Proposal to improve FAP Route 573 (Illinois Route 56) at Hankes Road, as well as two structures that carry Hankes Road over IL Route 56 and over Lake Run Creek. The proposed project would begin at Hankes Road approximately 92 feet west of the Norris Road intersection and extend 2,436 feet eastward, in the Village and Township of Sugar Grove, Kane County, Illinois.

PUBLIC NOTICE

APPLICATION FOR PERMIT

U.S. ArmyCorps of Engineers Chicago District

Public Notice/Application Number: LRC-2018-00498

Comment Period BEGINS: 11/6/2018 Comment Period Expires: 12/6/2018

U.S. Army Corps of Engineers

Applicant Anthony Quigley Illinois Department of Transportation 201 West Center Court Schaumburg, Illinois 60196-1096

Proposed Action Proposal to improve FAP Route 573 (Illinois Route 56) at Hankes Road, as well as two structures that carry Hankes Road over IL Route 56 and over Lake Run Creek. (See attached drawings). A detailed description of this proposal is provided on page 2 of this notice.

Location of Proposed Action The proposed project will begin at Hankes Road approximately 92 feet west of the Norris Road intersection and extend 2,436 feet eastward, in the Village and Township of Sugar Grove, Kane County, Illinois (Section 11, Township 38 N, Range 7 E) - Latitude 41.780988, Longitude -88.409285).

Interested parties are hereby notified that an application has been received for a Department of the Army permit for the activity described herein and as shown on the attached drawings. You are invited to provide your comments by December 6, 2018 on the proposed work, which will become part of the record and will be considered in the decision. A permit will be issued or denied under Section 404 of the Clean Water Act of 1972(33 U.S.C. 1344).

Written comments shall be mailed to:

U.S. Army Corps of Engineers Chicago District, Regulatory Branch Attn: LRC-2018-00498 – Julie Rimbault 231 South LaSalle Street, Suite 1500 Chicago, Illinois 60604-1437

It should be noted that ALL comments received by this office (via hard copy or electronic) will only be accepted with the full name and address, and email address, if available of the individual commenting, and must be received by the close of the public notice period. Electronic comments may be sent to the project manager at Julie.C.Rimbault@usace.army.mil.

Project Description IDOT is proposing to remove and replace the Hankes Road bridge structures over IL 56 and over Lake Run Creek due to the existing poor conditions of both bridges. The Hankes Road alignment will be shifted to the north so that the existing substandard curves can be straightened, and the profile will also be raised in order to accommodate the future reconstruction of IL 56. The project also proposes to replace a culvert over an unnamed intermittent tributary. Additional work includes the construction of storm sewers and drainage structures, cross-culverts under IL 56, pavement markings, shoulders, earthwork, erosion control, landscaping, compensatory storage ditch grading, and all incidental work necessary to complete the improvements.

In-stream work will be required for the construction of the bridge over Lake Run Creek, and will include earthwork for the abutments/piers, structure removal and replacement, temporary soil retention system, cofferdams, and riprap for scour protection.

The improvements will be completed using staged construction. Both bridges and the dual box culverts under IL 56 (north of the proposed Hankes Rd. bridge over IL 56) will be constructed utilizing traffic shifts and temporary pavement as shown in the staging plans. During stage 1, traffic along IL 56 will be shifted to the west side of the roadway so that the box culvert section under the east side of IL 56 can be constructed. During stage 2, traffic will be shifted to the east side of IL 56 so that the remaining box culvert section under the west side of IL 56 can be constructed. During stage 3, the north side of Hankes Road, north and south sides of the bridge over IL 56 as well the north side of the bridge over Lake Run Creek will be built. Finally, the south side of Hankes Road and the south side of the bridge over Lake Run Creek will be completed during stage 4.

Project purpose: improve the safety of the road by replacing two bridges that are in poor condition, realigning the road and straightening out substandard curves; improve access control and system linkage and continuity by shifting the road alignment to accommodate for future partial interchange; and reduce flooding by raising the profile of the road.

The following impacts and compensatory mitigation are proposed:

Site Impacted

Type

Station

Impact Acreage

Reason

Proposed Mitigation

Site 1

Wet meadow

24+00-38+00

1.92 acres

Embankment Fill

1.5:1 ratio 2.88 credits

Site 2

Wet floodplain forest

32+00-34+20

0.37 acres

Embankment Fill

1.5:1 ratio 0.56 credits

Site W1

Lake Run Creek Perennial stream

38+20

0.06 acres

Bridge Construction, channel excavation and scour protection

1.5:1 ratio 0.09 credits

Site W2

Unnamed intermittent tributary

29+00-30+50

0.01 acres

Culvert Replacement

1.5:1 ratio 0.015 credits

Total

2.36 perm

3.55 credits

Site 1 is a wet meadow dominated by reed canary grass, with a Native Floristic Quality Index of 11.87 and Native Mean C value of 2.4. Site 2 is a wet floodplain forest dominated by black willow and reed canary grass, with a Native Floristic Quality Index of 9.7 and Native Mean C value of 2.3.

Avoidance & Minimization The applicant has stated the following concerning avoidance and minimization of impacts to Waters of the United States: Impacts to the wetland were minimized firstly by implementing 1:3 embankment slopes to reduce the area of disturbance within the slope intercepts. Wetland impacts were further minimized when the proposed profile of Hankes Road was lowered after a revised FEMA study was released and contained lower flood elevations than in the prior study.

Regulatory Authority This proposed action will be reviewed according to the provisions of Section 404 of the Clean Water Act of 1972.

Jurisdiction This application will be reviewed according to the provisions of Section 404 of the Clean Water Act of 1972 due to placement of fill within stream tributaries and wetlands.

Evaluation Factors The decision whether to issue a permit will be based on an evaluation of probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments.

All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people. In addition, if the proposed activity involves the discharge of dredged or fill material into waters of the United States, the evaluation of the impact on the public interest will include application of Section 404(b)(1) guidelines (40 CFR 230) promulgated by the U.S. Environmental Protection Agency.

The Corps of Engineers is also soliciting comments from the public, Federal, state and local agencies, Indian tribes, and other interested parties in order to consider and evaluate the potential impacts of the proposed activity. Once this office completes a review of the comments received, it will be determined whether to issue, modify, condition, or deny a permit for this proposal.

To prepare this decision, comments are taken into consideration to assess impacts on the public interest factors listed above, as well as endangered species, historic properties, water quality, and general environmental effects. Comments will be used in the preparation of an Environmental Assessment and/or Environmental Impact Statement pursuant to the National Environmental Policy Act. A determination concerning the need for a public hearing will also be based on the comments received.

Preliminary Evaluation of Selected Factors

Water Quality: The applicant has applied to the Illinois Environmental Protection Agency (IEPA) for water quality certification, or waiver thereof, for the proposed activity in accordance with Section 401 of the Clean Water Act. Certification or waiver indicates that the IEPA believes the activity will not violate applicable water quality standards. The review by the IEPA is conducted in accordance with the Illinois water quality standards under 35 Illinois Administrative Code Subtitle C by providing an antidegradation assessment, which includes an evaluation of alternatives to any proposed increase in pollutant loading that may result from this activity.

The "Fact Sheet" containing the antidegradation assessment for this proposed project may be found on the IEPA's web site, at www.epa.state.il.us/public-notices/. In the event that the IEPA is unable to publish the "Fact Sheet" corresponding to the timeframe of this Joint Public Notice, a separate public notice and "Fact Sheet" will be published by the IEPA at the web site identified above. You may also obtain a copy of the "Fact Sheet" by contacting the IEPA at the address or telephone number shown below.

Written comments concerning possible impacts to water quality should be addressed to the following agency, along with a copy of the comments provided to the Corps of Engineers:

Illinois Environmental Protection Agency Bureau of Water Watershed Management Section 1021 N. Grand Avenue East P.O. Box 19276 Springfield, Illinois 62794-9276

If you have any questions please contact the IEPA at (217) 782-3362.

Department of Natural Resources: The applicant may have to submit an application to the Illinois Department of Natural Resources, Office of Water Resources (IDNR-OWR) for a permit pursuant to the State of Illinois Rivers, Lakes and Streams Act (615 ILCS 5). Comments concerning the IDNR-OWR permit should be addressed to the following agency, along with a copy of the comments provided to the Corps of Engineers:

Illinois Department of Natural Resources Office of Water Resources 2050 West Stearns Road Bartlett, Illinois 60103

If you have any questions please contact the IDNR at (847) 608-3116.

Endangered and Threatened Species: FHWA is the lead federal agency and has provided documentation that addresses compliance with Section 7 of the Endangered Species Act of 1973, as amended (16 U.S.C. 1531 et seq.). The Corps will evaluate the documentation and determine if it is sufficient to confirm Section 7 ESA compliance for this permit authorization.

Historic Properties/Cultural Resources: FHWA is the lead federal agency and is, therefore, responsible for ensuring compliance with Section 106 of the National Historic Preservation Act of 1966. The applicant provided a letter of concurrence, dated July 3, 2003, from the State Historic Preservation Officer indicating that the project will have no effect on historic properties subject to protection under Section 106 of the National Historic Preservation Act. Cultural clearance was updated on December 5, 2017 by IDOT’s qualified professional Cultural Resources staff with the same conclusion.

Environmental Impact Statement A preliminary determination has been made that an environmental impact statement is not required for the proposed work.

Public Hearing Any person may request in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. Requests for public hearing shall state with particularity the reasons for holding a public hearing. A request for a hearing may be denied if substantive reasons for holding a hearing are not provided or if there is otherwise no valid interest to be served.

It should be noted that materials submitted as part of the permit application become part of the public record and are thus available to the general public under the procedures of the Freedom of Information Act (FOIA). Individuals may submit a written request to obtain materials under FOIA or make an appointment to view the project file at the Chicago District Corps of Engineers Office of Counsel.

Interested parties wishing to comment on the proposed activity must do so in writing no later than December 6, 2018. It is presumed that all parties receiving this notice will wish to respond to this public notice; therefore, a lack of response will be interpreted as meaning that there is no objection to the project as described.

This public notice is not a paid advertisement and is for public information only. Issuance of this notice does not imply Corps of Engineers endorsement of the project as described.

If you have any questions, please contact Julie Rimbault, Project Manager, by telephone at (312) 846-5542, or email at Julie.C.Rimbault@usace.army.mil. It should be noted that ALL comments received by this office (via hard copy or electronic) will only be accepted with the full name and address of the individual commenting. You can also visit our website at http://www.lrc.usace.army.mil/Missions/Regulatory.aspx for more information on our program.

PUBLIC NOTICE APPLICATION FOR PERMIT U.S. ARMY CORPS OF ENGINEERS CHICAGO DISTRICT PUBLIC NOTICE/APPLICATION NUMBER: LRC-2018-00498 COMMENT PERIOD BEGINS: 11/6/2018 COMMENT PERIOD EXPIRES: 12/6/2018

U.S. Army Corps of Engineers APPLICANT Anthony Quigley Illinois Department of Transportation 201 West Center Court Schaumburg, Illinois 60196-1096 PROPOSED ACTION Proposal to improve FAP Route 573 (Illinois Route 56) at Hankes Road, as well as two structures that carry Hankes Road over IL Route 56 and over Lake Run Creek. (See attached drawings). A detailed description of this proposal is provided on page 2 of this notice. LOCATION OF PROPOSED ACTION The proposed project will begin at Hankes Road approximately 92 feet west of the Norris Road intersection and extend 2,436 feet eastward, in the Village and Township of Sugar Grove, Kane County, Illinois (Section 11, Township 38 N, Range 7 E) - Latitude 41.780988, Longitude 88.409285). Interested parties are hereby notified that an application has been received for a Department of the Army permit for the activity described herein and as shown on the attached drawings. You are invited to provide your comments by December 6, 2018 on the proposed work, which will become part of the record and will be considered in the decision. A permit will be issued or denied under Section 404 of the Clean Water Act of 1972(33 U.S.C. 1344).

-2Written comments shall be mailed to: U.S. Army Corps of Engineers Chicago District, Regulatory Branch Attn: LRC-2018-00498 ­ Julie Rimbault 231 South LaSalle Street, Suite 1500 Chicago, Illinois 60604-1437 It should be noted that ALL comments received by this office (via hard copy or electronic) will only be accepted with the full name and address, and email address, if available of the individual commenting, and must be received by the close of the public notice period. Electronic comments may be sent to the project manager at Julie.C.Rimbault@usace.army.mil. PROJECT DESCRIPTION IDOT is proposing to remove and replace the Hankes Road bridge structures over IL 56 and over Lake Run Creek due to the existing poor conditions of both bridges. The Hankes Road alignment will be shifted to the north so that the existing substandard curves can be straightened, and the profile will also be raised in order to accommodate the future reconstruction of IL 56. The project also proposes to replace a culvert over an unnamed intermittent tributary. Additional work includes the construction of storm sewers and drainage structures, cross-culverts under IL 56, pavement markings, shoulders, earthwork, erosion control, landscaping, compensatory storage ditch grading, and all incidental work necessary to complete the improvements. In-stream work will be required for the construction of the bridge over Lake Run Creek, and will include earthwork for the abutments/piers, structure removal and replacement, temporary soil retention system, cofferdams, and riprap for scour protection. The improvements will be completed using staged construction. Both bridges and the dual box culverts under IL 56 (north of the proposed Hankes Rd. bridge over IL 56) will be constructed utilizing traffic shifts and temporary pavement as shown in the staging plans. During stage 1, traffic along IL 56 will be shifted to the west side of the roadway so that the box culvert section under the east side of IL 56 can be constructed. During stage 2, traffic will be shifted to the east side of IL 56 so that the remaining box culvert section under the west side of IL 56 can be constructed. During stage 3, the north side of Hankes Road, north and south sides of the bridge over IL 56 as well the north side of the bridge over Lake Run Creek will be built. Finally, the south side of Hankes Road and the south side of the bridge over Lake Run Creek will be completed during stage 4. Project purpose: improve the safety of the road by replacing two bridges that are in poor condition, realigning the road and straightening out substandard curves; improve access control and system linkage and continuity by shifting the road alignment to accommodate for future partial interchange; and reduce flooding by raising the profile of the road.

-3The following impacts and compensatory mitigation are proposed: Site Impacted Site 1 Site 2 Site W1 Site W2 Total

Type Wet meadow

24+00-38+00

Impact Acreage 1.92 acres

Wet floodplain forest Lake Run Creek Perennial stream

32+00-34+20

0.37 acres

Embankment Fill

38+20

0.06 acres

29+00-30+50

0.01 acres

Bridge Construction, channel excavation and scour protection Culvert Replacement

Unnamed intermittent tributary

Station

2.36 perm

Reason Embankment Fill

Proposed Mitigation 1.5:1 ratio 2.88 credits 1.5:1 ratio 0.56 credits 1.5:1 ratio 0.09 credits 1.5:1 ratio 0.015 credits 3.55 credits

Site 1 is a wet meadow dominated by reed canary grass, with a Native Floristic Quality Index of 11.87 and Native Mean C value of 2.4. Site 2 is a wet floodplain forest dominated by black willow and reed canary grass, with a Native Floristic Quality Index of 9.7 and Native Mean C value of 2.3. AVOIDANCE & MINIMIZATION The applicant has stated the following concerning avoidance and minimization of impacts to Waters of the United States: Impacts to the wetland were minimized firstly by implementing 1:3 embankment slopes to reduce the area of disturbance within the slope intercepts. Wetland impacts were further minimized when the proposed profile of Hankes Road was lowered after a revised FEMA study was released and contained lower flood elevations than in the prior study. REGULATORY AUTHORITY This proposed action will be reviewed according to the provisions of Section 404 of the Clean Water Act of 1972. JURISDICTION This application will be reviewed according to the provisions of Section 404 of the Clean Water Act of 1972 due to placement of fill within stream tributaries and wetlands. EVALUATION FACTORS The decision whether to issue a permit will be based on an evaluation of probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments.

-4All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people. In addition, if the proposed activity involves the discharge of dredged or fill material into waters of the United States, the evaluation of the impact on the public interest will include application of Section 404(b)(1) guidelines (40 CFR 230) promulgated by the U.S. Environmental Protection Agency. The Corps of Engineers is also soliciting comments from the public, Federal, state and local agencies, Indian tribes, and other interested parties in order to consider and evaluate the potential impacts of the proposed activity. Once this office completes a review of the comments received, it will be determined whether to issue, modify, condition, or deny a permit for this proposal. To prepare this decision, comments are taken into consideration to assess impacts on the public interest factors listed above, as well as endangered species, historic properties, water quality, and general environmental effects. Comments will be used in the preparation of an Environmental Assessment and/or Environmental Impact Statement pursuant to the National Environmental Policy Act. A determination concerning the need for a public hearing will also be based on the comments received. PRELIMINARY EVALUATION OF SELECTED FACTORS WATER QUALITY: The applicant has applied to the Illinois Environmental Protection Agency (IEPA) for water quality certification, or waiver thereof, for the proposed activity in accordance with Section 401 of the Clean Water Act. Certification or waiver indicates that the IEPA believes the activity will not violate applicable water quality standards. The review by the IEPA is conducted in accordance with the Illinois water quality standards under 35 Illinois Administrative Code Subtitle C by providing an antidegradation assessment, which includes an evaluation of alternatives to any proposed increase in pollutant loading that may result from this activity. The "Fact Sheet" containing the antidegradation assessment for this proposed project may be found on the IEPA's web site, at www.epa.state.il.us/public-notices/. In the event that the IEPA is unable to publish the "Fact Sheet" corresponding to the timeframe of this Joint Public Notice, a separate public notice and "Fact Sheet" will be published by the IEPA at the web site identified above. You may also obtain a copy of the "Fact Sheet" by contacting the IEPA at the address or telephone number shown below. Written comments concerning possible impacts to water quality should be addressed to the following agency, along with a copy of the comments provided to the Corps of Engineers:

-5Illinois Environmental Protection Agency Bureau of Water Watershed Management Section 1021 N. Grand Avenue East P.O. Box 19276 Springfield, Illinois 62794-9276 If you have any questions please contact the IEPA at (217) 782-3362. DEPARTMENT OF NATURAL RESOURCES: The applicant may have to submit an application to the Illinois Department of Natural Resources, Office of Water Resources (IDNR-OWR) for a permit pursuant to the State of Illinois Rivers, Lakes and Streams Act (615 ILCS 5). Comments concerning the IDNR-OWR permit should be addressed to the following agency, along with a copy of the comments provided to the Corps of Engineers: Illinois Department of Natural Resources Office of Water Resources 2050 West Stearns Road Bartlett, Illinois 60103 If you have any questions please contact the IDNR at (847) 608-3116. ENDANGERED AND THREATENED SPECIES: FHWA is the lead federal agency and has provided documentation that addresses compliance with Section 7 of the Endangered Species Act of 1973, as amended (16 U.S.C. 1531 et seq.). The Corps will evaluate the documentation and determine if it is sufficient to confirm Section 7 ESA compliance for this permit authorization. HISTORIC PROPERTIES/CULTURAL RESOURCES: FHWA is the lead federal agency and is, therefore, responsible for ensuring compliance with Section 106 of the National Historic Preservation Act of 1966. The applicant provided a letter of concurrence, dated July 3, 2003, from the State Historic Preservation Officer indicating that the project will have no effect on historic properties subject to protection under Section 106 of the National Historic Preservation Act. Cultural clearance was updated on December 5, 2017 by IDOT's qualified professional Cultural Resources staff with the same conclusion. ENVIRONMENTAL IMPACT STATEMENT A preliminary determination has been made that an environmental impact statement is not required for the proposed work. PUBLIC HEARING Any person may request in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. Requests for public hearing shall state with particularity the reasons for holding a public hearing. A request for a hearing may be denied if

-6substantive reasons for holding a hearing are not provided or if there is otherwise no valid interest to be served. It should be noted that materials submitted as part of the permit application become part of the public record and are thus available to the general public under the procedures of the Freedom of Information Act (FOIA). Individuals may submit a written request to obtain materials under FOIA or make an appointment to view the project file at the Chicago District Corps of Engineers Office of Counsel. Interested parties wishing to comment on the proposed activity must do so in writing no later than December 6, 2018. It is presumed that all parties receiving this notice will wish to respond to this public notice; therefore, a lack of response will be interpreted as meaning that there is no objection to the project as described. This public notice is not a paid advertisement and is for public information only. Issuance of this notice does not imply Corps of Engineers endorsement of the project as described. If you have any questions, please contact Julie Rimbault, Project Manager, by telephone at (312) 846-5542, or email at Julie.C.Rimbault@usace.army.mil. It should be noted that ALL comments received by this office (via hard copy or electronic) will only be accepted with the full name and address of the individual commenting. You can also visit our website at http://www.lrc.usace.army.mil/Missions/Regulatory.aspx for more information on our program.

SEE INSTRUCTIONS FOR ADDRESS

LOCATION MAP FAP 573 (IL Route 56) At Hankes Road Bridge Replacement and Reprofiling Section 61HB-B Contract #: 60W52 Job #: D-91-309-13

N

PROJECT LOCATION

Revised 2011 Corps of Engineers

IL Dept of Natural Resources

IL Environmental Protection Agency

Applicant's Copy

36

_

56 U V

_

Site 1 Site 1 1E ! !

1D

Site 2

_

2A

OSW 2

! !

Site 1

1C

!

2B 1B

!

! 1A

Lake Run Creek

_ OSW 1

_

Site 1

OSW 2

Site 1

H an

_

ke s

Roa d

Project Boundary Wetland Site

(

3A !

!

(3

Sampling Point Other Surface Waters

_

INHS/IDOT Wetland Science Program 1816 South Oak Street Champaign, Illinois 61820

Non-Wet Determination Site

Wetland Continues

Figure 5 Wetland Determination Map IL 56 (FAP 573) at Hankes Road - Addendum C Kane County Seq. No: 10851C 0

Meters

100

0

Feet

400

May 2018

q

SEEDING FOR LANDSCAPED MEDIAN

RIP RAP CLASS A4

EXTENDS TO LIMITS OF TEMPORARY 3 OAKS,

PAVEMENT (SEE IL 56 MOT PLANS)

25' O.C. 3 OAKS, 25' O.C. PROP.R. O. W.

+14. 8

+35. 6

RIP RAP CLASS A4

WETLAND (TYP) W. O. PROP.R.

25+00

30+00

0 +0 20

3 0+00

PROP.R. O. W.

PROP. TEMP. EASEMENT

3 PINES, 15' O.C.

50'

50 9. +6

+47. 8

RIP RAP CLASS A4

+27. 2

W. O. . .R ST I EX RIP RAP CLASS A5

56 TE. IL R NB

STA 18+90.00

MATCH LINE STA 32+00

0 50+0

75 9. +5 BEGIN IMPROVEMENTS

PROPOSED ~ HANKES ROAD

HANKES ROAD

6 E. 5 L RT SB I

5 7.2 +4

OAD IS R NORR

E XI ST.R. O. W.

RIP RAP CLASS A4 SELECTIVE MOWING STAKE (TYP)

+00 225

RIP RAP CLASS A5 3 OAKS, 25' O.C.

W. O. . ST. R EXI

+23. 30

W. O. PROP.R.

0 45+0

W. O. . ST. R EXI EXIST. R.O.W.

0+00 4

END IMPROVEMENTS +00 5 3

STA 43+26.32 TREE, SWAMP WHITE OAK

W. O. . R. PROP

HANKES ROAD +47. 95

EVERGREEN, LIMBER PINE +97. 00

MATCH LINE STA 32+00

+71. 50

RIP RAP CLASS A4 (TYP) )

WETLANDS

SEEDING, CLASS 2A

CENTER OF LAKE

TOPSOIL EX. AND PLACE (4")

RUN CREEK EDGE OF WATER (TYP)

SEEDING, CLASS 4B

+26. 50

TOPSOIL EX. AND PLACE (6")

W. O. R. ST. EXI

SEEDING, CLASS 4A (MODIFIED) SEEDING, CLASS 5A (MODIFIED) TOPSOIL EX. AND PLACE (6")

WETLAND (TYP)

STONE RIPRAP (CL. A4 OR A5) WITH FILTER FABRIC SELECTIVE MOWING STAKE W/ SIGN

HANKES ROAD

DESIGNED

-

MTC

REVISED

-

DRAWN

-

MTC

REVISED

-

STATE OF ILLINOIS

PLOT SCALE = 100.0000 ' / in.

CHECKED

-

JIP

REVISED

-

DEPARTMENT OF TRANSPORTATION

PLOT DATE

DATE

-

03/20/2018

REVISED

-

USER NAME

= WTeng

BLA, Inc. ITASCA, ILLINOIS

= 8/31/2018

ITEM

CL. 2A SEEDING

RATE

QUANTITY

NITROGEN FERTILIZER NUTRIENT

4.50 AC

90 LBS/AC

405 LBS

4.50 AC

90 LBS/AC

405 LBS

IL ROUTE 56 AT HANKES RD LANDSCAPING PLAN

F.A.P RTE.

SECTION

COUNTY

573

61HB-B

KANE

TOTAL SHEET SHEETS NO.

179

74

CONTRACT NO. 60W52 SCALE: 1" = 50'

SHEET

1

OF

1

SHEETS

STA. N/A

TO STA.

N/A

ILLINOIS FED. AID PROJECT

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas