You can copy from here when filling out the rest of the page.
Proposed Discharge of Fill Material, and Construction of a House and Deck on Pilings in wetlands adjacent to Lake Michigan at Suttons Bay, Michigan
Please see attachment for full Public Notice.
Public Notice
US Army Corps
of Engineers
Detroit District
Applicant:
Elizabeth Davis
In Reply Refer To:
Corps File No. LRE-2017-00460-56-S18
October 19, 2018
November 17, 2018
Date:
Expires:
Proposed Discharge of Fill Material, and Construction of a House and Deck on
Pilings in wetlands adjacent to Lake Michigan at Suttons Bay, Michigan
Applicant: Elizabeth Davis, 28510 West River Road, Perrysburg, Ohio 43551
Project Location: The site is located at 49 South Nanagosa Trail, Suttons Bay,
Section 35, Township 30N, Range 11W, Leelanau County, Michigan, 49682.
Federal Authority: The applicant has applied for a Department of the Army permit
under Section 404 of the Clean Water Act.
State Authority: Section 401 of the Clean Water Act requires that all discharges of
dredged or fill material must be certified by the State as complying with applicable
effluent limitations and water quality standards. Coastal Zone Management Certification
(or waiver thereof) is required from the State of Michigan if this proposed activity would
occur within the designated coastal zone.
Project Description: As shown on the attached plans, the applicant proposes the
following work: Install temporary construction mats in an approximate 10-foot-long by 8foot-wide by 1-foot-deep wetland area located approximately 7 feet south of the north
property line, and about 23 feet east of the center line of South Nanagosa Trail. Install
temporary construction mats in an approximate 100-foot-long by 8-foot-wide by 1-footdeep wetland area located parallel to, and approximately 10 feet north of the south
property line; and about 68 feet east of the center line of South Nanagosa Trail.
Discharge a total of approximately 5 cubic yards of fill material in a 15-foot-long by an
average 1-foot-wide by 1-foot-deep wetland area, and in a 28-foot-long by an average
4-foot-wide by 1-foot-deep wetland area to construct a driveway/turnaround. The
discharge areas are located approximately 28 feet east of the center line of South
Nanagosa Trail, and about 18 feet north of the south property line. Construct 832
square feet of a single family house on pilings over a wetland area located
approximately 217 feet east of the center line of South Nanagosa Trail, and about 16
feet north of the south property line. The entire footprint of the house would be 1,400
square feet. Construct a 24-foot-long by 12-foot-wide deck on pilings spaced 8-14 feet
apart over a stream and adjacent wetland located approximately 8 feet landward of the
File No. LRE-2017-00460-56-S18
October 19, 2018
Ordinary High Water Mark elevation of 581.5 feet (International Great Lakes Datum,
1985) on Lake Michigan. Construct a 100-foot-long by an average 9-foot-wide
boardwalk on pilings over a wetland parallel to, and approximately 10 feet north of the
south property line; and located about 68 feet east of the center line of South Nanagosa
Trail. The purpose of the proposed work is to prepare the site for the construction of a
residence, driveway, and garage; and to provide access to Lake Michigan.
Avoidance & Minimization: The applicant has stated the following concerning
avoidance and minimization of impacts to Waters of the United States: "The project
maximizes the use of available uplands and minimizes wetland impacts to the extent
reasonably possible. A modest-sized driveway and small stand-alone garage will
minimize the need for fill. A boardwalk constructed on pilings will connect the driveway
and garage to the house, as opposed to a filled driveway being constructed directly to
the house. The portion of the house over the wetland will be constructed on pilings. A
monolithic septic tank system will be installed in an upland area (pending approval by
the Health Department). Utilities will be installed by jack boring from upland to upland
as opposed to trenching. The stream cut is the only place that will allow construction of
the deck and lake access, considering the steep slope along the shoreline. The deck
will be constructed on pilings placed outside of the stream and adjacent wetland."
The Corps has not verified the adequacy of the applicant's avoidance and minimization
statement at this time.
Compensatory Mitigation: The applicant has stated the following concerning
compensatory mitigation for unavoidable impacts to Waters of the United States: The
applicant has stated that compensatory mitigation is not necessary or appropriate for
the proposed work because: "The impact will result in less than 1/3 acre of impact to
waters of the United States; therefore mitigation is not necessary."
The Corps has not verified the adequacy of this mitigation proposal at this time.
Other Authorizations: A permit is required from the Michigan Department of
Environmental Quality under applicable provisions of the Natural Resources and
Environmental Protection Act (NREPA), 1994 PA 451. The State file number is 45-011460-049-01 S NANAGOSA TR-SUTTONS BAY.
2
File No. LRE-2017-00460-56-S18
October 19, 2018
Comments: We are publishing this notice in compliance with Title 33 Code of Federal
Regulations Parts 320-332. Comments on the project should be submitted in writing
and postmarked or delivered by the expiration date of this public notice. Comments of a
positive or negative nature may be submitted. All responses must refer to file number
LRE-2017-00460-56-S18. We will interpret a lack of response as meaning that there is
no objection to the permit application. Comments should be filed with:
Kerrie E. Kuhne
Chief, Permit Evaluation Western Branch
Regulatory Office
Detroit District, Corps of Engineers
477 Michigan Avenue
Detroit, Michigan 48226-2550
Comments may be e-mailed to: april.r.champion@usace.army.mil, but must include a
name and mailing address.
Public Hearing: Any person may request, in writing, within the comment period
specified in this notice, that a public hearing be held to consider this application.
Requests for public hearings shall state, with particularity, the reasons for holding a
public hearing.
Evaluation: The decision whether to issue the Department of the Army permit will be
based on evaluation of the probable impacts of the proposed activity on the public
interest. That decision will reflect the national concerns for both protection and
utilization of important resources. The benefit which reasonably may be expected to
accrue from the proposal must be balanced against its reasonably foreseeable
detriments. All factors which may be relevant to the proposal will be considered
including the cumulative effects thereof; among those are conservation, economics,
aesthetics, general environmental concerns, wetlands, historic properties, fish and
wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion
and accretion, recreation, water supply and conservation, water quality, energy needs,
safety, food and fiber production, mineral needs, considerations of property ownership,
and, in general, the needs and welfare of the people.
The Corps of Engineers is soliciting comments from the public; Federal, State, and local
agencies and officials; Indian Tribes; and other interested parties in order to consider
and evaluate the impacts of this proposed activity. Any comments received will be
considered by the Corps of Engineers to determine whether to issue, modify, condition
or deny a permit for this proposal. To make this decision, comments are used to assess
impacts on endangered species, historic properties, water quality, general
environmental effects, and the other public interest factors listed above. Comments are
3
File No. LRE-2017-00460-56-S18
October 19, 2018
used in the preparation of an Environmental Assessment and/or an Environmental
Impact Statement pursuant to the National Environmental Policy Act. Comments are
also used to determine the need for a public hearing and to determine the overall public
interest of the proposed activity.
This activity involves the discharge of dredged or fill material into waters of the United
States. Therefore, the U.S. Army Corps of Engineers' evaluation of the impact of the
activity on the public interest will include application of the guidelines promulgated by
the Administrator of the Federal Environmental Protection Agency, under the authority
of Section 404(b)(1) of the Clean Water Act.
Endangered Species: We will review this application for the potential impact on
threatened or endangered species pursuant to Section 7 of the Endangered Species
Act as amended. We are not aware of the presence of any listed species or critical
habitat at or in the vicinity of the proposed worksite. We invite information and/or
comments regarding the potential presence of, or impacts to, any listed species or
critical habitat.
Cultural Resources: The District Staff has reviewed existing information on historic
properties potentially affected by the proposed project, including the National Register
of Historic Places. There are no recorded historic properties within the permit area.
The proposed work is of such a limited nature and extent that little likelihood exists for
the project to impinge upon an unrecorded historic property.
The District Engineer invites responses to this public notice from federal, state and local
agencies, historical and archaeological societies, Indian tribes, and other parties likely to
have knowledge of or concerns with historic properties in the area.
Additional Information: This public notice and drawings are also available for
viewing/printing at:
http://www.lre.usace.army.mil/Missions/RegulatoryProgramandPermits/PublicNotices.as
px. Questions concerning this application may be directed to April Champion at the
Corps of Engineers address listed above, or telephone number (313) 226-5380.
FOR THE DISTRICT ENGINEER:
Kerrie E. Kuhne
Chief, Permit Evaluation Western Branch
Regulatory Office
4
File No. LRE-2017-00460-56-S18
October 19, 2018
NOTICE TO POSTMASTERS:
We request that the above notice be conspicuously and continuously posted for the time
period of this notice.
5