You can copy from here when filling out the rest of the page.
This notice announces a prospectus has been submitted for the development of the Buffalo Valley Stream Mitigation Bank (BVSMB) pursuant to 33 CFR 332, Compensatory Mitigation for Losses of Aquatic Resources (Federal Register: April 10, 2008, effective June 9, 2008).
Public Notice No. 18-48
Nashville District
Application No. LRN-2018-00680
Date: November 1, 2018; Expires: November 30, 2018
Please address comments to: Nashville District Corps of Engineers
Regulatory Division
3701 Bell Road, Nashville, TN 37214-2660
SUBJECT: This notice announces a prospectus has been submitted for the development of the Buffalo Valley Stream Mitigation Bank (BVSMB) pursuant to 33 CFR 332, Compensatory Mitigation for Losses of Aquatic Resources (Federal Register: April 10, 2008, effective June 9, 2008).
BANK SPONSOR: City of Johnson City
601 E Main Street
Johnson City, TN 37601
LOCATION: The proposed stream mitigation project encompasses 123 acres located in Unicoi County, Tennessee, approximately 5.9 miles southeast of Johnson City (Latitude N 36.229602, Longitude W -82.328816). The proposed mitigation project would incorporate approximately 2.4 miles (12,800 +/- linear feet) of buried, intermittent and perennial stream channels in the Buffalo Creek watershed, which is a tributary of Watauga River that ultimately flows into the Holston River.
PURPOSE: The BVSMB is proposed to provide compensatory stream mitigation for permitted impacts within the proposed geographic service area of the Watauga (06010103), South Fork Holton (06010102), and Nolichucky (06010108) HUC 8 watersheds.
GENERAL INFORMATION: Mitigation banks are defined as a site, or suite of sites, where aquatic resources (e.g., wetlands, streams, riparian areas) are restored, established, enhanced, and/or preserved for the purpose of providing compensatory mitigation for impacts authorized by Department of the Army (DA) permits pursuant to Section 10 of the Rivers and Harbors Act of 1899 and/or Section 404 of the Clean Water Act. In general, units of restored, established, enhanced or
preserved wetlands or streams are expressed as “credits” which may subsequently be withdrawn to offset “debits” incurred at a permitted project site. In this way, a permit requirement to provide compensatory mitigation can be transferred to the mitigation bank sponsor. The operation and use of a mitigation bank are governed by an approved mitigation banking instrument (MBI). The MBI is the legal document for the establishment, operation and use of a mitigation bank. This bank is intended to be a private commercial bank. The sponsor would be responsible for the successful development of the mitigation bank including monitoring and
reporting requirements.
A group of federal and state regulatory and resource agency representatives known as the Interagency Review Team (IRT) would oversee the execution and management of the project. The IRT is chaired by the US Army Corps of Engineers, Nashville District (USACE). The primary role of the IRT is to facilitate establishment of the mitigation site through the development of a MBI. The IRT will review the prospectus, instrument, and other appropriate documents and provide comments to the USACE.
Approval of the use of the bank for specific projects is the decision of the USACE pursuant to Section 10 of the Rivers and Harbors Act of 1899 and/or Section 404 of the Clean Water Act and/or the Tennessee Department of Environment and Conservation (TDEC) pursuant to Section 401 of the CWA and/or applicable state of Tennessee statute(s) and regulation(s).
PROJECT DESCRIPTION: The existing streams are degraded due to channelization, channel habitat modifications, and stream encapsulation. Prior land uses include modification of the watershed to support a golf course, which is the current state. Stream 1 is listed as ‘Fully Supporting’ by TDEC, and Stream 2 is listed as a ‘Non-Assessed Misc. Tributary to Buffalo Creek. The overall goal of the mitigation bank is to improve overall ecological function and stabilization of tributaries in the Buffalo Creek watershed, and to provide water quality and ecological benefits within the Buffalo Creek and Watauga watersheds of the Tennessee River Basin. The proposed project would consist of the restoration, re-establishment, and enhancement within the Buffalo Creek watershed by utilizing natural channel design techniques capable of providing a functional lift to natural channel hydrology, hydraulic, geomorphic, physiochemical, and biological characteristics. Of the approximately 12,800 linear feet in the project area, 10,005 feet would be restored, 2,709 feet would be reestablished, and 99 linear feet would be enhanced.
Specific project goals include: (1) restoration of dynamically stable stream channels to improve bedform diversity and lateral stability; (2) restore natural, stable dimensions, patterns and profiles to stream reaches using natural channel design techniques; (3) restore natural channel hydrology by removing culverts and impoundments and reattaching streams back to their relic floodplain; (4) decrease channel velocities by increasing channel sinuosity and improving floodplain connectivity; (5) install Large Woody Debris (LWD) and rock structures to improve aquatic habitat and lateral stability; (6) improve water quality by reducing non-point source pollution and in-stream sediment contribution through livestock exclusion; (7) increase re-oxygenation zones to improve water quality and biological integrity; (8) establish a minimum 50-foot riparian buffer with native vegetation to provide shade, increase stream bank stability, nutrient filtration, and habitat; (9) protect streams and riparian zones through land use restrictions; and (10) establish streams with adjacent floodplain wetlands to provide water benefits with the understanding that it could generate additional mitigation credits.
The project prospectus can be viewed bycontactingryan.evans@usace.army.mil.Information in the mitigation plan would serve as the basis for deriving and releasing credits for the mitigation bank.
HISTORIC AND CULTURAL RESOURCES: A search of the National Register returned no findings of historic properties currently listed on the National Register of Historic Places within the project area. A Phase I cultural/archaeological survey has not been conducted for the site. At this early stage in the regulatory process, no project design plans have been submitted; therefore, USACE cannot complete an effects determination for historic and cultural resources. The Corps invites
responses to this public notice from American Indian Tribes or tribal governments; federal, state, and local agencies; historical and archeological societies; and other parties likely to have knowledge of or concerns regarding historic properties and cultural significance at or near the project area. Upon submittal of the design plans, USACE would evaluate the design plans along with any substantive comments from this public notice to determine the potential of impacts to historic and cultural resources for Section 106 compliance. If the Corps determines that consultation is required, the Corps would consult with the Tennessee Historic Commission (SHPO) and American Indian Tribes in accordance with Section 106 of the National Historic Preservation Act, as appropriate.
ENDANGERED/THREATENED SPECIES REVIEW: A review of the United States Fish and Wildlife Service (USFWS) website, http://ecos.fws.gov/ipac identified the following federally-listed species that are known to or believed to occur near the proposed project area:
Species Nomenclature
Federal Status
Mammals
Carolina Northern Flying Squirrel
Glaucomys sabrinus coloratus)
Endangered
Gray bat (Myotis grisescens)
Endangered
Indiana bat (Myotis sodalis)
Endangered
Northern long-eared bat (Myotis septentrionalis)
Threatened
Flowering Plants
Virginia Spirea (Spirea virginiana)
Threatened
A copy of this notice is being furnished to USFWS for their review. After receipt of any comments, the USACE will evaluate the potential effects to proposed and/or listed species and their designated critical habitat, and initiate consultation with the U.S. Fish & Wildlife Service, if required.
COMMENT PERIOD: Written statements received by November 30, 2018 will become a part of the record and will be considered in the determination. Any response to this notice should be directed to the Nashville District Corps of Engineers, Regulatory Division, Attention: Mr. Ryan Evans at the above address or by email: ryan.evans@usace.army.mil.
\s\
Joshua W. Frost
Chief, Technical Services Branch
Regulatory Division
U.S. Army Corps of Engineers