and an Informational Public Notice will be issued regarding the District Commander's
final decision. CEMVN will post the informational Public Notice on the CEMVN webpage
at: https://www.mvn.usace.army.mil/Missions/214-Agreement/214-Public-Notices/ in
the same location used for this Special Public Notice and will distribute the Public Notice
to concerned agencies, organizations, and the interested public.
CEMVN will implement the Funding Agreement through a signed Memorandum of
Agreement ("MOA") for the purpose of establishing the framework for the acceptance
and expenditure of funds provided by CPRA to expedite the evaluation and processing
of the Section 10/404 permit application, the Section 408 permission request, and the
acceptance of the funds from CPRA. Provided that the purpose of accepting funds
remains the same as that described in this Special Public Notice, a new Public Notice is
not required in the event that the MOA is amended to extend the term of the MOA, or to
adjust the terms of the annual advance payment contemplated by the MOA. However,
an updated analysis is required and must be documented each time that a funding
agreement is renewed or substantially modified.
Submission of Comments.
Interested parties may submit written comments related to this Special Public Notice of
the proposed intent of CEMVN to accept and expend funds under Section 214, for the
expedited processing of the DA Section 10/404 permit application and the Section 408
permission request to be submitted for the Project by CPRA. All comments must be
post-marked by the comment due date of October 31, 2018. All comments should refer
to this Special Public Notice dated October 11, 2018, "Proposed CPRA Section 214
Funding Agreement". Comments must be sent to:
The United States Army Corps of Engineers, New Orleans District
Programs and Project Management Division
ATTN: Brad L. Inman, Chief, Projects and Restoration Branch
7400 Leake Ave
New Orleans, Louisiana 70118
Alternatively comments may be sent electronically to: Brad L. Inman at
Brad.L.Inman@usace.army.mil Email comments must be received no later than October
11, 2018
For additional information regarding the Section 10/404 permit process, please contact
Martin S. Mayer at (504) 862-2255 or by email to Martin.S.Mayer@usace.army.mil