The applicant proposes modifications to their existing permit.

Full Public Notice Permit Plans

PROJECT DESCRIPTION: The applicant proposes to modify their existing permit by (1) changing the slip configuration; (2) increase the dredging depth; (3) armor the bottom of the slip with concrete articulating mat; (4) add hydraulic, bed-leveling, and water injection dredging; and (5) add dredge material placement areas.