Stalp Gravel Greta Roth Property - The applicant has proposed to amend the existing Standard Permit authorized, May 17, 2016. The existing Standard Permit was authorized as follows: The project is a sand and gravel mining operation. The project involves removing existing vegetation and then excavating soil overburden to expose sand and gravel deposits. Those materials will then be extracted and sorted by use of a floating dredge operation. Materials mined will be sorted and processed at a facility to be constructed in an upland site location on the property. Mined areas will be backfilled with unused overburden sand, soil and gravel materials concurrently as mining progresses. Mining will impact about 83 acres out of the 100-acre property site including 2.71 acres of wetlands. It is estimated that 1.53 acres of wetlands impacted will be filled and converted to uplands and 1.18 acres will be converted to open water. Hydric soils located in the overburden layer will be stockpiled for use in final grading of a compensatory wetland mitigation site planned for creation in the southwestern corner of the property. The anticipated life of the sand and gravel mining operation is ten years once the project starts. The following amendments have been proposed: Within the existing 100-acre permit area, the project involves removing additional vegetation and then excavating soil overburden to expose sand and gravel deposits within “Lake B”. Those materials will then be extracted and sorted by use of a floating dredge operation within “Lake B”. Materials mined will be sorted and processed at a facility to be constructed in an upland site location on the property. Additionally, unused overburden sand, soil and gravel materials will be discharged into the pond located approximately 1,100 feet east of “Lake B”, which is outside the previously authorized 100-acre permit area. It is estimated that an additional 0.45 acre of wetlands will be filled and converted to uplands. Filling and excavation activities associated with the previously authorized work and currently proposed work will permanently impact approximately 3.16 acres of wetlands to include: 2.21 acres of Palustrine Forested (PFO), 0.68 acre of Palustrine Emergent (PEM), and 0.27 acre of wetlands in an agricultural setting. The anticipated life of the sand and gravel mining operation is ten years once the project starts.
Stalp Gravel Greta Roth Property - The applicant has proposed to amend the existing Standard Permit authorized, May 17, 2016. The existing Standard Permit was authorized as follows: The project is a sand and gravel mining operation. The project involves removing existing vegetation and then excavating soil overburden to expose sand and gravel deposits. Those materials will then be extracted and sorted by use of a floating dredge operation. Materials mined will be sorted and processed at a facility to be constructed in an upland site location on the property. Mined areas will be backfilled with unused overburden sand, soil and gravel materials concurrently as mining progresses. Mining will impact about 83 acres out of the 100-acre property site including 2.71 acres of wetlands. It is estimated that 1.53 acres of wetlands impacted will be filled and converted to uplands and 1.18 acres will be converted to open water. Hydric soils located in the overburden layer will be stockpiled for use in final grading of a compensatory wetland mitigation site planned for creation in the southwestern corner of the property. The anticipated life of the sand and gravel mining operation is ten years once the project starts. The following amendments have been proposed: Within the existing 100-acre permit area, the project involves removing additional vegetation and then excavating soil overburden to expose sand and gravel deposits within “Lake B”. Those materials will then be extracted and sorted by use of a floating dredge operation within “Lake B”. Materials mined will be sorted and processed at a facility to be constructed in an upland site location on the property. Additionally, unused overburden sand, soil and gravel materials will be discharged into the pond located approximately 1,100 feet east of “Lake B”, which is outside the previously authorized 100-acre permit area. It is estimated that an additional 0.45 acre of wetlands will be filled and converted to uplands. Filling and excavation activities associated with the previously authorized work and currently proposed work will permanently impact approximately 3.16 acres of wetlands to include: 2.21 acres of Palustrine Forested (PFO), 0.68 acre of Palustrine Emergent (PEM), and 0.27 acre of wetlands in an agricultural setting. The anticipated life of the sand and gravel mining operation is ten years once the project starts.
PUBLIC NOTICE
Application No: NWO-2015-01403-WEH
Project Name: Stalp Gravel Greta Roth Property
Applicant: Stalp Gravel Company
Waterway: Wetlands Adjacent to the Elkhorn River
Issue Date: January 3, 2019
Expiration Date: January 24, 2019
21 DAY NOTICE
Reply To:
NEBRASKA REGULATORY OFFICE
8901 SOUTH 154TH STREET, SUITE 1, OMAHA, NEBRASKA 68138-3635
JOINT PUBLIC NOTICE: This public notice is issued jointly by the U.S. Army Corps of
Engineers (USACE), Omaha District, and the Nebraska Department of Environmental Quality
(NDEQ). The NDEQ will review the proposed project for state certification in accordance with
the provisions of Section 401 of the Clean Water Act. The NDEQ hereby incorporates this public
notice as its own public notice and procedures by reference thereto. For the purposes of the NDEQ,
their public notice will expire 30 calendar days from the issue date shown above.
AUTHORITY: Section 404 of the Clean Water Act (33 USC 1344).
APPLICANT: Stalp Gravel Company, 1598 River Road, West Point, Nebraska 68788.
PROJECT LOCATION: The project is located on the Greta Roth Property in Sections 3 and 4,
Township 23 North, Range 4 East, Cuming County, Nebraska. The center of the proposed sand
and gravel mining project is 42.00123, -96.96795.
PROJECT DESCRIPTION: The applicant has proposed to amend the existing Standard Permit
authorized, May 17, 2016. The existing Standard Permit was authorized as follows: The project
is a sand and gravel mining operation. The project involves removing existing vegetation and
then excavating soil overburden to expose sand and gravel deposits. Those materials will then be
extracted and sorted by use of a floating dredge operation. Materials mined will be sorted and
processed at a facility to be constructed in an upland site location on the property. Mined areas
will be backfilled with unused overburden sand, soil and gravel materials concurrently as mining
progresses. Mining will impact about 83 acres out of the 100-acre property site including 2.71
acres of wetlands. It is estimated that 1.53 acres of wetlands impacted will be filled and
converted to uplands and 1.18 acres will be converted to open water. Hydric soils located in the
overburden layer will be stockpiled for use in final grading of a compensatory wetland mitigation
1
site planned for creation in the southwestern corner of the property. The anticipated life of the
sand and gravel mining operation is ten years once the project starts.
The following amendments have been proposed: Within the existing 100-acre permit area, the
project involves removing additional vegetation and then excavating soil overburden to expose
sand and gravel deposits within "Lake B". Those materials will then be extracted and sorted by
use of a floating dredge operation within "Lake B". Materials mined will be sorted and processed
at a facility to be constructed in an upland site location on the property. Additionally, unused
overburden sand, soil and gravel materials will be discharged into the pond located
approximately 1,100 feet east of "Lake B", which is outside the previously authorized 100-acre
permit area. It is estimated that an additional 0.45 acre of wetlands will be filled and converted to
uplands. Filling and excavation activities associated with the previously authorized work and
currently proposed work will permanently impact approximately 3.16 acres of wetlands to
include: 2.21 acres of Palustrine Forested (PFO), 0.68 acre of Palustrine Emergent (PEM), and
0.27 acre of wetlands in an agricultural setting. The anticipated life of the sand and gravel mining
operation is ten years once the project starts. See plans and drawings included with this Public
Notice for further information on the project.
PROJECT PURPOSE: The applicant's purpose of the project is to dredge sand and gravel to
be used in the production of aggregate, fill and landscaping materials for regional commercial,
residential, and transportation projects.
The basic project purpose, as defined by the USACE, is sand and gravel mining.
The overall project purpose, as defined by the USACE, is to dredge sand and gravel to provide
aggregate, fill, and landscaping materials for residential, commercial, and transportation projects.
The anticipated service range of ninety percent of the aggregate produced would be about 25
miles and include the counties of Burt, Colfax, Cuming, Dakota, Dixon, Dodge, Platte, Stanton,
Thurston, and Wayne.
SPECIAL AQUATIC SITES: The project will permanently impact approximately 3.16 acres
of wetlands to include: 2.21 acres of Palustrine Forested (PFO), 0.68 acre of Palustrine
Emergent (PEM), and 0.27 acre of wetlands in an agricultural setting. The wetland delineation
will be reviewed further by the USACE during the permit evaluation process.
AVOIDANCE, MINIMIZATION, AND MITIGATION: This project is located in the Rock
Creek-Elkhorn River HUC 1022000304, 10-digit HUC. The applicant has provided avoidance
and minimization measures and alternatives that were evaluated to reduce or eliminate proposed
project impacts to wetlands. Those efforts include off-site locations considered with no impacts
to wetlands or off-site locations that had fewer impacts to wetlands. The applicant will avoid four
of the twelve wetland areas identified on site. The applicant proposed a conceptual compensatory
mitigation plan in the application for unavoidable project impacts which would involve creating
wetlands in the southwestern corner of the property in an upland forested area within the existing
mitigation site. The applicant proposes to establish a minimum 6.3 acre permittee responsible
2
mitigation site. The location of the proposed mitigation site is shown on drawings included with
this notice. A final mitigation plan completed in accordance with the 2008 mitigation rule will be
required to be submitted by the applicant and approved by the Corps prior to any permit
issuance.
CULTURAL RESOURCES: The USACE, Omaha District will comply with the National
Historic Preservation Act of 1966, and amendments and the procedures set forth in 33 CFR 325,
Appendix C. We have checked the National Register of Historic Places, and any available site
database information, and there are no known National Register sites in the vicinity.
Consultation between the Corps and Nebraska State Historic Preservation Office (SHPO) was
initiated for the previously authorized project with a determination of "no historic properties
affected". SHPO provided concurrence in a letter dated December 7, 2015. We will evaluate
input by the State Historic Preservation Office, Tribes, and the public in response to this public
notice, and we may conduct or require a survey of the permit area to check for unknown historic
or prehistoric properties, if warranted.
ENDANGERED SPECIES: The project is within the known range of the threatened Northern
Long-Eared Bat (Myotis septentrionalis) and Piping Plover (Charadrius melodusrand), as well
as, the endangered Interior Least Tern (Sternula antillarum athalassos). The project is outside
the current range of the endangered Pallid Sturgeon (Platanthera praeclara) however,
cumulative impacts from Platte River water depletions have the potential to impact the fish's
habitat. In compliance with the Endangered Species Act, a preliminary determination has been
made that the described work may affect, but is not likely to adversely affect the Northern LongEared Bat, the Piping Plover, the Interior Least Tern and the Pallid Sturgeon. Consultation
between the Corps and USFWS was initiated for the previously authorized project with a "may
affect, not likely to adversely affect" determination for the Northern Long-eared Bat, Interior
Least Tern, Piping Plover and Pallid Sturgeon. USFWS provided concurrence in a letter dated
December 23, 2015, provided special conditions were added to the permit to minimize impacts to
these species. Nebraska Game and Parks commented on the project and provided a determination
of "may affect, not likely to adversely affect" the Northern Long-eared Bat, and "no effect" for
all other state and federally listed species in a letter dated March 11, 2016. In order to complete
our evaluation of this activity, coordination with the U.S. Fish and Wildlife Service and other
interested agencies will be completed to determine the effects on the above listed species and/or
critical habitat.
FLOODPLAIN: This activity is being reviewed in accordance with Executive Order 11988,
Floodplain Management, which discourages direct or indirect support of floodplain development
whenever there is a practicable alternative. By this notice, comments are requested from
individuals and agencies that believe the described work will adversely impact the floodplain.
WATER QUALITY CERTIFICATION: Section 401 of the Clean Water Act (33 USC 1341)
requires that all discharges of fill material must be certified by the appropriate state agency as
complying with applicable effluent limitations and water quality standards. The discharge must
be certified before a Department of the Army permit can be issued. Certification, if issued,
3
expresses the State's opinion that the discharge will not violate applicable water quality
standards. It is the responsibility of the applicant to contact Nebraska Department of
Environmental Quality as soon as possible in the permitting process to discuss
requirements for certification. Please contact:
CWA Section 401 Coordinator
Water Quality Division, Planning Unit
Nebraska Department of Environmental Quality
1200 'N' Street, Suite 400
Lincoln, NE 68509-8922
Phone: 402.471.2875
Fax: 402.471.2909
E-mail: ndeq.401certification@nebraska.gov
PUBLIC INTEREST REVIEW: The decision whether to issue the USACE permit will be
based on an evaluation of the probable impacts including cumulative impacts of the
proposed/completed activity on the public interest. That decision will reflect the national concern
for both protection and utilization of important resources. The benefits, which reasonably may be
expected to accrue from the proposal, must be balanced against their reasonably foreseeable
detriments. All factors which may be relevant to the proposal will be considered including the
cumulative effects thereof; among those are conservation, economics, aesthetics, general
environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards,
floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply
and conservation, water quality, energy needs, safety, food and fiber production, mineral needs,
considerations of property ownership and, in general, the needs and welfare of the people. In
addition, the evaluation of the impact of the work on the public interest will include application
of the guidelines promulgated by the Administrator, Environmental Protection Agency, under
authority of Section 404(b) of the Clean Water Act (40 C.F.R. Part 230).
COMMENTS: The USACE is soliciting comments from the public, Federal, State, and Local
agencies and officials, Indian Tribes and other interested parties in order to consider and evaluate
the impacts of this activity. Any comments received will be considered by the USACE to
determine whether to issue, modify, condition or deny a permit for this project. To make this
decision, comments are used to assess impacts on endangered species, historic properties, water
quality, general environmental effects, and the other public interest factors listed above.
Comments are used in the preparation of an Environmental Assessment and/or an Environmental
Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to
determine the need for a public hearing and to determine the overall public interest of the
activity.
Anyone whose interests may be affected by the proposed/completed work is invited to submit
favorable or unfavorable written comments to the Nebraska Regulatory Office, 8901 South 154th
Street, Suite 1, Omaha, NE 68138-3635. The District Engineer is particularly interested in
receiving comments related to the proposal's probable impacts on the affected aquatic system's
functional values, cumulative and secondary effects and endangered species. All comments
4
received will be considered public information; copies of all comments, including names and
addresses of commenters, may be provided to the applicant unless confidentiality is requested.
Comments must be submitted on or before the expiration date (located at the top of the first
page) of this notice to be considered in the subsequent actions on this application.
PUBLIC HEARING: Before the expiration date of this notice, anyone may request, in writing,
that a public hearing be held to consider this application. Requests shall specifically state the
reason(s) for holding a public hearing. If the District Engineer determines that the information
received in response to this notice is inadequate for thorough evaluation, a public hearing may be
warranted. If a public hearing is warranted, interested parties will be notified of the time, date,
and location.
ADDITIONAL INFORMATION: Additional information about this application may be
obtained by writing to Mr. Drew Vlazny at the address shown on page one or by calling (402)
896-0896. You can also e-mail Andrew.J.Vlazny@usace.army.mil.
REQUEST TO POSTMASTERS: Please post this notice conspicuously and continuously
until the expiration date specified at the top of page one.
NOTICE TO EDITORS: This notice is provided as background information for your use in
formatting news stories. This notice is not a contract for classified display advertising.
5
=
Site
\
-..
NE-51 High-.v-y-
51
'
1
. Elkhorn River
Project Mgr.
Project No.
BLJ
Drawn By:
Vicinity Map
P2015.587.002
Scale
BLJ
1" = 4,000'
File Na.
Checked By:
ZAJ
P2015.587.002MP
Stalp Gravel - Greta Roth Property
E & A CONSULTING GROUP, INC.
NEY. of Section 4, Township
Engineering Answers
Approved By:
Date: 10/30/2015
ZAJ
10909 Mill Valle Road
PH. (402) 8954700
23 North, Range 4 East
Wisner, Nebraska
OMAHA, NE 68154
Exh.
ii
CHiCAGO
=t-=--= -==-=
I
'·
Projects\
_,..
·--
Project No.
Project Mgr.
BLJ
Topographic/Location Map
P2.015.587.002.
Scale
Drawn By:
1' = 1.000·
BLJ
File No.
Checked By:
ZAJ
Stalp Gravel - Greta Roth Property
E & A CONSULTING GROUP, INC.
P2.015.587.002.
NEY. of Section 4, Township
Engineering Answers
Date: 1/512015
Approved By:
ZAJ
10909 MiU Valle Road
PH. (402) 895-4700
23 North, Range 4 East
Wisner, Nebraska
OMAHA. NE 68154
Exh.
Project Name
Wetland Delineation Map - Dredge Placement Pond
Wisner AddHion
Scale
1· = 225'
Stalp Gravel - Greta Roth Property
FlleNo.
WOP
NE V. of Section 4, Township 23 North, Range 4 East
Wisner, Nebraska
Date: 11/15118
1598 River Road
PH. (402) 372·5491
West Point NE 66788