Proposed discharge of fill material into waters of the United States to facilitate the realignment and widening of SR-317 (Apison Pike) from SR-321 (Ooltewah-Ringgold Road) to near Layton Lane, located within the City of Collegedale, in Hamilton County, Tennessee and the Citico Creek compensatory mitigation site located within the City of Chattanooga, in Hamilton County, Tennessee. TDOT Projects # 33070-1229-14(A) and 99109-1651-14. TDOT PINs 112524.0 and 104027.09

Public Notice No. 19-18 Nashville District Application No. LRN-2019-00178 Date: May 3, 2019;Expires: June 3, 2019

Please address comments to: Nashville District Corps of Engineers Regulatory Division 501 Adesa Parkway, Suite 250 Lenoir City, Tennessee 37771

SUBJECT: Proposed discharge of fill material into waters of the United States to facilitate the realignment and widening of SR-317 (Apison Pike) from SR-321 (Ooltewah-Ringgold Road) to near Layton Lane, located within the City of Collegedale, in Hamilton County, Tennessee and the Citico Creek compensatory mitigation site located within the City of Chattanooga, in Hamilton County, Tennessee. TDOT Projects # 33070-1229-14(A) and 99109-1651-14. TDOT PINs 112524.0 and 104027.09

TO ALL CONCERNED: The application described below has been submitted for a Department of the Army (DA) Permit pursuant to Section 404 of the Clean Water Act (CWA) for the discharge of fill material into waters of the United States (U.S.). Before a permit can be issued, certification must be provided by the State of Tennessee, pursuant to Section 401(a)(1) of the CWA, that applicable water quality standards will not be violated. The applicant has applied for the required certification.

APPLICANT: Tennessee Department of Transportation 505 Deaderick Street Suite 900, J.K. Polk Building Nashville, Tennessee 37243

LOCATION: The 2.95-mile project begins near the intersection of State Route (SR) 317 with Ooltewah-Ringgold Road, and ends near the intersection of SR-317 with Layton Lane, located within the City of Collegedale. Coordinates of the project beginning and ending are approximately 35.0588°, -85.0645° and 35.0346°, -85.0253°, respectively. Waters of the U.S. proposed for impact include Wolftever Creek, Chesnutt Creek, unnamed tributaries to Wolftever Creek and Chesnutt Creek, unnamed wetlands, and an unnamed pond. The proposed off-site permittee-responsible compensatory mitigation, at Citico Creek, is located in the City of Chattanooga, centered at approximate coordinates 35.05159°, -85.27333°. The road project and the compensatory mitigation site are both located within Hamilton County, Tennessee and within the Middle Tennessee-Chickamauga Watershed (HUC-8: 06020001).

PROJECT DESCRIPTION: The Tennessee Department of Transportation (TDOT) proposes to realign and widen SR-317, at the above described location in Hamilton County, Tennessee. The project would be built primarily on new alignment, due to constraints with the existing alignment, which prevents widening. Approximately 0.25 mile from the start of the project, the proposed alignment transitions to a new location. The roadway continues on a new alignment for approximately 1.6 miles, generally north of the existing SR-317, until the proposed alignment transitions back to the existing SR-317 near College Drive East. The new alignment would consist of a five-lane roadway with two 12 feet wide travel lanes in each direction and a 12 feet wide center turn lane. Four feet wide shoulders would be provided on either side of the roadway and will also serve as bike lanes. Two feet of curb and gutter will separate the shoulders/bike lanes from a greenway path. The greenway path will include five feet of concrete sidewalk separated with three feet of sod on one side (adjacent to the curb and gutter), and four feet of sod on the other side of the sidewalk. All of the improvements are expected to occur within approximately 96 feet of right-of-way width. The total proposed length of roadway construction and improvements is 2.95 miles. The estimated time for completing this project is four years.

The project scope includes all associated drainage improvements. In order to facilitate theproject, the discharge of fill material is proposed within one (1) ephemeral stream, nine (9)intermittent or perennial streams, twelve (12) wetlands, and one (1) open water feature (pond/detention basin). A total of 2,476 linear feet of streams (0.544 acre), 0.01 acre of open water feature, and 3.86 acres of wetland would be permanently impacted by the proposed discharge of fill material related to the roadway improvements. An estimated total of up to 2,580 linear feet of streams (0.592 acre) and 0.189 acre of wetland would be temporarilyimpacted by the proposed discharge of fill material related to the relocation of various utilities required as part of the roadway project. A complete set of project drawings for this public notice is located at: https://www.lrn.usace.army.mil/Media/Public-Notices/

PURPOSE AND NEED: According to the permit application, the purpose of the proposed project is to improve access to Interstate 75 (I-75) for numerous educational, commercial, and industrial facilities in the project area. Other core transportation objectives of the proposed project are improved safety and improved traffic operational efficiency. The existing roadway is two lanes, one in each direction, which is operating at a Class E Level of Service as defined by the American Association of State Highway and Transportation Officials (AASHTO).

Predictions indicate that by 2037 the Level of Service would decrease to Class F, if the No-Buildoption was selected. To improve the operational functionality of the route, additional lanes are proposed. Along with operational efficiency improvements, the selected alternative would also improve safety, and local and regional accessibility.

AVOIDANCE AND MINIMIZATION OF IMPACTS TO WATERS OF THE U.S.:

According to the applicant, efforts were made during the planning and design phases of this project to avoid impacts to waters of the U.S. to the extent practicable, and to minimize impacts that were not avoidable. The applicant has examined several alternatives to the proposed project. According to the applicant, widening the existing roadway was not an option due to various constraints such as residences, churches, businesses, topography, and railroad right-of-way. Two alternatives were evaluated by TDOT for the proposed project: the No-Build Alternative and the Build Alternative.The No-Build Alternative is not proposed by TDOT, since it does not meet the purpose and need of the project.

To minimize impacts to streams and wetlands, span bridges are proposed at multiple locations, andsteeper roadway side slopes and/or retaining walls are proposed, where practicable; these design features allow for minimized impacts to aquatic resource functions and aquatic species passage.

Additionally, the proposed structures at STR-5, STR-6, and STR-9 are to be embedded two feet deep within the stream channels to facilitate aquatic species passage; these embedded structures are proposed to be back-filled with natural channel materials. Measures to facilitate aquatic species passage are not proposed for the following structures: STR-8, STR-A, STR-4, STR-C, and ephemeral streams; data shows that these stream resources do not currently allow for aquatic species passage because of ephemeral flow, existing nearby obstructions, or because the streams originate within the project footprint. Staging areas for construction of the bridges are located outside of wetland areas. Any riprap channel protection placed within the stream channels at the inlet or outlet of culverts would be placed to mimic the existing contours of the stream. The top of the proposed riprap would be installed at grade with the bottom of the stream channel and voids within the riprap would be filled with creek gravel to prevent stream loss within riprap areas.

To minimize erosion and avoid sediment release into waters of U.S., three phases of construction are designed and included in the construction plans. Only 50 acres of land disturbance are proposed at a time and all in-water construction activities would be done in the dry and separated from flowing water, to the maximum extent practicable. Standard Best Management Practices are proposed to reduce erosion and sedimentation. High visibility fencing would be installed during construction to ensure that only authorized impacts to waters of the U.S. occur.

COMPENSATORY MITIGATION: To compensate for unavoidable permanent impacts to 2,215 linear feet of streams, the applicant proposes off-site permittee-responsible compensatory mitigation at Citico Creek, located in the City of Chattanooga, in Hamilton County, Tennessee. The Citico Creek compensatory mitigation site is located in close proximity to the SR-317 roadway improvement project, is centered at approximate coordinates 35.05159°, -85.27333°, and is within the same HUC-8 watershed (06020001). The proposed “Citico Creek Compensatory Mitigation Plan” includes the restoration, re-establishment, and/or enhancement of three streams, which are all tributaries of Citico Creek. The total protected area associated with the mitigation project, including vegetative stream buffers, would total approximately 13.1 acres, and would be protected into perpetuity. Nearby land usage in the mitigation project area is high density residential and industrial. The project streams have been historically altered by channelization, concrete (bed) and flagstone (banks) hard armoring, and other human caused impacts that have resulted in the streams having limited aquatic resource function, increased bank height ratios, lack of stable bed, lack of aquatic species habitat, and other unnatural characteristics. The mitigation project goals and objectives propose to address the impairments to the project streams, restoring streams to a more natural and sustainable condition.

The proposed mitigation project would consist of the restoration, enhancement, and riparian buffer vegetation planting of approximately 3,617 linear feet of degraded stream channel. Of the 3,617 linear feet of streams proposed for improvements, the proposal includes 3,353 linear feet of restoration, 51 linear feet of re-establishment, and 213 linear feet of enhancement. The restoration effort would improve aquatic species habitat by installing large logs, natural river rock, log vanes, riffles, pools, woody toe protection, and live brush layering to protect stream banks. Approximately 2.33 acres of on-site wetlands would be perpetually preserved within the protected mitigation site; however, no wetland mitigation credits are being proposed. USACE is currently reviewing the applicant’s permittee-responsible compensatory mitigation plan for the Citico Creek site.

To compensate for unavoidable permanent impacts to 3.86 acres of wetland, the applicant proposes debiting, at a 2:1 ratio, 7.72 acres from available wetland credits at the Sequatchie Valley Wetland Mitigation Bank, located in Marion County, Tennessee. The proposed wetland impacts are within the primary service area of the Sequatchie Valley Wetland Mitigation Bank.

PUBLIC INTEREST REVIEW/CUMULATIVE EFFECTS: The decision whether to issue a permit will be based on an evaluation of the probable impacts including cumulative impacts of the activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit, which reasonably may be expected to accrue from the work, must be balanced against its reasonably foreseeable detriments. All factors, which may be relevant to the work, will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, cultural values, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shore erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership, and, in general, the needs and welfare of the people. In addition, the evaluation of the impact of the activity on the public interest will include application of the guidelines promulgated by the Administrator, Environmental Protection Agency, under authority of Section 404(b)(1) of the CWA(40 CFR Part 230).

SOLICITATION OF COMMENTS: The U.S. Army Corps of Engineers (USACE) is soliciting comments from the public; federal, state, and local agencies and officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts of the proposed road improvement and widening project. Any comments received will be considered by the USACE to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment (EA) and/or an Environmental Impact Statement pursuant to NEPA. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. An EA will be prepared by this office prior to a final decision concerning issuance or denial of the requested DA Permit.

HISTORIC AND CULTURAL RESOURCES: TDOT, acting on behalf of the Federal Highway Administration (FHWA), has been identified as the lead agency for complying with Section 106 of the NHPA. Previous archaeological studies were completed for this project, including two Phase I Surveys and Phase II testing, in 2010 and 2012, respectively. Two archaeological sites were identified, but were recommended ineligible for listing in the National Register of Historic Places (NRHP). TDOT submitted the findings of these reports to the State Historic Preservation Office (SHPO) on February 7, 2012, indicating that no NRHP listed or eligible archaeological properties would be affected by the project. The SHPO concurred with TDOT's findings on February 15, 2012.

Due to design modifications related to the Wolftever Creek Greenway, an additional Phase I surveywas conducted in August 2015. Three previously unidentified sites were discovered, but were consequently recommended ineligible for the NRHP. The SHPO concurred with TDOT's determination on December 29, 2016, indicating “we find that no archaeological resources eligible for listing in the National Register of Historic Places will be affected by this undertaking.” A historic architecture assessment was conducted by TDOT for this project in 2006. TDOT historians performed a SHPO record search to determine if any previous architectural surveys had identified any historic properties in the area. State Historic Preservation Maps did not indicate that any previously surveyed properties eligible for listing on the NRHP were within the project's Area of Potential Effect (APE). TDOT surveyed the APE for possible NRHP-eligible properties and identified five properties which had not been surveyed previously. The properties were recommended ineligiblefor listing in the NRHP. The SHPO concurred with this finding on August 29, 2006, indicating “we find that the area of potential effect contains no architectural resources eligible for listing in the National Register of Historic Places affected by this undertaking.”

USACE invites responses to this public notice from Native American Tribes or tribal governments; federal, state, and local agencies; historical and archeological societies; and other parties likely to have knowledge of or concerns regarding historic properties and sites of religious and cultural significance at or near the project area. Any substantive comments from this public notice will be provided to TDOT, for consideration of potential effects to historic and cultural resources for Section 106 compliance. If USACE/TDOT determines that consultation is required, USACE/TDOT would consult with the Tennessee Historic Commission (SHPO) and Native American Tribes in accordance with Section 106 of the National Historic Preservation Act, as appropriate. TDOT is required to submit all applicable Section 106 documentation to USACE prior to final permit decision.

ENDANGERED/THREATENED SPECIES REVIEW: TDOT, acting on behalf of the Federal Highway Administration (FHWA), has been identified as the lead agency for conducting environmental review under Section 7 of the ESA. TDOT completed an Endangered Species Act (ESA) records review, by searching the TDEC Division of Natural Areas, Endangered Species Database, on January 22, 2015 and February 11, 2019. Additionally, the applicant conducted ESA field reviews in December 2014. Accordingly, effects determinations were made by the applicant for each species. The field review, records review, and accompanying effects determinations provide documentation of the potential effects of the project on endangered and threatened federally listed species within the action area. Listed species potentially located within a four-mile radius of the project site include:

Species Nomenclature

Federal Status

Flowering Plants

Large-flowered skullcap (Scutellaria montana)

Threatened

Mammals

Indiana bat (Myotis sodalis)

Endangered

Northern long-eared bat (Myotis septentrionalis)

Threatened

There is no critical habitat designated within the project area.

The above described ESA documentation was provided to the USFWS for consultation. In order to determine the presence of bats, a mist netting survey was performed between July 14 and July 18, 2018, at five sites along the project corridor. Efforts resulted in the capture of five bats, including two federally endangered gray bats (Myotis grisescens). The survey information was provided to the U.S. Fish and Wildlife Service (USFWS) on August 14, 2018. On August 31 2018, the USFWS concurred with TDOT’s determination of “not likely to adversely affect” for the Indiana bat and northern long-eared bat based on the negative survey results. The USFWS additionally concurred with TDOT’s finding of “not likely to adversely affect” for the gray bat based on surrounding land use and the absence of caves within the project area, and TDOT’s commitment to implementation of water quality measures. The USFWS also wrote “based on the best information available at this time, we believe that the requirements of section 7 of the Endangered Species Act (Act) of 1973, as amended, are fulfilled for all species that currently receive protection under the Act.”

OTHER APPROVALS: Before a permit may be issued, water quality certification must be provided by the Tennessee Department of Environment and Conservation (TDEC) pursuant to Section 401(a)(1) of the CWA (33 U.S.C. 1341), that applicable water quality standards will not be violated. Other federal, state, and/or local approvals may be required for the proposed work.

REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The request must be submitted in writing to the District Engineer within the designated comment period of the notice and must state the specific reasons for requesting the public hearing.

COMMENT PERIOD: Written statements received in this office within 30 days from the date of this notice will become a part of the administrative record and will be considered in the determination.Any response to this notice should be directed to John Price, Nashville District Corps of Engineers, Regulatory Division, at the above address, at 865-986-7296, or via email: john.c.price@usace.army.mil.

Joshua W. Frost Chief, Technical Services Branch Regulatory Division U.S. Army Corps of Engineers

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas