Public Notice No. 19-14-A

Basic information

Fill out these two fields at minimum.

— or —

How Big?

Where?

Links to source documents

Raw text

You can copy from here when filling out the rest of the page.

Project Plan Modification and Correction to File Number as advertised by Public Notice 19-14, dated May 7, 2019, for proposed conveyance of approximately 9.19 acres of U.S. Army Corps of Engineers (USACE) Cheatham Lock and Dam Project lands for construction of a flood control levee to protect A.O. Smith Facility, in Ashland City, Cheatham County, Tennessee

Public Notice No. 19-14-A Nashville District Corps Application No. LRN-2014-00124 Date: September 26, 2019;Expires: October 11, 2019

Please address all comments to: Nashville District Corps of Engineers, Regulatory Division (Attn: Amy Robinson), 3701 Bell Road, Nashville, TN 37214

SUBJECT: Project Plan Modification and Correction to File Number as advertised by Public Notice 19-14, dated May 7, 2019, for proposed conveyance of approximately 9.19 acres of U.S. Army Corps of Engineers (USACE) Cheatham Lock and Dam Project lands for construction of a flood control levee to protect A.O. Smith Facility, in Ashland City, Cheatham County, Tennessee

TO ALL CONCERNED: The application described below has been submitted for a Department of the Army (DA) Permit pursuant to Section 404 of the Clean Water Act (CWA) (33 U.S.C. 1344). In addition, a joint National Environmental Policy Act (NEPA) document will be prepared for the DA Permit and USACE real estate conveyance action.

APPLICANT:A. O. Smith Corporation 500 Tennessee Waltz Parkway Ashland City, Tennessee 37015

LOCATION: Tributaries and wetlands adjacent to Cumberland River Mile 185.4, right descending bank, Cheatham Lake, By Pass Road and Tennessee Waltz Parkway, in Ashland City, Cheatham County, TN (Latitude 36.266621°, Longitude -87.067433°)

DESCRIPTION OF ORIGINAL AND REVISED PROPOSAL: Public Notice 19-14, issued on May 7, 2019, advertised A.O. Smith’s original proposal to construct a 500-year flood protection levee for its facility in Ashland City, TN. Originally proposed, the work would have impacted 986.5 linear feet of streams and 3.67 acres of wetlands as shown in Table 1:

Table 1: Original Project Impact Table

Streams

Wetlands

ID

Impact

Impact

Type

ID

Impact

Impact

Type

Feet

Acres

Acres

STR-3

130

0.01

Encapsulation

WTL-1

0.41

Permanent Fill

STR -4

138

0.02

Encapsulation

WTL-2

0.08

Permanent Fill

STR -8

24

0.002

Relocation

WTL-3

0.01

Permanent Fill

STR -9

2.5

0.00005

Encapsulation

WTL-9

1.35

Permanent Fill

STR-10

137

0.03

Excavation

WTL-11

1.78

Permanent Fill

P STR-11

228

0.05

Excavation

WTL-12

0.04

Permanent Fill

I STR-11

327

0.08

Excavation

Totals

986.5

0.19

3.67

After expiration of Public Notice 19-14, the applicant researched design options to avoid and minimize project impacts. As a result, revised plans were submitted that involves relocating the borrow area to avoid Streams 10 and 11 that eliminated 692 linear feet (0.154 acres) of impacts on these streams. Other design adjustments to the project involve increases of fill to Wetland 1 by 0.01 acres (for access road to borrow area), Wetland 12 by 0.04 acres, Stream 8 by 24 linear feet, and Stream 9 by 1.5 linear feet (to construct a portion of earthen levee). The overall plan modifications result in a large reduction of stream impacts and a slight increase of wetland impacts from the original impacts. Revised totals are shown in Table 2 below:

Table 2: Revised Project Impact Table

Streams

Wetlands

ID

Impact

Impact

Type

ID

Impact

Impact

Type

Feet

Acres

Acres

STR-3

130

0.01

Encapsulation

WTL-1

0.42

Permanent Fill

STR-4

138

0.02

Encapsulation

WTL-2

0.08

Permanent Fill

STR-8

48

0.006

Relocation

WTL-3

0.02

Permanent Fill

STR-9

4

0.00005

Encapsulation

WTL-9

1.35

Permanent Fill

STR-10

0

0

Excavation

WTL-11

1.78

Permanent Fill

P STR-11

0

0

Excavation

WTL-12

0.08

Permanent Fill

I STR-11

0

0

Excavation

Totals

320

0.036

3.72

Net Change from Original Proposal

-666.5

-0.154

+0.05

Additionally, Public Notice 19-14 identified an incorrect file number for the project. The correct file number is LRN-2014-00124 which is referenced throughout this public notice.

The revised project plans are provided in this notice, Attachments 1-7.

If you received this notice by mail and wish to view all of the diagrams, visit our web site at: http://www.lrn.usace.army.mil/Media/PublicNotices.aspx.

PURPOSE AND NEED: The purpose and need of the project remains the same as the original project as advertised in Public Notice 19-14.

AVOIDANCE AND MINIMIZATION OF IMPACTS TO WATERS OF THE U.S.: The proposed revisions avoid and minimize stream impacts by a total of 666.5 linear feet compared tothe original plans. Other design modifications involve a slight increase of total wetland impacts by 0.05 acre.

COMPENSATORY MITIGATION: A revised compensatory mitigation plan was submitted to offset the new stream and wetland impacts. A total of 268 linear feet (0.036 acre) of stream impacts (encapsulation of 130 linear feet (0.01 acre) of Stream 3 and 138 linear feet (0.02 acre) of Stream 4) are characterized as Cumberland River backwater/open water slough (lentic) areas. The applicant proposes to mitigate these impacts with onsite, in-kind lentic mitigation by converting the soil borrow area into a 6.0-acre (fishing) lake with fringe wetlands (approximate ratio of 200:1). When the soil borrow area is no longer needed, its banks would be shaped to 3:1 slopes banks and variety of depths, substrates, and habitats for fish, reptiles, amphibians, and benthic macroinvertebrates.Stream 8 (48 linear feet) would be relocated onsite and constructed using natural channel design principles that equal the length of channel to be relocated. Additional mitigation measures involve removing two existing bridges and provide restoration activities including bank stabilization on approximately 100 linear feet of Stream 7 (Puzzelfool Creek).

For wetland impacts, the revised compensatory mitigation will involve a combination of onsite, permittee-responsible mitigation and wetland mitigation bank credit purchase. Mitigation for 3.50 acres of the 3.72 acres of permanent wetland impacts includes creation of 12.41 acres (4:1 ratio) of wetlands on applicant-owned property in mitigation areas A and B, the preservation of 1.42 acres (10:1 ratio) of existing wetlands adjacent to mitigation areas A and B, and the preservation of 3.97 acres (15:1 ratio) of upland riparian buffer. The wetland creation would involve excavating higher areas of the Cumberland River floodplain adjacent to existing wetlands to a similar bottom elevation. Additionally, this will link the existing wetland areas into a larger wetland system resulting in the enhancement of habitat of onsite existing wetlands. The remaining 0.22 acre of permanent wetland impacts will be mitigated through the purchase of 0.44 credits (2:1 ratio) from the Swamp Road Wetland Mitigation Bank II. According to the applicant, the proposed mitigation plan would generate compensation equivalent to offset the loss of 3.72 acres of wetlands, create a larger, connected wetland system within the floodplain area, and increase existing wetland functions.

The proposed permittee-responsible mitigation plan for this project is on file in the Regulatory Division office.

PUBLIC INTEREST REVIEW/CUMULATIVE EFFECTS: The decision whether to issue a DA permit for the revised project plans will be based on an evaluation of the probable impacts including cumulative impacts of the activity on the public interest. These interest factors and effects are the same as described in Public Notice 19-14.

SOLICITATION OF COMMENTS: The Corps is soliciting comments on the proposed revised plans from the public; federal, state, and local agencies and officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. USACE is soliciting comments from the public; federal, state, and local agencies and officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by USACE to determine whether to issue, condition, or deny a permit for this proposal. Comments are used in the preparation of a joint Environmental Assessment (EA), supplemental EA, and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act (NEPA).

HISTORIC AND CULTURAL RESOURCES: Coordination and concurrence for the levee project have previously been performed under Section 106 of the National Historic Preservation Act (NHPA). For the new borrow area, the applicant submitted an archaeological survey and its results for USACE’s review. The Corps has provided copies of the report to the State Historic Preservation Office (SHPO), Tennessee Historical Commission (THC), and Tribes in association with Section 106 consultation, as necessary. A final determination for the borrow area is forthcoming. A copy of this notice is being sent to THC, SHPO, and Federally recognized tribes for their comments and consultation under Section 106 of the NHPA. The Corps invites responses from American Indian Tribes or tribal governments; Federal, State, and local agencies; historical and archeological societies; parties likely to have knowledge of or concerns regarding historic properties and cultural significance at or near the project area, and the public.

THREATENED and ENDANGERED (T&E) SPECIES REVIEW: Coordination and concurrence for the levee project have previously been performed under Section 7 of the Endangered Species Act (ESA). This public notice serves as coordination with the U.S. Fish and Wildlife Service (USFWS) pursuant to Section 7 of the ESA of 1972 (as amended) and Fish and Wildlife Coordination Act for the new borrow site location. No significant adverse effects to fish and wildlife, their habitats and human uses are expected to result from the new borrow site due to past disturbances/agricultural uses. Per this notification, we request comments from the USFWS concerning potential impacts to T&E species for the new borrow site location.

OTHER APPROVALS: In addition to the DA permit, other federal, state, and/or local approvals may be required for the revised project plans including:

1. Water quality certification must be provided by the State of Tennessee, Department of the Environment and Conservation, pursuant to Section 401(a)(1) of the CWA (33 U.S.C. 1341) prior to DA permit issuance.

2. USACE Real Estate Division approval for work on U.S. Government land.

PUBLIC HEARING REQUESTS: Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. Requests for public hearings shall state, with particularity, the reasons for holding a hearing.

COMMENT PERIOD: Written statements received by October 4, 2019, will become a part of the record and considered in the determination. Any response to this notice should reference Corps Application No. LRN-2014-00124, and be directed to the Regulatory Division, Attn: Amy Robinson, at the above address or email: amy.m.robinson@usace.army.mil.

/s/

Timothy C. Wilder Chief, West Branch Regulatory Division U.S. Army Corps of Engineers

Rough impact

We use the fields in this section to decide whether to conduct an in-depth review.

Permit Manager

Dates

Identity numbers

Permits, certifications, and locations related to this particular notice

History of edits

Data are available as CSV download in the following schemas