ADDITIONAL PILINGS AT EXISTING FACILITY IN THE MISSISSIPPI RIVER IN ASCENSION PARISH

NAME OF APPLICANT: Impala Warehousing (US), LLC, c/o Providence Engineering and Environmental Group, LLC, 1201 Main Street, Baton Rouge, Louisiana 70802.

LOCATION OF WORK: Within the Mississippi River Basin, in the Lower Mississippi River – Baton Rouge hydrologic unit (HUC 08070100), in the Mississippi River, left descending bank, mile marker 169.7, near Burnside, Louisiana, in Ascension Parish, as shown on the enclosed drawings.

CHARACTER OF WORK: The applicant has requested to modify their existing authorization to include the installation and maintenance of six 18-inch diameter batter piles and three 20-inch diameter batter piles to improve the structural integrity of the existing CBU walkway. Approximately 3,000 cubic yards of rip rap will be placed around the pilings when there is revetment present. Approximately 0.05 acre of open water will be impacted by the proposed activity. The applicant has minimized the impacts as much as practicable. No impacts to vegetated wetlands are anticipated, thus, no compensatory mitigation will be required.

JOINT PUBLIC NOTICE February 25, 2019 United States Army Corps of Engineers New Orleans District Regulatory Branch 7400 Leake Avenue New Orleans, Louisiana 70118

State of Louisiana Department of Environmental Quality Water Permits Division Post Office Box 4313 Baton Rouge, Louisiana 70821-4313

(504) 862-2675 Project Manager Jamie Crowe Jamie.M.Crowe@usace.army.mil Permit Application Number MVN 2011-02044 CO

(225) 219-3225 Project Manager Elizabeth Hill WQC Application Number WQC 190220-03

Interested parties are hereby notified that a permit application has been received by the New Orleans District of the U.S. Army Corps of Engineers pursuant to: [ X ] Section 10 of the Rivers and Harbors Act of March 3, 1899 (30 Stat. 1151; 33 USC 403); and/or [X] Section 404 of the Clean Water Act (86 Stat. 816; 33 USC 1344). Application has also been made to the Louisiana Department of Environmental Quality, Office of Environmental Services, for a Water Quality Certification (WQC) in accordance with statutory authority contained in LRS30:2047 A(3), and provisions of Section 401 of the Clean Water Act (P.L.95-17). ADDITIONAL PILINGS AT EXISTING FACILITY IN THE MISSISSIPPI RIVER IN ASCENSION PARISH NAME OF APPLICANT: Impala Warehousing (US), LLC, c/o Providence Engineering and Environmental Group, LLC, 1201 Main Street, Baton Rouge, Louisiana 70802. LOCATION OF WORK: Within the Mississippi River Basin, in the Lower Mississippi River ­ Baton Rouge hydrologic unit (HUC 08070100), in the Mississippi River, left descending bank, mile marker 169.7, near Burnside, Louisiana, in Ascension Parish, as shown on the enclosed drawings. CHARACTER OF WORK: The applicant has requested to modify their existing authorization to include the installation and maintenance of six 18-inch diameter batter piles and three 20-inch diameter batter piles to improve the structural integrity of the existing CBU walkway. Approximately 3,000 cubic yards of rip rap will be placed around the pilings when there is revetment present. Approximately 0.05 acre of open water will be impacted by the proposed activity. The applicant has minimized the impacts as much as practicable. No impacts to vegetated wetlands are anticipated, thus, no compensatory mitigation will be required.

The comment period for the Department of the Army Permit and the Louisiana Department of Environmental Quality WQC will close 30 days from the date of this joint public notice. Written comments, including suggestions for modifications or objections to the proposed work, stating reasons thereof, are being solicited from anyone having interest in this permit and/or this WQC request and must be mailed so as to be received before or by the last day of the comment period. Letters concerning the Corps of Engineers permit application must reference the applicant's name and the Permit Application Number, and be mailed to the Corps of Engineers at the address above, ATTENTION: REGULATORY BRANCH Letters concerning the Water Quality Certification must reference the applicant's name and the WQC Application number and be mailed to the Louisiana Department of Environmental Quality at the address above. The application for this proposed project is on file with the Louisiana Department of Environmental Quality and may be examined weekdays between 8:00 a.m. and 4:30 p.m. Copies may be obtained upon payment of costs of reproduction. Corps of Engineers Permit Criteria The decision whether to issue a permit will be based on an evaluation of the probable impacts, including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people. The U.S. Army Corps of Engineers is soliciting comments from the public, federal, state, and local agencies and officials, Indian Tribes, and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the U.S. Army Corps of Engineers to determine whether to make, modify, condition, or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. The New Orleans District is unaware of properties listed on the National Register of Historic Places near the proposed work. The possibility exists that the proposed work may damage or destroy presently unknown archeological, scientific, prehistorical,

historical sites, or data. Copies of this notice are being sent to the State Archeologist and State Historic Preservation Officer. Our initial finding is that the proposed work would not affect any species, nor affect any habitat designated as critical to the survival and recovery of such species, listed as endangered by the U.S. Department of Commerce. The New Orleans District has determined that the proposed project is located in waters known to be utilized by the pallid sturgeon (Scaphirhynchus albus) and determined that the proposed activity is not likely to adversely affect the species. This determination is based on the Standard Local Operating Procedure for Endangered Species of Louisiana (SLOPES), dated October 22, 2014, between the U.S. Army Corps of Engineers and U.S. Fish and Wildlife Service, Ecological Services Office. This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the Magnuson-Stevens Fishery Conservation and Management Act. The applicant's proposal would result in the destruction or alteration of n/a acres of EFH utilized by various life stages of red drum and penaeid shrimp. Our initial determination is that the proposed action would not have a substantial adverse impact on EFH or federally managed fisheries in the Gulf of Mexico. Our final determination relative to project impacts and the need for mitigation measures is subject to review by and coordination with the National Marine Fisheries Service. If the proposed work involves deposits of dredged or fill material into navigable waters, the evaluation of the probable impacts will include the application of guidelines established by the Administrator of the Environmental Protection Agency. Also, a certification that the proposed activity will not violate applicable water quality standards will be required from the Department of Environmental Quality, Office of Environmental Services, before a permit is issued. Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. Requests for public hearings shall state, with particularity, the reasons for holding a public hearing. You are requested to communicate the information contained in this notice to any other parties whom you deem likely to have interest in the matter. You are requested to communicate the information contained in this notice to any other parties whom you deem likely to have interest in the matter.

John M. Herman Chief, Central Evaluation Section Regulatory Branch Enclosure

So1n9<>1 Br1dg;, Rd

t

r.c"'nt1,".,c,;:. Rd

St Am.int

'I

N

~

S Cfrento

''I

....

ti

Project Center Latitude: 30.133911° Longitude: -90.923325°

· 1. I·

Dao.ii dsonvil le

Bell e Rose

; ~·

---Legend 2

*

0

2 Miles

Vicinity Map

u

Section 10 Permit Application Ascension Parish, LA

i5

..J ..J 0.

:>

Project Center

..

iii E E

Impala Warehousing (US) LLC

c

·~c

CSU Walkway Batter Pile Installation Project Drawn By

Reference Base map comprised of ESRI StreetMap USA data.

rfl!!I

w

TOJ

1018118

Checked By

BM

10/8118

Approved By

RPC

10/8118

"..c

.."' c

~

!;

"'

Project Number

c:

w

·

874-019

PROVIDENCE

Drawing Number

1

874-019-A001

Figure

.."' u

c:

·~

£

I

____ J

, /

XM1Je 171

\

POINT \ '8

i

\

l

M ilo , "1"" 159

11 - ~ _J \. I

2,000

Legend

*

1,000

- -

-

I

,

I /

0 Feet

Project Center

Site Location Map

u _,

Section 10 Pennit Application Ascension Parish, LA

c3 !!c

_, a.

"

0

.. ~

Impala Warehousing (US) LLC

~

c w

CBU Walkway Baller Pile Installation Project

Reference Base map comprised of United States Geological Survey (USGS) 7.5-minute topographic maps. "Gonzales. LA" and "Donaldsonville. LA".

r!Ja ·

PROVIDENCE

Drawn By

TDJ

10/8/18

Checked By

BM

10/8/18

Approved By

RPC

10/8/18

" .,2'c ~

]'

Project Numbor

874-019

"2

Drawing Numbor

2

874-019-A002

Foguro

1l

~

£

18" Batter Piling Latitude: 30.134368° Longitude: -90.923889° 18" Batter Piling Latitude: 30.134263° Longitude: -90.923755° 20" Batter Piling Latitude: 30.13382° Longitude: -90.923189°

20" Batter Piling Latitude: 30.13436° Longitude: -90.923902°

18'' Batter Piling Latitude: 30.133641° Longitude: -90.92293° 18'' Batter Piling Latitude: 30.133404° Longitude: -90.922641°

18" Batter Piling Latitude: 30.133792° Longitude: -90.92313°

60" Monopile Replacement Latitude: 30.133295° Longitude: -90.922554°

18'' Batter Piling Latitude: 30.133522° Longitude: -90.922775°

60" Monopile Replacement Latitude: 30.133241° Longitude: -90.92255°

20'' Batter Piling Latitude: 30.133457° Longitude: -90.922705°

200

100

0

Legend Proposed Installations 18" Batter Piling

Note

200 Feet

20" Batter Piling 60" Monopile Replacement Mississippi River Levee Centerline

Approximate distance from batter pilings to navigation centerline is 1,097' to 1,217'.

Reference Base map comprised of ESRI's World Imagery exported 10/8/18.

Aerial Photograph Section 10 Application Ascension Parish, LA

Impala Warehousing (US) LLC CBU Walkway Batter Pile Installation Project Drawn By

TDJ

01/10/19

Checked By

BM

01/10/19

Approved By

RPC

01/10/19

Project Number

Drawing Number

1

874-019-A013

Figure

874-019

Providence Engineering and Environmental Group LLC

Piling Size Minimum Distance from Levee Maximum Distance from Levee 18" 466' 530' 20" 470' 521' 60" 555' 573'

18" Batter Piling

18" Batter Piling

20" Batter Piling

CBU Cab Relocation Piling #3 (2015) CBU Cab Relocation Piling #4 (2015)

CBU Monopile #2 Installation (2018) CBU Monopile #1 Installation CBU Cab Relocation Piling #1 (2015) 20" Batter Piling

60" Monopile Replacement

18" Batter Piling 18'' Batter Piling

18'' Batter Piling 20'' Batter Piling 18'' Batter Piling

60" Monopile Replacement Proposed Tripod Dolphin #2

300

150

0

Legend

300 Feet

Previ o usly Perm i ttedDredg eAreas ( 4. 99acres) Previ o usly Perm i ttedLo cati ons Pro po sedPi li n g Lo ati ons 18"Batter Pi li ng 20"Batter Pi li ng

60"Mo n o pi leR eplacem en t

Reference

Basem ap co m pri sedo f ESR I 's Wo rldI m ag ery expo rted7/ 2/ 18.

Aerial Photograph Section 10 Application Ascen si o n Pari sh,Lo ui si an a

Impala Burnside Terminals LLC Burn si deT erm i n al Drawn By

T DJ

1/ 11/ 19

Approved By

R PC

1/ 11/ 19

Checked By

TK

Project Number

874019

Drawing Number

874019A014

1/ 11/ 19

2

Fi g ure

Pro vi den ceEn g i n eeri n g an dEn vi ro n m en tal Gro up LLC

Proposed Tripod Dolphin #1

100

100 -

Existing Facility

See Batter Pile Detail (Figure 5) 50

50 New Batter Pile(s) (18"/20"0 x 160'L)

0

~

u.

0

~

u.

I:

I:

0

0

;

;

> .2:!

> .2:!

m

w

m

-50

-50

-100

-100

-150

-150

w

Typical Batter Pile Cross Section Horizontal Scale: 1" = 100' Vertical Scale: 1" = 50'

100' 50'

Horizontal Scale: 1" = 100' 50' 0 25' 0 Vertical Scale: 1"

=50'

Typical Batter Pile Cross Section

100' 50'

~ _, Q.

§ <.:>

Section 10 Permi t Application

sc

Ascension Paris h , Louisiana

0

E

c

Impal a Warehousing (US) LLC

..

e

>c

CBU Walkway Batter Pile Installation Project

'l

PROVIDENCE

w

Drawn By

LMM

10/17/18

Checked By

LMM

10/17/18

Approved By

TCK

10/17/18

-g

"c

c;, c w

Project Number

874-019

"c "' c"'

Drawing Number

4a

874-019-A011

Flgure

.,"'c (.)

-0

>

e

0.

100

100 Existing Facility

50

50

2 - New Monopile (60"0 x 140'L)

I-

0

LL

c:

l

'

0

ILL

.

~

c:

0

0

nJ

nJ

>

>

..!!:!

..!!:!

w

w

-50

-50

-100

-100

-150

-150

Typical Monopile Cross Section Horizontal Scale: 1" = 100' Vertical Scale: 1· = 50'

100' 50'

Horizontal Scale: 1· = 100' 50' 0 25' 0 Vertical Scale: 1· = 50'

Typical Monopile Cross Section

u_,

Section 10 Permit Application Ascension Parish, Louisiana

g

Impala Warehousing (US) LLC

!

100' 50'

...

..

_,

~

C>

.. c

c w

CBU Walkway Batter Pile Installation Project

'I

·

PROVIDENCE

Drawn By

LMM

10/17118

Checked By

LMM

10117/18

Approved By

TCK

10117/18

Drawing Number

874-019-A012

.~

8'

Project Number

874-019

..

'!! 8' "C w

4b ..g ~

Figure

e

Cl.

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas