This project proposes to add a new site to the Montana Aquatic Resources Services in-lieu fee program to generate compensatory mitigation credit to offset unavoidable impacts to waters of the United States. The project proponent is proposing to construct a siphon to divert water from Big Muddy Creek into an abandoned historic channel of the creek and to construct a channel plug, within the historic channel, at the southwest portion of the project boundary, in order to restore the water table depth within the existing salt flat wetland. The preliminary site plan proposes to generate 81.5 wetland mitigation credits (57 credits from preservation of existing wetlands and 24.5 credits from restoration of salt flat wetlands and rehabilitation of the stream channel.
This project proposes to add a new site to the Montana Aquatic Resources Services in-lieu fee program to generate compensatory mitigation credit to offset unavoidable impacts to waters of the United States. The project proponent is proposing to construct a siphon to divert water from Big Muddy Creek into an abandoned historic channel of the creek and to construct a channel plug, within the historic channel, at the southwest portion of the project boundary, in order to restore the water table depth within the existing salt flat wetland. The preliminary site plan proposes to generate 81.5 wetland mitigation credits (57 credits from preservation of existing wetlands and 24.5 credits from restoration of salt flat wetlands and rehabilitation of the stream channel.
PUBLIC NOTICE
Omaha District
Application No: NWO-2011-01760-MTH
Applicant: Montana Aquatic Resources Services
(Wendy Weaver)
Waterway: Big Muddy Creek
Issue Date: October 26, 2018
Expiration Date: November 27, 2018
30 DAY NOTICE
Missoula Regulatory Office | 1600 North Avenue West | Suite 105
Missoula, Montana 59801
PUBLIC NOTICE
FOR MARS' IN LIEU FEE MITIGATION SITE SUBMITTED TO
U.S. ARMY CORPS OF ENGINEERS,
in cooperation with the Interagency Review Team (IRT)
SUBJECT: The U.S. Army Corps of Engineers, Omaha District (Corps) is evaluating a
request by Montana Aquatic Resources Services (MARS) to add an In-Lieu Fee (ILF)
compensatory mitigation site to the Program's Instrument, established in January 2013.
This proposed mitigation site would cover the Lower Missouri Watershed District. This
notice may also be viewed at the Corps web site at:
http://www.nwo.usace.army.mil/Missions/Regulatory-Program/Montana/Public-Notices/
The project described herein is not being proposed by the Corps, but by the
applicant; the Corps will evaluate the proposed work to determine if it is
allowable under current laws and regulations.
AUTHORITY: The purpose of this public notice is to evaluate the potential of this
proposed site plan to adequately compensate for wetland impacts authorized under
Section 404 of the Clean Water Act.
LOCATION: The approximately 265-acre project site, including approximately 7 acres of
historic stream channel and approximately 30 acres of salt flat wetland is located in the
eastern portion of the Fort Peck Indian Reservation adjacent to Medicine Lake National
Wildlife Refuge, in the Manning Lake Wetlands Complex (Complex), near Big Muddy
Creek within the NW ¼ NW ¼ Section 9, Township 29 North, Range 54 East, Latitude
48.28728°, Longitude -104.71345°, Roosevelt County, Montana.
PROJECT DESCRIPTION: The purpose of the proposed wetland mitigation project is
to provide compensatory wetland mitigation credit for 20 advance wetland credits sold
to the Montana Department of Transportation (MDT). This was a bulk credit sale
transaction and there were no permits at the time of the sale. Additionally, this project is
U.S. ARMY CORPS OF ENGINEERS OMAHA DISTRICT
http://www.nwo.usace.army.mil/Missions/Regulatory-Program/Montana/Public-Notices/
CENWO-ODR-MT
Page 2
Action ID: NWO-2011-01760-MTH
proposed to provide mitigation for 2.09 advance wetland mitigation credits sold to offset
permitted impacts to 1.39 acres of emergent wetland adjacent to the Missouri River.
The project proponent is proposing to construct a siphon to divert water from Big Muddy
Creek into an abandoned historic channel of the creek and to construct a channel plug,
within the historic channel, at the southwest portion of the project boundary, in order to
restore the water table depth within the existing salt flat wetland. The preliminary site
plan proposes to generate 81.5 wetland mitigation credits (57 credits from preservation
of existing wetlands and 24.5 credits from restoration of the salt flat wetlands and
rehabilitation of the stream channel). The conceptual layout of the project is provided in
Figure 3 of the attached proposed site plan.
HISTORIC PROPERTIES: The Corps is lead federal agency for determining
compliance with Section 106 of the National Historic Preservation Act for this project
and will complete a cultural resource review of the project site in conjunction with their
obligations under Section 106 and the National Environmental Policy Act. The Corps
has not determined effects to properties eligible for listing on the National Register of
Historic Properties.
ENDANGERED SPECIES: The proposed activity has the potential to affect the
following Federally-listed endangered (e) or threatened (t) species: northern long-eared
bat (t), piping plover (t), and whooping crane (e). There is no designated critical habitat
within the permit area. Effects to species and critical habitat will be evaluated after a
Draft Site Plan has been submitted.
EVALUATION FACTORS: The decision whether to approve the proposal will be based
on an evaluation of the overall proposed activity on the public interest. That decision will
reflect the national concern for both protection and utilization of important resources. The
benefits which reasonably may be expected to accrue from the proposed activity must be
balanced against any reasonably foreseeable detriments. All factors which may be relevant
to the proposal will be considered. This Public Notice allows the public to provide
comments or concerns about the project which will be considered before a decision is made
to notify MARS to proceed with a Draft Mitigation Site Plan.
COMMENTS: The Corps of Engineers is soliciting comments from the public; Federal,
state, and local agencies and officials; Indian Tribes; and other interested parties in order
to consider and evaluate the impacts of this proposed activity. Any comments received
will be considered by the Corps of Engineers to determine whether to issue, modify,
condition or deny this proposal. To make this decision, comments are used to assess
impacts on endangered species, historic properties, water quality, general environmental
effects, and the other public interest factors listed above. Comments are also used to
determine the need for a public hearing and to determine the overall public interest of the
proposed activity. All public notice comments will be considered public information and
will be subject to review by the applicant.
Any person may request, in writing and within the comment period specified in this notice,
that a public hearing be held for the purpose of gathering additional information.
U.S. ARMY CORPS OF ENGINEERS OMAHA DISTRICT
http://www.nwo.usace.army.mil/Missions/RegulatoryProgram/Montana.aspx
CENWO-ODR-MT
Page 3
Action ID: NWO-2011-01760-MTH
Requests for public hearings must be identified as such and shall state specifically the
reasons for holding a public hearing and what additional information would be obtained.
The request must be submitted to the U.S. Army Corps of Engineers, at the Missoula
Regulatory Office, 1600 North Avenue West, Suite 105, Missoula, Montana 59801. If it is
decided that additional information is required and that a public hearing should be held,
interested parties will be notified of the date, time and location.
Any interested party (particularly officials of any town, city, county, state, or Federal
agency; Indian tribe; or local association whose interests may be affected by the work) is
invited to submit to this office written facts, arguments, or objections on or before the
expiration date listed on the front of this notice. Any agency or individual having an
objection to the work should specifically identify it as an objection with clear and specific
reasons. Comments, both favorable and unfavorable, will be accepted, made a part of
the record and will receive full consideration in subsequent actions on this application. All
replies to the public notice should be addressed to Nathan Green at the Missoula
Regulatory Office, 1600 North Avenue West, Suite 105, Missoula, Montana 59801, by
email at Nathan.J.Green@usace.army.mil, or telephone at (406) 541-4845 extension 323.
Please refer to identification number NWO-2011-01760-MTH in any correspondence
concerning this project.
Comments postmarked after the expiration date of this public notice, or received by fax or
e-mail after the expiration date, will not be considered. Comments left on our voicemail
system will not be considered.
Attachments: Proposed Site Plan
U.S. ARMY CORPS OF ENGINEERS OMAHA DISTRICT
http://www.nwo.usace.army.mil/Missions/RegulatoryProgram/Montana.aspx
Proposal for Modification of In-Lieu Fee Program Instrument
Proposed Site Plan
Manning Lake Salt Marsh Flat Wetland Restoration Project on
Fort Peck Tribal Lands
Lower Missouri Watershed District (#12)
OCTOBER 2018
Prepared for:
U.S. Army Corps of Engineers
Regulatory Program
Omaha District Headquarters
1616 Capitol Ave., Ste. 9000
Omaha, NE 68102
Prepared by:
Montana Aquatic Resources Services, Inc.
Statewide In-Lieu Fee Mitigation Program
P.O. 338
Livingston, MT 59047
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
Proposed Amendment to the MARS Approved ILF Program Instrument
Modification of an approved Instrument, including the addition and approval of new in-lieu fee
(ILF) project sites or expansions of previously approved ILF project sites, must follow the
appropriate Instrument amendment procedure outlined in Section 332.4 and Section 230 of the
Army Corps of Engineers (ACOE) and Environmental Protection Agency (EPA) 2008 Final
Compensatory Mitigation Rule.
This amendment proposal is submitted to the ACOE District Engineer following the outline and
requirements of the 2008 Final Rule at Sections 332.4(c)(2) through (14). As stated, the ILF
program sponsor must prepare and obtain ACOE approval for a mitigation plan including items
in paragraphs (c)(2) through (c)(14) of that section for each new compensatory mitigation
project site, and submit an Instrument amendment proposal for the new mitigation site.
(1) Introduction
Montana Aquatic Resources Services (MARS) has identified a potential restoration project on
the Fort Peck Indian Reservation, Roosevelt County, northeast Montana within the Lower
Missouri Watershed (Watershed #12) (Figure 1). The project occurs both within and
immediately adjacent to the Manning Lake Wildlife Refuge.
The Assiniboine and Sioux Tribes of the Fort Peck Indian Reservation (Tribes) hold a great
respect for and desire to conserve and protect all species. The traditional culture of the
Assiniboine and Sioux people focuses around the various fish and wildlife species that we share
with the earth. In line with this philosophy, the Tribes are working toward the conservation,
protection, and restoration of what may be one of the most unique and valuable wetland
complexes in the state of Montana. The Manning Lake Wetlands Complex (Complex), an
extensive wetland/wet meadow complex along with adjacent upland habitats, lies in the
eastern portion of the Fort Peck Indian Reservation near Big Muddy Creek. Adjacent to
Medicine Lake National Wildlife Refuge, the Complex is an incredible, unique landscape
providing vital breeding and rearing habitat for a diversity of waterfowl, shore birds, songbirds,
and other species of conservation concern. The Complex was nominated by the Tribes and
designated by Montana Audubon in 2008 as an Important Bird Area (IBA) of Montana.
This plan outlines the conceptual restoration plan, general information about each of the 12
different components of a mitigation plan, and identified specific next steps the project will
take if initially approved by the U.S. Army Corps of Engineers to proceed.
(2) Objectives
MARS' goal for this project is to restore, enhance, and preserve a salt marsh flat area on the
Manning Lake Wildlife Refuge of the Fort Peck Indian Reservation in the Lower Missouri
Watershed (#12) in 2018/2019 using mitigation fees resulting from two credit sales. The
proposed compensatory mitigation project proposes to offset the impacts to wetlands
resources with in-kind, in-watershed restoration (Figure 1).
The primary objectives of this compensatory mitigation project are to:
Proposal for Modification of In-Lieu Fee Program Instrument Proposed Site Plan
Manning Lake Salt Marsh Flat Wetland Restoration in Lower Missouri Watershed District (#12)
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
1.) Restore the frequency and duration of inundation and soil saturation of a salt marsh
flat that was impacted by the channelization of Big Muddy Creek that occurred at
some point prior to 1946 (aerial photos earlier than this were not immediately
found),
2.) Restore partial flows to a 2.6 mile segment of the historic alignment of Big Muddy
Creek, and
3.) Preserve these resources via a 25-yr, auto-renewing lease with the Tribal Council
and a deed restriction with one landowner.
Related Credit Sales
The first credit sale occurred on July 26, 2016 for 20 advance wetland credits to the Montana
Department of Transportation (MDT). This was a bulk credit sale transaction and there were no
permits at the time of the sale. On August 27, 2018, MDT provided information on future
projects that will debit from the MARS sale and include the following:
· Bainville-East (PE II, NH-MT1-MT(63)659, CN#6388001) which will impact 1.65
acres of wetland. This permit has not been submitted yet.
· Culbertson - East (NH-MT 1-10(85)6464, CN # 6388002) which will impact 1.01
acres of wetland. The 404 application was submitted August 14, 2018 and are
anticipating a permit at the end of September.
· Westby-West (STPP 30-(3)16, CN #7953000) which will impact approximately 3
acres of wetland. This permit has not been submitted yet.
The second credit sale transaction using mitigation fees anticipated is a wetland credit sale to
BNSF Railway for 2.09 wetland credits for permanent impacts to 1.39 acres of emergent
wetland adjacent to the Missouri River.
The project area falls on both the Fort Peck Indian Reservation and a private parcel owned by
Mark Wolff. MARS originally contacted Deb Madson from the Office of Environmental
Protection to discuss opportunities to work with the tribe for wetland restoration to become a
partner in the project and to bring funds to facilitate restoration and preservation of the
wetland area on these lands.
(3) Site selection
The Manning Lake Salt Flat Marsh restoration site was selected because:
1) the site's hydrology has clearly been degraded by historic agricultural practices through
the straightening and channelization of Big Muddy Creek in this area adjacent to
Manning Lake, thereby creating an opportunity for restoration to take place;
2) supports goals and objectives from the Comprehensive Conservation and Management
Plan for the Manning Lake Wetland Tribal Wildlife Refuge;
3) offsets impacts to wetland areas in the Lower Missouri Watershed for mitigation
responsibilities contracted by MARS (see previous sub-section on Related Credit Sales);
and
4) addresses threats identified in the Compensation Planning Framework (CPF) for this
watershed (CFR §332.8(c). Threats to the Lower Missouri watershed, articulated in
MARS' approved Compensation Planning Framework for Watershed District #12, include
pg. 3
Proposal for Modification of In-Lieu Fee Program Instrument Proposed Site Plan
Manning Lake Salt Marsh Flat Wetland Restoration in Lower Missouri Watershed District (#12)
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
oil and gas development, certain agricultural practices, transportation infrastructure,
dams, urban and residential developments and invasive species.
Securing management protection for the Complex is a necessary step towards avoiding and/or
reducing the effects of such possible threats. However, extending management protection
over the Complex is complicated by the diverse mixture of tribal trust, allotted trust, and fee
lands. Trust land is defined as land that is held in trust by the United States government for
Indian owners. Tribal trust land is collectively owned by a tribe(s) while allotted trust land is
owned by a single or multiple Indian owners. Allotted trust lands are often highly
fractionalized, with a forty acre parcel potentially having sixty or more owners, all holding
varying percentages of undivided ownership interest.
Determining the current lease status of allotted land can be complicated as lease contracts may
be secured through agreements with the Bureau of Indian Affairs (BIA), Tribal Natural Resource
Department, or through private agreement, making record searches difficult. In addition, many
owners are not actively involved in the management of their lands, many live out of state, and
some do not keep up their contact information to date. BIA leases require a minimum of 51%
interest approval, which depending on the number of interest holders, can be a lengthy
process. Trust land leases are secured through either the BIA or a private agreement with the
landowner(s). The standard length of business leases are 10 years and run from January 1
December 31st. Lease bidding for BIA managed trust lands opens in the fall of the lease end
year. Current Complex-area business leases for pasture lands start at $4/acre.
To simplify management strategies within the Complex, the Tribes passed Resolution #2392008-01, designating a portion of the Complex as the Manning Lake Wetlands Tribal Wildlife
Refuge (Refuge) and authorizing the drafting of a Refuge Management plan. The Tribes are
striving to extend management protection over all available lands within the Refuge through
purchase or lease. (Spaur, 2014).
This in-lieu fee project is composed of two discrete tax parcels. The Salt Marsh is located on
both Fort Peck Indian Reservation lands and also a private landowner, Mark Wolff. As a part of
the mitigation project, the Fort Peck Tribe lands will be protected in perpetuity by auto
renewing 25-year leases and the private parcel will be protected by virtue of a deed restriction.
These land protections will be placed on the properties to protect the project from any future
human-caused disturbances and will run with the land so that it prohibits the current owners
(and its successors or assigns) from activities that will impact the sites (see Section X. Site
Protection Instruments and Appendix X for Cooperative Management Agreement and Deed
Restriction).
pg. 4
Proposal for Modification of In-Lieu Fee Program Instrument Proposed Site Plan
Manning Lake Salt Marsh Flat Wetland Restoration in Lower Missouri Watershed District (#12)
131
132
pg. 5
Proposal for Modification of In-Lieu Fee Program Instrument Proposed Site Plan
Manning Lake Salt Marsh Flat Wetland Restoration in Lower Missouri Watershed District (#12)
133
pg. 6
Proposal for Modification of In-Lieu Fee Program Instrument Proposed Site Plan
Manning Lake Salt Marsh Flat Wetland Restoration in Lower Missouri Watershed District (#12)
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
(4) Site protection instrument
The project site falls on both Fort Peck Indian Reservation tribal lands and a portion on private
landowner, Mark Wolff. MARS is currently in negotiations with the Tribal Council to establish
25-year auto-renewing land leases within a Cooperative Management Agreement and Mark
Wolff to establish a deed restriction. MARS has reserved sufficient funds to pay for these
permanent land protection agreements.
A copy of the Site Protection Agreements documents are provided in Appendix X.
(5) Baseline information
The project site occurs in the Glaciated Dark Brown Prairie Level IV Ecoregion that is part of the
larger Northwestern Glaciated Plains Level III Ecoregion. The Glaciated Dark Brown Prairie
ecoregion is characterized as rolling glacial drift plains with gravel benches and scattered paleodunes (Woods et al. 2002). The prairie is considered semi-arid, with precipitation generally
ranging from 11 to 16 inches annually. Temperatures average a low of -6o F in January, to an
average high of 88o F in July (Woods et al. 2002). The land cover is comprised of a mosaic of
cropland and rangeland that has a potential climax community dominated by wheatgrassneedlegrass. Saline soils are common along the lower Big Muddy area (Woods et al. 2002).
Soils found at the site are mapped by the Natural Resources Conservation Service (NRCS) as soil
map unit 34 - Lallie silty clay, saline, 0 to 2 percent slopes. These soils are thought to have
formed in an ancient lakebed and have a clayey alluvium parent material. Soil texture is a silty
clay to a depth of 60 inches. This soil is very poorly drained, is slightly to strongly saline, and
typically has a maximum sodium adsorption ratio of 5.0. The project area is classified as a Wet
Meadow (WM) 10-14" p.z. (R053AE068MT) ecological site (NRCS 2018). A formal description
of this type of ecological site has not been finalized and is not currently available.
Agricultural uses in the Manning Lake area include haying, grazing and a small amount of
dryland farming. Most of the southern portion of the Refuge consists of marsh or open water.
While much of the Complex is currently in good condition due to its remote location and limited
usefulness for agricultural purposes, about 2,100 acres have been identified by the National
Wetland Inventory as drained wetlands. Potential threats to the Refuge include additional
drainage, energy development (including biomass production), overgrazing, breaking of native
prairie for farming, drought, invasive species, climate change, and complex ownership including
a high degree of land fractionalization. (Spaur 2014).
The Fort Peck Tribes Non-Point Source (NPS) Assessment report identified the Big Muddy Creek
watershed as moderately to severely impaired from pollutants such as excess sediment and
nutrients. Nitrogen and phosphorous were the specific non-point source nutrients of concern
in their report. The causes for increased sediment and nutrients were attributed to be livestock
grazing, dryland and irrigation farming, streambank erosion, and natural sources.
Grazing was also identified by the Montana Department of Environmental Quality as a source of
impairment to Big Muddy Creek water quality in their 2016 Water Quality Assessment Report
pg. 7
Proposal for Modification of In-Lieu Fee Program Instrument Proposed Site Plan
Manning Lake Salt Marsh Flat Wetland Restoration in Lower Missouri Watershed District (#12)
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
submitted to the U.S. Environmental Protection Agency Region VIII. Big Muddy Creek is rated
as impaired for the designated use of aquatic life (fish, shellfish, and wildlife protection and
propagation). The causes of impairment are similar to that of the Fort Peck Tribes NPS
Assessment Report and include nutrients (total nitrogen and total phosphorous), and
sedimentation/siltation due to agriculture and grazing.
Based on the site visit conducted on July 17, 2018, the proposed salt marsh mitigation site has
three distinct wetland habitats, salt flat, softstem bulrush marsh, and wetland meadows.
Photos of these areas are included in Appendix A.
Salt Flat - The salt flat is a sparsely vegetated area.
Softstem Bulrush Marsh The softstem bulrush marsh occurs near the center of the slat
flat, and that is relatively linear feature, oriented from north to south.
Wet Meadow Wet Meadow habitats occur within the old alignment of Big Muddy
Creek, as well as in the areas between the old channel alignment and the salt
flat.
Additional ecological information that will be collected/generated for this site includes:
· wetland delineation
· wetland functional assessment
· soil samples from the salt flat area
· topographic data
· comprehensive water budget
This information will be used to update the preliminary draft mitigation plan.
(6) Determination of Credits
MARS proposes to generate a minimum of 37 mitigation ratio-based credits from this project to
satisfy the 22.09 wetland credit obligation (Table 2). MARS estimated the wetland mitigation
credits using the compensatory wetland mitigation ratios provided by the ACOE's Omaha
District Montana Wetland Mitigation Procedure (January 2013). These credits are based on the
following components:
1.) Restoration of a more natural hydrologic regime to the salt flat site;
2.) Hydrologic restoration to the historic channel of Big Muddy Creek;
3.) Fencing to exclude livestock;
4.) Wetlands will be preserved through the restrictions imposed on the area by the
establishment of the Manning Lake Refuge and by 25 year auto-renewing land and
water lease agreements between the Tribal Council and MARS; and
5.) Adjacent buffer areas will also be preserved by 25-year auto-renewing land and water
lease agreements.
Any additional stream or wetland credits above those required to offset MARS current
obligations in the Watershed from the two credit sales discussed previously are proposed to be
certified by the Corps and available for MARS to use for additional sales in the watershed as
certified wetland credits to be sold at a 1:1 ratio.
pg. 8
Proposal for Modification of In-Lieu Fee Program Instrument Proposed Site Plan
Manning Lake Salt Marsh Flat Wetland Restoration in Lower Missouri Watershed District (#12)
222
223
224
225
226
227
228
The Draft Mitigation Plan will include the credit release schedule (see Section VI-C of the MARS
Final Instrument). The scheduled release of credits will correspond to the timeframe
established for Plan approval and completion of the monitoring of the compensatory mitigation
project to ensure that performance measures have been met.
Table 2. Wetland Credit Generation
Credit
Ratio*
Restoration (Rehabilitation)
Wetland Preservation
Upland Preservation
Total
Debits
229
230
231
232
233
234
235
236
237
1.5 to 1
4 to 1
5 to 1
--
Acres
Credits
To be determined
To be determined
265
81.5
22.09
59.41
37
228
24.5
57
Remaining Credits
* Ratios taken directly from the ACOE Omaha District's Wetland Compensatory Mitigation Ratios (April 2005).
(7) Mitigation work plan
The purpose of this project is to improve wetland health through hydrologic restoration to the
salt flat and the historic channel of Big Muddy Creek. The project will enhance native wetland
plant communities through this hydrologic restoration and site protection from grazing.
Increasing the frequency, duration, and consistency of site inundation will also support
migrating and breeding populations of waterfowl, sandpipers, and other wading birds. The
conceptual layout of the project is provided in Figure 3.
pg. 9
Proposal for Modification of In-Lieu Fee Program Instrument Proposed Site Plan
Manning Lake Salt Marsh Flat Wetland Restoration in Lower Missouri Watershed District (#12)
238
pg. 10
Proposal for Modification of In-Lieu Fee Program Instrument Proposed Site Plan
Manning Lake Salt Marsh Flat Wetland Restoration in Lower Missouri Watershed District (#12)
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
If approved by the Corps, MARS will complete the following activities and revise/update the
Draft Mitigation Plan:
1. Defining the geographic boundaries of the project A rough conceptual design has
been developed and with that design as a starting point for this proposal, MARS proposes to
implement creditable activities within that area. This area will be the basis for a lease
agreement with the Fort Peck Tribal Council and Mr. Wolff.
2. Securing water rights to support project: Determination of water right allocation for
project is necessary. Investigation into either a tribal water right allocation from Big Muddy
Creek or a state right from DNRC is ongoing. At this time MARS is working directly with the
Fort Peck Tribes to secure a portion of their total allocation for Big Muddy Creek for the salt
marsh mitigation site and has submitted an application for a beneficial water use permit to
the Water Resource Office. Additional and updated information on physical water
availability and water rights will be provided in the Draft Mitigation Site Plan.
3. Developing a water management plan A preliminary water budget was developed for
the site, indicating that a minimum of 65 ac-ft of water would be necessary to support the
site with water through the growing season. This estimate will be revised. MARS has
consulted and will continue to consult with the Tribes regarding water rights. Depending on
the interest and ability for the Fort Peck Tribes to supply water to the site, some
management parameters may need to be modified. More detail will be provided in the
Draft Mitigation Site Plan.
4. Conducting Soil Analyses Soil test pit analysis and testing has been completed to
determine levels of contaminants and naturally occurring salts found in the soils to inform
site restoration and management. Based on discussions with the Montana Salinity Control
Association and Energy Labs in Helena, specific tests will be conducted in the 0-6 inch and 6
to 24 inch depth classes for soil pH, conductivity, Lime, Sodium Adsorption Ratio (SAR),
Exchangeable Sodium Percentage (ESP), Sulfate/Chloride, Selenium, Arsenic, Cadmium, and
Boron. These soil testing results will be provided in the Draft Mitigation Site Plan.
5. Mapping baseline extent of wetlands found at the site. Details of the existing wetlands
will be provided in the Draft Mitigation Site Plan.
6. Executing prescribed construction methods, timing and sequence MARS proposes to
contract with Confluence Consulting to fully develop a site restoration plan for the site. This
will include designs for the proposed siphon to get water out of Big Muddy Creek, the
channel plug, and revegetation efforts. MARS will provide additional information in the
Draft Mitigation Site Plan once approval of the Amendment to MARS ILF Instrument is
granted by the Corps.
(8) Maintenance plan
The proposed leases will legally bind the Fort Peck Tribal Council, Mr. Wolff, and any future
owners to protect the restored wetland site, especially by prohibiting any uses that would limit
the wetland's ability to function at a high level. MARS is working on a cooperative agreement
with the Tribe regarding long-term management of the site. MARS or an independent third
party will monitor the leases to ensure that maintenance of the area continues and any
required adaptive management activities are initiated.
pg. 11
Proposal for Modification of In-Lieu Fee Program Instrument Proposed Site Plan
Manning Lake Salt Marsh Flat Wetland Restoration in Lower Missouri Watershed District (#12)
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
In addition, MARS will grant the Office of Environmental Protection (OEP) an endowment to
manage these parcels to the specifications in the Management Plans that MARS will complete
for each parcel. To assist with this maintenance, MARS will grant OEP an endowment using
long-term management funds to repair fences, maintain the siphon, and to conduct invasive
species treatments if needed.
(9) Performance standards
The following general areas of performance will be evaluated as part of the project and be
described in greater detail in the Draft and Final Mitigation Site Plans:
1.) Inundation of the historic channel and soil saturation with 12-inches of the ground
surface in the salt flat areas for a minimum of 12.5% of the growing season
(approximately 18 consecutive days per year);
2.) Habitat mapping to show how the increased hydrology is changing local plant
communities;
3.) Removal of disturbance by prohibiting livestock grazing and other activities from the
buffer area;
4.) Measuring success of native vegetative plantings; and
5.) Annual monitoring of the siphon to ensure it functions smoothly.
(10) Monitoring requirements
The preservation aspect of the mitigation project will be monitored continually by the Fort Peck
Tribe to ensure terms of the Deed Restriction/Conservation Easement are being adhered to.
Performance of the success of the restoration aspects of the project will be defined as
performance measures in the Final Site Mitigation Plan that MARS will develop. MARS will
monitor the site at least annually for a minimum of five consecutive years.
(11) Long-term management plan
MARS and the Fort Peck Tribe will enter into a long-term Cooperative Management Agreement
with responsibility to manage the site and any subsequent landowner in perpetuity. Deed
restriction/conservation easement monitoring by MARS or an independent third party will
ensure that the long-term management of the area continues to show that no further loss of
ecological function of the wetland or stream features within the project area has occurred.
(12) Adaptive management plan
Annual performance monitoring will indicate when adaptive management is required.
MARS intends that the mitigation project be maintained in perpetuity as 25-year auto renewing
leases and a deed restriction in the mitigation area. Steps to be taken in the event of the need
for adaptive management or enforcement of the land protection document terms and
conditions will be identified in the Draft Mitigation Plan.
(13) Financial assurances
pg. 12
Proposal for Modification of In-Lieu Fee Program Instrument Proposed Site Plan
Manning Lake Salt Marsh Flat Wetland Restoration in Lower Missouri Watershed District (#12)
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
MARS ILF Instrument stipulates that 17% and 13%, respectively, of the ILF fees collected for its
compensatory mitigation projects be dedicated to contingency and long-term management of
ILF projects statewide. MARS maintains those contingency and long-term management fees in
an interest-bearing, FDIC-insured account. (Note: According to the Final Mitigation Rule,
performance bonds, casualty insurance, letters of credit and other similar financial assurances
apply only to mitigation banks. Because this project is an In-Lieu Fee Compensatory Mitigation
Project, these forms of financial assurances are not included in MARS ILF Instrument and do not
apply.)
References
Fort Peck Assiniboine and Sioux Tribes, Office of Environmental Protection, FY 2017 Grant
Proposal NPS Management Grant CWA Section 319, 2017.
Natural Resources Conservation Service (NRCS). 2018. Web Soil Survey. Available URL:
https://websoilsurvey.sc.egov.usda.gov/App/WebSoilSurvey.aspx. Site accessed September
2019.
Spaur, Jeanne. 2014. Comprehensive Conservation and Management Plan for the Manning Lake
Wetland Tribal Wildlife Refuge 2014-2019. Fort Peck Tribes, Office of Environmental
Protection, Poplar, MT.
Woods, Alan J., J.M. Omernik, , J.A. Nesser, J. Shelden, J.S. Comstock, S.H. Azevedo, 2002,
Ecoregions of Montana, 2nd edition (color poster with map, descriptive text, summary
tables, and photographs). Map scale 1:1,500,000.
pg. 13
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
Appendix A - Site Photographs
Salt Flat Mitigation Site
Fort Peck Tribes' Manning Lake Wildlife Refuge
Fort Peck Indian Reservation, Montana
Proposal for Modification of In-Lieu Fee Program Instrument Proposed Site Plan
Manning Lake Salt Marsh Flat Wetland Restoration in Lower Missouri Watershed District (#12)
Photo 1. Example photo of the salt flat and adjacent
Photo 2. Example photo of the salt flat and the
Photo 3. Example of wet meadow habitats. The old
Photo 4. Example of the old channel of Big Muddy
wet meadow areas.
Big Muddy Creek channel is on the right side of the
photo.
softstem bulrush marsh.
Creek.
Photo 5. Facing downstream at the straightened and
channelized reach of Big Muddy Creek, just south of the
salt flat.
pg. 15
Proposal for Modification of In-Lieu Fee Program Instrument Proposed Site Plan
Manning Lake Salt Marsh Flat Wetland Restoration in Lower Missouri Watershed District (#12)
386
pg. 16